2. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - i
July, 2016
Table of Contents
Description Page
Executive Summary
1.0 Introduction
1.1 Project Background …………………………………………………………………… 1-1
1.2 Scope of Study ………………………………………………………………………… 1-2
1.3 Study Objectives ………………………………………………………………............ 1-2
1.4 Need of EIA Study for the Proposed Project ……………………………………….. 1-3
1.5 The Proponent and Consultant ………………………………………………………. 1-4
1.6 Study Team ……………………………………………………………………………. 1-4
1.7 Study Approach & Methodology …………………………………………………….. 1-5
1.7.1 Study Approach ……………………………………………………………… 1-5
1.7.2 Methodology …………………………………………………………………. 1-5
1.8 Extent of the Study …………………………………………………………………… 1-8
1.9 Structure of the Report ………………………………………………………………. 1-9
2.0 Policy, Legal and Administrative Frameworks
2.0 General................................................................................................ 2-1
2.1 Legal Framework................................................................................................ 2-1
2.1.1 Pakistan Environmental Protection Agency Review of IEE/EIA
Regulations,2000............................................................................................... 2-1
2.1.2 Pakistan Environmental Assessment Procedure 1997......................... 2-1
2.1.3 Sindh Environmental Protection Act,2014............................................... 2-2
2.1.4 Sindh EPA Review of IEE/EIA Regulations,2014................................... 2-2
2.2 Sindh Environmental Quality Standards (SEQS), 2016.................................... 2-3
2.2.1 Air Quality Standards............................................................................ 2-4
2.2.2 Noise Quality Standards....................................................................... 2-4
2.2.3 Drinking Water and Wastewater Quality Standards............................. 2-5
2.3 Other Relevant Laws………………………………………...................................... 2-7
2.4 Policy Framework................................................................................................ 2-12
2.4.1 National Environment Policy, 2005........................................................ 2-12
2.4.2 National Resettlement Policy, 2002....................................................... 2-12
2.4.3 National Power Policy, 2013.................................................................. 2-12
2.5 Administrative Framework.................................................................................. 2-13
2.5.1 Port Qasim Authority GoP…………………………….…………………… 2-13
2.5.2 Environmental Protection Agency, Sindh..................................... 2-13
3. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - ii
July, 2016
3.0 Description of the Project
3.1 Rationale of the Project ……………………………………………………………. 3-1
3.2 Coal Handling Facilities at Port Qasim ……………………………………………. 3-2
3.3 Transport of Coal from PIBT to Coal Fired Power Plants ……………………….. 3-3
3.4 Coal conveying System from PIBT to Existing Railway network ………………. 3-5
3.5 Site Selection for coal Conveyor from PIBT to New Stockyard ………………… 3-9
3.6 Route Selection for coal Conveyor from PIBT to New Stockyard ……………… 3-12
3.7 Location of the Project …………………………………………............................. 3-14
3.8 Project Administrative Jurisdiction ………………………………………………… 3-15
3.9 Project Implementation Schedule………………………….................................. 3-15
3.10 Cost of the Project………………………............................................................ 3-15
3.11 Financing of the Project……………………….................................................... 3-15
3.12 Construction Materials ………………………………………………………………… 3-15
3.13 Construction Camps …………………………………………………………………… 3-15
3.14 Manpower Requirements ……………………………………………………………… 3-15
3.15 Construction Equipment ……………………………………………………………….. 3-16
4.0 Environmental Baseline Profile
4.1 Physical Environment ………………………………………………………………….. 4-1
4.1.1 Topography and Geography ………………………………………………… 4-1
4.1.2 Geology and Soil ……………………………………………………………… 4-1
4.1.3 Climate and Meteorology……………………………………………………… 4-2
4.1.4 Seismicity ……………………………………………………………………… 4-7
4.1.5 Water Resources and Drainage……………………………………………... 4-8
4.1.6 Creek system Hydraulics…….. ……………………………………………… 4-10
4.1.7 Ambient Air Quality …………………………………………………………... 4-10
4.1.8 Air dispersion Modeling of Particulate Matter……………………………… 4-12
4.1.9 Noise Level ……………………………………………………………………. 4-12
4.1.10 Drinking Water Quality………………………………………………………….4-13
4.2 Ecological Resources …………………………………………………………………. 4-17
4.2.1 Flora ……………………………………………………………………........... 4-17
4.2.2 Fauna …………………………………………………………………………. 4-19
4.2.3 Wet Lands ……………………………………………………………………. 4-19
4.2.4 Endangered Species………………………………………………………… 4-20
4.2.5 Wild life Sanctuaries and Game reserves……………………………....... 4-20
4.2.6 Critical Habitats……………………………………………………………… 4-20
4.3 Social Economic Structure……………………………………………………………. 4-20
4.3.1 Malir District ………………………………………………………………….. 4-20
4. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - iii
July, 2016
4.3.2 Study Area …………………………………………………………………… 4-21
4.3.3 Political and administrative Setup ………………..………………………… 4-21
4.3.4 Data Source/Methodology …………………………………………………… 4-22
4.3.5 Characteristics of the Project Area…………………………………………. 4-22
4.4 Economic Conditions…………………………………………………………………. 4-26
4.5 Transportations………………………………………………………………………… 4-28
4.6 Health facilities………………………………………………………………………… 4-29
4.7 Educations…………………………………………………………………………….. 4-30
4.8 Socioeconomic Baseline Survey……………………………………………………. 4-32
4.8.1 Field Survey …………………………………………………………………. 4-32
4.8.2 Survey Results ……………………………………………………………… 4-33
5.0 Public Consultation
5.0 General…………………………………………………………………………………. 5-1
5.1 Consultation and Participation Process ……………………………………………. 5-1
5.2 Methods of Public Consultation........................................................................... 5-2
5.3 Identification of Stakeholders............................................................................... 5-2
5.4 Categories of Stakeholders Contacted................................................................ 5-2
5.5 Major Stakeholders and their Apprehensions...................................................... 5-3
5.6 Consultation Meetings and Formal and Informal Group Discussions................... 5-5
5.7 Concerns / Suggestions of the Stakeholders........................................................ 5-7
5.8 Mitigation Measures proposed by EIA Consultants for Addressing the
Stakeholder’s Concerns.................................................................................... 5-8
5.9 Details of Meetings with the Stakeholders................................................... 5-9
6.0 Anticipated Environmental Impacts and Mitigation Measures
6.0 General……………………………………………………………………………….. 6-1
6.1 Environmental Impact Matrix ............................................................................ 6-1
6.2 Anticipated Impacts during Pre-Construction/Design Phase....................... 6-4
6.2.1 Design and Layout Planning................................................................... 6-4
6.2.2 Topography.& Geology.............................................................................. 6-4
6.2.3 Land Acquisition and Resettlement........................................................ 6-4
6.2.4 Transportation and access..........................................................................6-5
6.2.5 Ecological Impacts.................................................................................. 6-5
6.2.6 Flora.................................................................................................... 6-5
6.2.7 Fauna.................................................................................................... 6-6
6.2.8 Marine Fauna and Flora............................................................................. 6-6
6.2.9 Air Quality and Noise.............................................................................. 6-7
6.2.10 Public Utilities......................................................................................... 6-7
6.2.11 Archaeological and Heritage sites............................................................. 6-7
5. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - iv
July, 2016
6.2.12 Impact on Traffic..................................................................................... 6-8
6.2.13 Seismic Hazard...................................................................................... 6-8
6.3 Anticipated Impacts during Construction Phase........................................... 6-9
6.3.1 Soil.......................................................................................................... 6-9
6.3.2 Construction Camps/Camp Sites........................................................... 6-10
6.3.3 Health and Safety................................................................................... 6-13
6.3.4 Air Quality............................................................................................... 6-16
6.3.5 Noise& Vibrations................................................................................... 6-18
6.3.6 Waste (Construction Waste and Hazardous Waste) ...................... 6-20
6.3.7 Surface and Groundwater ...................................................................... 6-21
6.3.8 Biodiversity Conservation and Natural Resources.................................. 6-22
6.3.9 Disposal of Mucking Material.................................................................. 6-23
6.3.10 Disruption of Existing Public Utilities/ Infrastructure ............................... 6-23
6.3.11 Traffic Management................................................................................. 6-24
6.3.12 Economic Activity.................................................................................... 6-24
6.3.13 Lifestyle and Culture ............................................................................... 6-25
6.3.14 Impacts and Sensitive Receptors.......................................................... 6-25
6.3.15 Impacts of heavy vehicles on the existing road Network...................... 6-26
6.3.16 Physical and Cultural Resources............................................................... 6-26
6.3.17 Storage of fuel on Site............................................................... 6-26
6.4 Anticipated Impacts during Operational Phase .............................................. 6-27
6.4.1 Ecology.................................................................................................... 6-27
6.4.2 Wastewater collection and Treatment at Depot...................................... 6-28
6.4.3 Coal Dust................................................................................................ 6-28
6.4.4 Noise....................................................................................................... 6-32
6.4.5 Solid Waste............................................................................................. 6-32
6.4.6 Socioeconomic....................................................................................... 6-33
6.4.7 Improvement of Infrastructure Facilities...................................... 6-33
6.4.8 Wider Economic Growth........................................................................ 6-33
6.4.9 Better Rail Transportation................................................................ 6-33
6.4.10 Reduced Health Risk and Accidental Hazards................................... 6-33
6.4.11 Fire Hazards..................................................................... 6-34
6.4.11 Emergency Management..................................................................... 6-34
7.0 Environmental Monitoring and Management Plan
7.1 Environmental Management................................................................................. 7-1
7.2 Worker’s Health and Safety................................................................................. 7-2
7.3 Anticipated Impacts During Construction Phase................................................ 7-3
7.4 Environmental Monitoring .................................................................................... 7-15
7.4.1 Construction Phase................................................................................ 7-15
6. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - v
July, 2016
7.4.2 Operational Phase .................................................................................. 7-16
7.4.3 Responsibilities for Monitoring and Reporting ........................................ 7-17
7.5 Plantation ............................................................................................................. 7-19
7.6 Environmental Technical Assistance and Training Plan....................................... 7-19
7.7 Environmental Monitoring, Mitigation and Training Cost ..................................... 7-20
8.0 Conclusion and Recommendations
Annexure
Annexure-I Sind Environmental Quality Standards SEQS
Annexure-II Environmental Monitoring Results
Annexure-III Noise Modelling & Methodology
Annexure-IV Air dispersion Modeling of Particulate Matter
Annexure-V Emergency Response Plan
Annexure-VI Tree Plantation Plan
Annexure-VI Attendance Sheet of Scoping Meeting
7. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - vi
July, 2016
Table
List of Tables
Description
2.1 Ambient Air Quality Standards
2.2 Drinking Water and Wastewater Quality Standards
2.3 SEQS for Drinking Water Quality
2.4 SEQS for municipal &Liquid Industrial Effluents (mg/l)
3.1 Machinery and Equipment Requirement for the Proposed Project
4.1 Meteorological Data (24-hr.) at NWIZ Water Pumping Station PQA
4.2 Meteorological Data (24-hr.) at Pharm Evo, PQA
4.3 Meteorological Data (24-hr.) at PIBT
4.4 Tide Levels at Port Qasim
4.5 Ambient Air Quality Test Results
4.6 Average values of noise levels
4.7 Groundwater Analysis of the Project Area
4.8 Area and Production Average Yield of Crops 1997-1998
4.9 Tree Species of the Project Area
4.10 Population and Intercensal Increase and Growth Rates since 1951
4.11 Percentage of Population by Religion
4.12 Percentage of Population by Mother Tongue and Rural/Urban Areas, 1998.
4.13 Life Time Migrants in the District by Rural/ Urban Areas, 1998
4.14 Percentage (%) of Population by Economic Categories, Gender and Rural/Urban
Areas, 1998
4.15 Number of Schools and Enrollment of Students, 1997-98
4.16 Literacy Ratios by Sex and Rural/Urban Areas, 1981 & 1998
4.17 Gender Ratio of the Respondents
4.18 Age Composition of the Respondents
4.19 Marital Status of the Respondents
4.20 Caste / Ethnic of the Respondents
4.21 Mother Tongue of the Respondents
4.22 Qualification of the Respondents
4.23 Professional Status of the Respondents
4.24 Average Monthly Income of the Respondents
4.25 Average Monthly Expenditures of the Respondents
4.26 Family System of the Respondents
4.27 Average Household Size of Respondents
8. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - vii
July, 2016
4.28 Ownership Status of the Houses
4.29 Nature of Construction of Houses
4.30 Availability of Utilities
4.31 Source of Water for Domestic Use
4.32 Satisfaction Level with Water Quality
4.33 Satisfaction Level with Industrial Development
4.34 Impact of Proposed Project on Employment of Workers
4.35 Nature of Impact of Project on Employment of Workers
4.36 Location of Proposed Project in High Population Density
4.37 Acquisition of Private Land
4.38 Awareness about the Proposed Project
4.39 Implementation of the Proposed Project
4.40 Perceived Impacts (During construction)
4.41 Perceived Impacts (after Construction)
4.42 Protective Measures
4.43 Pressing Needs of the Project Area
5.1 Stakeholders Contacted in the Project Area
5.2 Major Stakeholders and their Apprehensions in the Project Area
5.3 Schedule of Meetings with Stakeholders and their Concerns / Apprehensions
6.1 Environmental Impact Matrix for the Construction Phase
6.2 Environmental Impact Matrix for the Operational Phase
6.3 Summary of Impact of Work Camp & Mitigation Measures
6.4 Maximum Limits of Noise Levels
6.5 Damage Risk Criteria for Hearing Loss
6.6 List of industries located on the either side of the Conveyor Belt
7.1 Environmental Management Plan
7.2 Budget Estimate for Environmental Monitoring During the Construction and Operation
Phases
7.3 Personnel Training Program/ Technical Assistance Services
7.4 Environmental Mitigation and monitoring Cost
7.5 Break-up for Health Safety & Environment cost
List of Figure
Figure Description
1.1 Study Area of the Proposed Project
3.1 Existing Coal handling Facility at Port Qasim
3.2 Material flow Diagram
9. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - viii
July, 2016
3.3 Coal Stalk Yard near Railway Track/Sliding
3.4 Combine Stacker Reclaimer
3.5 Load out Station
3.6 Schematic Layout Plan
3.7 Convey System for Coal Stockyard to load out Station
3.8 Potential Sites for Coal Stockyard
3.9 Routes for Coal Conveying System
3.10 Location of the Project
4.1 Wind rose at NWIZ Water Pumping Station PQA
4.2 Wind rose at PharmEvo, PQA
4.3 Wind rose at PIBT
4.4 Seismic zoning map of Pakistan
4.5 Present Water Supply Zones of Karachi
4.6 Ambient Air Quality Monitoring in the Project Area
4.7 noise level measurement at the project site.
4.8 A General View of Water Sampling
4.9 Floral species present in the project area
4.10 The Map of Malir District
4.11 A view of Karachi International Airport
4.12 A view of Karachi Bin Qasim Port
4.13 A view of Malir City
4.14 A view of Pakistan Steel Mills
4.15 Age Composition of the Respondents
4.16 Marital Status of the Respondents
4.17 Caste/Ethnic Group of the Respondents
4.18 Mother Tongue of the Respondents
4.19 Qualification of the Respondents
4.20 Professional Status of the Respondents
4.21 Average Monthly Income of Respondents
4.22 Average Monthly Expenditures of Respondents
4.22 Family System of the Respondents
4.23 Average Household Size of Respondents
4.24 Ownership Status of the Houses
4.25 Nature of Construction of House
4.26 Availability of utilities for Respondents
4.27 Source of Water for Domestic Use
4.28 Satisfaction Level with Water Quality
10. Table of Contents
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ToC - ix
July, 2016
4.29 Satisfaction Level with existing with Industrial Development
4.30 Impact of Proposed Project on Employment of Workers
4.31 Nature of the impacts proposed by the Respondents
4.32 Location of Proposed Project
4.33 Acquisition of Private Land
4.34 Awareness about the Proposed Project
4.35 Implementation of Proposed Project
4.36 Impacts Perceived by Respondents
4.37 Impacts Perceived by Respondents
4.38 Protective Measures Suggested by Respondents
4.39 Pressing Needs of the Project Area
5.1 Interviews and group discussions with stakeholders
11. Acronyms
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK 1
July, 2016
ACRONYMS
AASHTO : American Association of State Highway and
Transportation Officials
BOD : Bio-chemical Oxygen Demand
BDL : Below Detection Limit
BWSR : Combine Bucket with Stake Reclaimer
O
C : Degree Centigrade
CCS : Coal Conveying System
CC : Construction Contractor
CO : Carbon Monoxide
COD : Chemical Oxygen Demand
dBA : Decibel
DC : Design Consultant
DNL : Day-night level
EC : Environmental Committee
EIA : Environmental Impact Assessment
EMMP : Environmental Monitoring & Management Plan
EMT : Emergency Response Group
EPA : Environmental Protection Agency
EPD : Environmental Protection Department
ERP : Emergency Response Plans
FGDs : Focused Group Discussions
GoP : Government of Pakistan
GoS : Government of Sindh
HSE : Health Safety and Environment
Km : Kilometer
KW&SB : Karachi Water & Sewage Board
KESC : Karachi Electric Supply Corporation
KMC : Karachi Metropolitan Corporation
MGD : Million Gallons per Day
mg/L : Milligram per Liter
MSL : Mean Sea Level
NWIZ : North West Industrial Zone
NCS : National Conservation Strategy
NEQS : National Environmental Quality Standards
NEP : National Environmental Policy
NESPAK : National Engineering Services Pakistan (Pvt.) Limited
NGO : Non-Government Organization
NOC : No Objection Certificate
12. Acronyms
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK 2
July, 2016
NRP : National Resettlement Policy
ND : Not Defined
PEPA : Pakistan Environmental Protection Agency
PNCS : Pakistan National Conservation Strategy
PM : Particulate Matter
PPC : Pakistan Penal Code
PHED : Public Health Engineering Department
PMU : Project Management Unit
ppm : Parts per million
PIBT : Pakistan International Bulk Terminal
PQA : Port Qasim Authority
RAP : Resettlement Action Plan
ROW : Right of Way
RP : Resettlement Plan
SEPA : Sindh Environmental Protection Agency
SEL : SUPARCO Environmental Lab
SPT : Standard Penetration Test
STP : Sewage Treatment Plant
SOx : Sulfur Oxides
SC : Supervision Consultant
SUPARCO : Pakistan Space and Upper Atmosphere Research Commission
SWM : Solid Waste Management
SBCA : Sindh Building Control Authority
SSGC : Sui Southern Gas Company
SEQS : Sindh Environmental Quality Standards
TA : Technical Assistance
TOR : Terms of Reference
TDS : Total Dissolved Solids
TSS : Total Suspended Solids
USEPA : United States Environmental Protection Agency
WHO : World Health Organization
13. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-i July, 2016
EXECUTIVE SUMMARY
A) PROJECT BACKGROUND
Electricity is considered to be most essential instrument for the socio-economic
development of a country. According to the “Annual Plan 2015-16” Pakistan
continues to suffer from the power crisis as nearly one-third of demand for
electricity, during the last year, could not be met due to the supply constraints. On
average, the supply deficit of around 5,000 Megawatt (MW) was experienced, while
it touched the peak of over 7,000 MW last July. And Pakistan’s existing primary
energy supplies are highly skewed towards more expensive fuels like oil and gas
instead of indigenous hydro and coal. Out of 67 Million Tons of Oil Equivalent
(MTOE) of total primary energy mix for 2013-14, 46.4 per cent share is of natural
gas, 35 per cent oil, 11.4 per cent hydro, 5.4 per cent coal and two per cent nuclear,
including imported energy. Disproportionate reliance on the imported oil, that is, 85
per cent of the total oil supply, is exerting a strain on the balance of payments
besides making the energy mix unfavorable.
To reduce the current deficit in the power supply in the country GoP has
implemented the “National Power Policy 2013” in the power sector.
Most of the upcoming coal fired power plants are being planned on imported coal
coming from South Africa, Indonesia or Australia.
Imported coal arriving at Port Qasim will be off loaded at Pakistan International Bulk
Terminal (PIBT) from where it will be transported to the coal fired power plants
situated in various parts of country.
The under construction PIBT, a private sector BOT project for handling coal, clinker
and cement is expected to start operations by December 2016. PIBT has been
planned for handling the import of coal and export of cement and clinker. The initial
handling capacity of PIBT is 8 million tonnes under its Phase-I and Phase-II. The
capacity will be enhanced to 12 million tones under Phase-III.
There are essentially two (02) modes of transport that are envisaged from PIBT to
the power plants.
a) By road, using trucks:
This is seen to be practical mainly for local power plants situated closer to Port
Qasim as the large number of trucks required to transport coal to plants located in
14. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-ii July, 2016
other parts of the country would significantly increase truck traffic in the port area as
well as the highway network adding to congestion on the roads, increasing the
chances of accidents and having an adverse impact on the environment.
b) By Rail, using wagons:
This is considered to be a safe and efficient method of bulk coal transportation over
long distances and is suitable for supply to power plants in other parts of the
country.
The main railway tracks are located on northern side of Port Qasim in North-West
Industrial Zone (NWIZ). Two tracks links Karachi to other parts of the country. These
tracks are also being used for freight trains as reported by Pakistan Railways (PR).
A single track exists on west of NWIZ which connects Port Qasim Marginal Wharf
Berths to Pipri Marshalling Yard and is connected onward with the main railway
lines.
Pakistan Railways track in NWIZ of Port Qasim is 5.0 KM away from PIBT. A
transportation link is needed between PIBT and existing railway track in NWIZ of
Port Qasim. To meet this requirement the Government of Pakistan (GoP) decided to
connect PIBT with existing railway network at Port Qasim with a bulk conveyor. GoP
has directed PQA to develop the connectivity of PIBT with existing railway network
by laying a coal conveying system.
The project is to be undertaken on Engineering, Procurement and Construction
(EPC) basis and is required to be completed on priority basis to meet the demand of
coal at power plants.
The transport of coal through train shall initially reduce the gap between electric
power demand and supply, which will give boost to the economy by way of
employment and increase in the GDP growth.
Additional employment will be generated at the project and power plants and the
use of additional power will create employment in various industries.
The project is expected to be environmentally in conformity with national
environmental laws.
The alternative to the conveyor system would be transport of coal, from PIBT to
railway yard, by trucks. This mode of transportation would be inefficient, slow,
15. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-iii July, 2016
unsafe, will cause pollution and road traffic congestion at port.
Presently, there is no connection between PIBT & existing railway network at
Port Qasim and hence, this link needs to be constructed.
Pakistan Railways has informed that the railway network cannot be extended to
PIBT due to the steep gradient and interface issues with the main line. Therefore;
connection between PIBT and existing railway network is required. GoP has
decided that this connectivity shall be through conveyor. The coal conveyor is to
be installed from PIBT to the existing Pakistan Railway Network measuring
approximately 4.5 km.
The Cabinet Committee in its meeting on 16th
September, 2015 decided that Port
Qasim Authority (PQA) shall take up the installation of conveying system from
PIBT to existing Railway Network at Port Qasim
Working Mechanism:
As per the conceived scheme, PIBT will unload the coal at its jetty and stock at its
backup area for the power plants and other consumers located in the vicinity of
Port Qasim. For the power plants and other consumers (if any) located upcountry
the PIBT will unload the vessel/ship at its jetty and load at PQA coal conveying
system for transportation of coal through Pakistan railway.
Transportation of coal from the coal loading area in Port Qasim to various power
plants in the country shall be performed by Pakistan Railways.
PQA’s coal conveyor will transport the coal to a coal stockyard near existing railway
track. The stockyard will be equipped with combined Bucket Wheel Stacker
Reclaimer (BWSR) coal stacking/reclaiming equipment. Coal will be stacked in
stock piles where approximately 440,000 tonnes of coal can be stored. Reclaiming
of coal from stockyard will be performed by the BWSR and coal will be loaded on a
coal conveyor for transportation to the load out station located at the railway track
for loading on railway wagons.
The arrangement for coal stacking, reclaiming and maintaining live and dead
storage at the power plant shall be made by the respective power plants.
Project Description
From PIBT to railway siding and loading of coal onto railway wagons for onward
transportation to the proposed coal fired power plants. The project is being taken
16. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-iv July, 2016
up on the directive of the Prime Minister’s Office as per the decision of Cabinet
Committee on energy .
The Coal Conveying System from PIBT to existing Railway Network at Port Qasim
shall be carried out as per the approved development scheme and be executed in
a manner that will not obstruct the normal port activities. Scheme of coal conveying
and development is as follows:
Take up of coal outside PIBT Terminal’s premises onto the PQA coal conveyor
and transfer coal through conveyor to PQA’s coal stockyard located near the
existing railway track. Storage of coal in stockpiles by utilizing BWSR in PQA’s
stockyard and loading of coal from stockpiles to belt conveyor via BWSR for
onward transportation up to load out station at railway track.
• Provision of railway loop / siding for coal loading into railway wagons;
• Rapid loading of coal in railway wagons through a load-out station;
• Provision of infrastructure facilities i.e. road, drainage, water supply, storm water
firefighting and sewerage system;
• Provision of water sprinkling system to control coal dust at coal stockyard;
• Provision of wind breaker and coal dust suppression wall around the coal
stockpiles;
• Provision of security and surveillance systems including emergency power
backup;
• Provision of electric power supply (approx.4.5 MW) for the project during
construction and operation;
• Provision of telecommunication connection from existing network; and
• Acquisition of 200 acres of land adjacent to existing railway track on east of PQA
NWIZ in Pakistan Steel Mill Area and necessary ROW required for conveyor.
The coal dust suppression system will be designed during detail design stage. The
following is a general description of the system.
Coal dust from coal stockpile and coal conveyor belt is the major source of fugitive
emissions. Dust suppression using the covers over coal conveyor belt, inbuilt dust
control systems in transfer stations and rapid load-out station, wind breaker wall,
dust suppression wall and water sprinkler system at coal stockyard will be primarily
employed to control the coal dust from these areas.
17. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-v July, 2016
PQA Coal Conveyor Belt and Coal Stockyard:
Different potential routes for coal conveyor belt and sites for coal stockyard were
studied to develop a conveyor belt and coal stockyard.
PQA Coal Conveyor Belt
Four (04) routes for the provision of Coal Conveyor Belt were studied by
considering the following factors to identify the most feasible route of coal
transportation from PIBT to PQA coal stockyard. The routes studied are shown in
figure 3.9 and described in detail in section 3.6.2 of this report.
a) Location of first coal transfer station near PIBT (starting point);
b) Location of PQA coal stockyard and load-out station (end point);
c) Minimum changes in the existing natural environment;
d) Relocation of existing utilities;
e) Topography of the area;
f) Geotechnical conditions;
g) Availability of R.O.W;
h) Physical features and impediments along the route;
i) Turning points along the route; and
j) Access roads for the inspection and maintenance of conveyor belt.
PQA Coal Stockyard
Different four (04) potential sites as shown in figure 3.8 and discussed in detail in
section 3.5.2 have been studied by considering the following site selection criteria
for the development of PQA coal stockyard from where the coal can be conveyed
to a rapid load-out station for loading railway wagons.
a) Availability of adequate parcel of land along the existing railway track;
b) Minimum changes in the existing natural environment ;
c) Access to site;
d) Relocation of any existing utilities;
e) Proximity to rapid load-out station;
f) Suitability of land with respect to topographic and sub-soil conditions; and
g) Capital and O & M cost of conveying system.
B) NEED FOR EIA STUDY
An Environmental Impact Assessment (EIA) Study has been conducted for
construction of COAL CONVEYING SYSTEM as a mandatory requirement of
18. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-vi July, 2016
Sindh Environmental Protection Act (SEPA), 2014, Environmental Examination
and Assessments Part VI 17. (1).
The Project Proponent, Port Qasim Authority, (PQA), Government of Pakistan
(GoP), entrusted National Engineering Services Pakistan Private Limited
(NESPAK) to fulfill this regulatory requirement of the project.
C) SCOPE OF STUDY
The scope of EIA Study includes Environmental Assessment of the project
including collection of data related to physical, biological and socio-economic
environment, assessment of impacts which may be caused by the project activities
and mitigation measures for the abatement of potential environmental impacts
along with the estimated budgeted cost of mitigation.
This study has been conducted in accordance with the Sindh Environmental
Protection Agency (SEPA) and Government of Sindh (GoS) Guidelines. The study
is based on both primary and secondary data and information. Discussions were
held with stakeholders including, different government department, utility service
providers, community representatives and a wide range of road users and
roadside dwellers.
D) STUDY AREA
Figure 1.1 shows the visual examination of Study Area and includes about 500 m buffer
area on either side from the centerline of the median of selected route for coal
conveyor belt and around the PQA coal stockyard.
E) RELEVENT LEGISLATIONS AND POLICIES
The 18th
amendment in the Constitution of Islamic Republic of Pakistan has
fundamentally altered the division of legislative powers between the National
Assembly and the Provincial Assemblies, resulting in a significant increase in the
extent of provincial autonomy. After this amendment, powers for the grant of No
Objection Certificate (NOC) have been delegated to the provincial EPAs. For this
project, Sindh EPA is the concerned authority.
In compliance with the regulatory requirement and commitment of Port Qasim
Authority (PQA) to sustainable development, this EIA Study has been conducted. The
EIA study has extensively considered all the relevant national and provincial
legislations, regulations and guidelines related to the project.
19. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-vii July, 2016
F) PROJECT DESCRIPTION
The estimated capital cost of the infrastructure development is approximately Rs. 16.0
billion.
G) DESCRIPTION OF THE ENVIRONMENT
The baseline information was collected for the Study Area utilizing the checklists,
preforms, Satellite Imagery from Google Earth, and General Topographic (GT)
sheets. Meetings and scoping sessions with all the concerned project stakeholders
were carried out for the collection of primary information, disclosure of Project
interventions, information and to clear queries about the Project. The Study Area was
marked using the GT sheets and Google Earth Image during desk studies which was
later finalized during the field visit.
Physical Environment
The physical environment includes topography, regional geology, soils, climate,
hydrology, drainage, seismology, surface water, groundwater, noise levels and
ambient air quality.
Port Qasim is located, adjacent to the Bin Qasim town, in the southern part of Malir
district, Karachi division, in Sindh. It is located in an old channel of the Indus River at
a distance of 35 kilometers east of Karachi city center.
The geographic position of the Port Qasim places it in close proximity to major
shipping routes. The approach to the port is along a 45-kilometre long Navigation
Channel which provides safe navigation for vessels up to 75,000 tones dead weight
(DWT).
The information, as per Geologic Survey of Pakistan, reveals that in the project area
and its adjoining areas only the middle and upper tertiary formations are present. The
formation found in the area is fresh and slightly weathered, recent and sub recent
shoreline deposits. These deposits are derived from Gaj / Manchhar formations of
lower Miocene to Middle Miocene / Upper Miocene to Pliocene age. Similar deposits
are found all along the coastal belt of Karachi and adjoining areas. The seabed is
predominantly sand and silt while the sediment of the delta is fine grained and
resembles the soil from the continental shelf at the mouth of the Indus delta.
Due to proximity to the sea, the city of Karachi has little variation in average maximum
and minimum temperatures. The average annual temperatures during summer are
26o
C to 35o
C (up to 42o
C in May/June), whereas temperature ranges between 10o
C
20. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-viii July, 2016
to 27o
C during winter. Day and night temperature also varies considerably as the sea
breeze in the afternoon rapidly decreases day time temperatures.
Seismicity
Sindh Building Control Authority (SBCA) has placed Karachi in Zone-2 B based on
the actual events, the past observations of fault movement and other geological
activities. Karachi is situated in a region where moderate earthquakes may occur of
magnitude 5.0 to 6.0 equivalents to intensity between VII and VIII on Modified
Mercallis Scale (M).
As per the building code of Pakistan, Seismic Provisions 2007, the project area falls in
Zone 2B Seismic Zoning Map of Pakistan (Figure 4.1). The project structures should
therefore be designed to cater for the ground acceleration of 0.16 g to 0.24 g.
Environmental Monitoring
To establish the baseline of the project area, air, noise, drinking and ground water
monitoring was carried out near project site. The results of ambient air monitoring,
noise quality, drinking and ground water quality indicates that all parameters are well
within the permissible limits of NEQS.
Ecological Environment
The climate of Malir District is arid and it is densely populated with wide variety of
vegetation in the form of natural foliage consisting diversity bushes, shrubs, trees
including agricultural products such as crops, vegetables and fruits.
Flora:
The floral species located in the project area are very few mainly the xerophytic.
Shrubs/weeds were observed grown in the project area. The footings for coal
conveyor belt will be installed/erected in the existing green belt located in the median
of the road where about twelve (12) numbers of trees would be affected. These trees
are poplar, neem, molsary and kikar.
Fauna:
In near past, Deer (Gazella benetti) Wolf (Canis lupus pellipes), Jackals (Canis
aureus) and Fox (Vulpes bengalenis) were found in abundance. Now days, these
wild animals can be seen only in the center of wild life development.
Among birds Indian Grey partridge, Chest-Nut-Bellied Sand Grouse, Rock Dove,
Indian Little Button Guail and Eurasian Roller are found in Malir District.
21. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-ix July, 2016
Socio-economic Environment
According to District Census Report (DCR) of Malir, 1998, the total area is 2268 Sq.
kilometer yielding a population density of 432.7 in 1998. The population of Malir
district was 981.41 thousand in 1998 as compared to 429.57 thousands in 1981. The
annual growth rate measured 4.98% during the 1981-1998.
A social survey was carried out in the project area to identify the impacts and their
magnitudes on the affected population. A sample of 100 respondents was taken on
the basis of random sampling technique, which included residents, Government
Officials and visitors etc.
SCREENING OF POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION
MEASURES
The project is linked with resolving the energy crisis by providing cheap base electric
power in quantum enough to let the various economic sectors to operate at optimum
capacity utilization and ability to make investment decisions with the knowledge that
cheaper base and reliable electric power shall be available.
Provision of power in adequate quantum will enhance capacity utilization, promote
higher employment, higher tax collection and a virtuous development cycle will be
started.
The potential impacts due to implementation of the proposed Project on physical,
ecological and socio-economic domains of the environment of the Project as well as
the Study Area have been identified.
The important and major impacts and respective mitigation measures are as follows:
Construction Stage
During construction of Coal Conveying System, proper mitigation measures are
necessary. During the field survey, significant efforts were made to identify the main
social, cultural and environmental issues related to the project for which a cross
section of the society including residents of the project area, various government
departments and agencies were contacted for obtaining the information. Most of the
perceived impacts are during construction phase. Following is a list of main concerns
identified in the study:
• Disturbance to the public movement during construction;
• Air and noise pollution due to the different construction activities and operation
of construction machinery during construction phase of the project;
22. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-x July, 2016
• Solid waste generation during construction;
• Accidental leaks/spills of hazardous chemicals from construction activities and
machinery;
• Health and safety issues of the workers;
• Contamination of water body by construction activities; and
• Disturbance in traffic movement during excavation and lying of utility pipe in
relocation of public utilities.
Operational Stage
Recommended mitigation measures to contain potential adverse impacts are
described in the Environmental Monitoring and Management Plan (EMMP). EMMP
shall be strictly enforced during the operational phase of the proposed Project.
H) ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN
The main objective of the Environmental Management and Monitoring Plan is to
ensure that all the necessary corrective actions are carried out to mitigate any
adverse environmental impacts, and that enhancement measures are used wherever
feasible and practical. This program includes Institutional Requirements;
Environmental Monitoring Program; Tree Plantation Plan; Training and Capacity
Building; Reporting Structure and Outcomes; Environmental Management and
Monitoring Cost.
To implement and monitor the mitigation measures, following organizations will be
involved:
• Port Qasim Authority (PQA) as the Proponent;
• NESPAK as the Consultant of the Project (Infrastructures Development only)
• Project Contractor, as the executor of the project;
• EPA-Sindh, as observer and top monitoring agency during the construction and
operations stage.
The Project Proponent will be responsible for ensuring the overall implementation of
EMMP during the construction and operation stages of the project.
Environmental Monitoring is recommended during the construction and operational
phases to ensure the effectiveness of the proposed mitigation measures.
23. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-xi July, 2016
I) CONCLUSIONS AND RECOMMENDATIONS
After the assessment of proposed project activities and investigation of the project
area, Screening of potential impacts reveals that the proposed CCS on adoption of
the suggested mitigation measures is an environmentally acceptable proposition.
It is suggested that in order to improve the disturbed ecology of the project site, a
landscape and plantation plan should be prepared and implemented by utilizing
available resources.
It is envisaged that the commitment of the PQA to maintain the quality of the
environment within and adjacent to project area through implementation of the
environmental management plan would mitigate any adverse impacts. For effective
environmental management, PQA should assign the necessary responsibilities to an
Environmental Committee (EC) which should be responsible for implementation of
the Environmental Monitoring of the proposed project.
It is concluded that the proposed project will not result in any significant negative
impact to the community or the environment during construction and subsequent
operation phase.
The mitigation measures are being proposed to control noise emission, wastes and
dust during construction and operation stage of the project. It will be ensured that the
project will comply with all the regulatory requirements, guidelines and safety
standards are followed and that the recommended environmental mitigation
measures as discussed in this report are adopted.
It is envisaged that the commitment of Port Qasim Authority (PQA) to maintain the
quality of environment within and adjacent to the project area through implementation
of the EMMP would mitigate any adverse impacts. For effective environmental
management, Port Qasim Authority (PQA) should assign the necessary
responsibilities to an Environmental Committee which should be responsible for
implementation of the Environmental Management and Monitoring of the proposed
project.
The implementation of Coal Conveying System (CCS) will provide;
• CCS includes features like inbuilt dust control in transfer stations, covered coal
conveyor, mechanized loading unloading features, dust suppression and
complete firefighting arrangements at coal stockyard, and rapid load-out station
for loading the train, all day service spans, and more frequent service than truck
24. Executive Summary
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK ES-xii July, 2016
transport;
• The use of exclusive trains, flexibility and lower-cost of transportation by train
allows it to provide cost effective, environment friendly, safe, swift, and greater
reliability of fuel for power plants;
• Reliable supply of fuel ensures the reliable power generation and supply;
• Improved tax / fare collection;
• The total capacity of a single train is 2400 tonnes;
• The greater frequency and larger quantities of coal transport through train will
reduce traffic on highways;
• Contributes to reductions in traffic crashes;
• Reduced traffic load noise & air pollution; and
• Reduced maintenance of roads.
Some recommendations those need to be followed for the project to make the project
sustainable are:
• The Project impacts and their mitigation will be monitored as per the Monitoring
Plan;
• All mitigation, compensation and enhancement measures proposed in this EIA
report are implemented in full, as described in the document;
• To ensure that the environmental impacts of the project are successfully
mitigated;
• The Environmental Management and Monitoring Plan must be implemented;
and
• The Implementing Agency (PQA) shall ensure that the EMMP prepared by the
contractor includes construction methodologies and submit this to PQA for
review and approval.
At the implementation stage, PQA assisted by Supervision Consultants (SC) will
make arrangements to monitor the implementation of mitigation measures and
conduct environmental effects monitoring activities specified in the EMMP.
With these measures in place, environmental impacts of the Project should be
manageable and will not result in any residual impacts on the project.
25. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-1
July, 2016
SECTION–1
INTRODUCTION
1.1 NEED OF THE PROJECT
Pakistan continues to suffer from the power crisis as nearly one-third of demand for
electricity, during the last year, could not be met due to the supply constraints. On
average, the supply deficit of around 5,000 Megawatt (MW) was experienced, while it
touched the peak of over 7,000 MW last July1
.
Pakistan’s existing primary energy supplies are highly skewed towards more
expensive fuels like oil and gas instead of indigenous hydro and coal. Out of 67
Million Tons of Oil Equivalent (MTOE) of total primary energy mix for 2013-14, 46.4
per cent share is of natural gas, 35 per cent oil, 11.4 per cent hydro, 5.4 per cent coal
and two per cent nuclear, including imported energy. Disproportionate reliance on the
imported oil, that is, 85 per cent of the total oil supply, is exerting a strain on the
balance of payments besides making the energy mix unfavorable1
.
Highly expensive generation of electricity (~Rs 12 / unit) due to an increased
dependence on expensive thermal fuel sources (44% of total generation). RFO,
HSD, and mixed are the biggest sources of thermal electricity generation in Pakistan
and range in price from ~Rs 12 / unit for mixed, to ~Rs 17 / unit for RFO, and a
tremendously expensive ~Rs 23 / unit for HSD. Dependence on such expensive fuel
sources has forced Pakistan to create electricity at rates that are not affordable to the
nation and its populace2
.
To reduce the current deficit in the power supply in the country GOP has
implemented the “National Power Policy 2013” in the power sector. The main feature
of the policy is to use coal as a lower cost energy source. As a result of policy the
number of coal fired power plant projects are being undertaken including Sahiwal,
Jamshoro and Lakhra.
1- Annual Plan 2015-16
2- National Power Policy 2013
26. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-2
July, 2016
Coal, as a fuel for power generation, has very low usage in Pakistan and the
infrastructure required for the handling and transportation of bulk coal cargo does not
exist. However, with the new up-coming coal based power projects, the provision of
necessary infrastructure has become an urgent need.
Imported coal arriving at Port Qasim will be off loaded at Pakistan International Bulk
Terminal (PIBT) from where it will be transported to the coal fired power plants
situated in various parts of the country.
The under construction PIBT, a private sector BOT project for handling coal, clinker
and cement is expected to start operations by December 2016. PIBT has been
planned for the import of coal and export of cement and clinker. The initial handling
capacity of PIBT is 8 million tonnes under Phase I & II, which will be enhanced to 12
million tonnes under Phase III.
Transportation of coal from PIBT, Karachi to the coal power plants located in the
vicinity of Karachi / nearby areas will be by trucks but this mode of transport is
unsuitable for plants located in other parts of the country. Therefore, for plants
located at Jamshoro, Lakhra, Muzaffargarh, Sahiwal, etc., coal transport is foreseen
by railway.
Presently, there is no connection between PIBT & existing railway network at
Port Qasim and hence, this link needs to be constructed. The project is to become
part of the existing infrastructure at Port Qasim.
Pakistan Railways has informed that the railway network cannot be extended to PIBT
due to the steep gradient and interface issues with the main line hence; a coal
conveying system is to be installed from PIBT to the Pakistan Railways Network
measuring approximately 4.5km by Port Qasim Authority (PQA).
The proposed project "Coal Conveying System from PIBT to existing railway network
at Port Qasim” will provide an important link in the establishment of a coal
transportation infrastructure. The project derives its need from being an integral part
of imported coal based power projects.
Port Qasim Authority (PQA), GoP entrusted National Engineering Services Pakistan
(NESPAK) with the assignment of carrying out an Environmental Impact Assessment
(EIA) Study of Coal Conveying System from PIBT to existing railway network at Port
Qasim.
27. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-3
July, 2016
1.2 SCOPE OF STUDY
The scope of EIA Study aims at collection and scrutiny of data related to biophysical
and socio-economic environment of the project area and to prepare the baseline
environmental profile. It also aims at the identification, prediction and evaluation of the
possible environmental impacts of the proposed project on its immediate surroundings
on both short and long-term basis. Based on the nature and levels of these impacts,
appropriate mitigation measures along with their cost have been incorporated in this EIA
Report.
1.3 STUDY OBJECTIVES
The overall objective of EIA is to assess the environmental impacts arising from the
project. The specific objectives of the EIA Study for Coal Conveying System (CCS)
from PIBT to Railway Network at Port Qasim are:
Collection of data related to physical, biological and socio-economic
environments of the project area and to prepare baseline environmental profile;
Identification, prediction and evaluation of environmental impacts of the proposed
project;
Suggesting appropriate mitigation measures to minimize the adverse impacts;
and
Preparation of an Environmental Monitoring and Management Plan.
1.4 NEED FOR EIA STUDY OF THE PROPOSED PROJECT
EIA is mandatory according to Sindh Environmental Protection Act, (SEPA), 2014,
Environmental Examination and Assessments Part VI 17. (1), which states that:
“No proponent of a project shall commence construction or operation unless he has
filed with the Provincial Agency an initial environmental examination or, where the
project is likely to cause an adverse environmental effect, an environmental impact
assessment, and has obtained from the Provincial Agency approval in respect
thereof.”
According to the Sindh Environmental Protection Agency (Review of Initial
Environmental Examination and Environmental Impact Assessment) Regulations,
2014, the proposed project falls under category J (Other Projects) of Schedule
II, which requires EIA before commencement of construction.
28. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-4
July, 2016
1.5 THE PROPONENT AND CONSULTANT
The proponent of the project is Port Qasim Authority (PQA) while the Consultant is
NESPAK. The details are given as under:
For the Proponent
Director General
Port Qasim Authority
Bin Qasim, Karachi-75530, Pakistan
Telephone : 021-99272111-30
Facsimile : 021-34730107
Email : sak_moro@yahoo.com
For the Consultant
Project Manager
National Engineering Services Pakistan Private Limited (NESPAK)
13th
Floor, NICL Building, Abbasi Shaheed Road, Karachi
Telephone : 021-35657140
Facsimile : 021-35651994
Email : nespakkh@gmail.com
1.6 STUDY TEAM
A multidisciplinary team was formulated to conduct the study. The team comprises of
the following persons:
Syed Munawwar Abbas
Mukesk Kumar
Riazul Huda
Ainuddin
Syed Ali Sher Shah
Hammad Qamar
Saeed Hussain
Adeel Pervez
Sanober Zubair
Shariq Ullah Khan
Zahir uddin Khan
Project Manager
Project Coordinator/Senior Engineer
Project Adviser (Civil)
Project Adviser (Mechanical)
Team Leader / Environmental Engineer
Environmental Engineer
Sociologist
Environmentalist/Ecologist
Environmental Engineer
Sociologist
Senior Civil Surveyor
29. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-5
July, 2016
1.7 STUDY APPROACH & METHODOLOGY
1.7.1 Study Approach
This study has been conducted in accordance with Environmental Protection Agency
(EPA), Government of Pakistan (GoP) Guidelines, 2000. The study is based on both
primary and secondary data and information. Discussions were held with stakeholders
including government officials, nearest community representatives and -factory owners
and employees. The main purpose of this approach was to obtain a fair impression of
the people’s perceptions of the project and its environmental impacts.
1.7.2 Methodology
The following methodology was adopted for carrying out the EIA study of the proposed
Project:
a) Orientation
Meetings and discussions were held among the members of the EIA Team. This activity
was aimed at achieving a common ground of understanding of various issues of the
study.
b) Planning for Data Collection
Subsequent to the concept clarification and understanding obtained in the preceding
step, a detailed data acquisition plan was developed for the internal use of the EIA
Team. The plan included identification of specific data requirements and their sources;
determined time schedules and responsibilities for their collection; and indicated the
logistics and other supporting needs for the execution of the data acquisition plan.
c) Data Collection
In this step, primary and secondary data were collected through field observations,
environmental monitoring in the field, concerned departments and published materials
to establish a baseline profile for physical, biological and socio-economic environmental
conditions.
Following steps were followed to collect the primary and secondary data related to this
study:
- Site Reconnaissance
- Analysis of Maps and Plans
- Literature Review
30. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-6
July, 2016
- Desk Research
- Public Consultations
- Field Observations & Studies
- Environmental Monitoring and Laboratory Analysis
The data was collected for physical, biological and socio-economic conditions, the
details of which are given below:
i. Physical Environment
Information was gathered on the existing physical environment, particularly as related to
geology, topography, soils, hydrology, drainage, water quality, air quality and noise.
Geology, Topography, Soils
A review of relevant literature was performed on the geology, topography, sub-
soil conditions of the project area.
Hydrology and Drainage
A literature review was conducted to identify the components of the hydrological
cycle that are likely to impact on the project and the possible impacts that the
project could have on the hydrologic regime. Field assessment includes
assessment of drainage issues, interviews with local community members, and
round-table discussions with stakeholders.
Air Quality
Ambient air quality measurements are essential to provide a description of the
existing conditions, to provide a baseline against which changes can be measured
and to assist in the determination of potential impacts of the proposed construction
on air quality conditions. Ambient air quality was continuously monitored for Carbon
Monoxide (CO), Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2), Particulate Matter
(PM10), for 24 hours. CO was analyzed by Test 317-3 CO Analyzer, while SO2
and NO2 were analyzed according to the Standard Operating Procedures (SOP)
based on recognized method ISO 6767 and method ISO 6768 of USEPA
respectively.
Noise
Noise level readings were monitored at 03 (three) sampling point for 24 hours with
the interval of one second and hourly average data was reported.
31. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-7
July, 2016
Water Quality
The objective of water quality monitoring was to determine water quality condition
before construction. It has been observed that the water and air quality are the
most important environmental variables to be affected in a road project. The extent
of water contamination in the project area was assessed based on the test results
of chemical and microbiological parameters for water. Dissolved oxygen (DO), pH
and conductivity measurements were taken in situ at all sampling stations.
Laboratory analyses have been performed in SUPARCO laboratory.
ii. Biological Environment
The status of the flora and fauna of the study area was determined by ecological
survey, a review of literature relevant to the area, and an assessment of terrestrial
environments.
Flora
The vegetative communities were identified and classified into community types.
Identification was carried out of dominant tree species.
Fauna
Information on fauna was gathered from existing literature on reported species as
well as observations in the field.
iii. Socio-Economic Environment
The Consultants utilized a combination of desk research, field investigations,
census data, structured interviews, maps and reports to generate the data required
for description of the existing social environment and assessment of the potential
impacts of the construction of the proposed project. Data was gathered on the
following aspects of the social environment:
- Land use and Municipal Status
- Livelihoods
- Poverty
- Education
- Health
- Social Setup
- Community Facilities
- Solid Waste Management
- Proposed Developments
32. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-8
July, 2016
- Recreational Activities
- Archaeological and Cultural Heritage
d) Identification and Evaluation of Environmental Impacts
The impacts of the proposed project on the physical, biological and socio-economic
environment prevalent in the project area were visualized at the Design, Construction
and Operational Phases.
e) Mitigation Measures and Implementation Arrangements
Adequate mitigation measures and implementation mechanisms were proposed so that
the Project Proponent could incorporate them beforehand in the design phase.
1.8 EXTENT OF THE STUDY
This document covers introduction of project, project description, analysis of
alternatives, baseline conditions, environmental impacts, mitigation measures,
institutional requirements and Environmental Management and Monitoring Plan
(EMMP) of the proposed coal conveyor route, in and around the Project Area covering
the physical, ecological and socio-economic aspects.
a) Study Area
Before proceeding to the environmental assessment of the Project, it is imperative to
delineate the area of project influence (referred to as the “Study Area”). While major
construction activities of the project are expected to remain confined within the project
area boundary, the environmental impact of these activities is expected to extend
beyond these boundaries to nearby residential and industrial areas.
Therefore, based on field visits and examination of the Study Area and surrounding
neighborhoods, the Study Area boundary was delineated. Figure 1.1 shows the visual
examination of Study Area and includes about 500 m buffer area on either side from
the centerline of the median and around the stockyard.
The description of the environment in this chapter pertains to the Study Area described
above as the potential environmental impacts are expected to remain within this
delineated boundary.
33. EIA OF COAL CONVEYING SYSTEM-PORT QASIM, KARACHI
FIGURE 1.1: STUDY AREA OF COAL CONVEYING SYSTEM
34. Section–1 Introduction
EIA of Coal Conveying System - Port Qasim, Karachi
____________________________________________________________________________________________________
NESPAK Page 1-9
July, 2016
1.9 STRUCTURE OF THE REPORT
The report has been structured as follows:
Section 1: Introduction briefly presents the project background, objectives,
methodology and need of the EIA study.
Section 2: Policy, Legal and Administrative Framework comprises policy guidelines,
statutory obligations and roles of institutions concerning EIA study of the proposed
project.
Section 3: Description of the Project furnishes information about the location of
proposed project, cost and size of the project, detailed description of project,
alternatives considered for the proposed project to select at the preferred alternative for
detailed environmental assessment.
Section 4: Environmental Baseline Profile establishes baseline conditions for
physical, biological and socio-economic conditions prevalent in the project area.
Section 5: Public Consultation identifies the main stakeholders and their concerns
raised through scoping sessions, stakeholder meetings and deals with the measures to
mitigate the social impacts.
Section 6: Anticipated Environmental Impacts and Mitigation Measures identifies,
predicts and evaluates impacts of the project activities during the Construction and
Operation stages and deals with the measures (including mitigation cost) proposed to
mitigate Potential Environmental Impacts of the project.
Section 7: Environmental Management and Monitoring Plan outlines institutional
arrangements for the implementation of the proposed mitigation measures, training
needs of the staff for implementation of the mitigation measures, monitoring
requirements, monitoring cost etc.
Section 8: Conclusions and Recommendations summarize findings of the study and
present its conclusions and recommendations.
35. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-1
July, 2016
SECTION – 2
POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
2.0 GENERAL
This chapter deals with the relevant policy, legal and administrative frameworks
instituted by the Government of Pakistan (GoP) and Government of Sindh (GoS) for
the protection of the environment. All the relevant provisions of these policies and
legal frameworks have been duly considered in this EIA study.
2.1 LEGAL FRAMEWORK
GoS has promulgated laws/acts, regulations and standards for the protection,
conservation, rehabilitation and improvement of the environment. In addition to this,
they have also developed environmental assessment procedures governing
developmental projects. Following are the excerpts of these laws and procedures
relevant to the proposed project.
2.1.1 Sindh Environmental Protection Agency (Review of IEE /EIA Regulations,
2014
The Sindh Environmental Protection Agency review of IEE)/EIA Regulations, 2014
provide the necessary details on the preparation, submission and review of the IEE
and the EIA. The regulation classifies projects on the basis of expected degree of
adverse environmental impacts and lists them in two separate schedules. Schedule-I
lists projects that may not have significant environmental impacts and therefore
require an IEE. Schedule-II lists projects of potentially significant environmental
impacts requiring preparation of an EIA.
2.1.2 Pakistan Environmental Assessment Procedures, 1997
Pakistan Environmental Assessment Procedures (1997) is in fact a package which
contains the following sets of information relevant to the proposed project:
a) Policy and Procedures for Filing, Review and Approval of Environmental
Assessment Reports.
36. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-2
July, 2016
It describes environmental policy and administrative procedures to be followed for
filing of environmental examination/assessment reports by the proponents and their
review and approval by the concerned environmental protection agencies.
b) Guidelines for the Preparation and Review of Environmental Reports
These guidelines are developed to facilitate both the proponents and decision
makers to prepare reports (inclusive of all the information contained therein) and
carry out their review so as to take informed decisions.
c) National Environmental Quality Standards (NEQS), 2010
Pakistan Environmental Protection Council (PEPC) first approved these standards in
1993. They were later revised in 1995, 2000 and 2010. They furnish information on
the permissible limits for discharges of municipal and industrial effluent parameters
and industrial gaseous emissions in order to control environmental pollution.
2.1.3 Sindh Environmental Protection Act, 2014
Legislative assembly of Sindh province of Pakistan passed the bill on 24th
February,
2014 to enact Sindh Environmental Protection Act 2014. The Act envisages
protection, improvement, conservation and rehabilitation of environment of Sindh
with the help of legal action against polluters. The Act is the basic legislative tool
that empowers the government to frame regulations to protect the environment. It
broadly applies to air, water, soil, and noise pollution.
Under this Act no project including construction activities or any change in the
existing physical environment can commence unless the fulfillment of prerequisite
to IEE or EIA has been conducted and its approval obtained from the Responsible
Authority, in the present case from Sindh EPA. It equally lays emphasis for the
preservation of the natural resources of Sindh and to adopt ways and means for
restoring the balance in its eco-system by avoiding all types of environmental
hazards.
2.1.4 Sindh EPA (Review of IEE/EIA) Regulations, 2014
The Sindh Environmental Protection Agency (Review of EIA/IEE) Regulations 2014
define Schedules (I & II) of projects falling under the requirement of IEE or EIA taken
account of the requirements of the Sindh Environmental Protection Agency (Review
of EIA/IEE) Regulations 2014 which define Schedules (I & II) as follows:
Schedule I: A project falls in Schedule (I) if it is likely to have adverse environmental
impacts, but of lesser degree or significance than those for category ‘A’ and all the
37. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-3
July, 2016
mitigation measures to handle the impacts are manageable. Such types of projects
need IEE report including EMP.
Schedule II: Projects are categorized in Schedule (II) if they generate significant
adverse environmental impacts that require a comprehensive management plan or if
the project is located within or passes through: a) Areas declared by the Government
of Pakistan as environmentally sensitive (National Parks/Sanctuaries/Game
Reserve), b) Areas of International significance (e.g. protected wetland as designated
by the Ramsar Convention), or c) Areas designated by the United Nations
Educational, Scientific, and Cultural Organization (UNESCO) as cultural heritage
sites.
According to Sindh Environmental Protection Agency Regulation, 2014, a proponent
of a project falling in any category listed in Schedule II shall file an EIA with the Sindh
Environmental Protection Agency, since the listed projects are generally major
projects and have the potential to affect a large number of people.
The proposed project falls under category J (Other Projects) of Schedule II, which
requires EIA before commencement of construction.
2.2 SINDH ENVIRONMENTAL QUALITY STANDARDS (SEQS), 2016
Sindh Environmental Protection Council (SEPC) first approved the SEQS in 2014.
The standards were later revised in 2016 and furnish information on the permissible
limits for discharges of municipal and industrial effluent parameters and industrial
gaseous emissions in order to control environmental pollution.
2.2.1 Air Quality Standards
In pursuance of the statutory requirement under Clause (g) of sub-section (1) of
section (6) of the Sindh Environmental Protection Act, 2014, the Sindh Environmental
Protection Agency with prior approval of the Sindh Environmental Protection Council,
has published the SEQS for Ambient Air (amended) 2016, which are given in Table
2.1.
38. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-4
July, 2016
Table 2.1: Ambient Air Quality Standards
# Pollutant
SEQS
Time-Weighted
average
Concentration standard
1 SO2
Annual average 80 µg/m
3
24 hours 120 µg/m
3
2 NO
Annual average 40 µg/m
3
24 hours 40 µg/m
3
3 NO2
Annual average 40 µg/m
3
24 hours 80 µg/m
3
4 O3
1 hour 130 µg/m
3
- -
5
Suspended
Particulate
Matters (SPM)
Annual average 360µg/m
3
24 hours 500 µg/m
3
6 PM10
Annual average 120 µg/m
3
24 hours 150 µg/m
3
7 PM2.5
Annual average 15 µg/m
3
24 hours 35 µg/m
3
1 hour 15 µg/m
3
8 Lead
Annual average 1 µg/m
3
24 hours 1.5 µg/m
3
9 CO
8 hours 5 mg/m
3
1 hour 10 mg/m
3
SEQS= Sindh Environmental Quality Standards
2.2.2 Noise Quality Standards
In pursuance of the statutory requirement under clause (g) of sub-section (1) of
section (6) of the Sindh Environmental Protection Act, 2014, the Sindh Environmental
Protection Agency with prior approval of the Sindh Environmental Protection Council,
has published the SEQS for Noise (2015). These standards are established for the
four different categories which include residential area, commercial area, industrial
area and silent zone. These standards vary according to the day and night timing;
day time hours are 6:00 am to 10:00 pm and night time hours are 10:00 pm to 6:00
am. Sindh Environmental Quality Standards for Noise effective from January, 2015
are used for bench marking purpose and given in Table 2.2.
Table 2.2: Noise Quality Standards
# Category of Area
SEQS
(dBA)
Day Time Night Time
1 Residential Area 65 50
2 Commercial Area 70 60
3 Industrial Area 80 75
4 Silence Zone 55 45
39. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-5
July, 2016
2.2.3 Drinking Water and Wastewater Quality Standards
In pursuance of the statutory requirement under clause (g) of sub-section (1) of
section (6) of the Sindh Environmental Protection Act, 2014 the Sindh Environmental
Protection Agency with prior approval of the Sindh Environmental Protection Council,
has published the National Standards for Drinking Water Quality, domestic Sewerage
and wastewater effluent.(2016).
Table 2.3: SEQS for Drinking Water Quality
Sr.No. Parameters
Concentration Standards
SEQS
(mg/L)
Chemical Parameters
1 Aluminum (Al) < 0.2
2 Ammonium (NH3) -
3 Antimony (Sb) < 0.005
4 Arsenic (As) < 0.05
5 Barium (Ba) 0.7
6 Boron (B) 0.3
7 Cadmium (Cd) 0.01
8 Chloride (Cl) < 250
9 Chromium (Cr) < 0.05
10 Copper (Cu) 2
11 Cyanide (CN) < 0.05
12 Fluoride (F) < 1.5
13 Iron (Fe) -
14 Lead (Pb) < 0.05
15 Manganese (Mn) < 0.5
16 Mercury (Hg) < 0.001
17 Molybdenum (Mo) -
18 Nickel (Ni) < 0.02
19 Nitrate (NO3) < 50
20 Nitrite (NO2) < 3
21 Selenium (Se) 0.01
22 Silver (Ag) -
23 Sodium (Na) -
24 Sulphate (So3) -
25 Residual Chlorine 0.2-0.5
26 Zinc (Zn) 5.0
40. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-6
July, 2016
Sr.No. Parameters
Concentration Standards
SEQS
(mg/L)
Physical Parameters
27 Color < 15 TCU
28 Taste Non Objectionable/ Acceptable
29 Odour Non Objectionable/ Acceptable
30 Turbidity < 5 NTU
31 Total hardness < 500 mg/l
32 TDS < 1000
33 pH 6.5-8.5
Biological Parameters
34 E-Coli Must not be detectable in any 100 ml sample
35 Total Coliforms Must not be detectable in any 100 ml sample
Table 2.4: SEQS for municipal &Liquid Industrial Effluents (mg/l)
Sr.
No.
Parameter Into
Inland
Waters
Into
sewage
Treatment
Into Sea
1 Temperature 40
0
C or Temperature
increase*
≤3
o
C ≤3
o
C ≤3
o
C
2 pH value (H*) 6-9 6-9 6-9
3 Biochemical Oxygen Demand (BOD)5
at 20
o
C
80 250 80**
4 Chemical Oxygen Demand (COD) 150 400 400
5 Total Suspended Solids (TSS) 200 400 200
6 Total Dissolved Solids (TDS) 3500 3500 3500
7 Oil and Grease 10 10 10
8 Phenolic compounds (as phenol) 0.1 0.3 0.3
9 Chloride (as CT) 1000 1000 SC***
10 Fluoride (as F) 10 10 10
11 Cyanide (as CN) total 1.0 1.0 1.0
12 An-ionic detergents (as MBAS) 20 20 20
13 Sulphate (S04
2
) 600 1000 SC***
14 Sulphate (S
2
) 1.0 1.0 1.0
15 Ammonia 40 40 40
16 Pesticides 0.15 0.15 0.15
17 Cadmium 0.1 0.1 0.1
18 Chromium (trivalent and hexavalent) 1.0 1.0 1.0
19 Cooper 1.0 1.0 1.0
20 Lead 0.5 0.5 0.5
21 Mercury 0.01 0.01 0.01
41. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-7
July, 2016
22 Selenium 0.5 0.5 0.5
23 Nickel 1.0 1.0 1.0
24 Silver 1.0 1.0 1.0
25 Total toxic metals 2.0 2.0 2.0
26 Zinc 5.0 5.0 5.0
27 Arsenic 1.0 1.0 1.0
28 Barium 1.5 1.5 1.5
29 Iron 8.0 8.0 8.0
30 Manganese 1.5 1.5 1.5
31 Boron 6.0 6.0 6.0
32 Chlorine 1.0 1.0 1.0
2.3 OTHER RELEVANT LAWS
2.3.1 Canal and Drainage Act, 1873
This Act entails provisions for the prevention of pollution of natural or man-made water
bodies.
2.3.2 The Forestry Act 1927
The Forestry Act 1927 provides rules and regulations for the protection of forests,
control of timber and other forest-produce transit, village forest and social forestry.
This act has been comprehensively formed and provides concerned agency the
power to declare protected and reserved forests by government notification, powers
entitled to forest settlement officers, power to acquire land over which right was
claimed, powers to stop ways and water-courses in reserved forests, healing of
claims relating to shifting cultivation, power to issue and publish notification to
reserve trees, power to make rules for protected forests, power to declare forest no
longer reserved, order on rights of pasture or transit forest-produce, record keeping
by the forest settlement officer, commutation of right to appeal, time limit for
resolution of claims and appeals, notification of acts prohibited in such forests
(unlawful cutting of trees) and awarding penalties on violations.
2.3.3 Provincial Wildlife (Protection, Preservation, Conservation and
Management) Acts, Ordinances and Rules (Act, 1972)
The Act empowers provincial wildlife departments for the creation of three classes of
special protected areas: national parks, wildlife sanctuaries, and game reserves. It
classifies wildlife by degree of protection, i.e, animals that may be hunted on a permit
or special license, and species that are protected and cannot be hunted under any
circumstances.
42. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-8
July, 2016
2.3.4 Sindh Wildlife Protection Act, 1974
Sindh Provincial Assembly passed the “Sindh Wildlife Protection Act” in 1974. The
Act provides protection, conservation, preservation and management of wildlife and
is applicable on entire areas of Sindh.
The Act regulates the issuance and validity of licenses and permits to public or
V.I.Ps, trapping or shooting near Game Reserves or Sanctuaries, empowering the
government officers to warranting, seizure or inspection of any person or hunting
equipment at any given time, prohibition of cooking of wild animals/birds meat in any
public place, as well as providing a set of fee structure for various permits including
hunting, trapping, possession or import and export of wild animals/birds.
2.3.5 Pakistan Penal Code, 1860
This defines the penalties for violations concerning pollution of air, water bodies and
land.
2.3.6 Pakistan Explosives Act, 1884
This Act provides regulations for the handling, transportation and use of explosives
during quarrying, blasting and other purposes.
2.3.7 Antiquities Act, 1975
The Antiquities Act of 1975 is designed to protect antiquities from destruction, theft,
negligence, unlawful excavation, trade, export and other cultural resources in
Pakistan. The act defines antiquities as ancient products of human activity, historical
sites, or sites of anthropological or cultural interest, national monuments, etc. The law
prohibits new developments in the proximity of a protected antiquity and empowers
the Government of Pakistan to prohibit excavation in any area that may contain such
articles of archaeological significance. Under the Act, the project proponents are
obligated to ensure that no activity is undertaken within 61 m (200 ft) of a protected
antiquity, and to report to the Department of Archaeology, Government of Pakistan
any archaeological discovery made during the course of the project.
2.3.8 Pakistan Clean Air Program
The Pakistan Clean Air Program (PCAP) is an initiative of the Pakistan
Environmental Protection Agency (Pak-EPA) to comprehensively address the air
quality issue in the country. Key elements of the PCAP include an Air Quality
Monitoring Program, Air Quality Indicators, Research Program, Air Quality Resource
43. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-9
July, 2016
Centre, Regulatory Measures, Economic Instruments, Emissions Inventory, Air
Dispersion Models, and Air Quality Abatement Technology Clearing House.
The objectives of the program are to: Protect and enhance the quality of the country’s
air resources; Protect public health and welfare against any actual or potential
adverse effects that may reasonably be anticipated to accrue from air pollution;
Preserve, protect, and enhance the air quality in urban areas and the countryside
and in areas of natural, recreational, scenic, cultural, or historic value, in particular,
the protected areas of the country, i.e., national parks, wildlife sanctuaries, game
reserves, and national monuments.
Ensure that economic growth will occur in a manner consistent with the preservation
of existing clean air resources; Assure that emissions from any source in any
province do not interfere with pollution prevention programs in any other province;
and Assure that Pakistan’s international obligations regarding the trans-boundary
effects of air pollution are met.
2.3.9 Pakistan Guidelines for Public Consultation, (October 1997)
These guidelines deal with possible approaches to public consultation and
techniques for designing an effective program of consultation that reaches out to all
major stakeholders and ensures the incorporation of their concerns in any impact
assessment study. These guidelines cover: Consultation, involvement and
participation of stakeholders; Effective public consultation (planning, stages of EIA
where consultation is appropriate); and Facilitation involvement (including the poor,
women and Non-Governmental Organizations (NGOs).
2.3.10 Cutting of Trees Act, 1975
This Act prohibits cutting or chopping of trees without permission of the Forest
Department. The act presents fine or imprisonment or both, for illegal cutting of tree
but has not mentioned any compensatory afforestation. However, it’s a common
practice to plant 7-10 trees for compensation of 1 tree to be rooted up.
2.3.11 Hazardous Substance Rules, 2003
These Rules make provisions for the granting of licences for the collection, treatment,
storage, importation, transportation, etc. of hazardous substances.
They consist of 22 Rules and 5 Schedules. Substances prescribed as hazardous
substances are listed in Schedule I. An Environmental Impact Assessment (EIA) of
44. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-10
July, 2016
the project involving hazardous substances shall accompany the application to obtain
a licence (Rule 5).
Rules 7 and 8 deal with the issuance of licences, along with the conditions and
requirements of obtaining licensees. Packaging and labelling provisions are outlined
in Rule 9. General safety precautions and precautions for workers are covered in
Rules 11 and 12, respectively. Provisions on the validity, renewal and cancellation of
licences are set out in Rules 13-15, respectively. Authorized staff of the Federal
Agency/Provincial Agency is entitled to enter and inspect the premises in which
hazardous substances are generated, collected, treated, disposed of, stored etc.
(Rule 16).
Safety plans and waste management plans shall be submitted to the Provincial
Agency (Rules 17-19). Details to be provided for the application to licences for the
importation and transportation of hazardous substances are given in Rules 20 and
21, respectively.
2.3.12 Disaster Management Act, 2010
This act declares the establishment of Pakistan's multi-tiered system for disaster
management.
The act is divided into eleven sections:
- Section 01 defines the terms used in the act, such as 'disaster' and 'disaster
management';
- Section 02 declares the establishment of the National Disaster Management
Commission, and explains its structure and responsibilities;
- Section 03 declares the establishment of a Provincial Disaster Management
Commission for each province, and explains its structure and responsibilities;
- Section 04 declares the establishment of a District Disaster Management
Authority for each district, and explains its structure and responsibilities;
- Section 05 explains the various measures that the government is prepared to
take for the purpose of disaster management;
- Section 06 explains the functions of local authorities in terms of disaster
management;
- Section 07 declares the establishment of the National Institute of Disaster
Management, and explains the Institute's responsibilities in research and training;
- Section 08 declares the establishment of a National Disaster Response Force for
more specialized management of disaster events;
45. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-11
July, 2016
- Section 09 explains how the sources of funding the government use to finance
the new disaster management projects;
- Section 10 warns of the punishments for those who abuse the disaster
management system; and
- Section 11 discusses other important factors of the disaster management
projects, such as a policy against discrimination and a plan for developing an
annual disaster management report.
2.3.13 Seismic Building Code of Pakistan, 2007
The objective of the provisions described in this code is to prescribe the minimum
requirements for the earthquake design and construction of buildings and building-
like structures and/or their components subjected to earthquake ground motions.
2.3.14 Land Acquisition Act, 1894
The Pakistani law governing land acquisition is the Land Acquisition Act (LAA) of
1894 and successive amendments. The LAA regulates the land acquisition process
and enables the provincial government to acquire private land for public purposes.
Land acquisition is a provincial responsibility and provinces have also their own
province specific implementation rules like Punjab and Sindh Land Acquisition Rules,
1983. The LAA and its Implementation Rules require that, following an impact
identification and valuation exercise, land and crops are compensated in cash at the
current market rate to titled landowners. The LAA mandates that land valuation is to
be based on the last 3 to 5 years average registered land-sale rates.
2.3.15 Occupational Health, Labor Laws (Amended) Ordinance, 1972
Construction and operational activities can affect the occupational health of the
workers. Quantitative national standards with respect to the above aspect are yet to
be developed in Pakistan. However, guidance in qualitative terms can be obtained
from the Labor Laws (Amended) Ordinance, 1972.
2.3.16 Toxic Or Hazardous Waste, Pakistan Penal Code (PPC), 1860.
Environment Protection Agency, Sindh
Protection of the environment with regards to toxic and hazardous waste is covered
by the Pakistan Penal Code (PPC), 1860. Environment Protection Agency, Sindh, is
mandated to monitor the transportation of hazardous materials within the provincial
limits.
46. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-12
July, 2016
2. 3.17 Preservation of Cultural Heritage, The Antiquities Act, 1975,
The Antiquities Act, 1975, administered by the Provincial Government, is aimed at
safeguarding the preservation of cultural heritage, destruction, damage or
defacement of antiquities is an offence under the Act.
2.4 POLICY FRAMEWORK
The Federal and Provincial Ministries dealing with the Environment are responsible
authorities for policy making on environmental protection in Pakistan and respective
provinces.
2.4.1 National Environment Policy, 2005
In March 2005, the GOP launched its National Environmental Policy, which provides
an overarching framework for addressing the environmental issues. Section 5 of the
policy commits for integration of environment into development planning as
instrument for achieving the objectives of National Environmental Policy. It further
states in clause (b) of subsection 5.1 that EIA related provisions of Environmental
Protection Act, 1997, shall be diligently enforced for all development projects. It also
provides broad guidelines to the federal government, provincial governments,
federally administered territories and local governments to address their
environmental concerns and to ensure effective management of their environmental
resources.
2.4.2 National Resettlement Policy, 2002
In March, 2002 Pakistan Environmental Protection Agency (PEPA), GoP issued its
National Resettlement Policy, which explains the basis for compensation,
rehabilitation and relocation of the affectees. It also explains the requirements and
implementation of Resettlement Action Plan (RAP). The Policy still is in the draft form
and has not yet passed Cabinet approval.
2.4.3 National Power Policy, 2013
The Ministry of Water and Power of the Government of Pakistan has developed an
ambitious power policy to support the current and future energy needs of the country.
This bold strategy has been developed to set Pakistan on a trajectory of rapid
economic growth and social development. Simultaneously, it addresses the key
challenges of the power sector in order to provide much needed relief to the citizens
of Pakistan. This policy has been designed to frame the broad contours of the energy
47. Section–2 Policy, Legal and Administrative Framework
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 2-13
July, 2016
policy articulating the vision for the power sector, highlighting its key challenges,
setting major goals, summarizing policy principles, and highlighting the strategy
devised to achieve Pakistan’s aspirations. The policy does not elaborate on issues
surrounding operational strategy, nor does it lay out detailed implementation plans.
The process of policy and strategy formulation is informed by the following organizing
principles:
a) Efficiency;
b) Competition; and
c) Sustainability.
2.5 ADMINISTRATIVE FRAMEWORK
2.5.1 Port Qasim Authority (PQA)
The project falls under administration of Port Qasim Authority (PQA). The
management of PQA will ensure that all the proposed measures are effectively
implemented at the design and construction stages. PQA will be responsible for the
operation and maintenance.
2.5.2 Sindh Environmental Protection Agency (SEPA)
Sindh Environmental Protection Council is the apex inter-ministerial and multi-
stakeholders decision-making body, which is headed by the Chief Minister. While
Sindh Environmental Protection Agency is meant for the enforcement of
environmental laws in Sindh, it has powers to review, approval and monitoring of
environmental examination/assessment projects. As regards the proposed Project,
Sindh EPA shall be responsible for reviewing the report, issuing No Objection
Certificate (NOC) and overall/broad-based monitoring of the proposed project
activities.
48. Section–3 Description of the Project
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-1
July 2016
SECTION –3
DESCRIPTION OF THE PROJECT
3.1 RATIONALE OF THE PROJECT
The total power generation in the country, after completion of Chashma Hydro Power
Plant, stands at 15,746 MW as per information from National Transmission and
Dispatch Company Limited (NTDCL). Current deficit of power supply is around 7000
MW which results in load shedding throughout the country.
The future power demand for Pakistan is projected through National Power System
Expansion Plan which provides load forecast. The future demand, even with a low
growth scenario, in years 2019-20 and 2029-30 is estimated as 42,612 MW and
82,457 MW respectively. The situation is, therefore, alarming and needs an
immediate and efficient solution. The GoP is working to attract investment of
adequate quantum into the power generation platform.
Coal, being considered as an economical power generation source, is seen as a
major source for fuelling power generation plants. Coal fired power generation, based
on imported coal, at supercritical and pulverized coal is a viable option for meeting
future demand.
However, necessary infrastructure for efficient transportation of bulk coal cargoes
does not exist in Pakistan. The proposed project will provide an important link in the
establishment of coal transportation infrastructure. The project derives its need from
being an integral part of imported coal based power projects.
Port Qasim is Pakistan’s main deep sea port located on the coastline of the Arabian
Sea. Port Qasim is the second largest port of Pakistan that handles 45% of national
cargo.
Port Qasim Authority (PQA) does not have any dedicated coal handling facility at
present. However, limited quantity of coal is being handled at Marginal Wharf Berths.
Pakistan Steel is handling coal for its own use through Iron Ore and Coal Berth
(IOCB). A new facility is being developed at PIBT for handling coal, clinker & cement
49. Section–3 Description of the Project
EIA of Coal Conveying System - Port Qasim, Karachi
NESPAK Page 3-2
July 2016
up to 12.0 Million tonnes per annum (MTPA). The locations of the above mentioned
facilities are shown in Figure 3.1.
3.2 EXISTING COAL HANDLING FACILITIES AT PORT QASIM
3.2.1 Marginal Wharf Berth Facility
Marginal Wharf berths 1 to 4 have shallow draft (up to 9m) and as such, only small
vessels of 25,000 to 35,000 DWT can be berthed. No facility is available to transport
the coal to existing railway siding located to the north of the Marginal Wharf Berths 1
to 4.
The coal from Marginal Wharf is transported to a temporary stock pile located in
Term Storage Area-A&B of Port Operation Zone. From the stock piles, the coal is
being transported to up-country through trucks and railway.
However, due to low draft and non-availability of requisite equipment, coal cargo
handling capacity at Marginal Wharf is constrained and bulk handling cannot take
place.
3.2.2 Iron Ore and Coal Berth (IOCB)
Ships up to 50,000 DWT can be berthed at the Iron Ore and Coal Berth. This berth
can handle cargo of up to 3.03 MTPA with ship to shore un-loaders of 1,000 tonnes /
hr. The Coal from IOCB is transported to Steel Mill Plant through 3.9 km long belt
conveyor.
Bulk handling facility of IOCB can be made available after necessary repair and
maintenance for coal handling. However, IOCB cannot be considered for the coal
unloading terminal of this project because of the on-going privatization process of
Pakistan Steel Mills.
3.2.3 Pakistan International Bulk Terminal (PIBT)
A dedicated terminal is being constructed at Port Qasim to handle coal, clinker and
cement by M/s. PIBT on BOT Basis. Under the present Implementation Agreement,
PIBT will handle cargo including coal, up to 8.0 MTPA. However, PIBT has plans to
expand its terminal for handling cargo up to 12.0 MTPA. In the backup area of the
terminal, 1.0 million tonnes of coal can be stacked.
50. pJIO.l!Cf'!
CONVEYING SYSTEM FROM PIBT COAL
TERMINAL TO EXISTING RAILWAY NETMJRK
AT PORT QASIM
PORT QASIM AUTHORITY