Dragline Planning
Dragline setup
Highwall Crest
Highwall Toe
Lowwall berm
Lowwall Crest
Lowwall Toe
Coal edge
KEY
Spoil Toe
Spoil
Cable boat
DL Cable
LV Park up
Direction of dig
DL boom radius + 30m
DL boom radius
Exclusion zone
BLOCK
TOP OF COALDe coaled
area
Call up Sign
Dragline Specifications – Marion 8200
Dragline Planning Process
1. It starts with Review of the recons of the previous strips considering the
below points.
• Dragline performance in the last strip – Prime, Rehandle, KPIs.
• Geological conditions – model variations with actual survey.
• Geological disturbances – faults, folds, intrusions, etc.
• Geotechnical structures – joint planes, highwall & lowwall stability,
failures, if any.
• Water management – low points, sump & pump locations.
• Drill and blast access.
• Coal access.
• Light vehicle access & cable access.
• Cable interactions.
• Dragline dig sequence.
• Spoil fit issues.
• Floor treatment – Ex. Floor blasting, Tuff push, etc
• Dragline entry and exit into the pit.
• Cast profiles.
Dragline Planning Process
2. Review the Geo-technical design parameters for highwall and lowwall for
angles and identify the potential areas of concerns. The general profile of
the dragline is as shown below.
TOPO Dragline designPrime
10m
10m
370
700
Presplit highwall
Highwall angle
HWC
HWT
CE LWT
LWC ST
SC
ST
370
Lowwall angle Spoil angle
SPOIL
Lowwall berm
SC
Max dump height=45m
Max dig depth=45m
Dragline horizon
HWC – Highwall Crest
HWT – Highwall Toe
CE – Coal Edge
LWT – Lowwall Toe
LWC – Lowwall Crest
ST – Spoil Toe
SC – Spoil Crest
LEGEND
Dragline Planning Process
2. Take the coal edge from the previous strip on floor of coal and offset it by 3m
and then normalise the line. If seam thick ness is more than 5m then reduce
the offset distance. As the seam thickness is 10m in this mine, so there is no
offset from the floor Coal edge. Hence normalise the coal edge line to get rid
of all the kinks in the line before projecting up to lowwall crest.
Coal edge line on Floor of Coal – As indicated by Survey
3m-Offset
Normalised line
without many kinks
Project this line
Project this line with Lowwall batter angle to a certain RL initially, may be 100m
high from the current coal edge RL. Then create a triangle surface (call
LW_37Batter) with these two lines to generate the Lowwall batter profile,
which will be used later to create Lowwall Toe & Crest lines.
PLAN SECTION
HWT-FloorofCoal
Coaledge-FOC
Offsetline-normalised
ProjectedtocertainRL
370
LW batter angle
Highwall Toe line on FOC- mostly taken from the medium term designs
Strip width=60m
Dragline Planning Process
3. Project the highwall Toe to the current Topo with the highwall batter angle. The
highwall batter angle is recommended by the Geo-tech analysis with a minimum
factor of safety 1.2. In a highly faulted areas, it is recommended to have a softwall
batter of 45 degrees rather than a presplit wall with 65 or 70 degree batter. Do the
same for endwall.
4. As the dragline exposes to top of coal so create the highwall toe line on TOC
and also take the coal edge line of the previous strip on the lowwall side from the
actual survey. Create the contours of the top of coal within this polygon.
SECTION
HWT
HWCHWC
CE
TOPO
Softwall – 450
Presplit wall – 650 to 700
CE
Previous strip
highwall
Dragline Planning Process
5. Offset the Coal edge line on TOC by 50m towards lowwall and create a triangle
using CE-TOC and offset line which will intersect with the lowwall batter profile
created earlier. The intersection of these two triangles will give you the lowwall toe
line.
HWC
HWT - TOC
TOC Contours
CE - TOC
CE - FOC
CE – TOC – Offset by 50m
Triangle with CE-TOC and 50m offset line
Triangle with CE-TOC and 50m offset line
Lowwall batter profile
SECTION
HWC
HWT - TOC
CE - TOC
CE - FOC
CE – TOC – Offset by 50m
Triangle with line-1 & 2 (Surface-2)
LWT Line
Intersection between Surface -1 & 2 will
give the Lowwall Toe line.
Lowwall
Toe
1 2
Section line
Dragline Planning Process
SECTION
HWC
HWT - TOC
CE - TOC
CE - FOC
LWT
Project the HWT-TOC line 90
degrees at a distance equal to
max dig depth of DL = 45m
Offset this line by 200m towards lowwall
Triangle surface with line-1 & 2 (Surface-2)
1 2
Intersection between Surface -1 & 2 will
give the Lowwall Crest line.
Lowwall
Crest
6. To create the lowwall crest line, project the Highwall Toe line at 90 degrees
vertical to an height equal to maximum dig depth of the dragline which is 45m in
this case and offset it by 200m towards lowwall. Generate the triangle with these
two lines and create an intersection line between this triangle and lowwall batter
profile to give you the lowwall crest line.
Dragline Planning Process
7. Then the remaining portion of the design process is to create the spoil.
1. Offset the lowwall crest line by 10m towards lowwall (which is the lowwall berm width,
it is different for different mines as recommended by the geo-tech analysis) which is
the spoil toe line.
2. Project this line at Spoil batter angle (which is 37 degrees – natural angle of repose,
this is also given by Geo-tech) to the maximum dump height of the dragline which is
45m in this case which gives the spoil crest line.
3. Then offset this line by 10m towards lowwall to give you the flat top of spoil &
4. Project down at 37 degrees to the topo to complete the design.
SECTION
HWC
TOPO
CE
HWT
LWC
ST
SC SC
ST
LWT
1
2
3
4
Sample Dragline design
HWC
HWT - TOC
CE - TOC
LWT
LWC
ST
SC
SC
ST
SOFTWALL – 450
HIGHWALL BATTER PRESPLIT WALL – 700
HIGHWALL BATTER
LOWEST
POINT
Create the triangle file from the design and find out the prime and spoil volumes
for each block to do the spoil balance.
At this stage get the Geo-tech approval of the design before start working on
sections and 3d-dig for the sequence and schedule.
● The dragline horizon in this cross section can be calculated using the following
formula:
𝑆𝑝𝑜𝑖𝑙 𝐴𝑟𝑒𝑎
1.25
÷ 𝑆𝑡𝑟𝑖𝑝 𝑊𝑖𝑑𝑡ℎ = 𝐷𝑟𝑎𝑔𝑙𝑖𝑛𝑒 𝐻𝑜𝑟𝑖𝑧𝑜𝑛
Dragline horizon - Volumes
Dragline Horizon
Strip Width
Spoil Area
Pre-strip
A
B
A = Prime = Topo – Design surface (find out for each block, this is in bcm)
B = Spoil = Design surface – Topo
(find out for each block, this is in lcm. Divide by swell to convert to bcm)
Spoil Balance
Fill the spoil balance sheet with Prime, Spoil room, Top of coal RLs, Seam dips,
Highwall, Lowwall batters, lowwall berm width, Spoil strike lengths, etc. Which
populates the spoil fit condition in each block. Then play with the Key, elevated
and double elevated bench elevations to make the spoil to fit. Sample sheet is
shown below.
Based on the bench
elevations decide the
sequence of digging and
ramp locations between the
benches. Think of the cable
and LV access all the time.
Range Diagrams
Based on the spoil balance sheet, cut the sections in each block for every 100m
to find out the approximate cast volumes, dozer push volumes, dragline prime
and rehandle volumes. As this is based on the 2D plane, it is difficult to predict
the rehandles in cases like rolling the bridges and crossing the central ramps,
etc.
Range Diagrams
Range diagrams can be done using different software like Vulcan, Minescape,
Drag sim, etc. A sample range diagram done using Minescape is shown below.
3d-dig – Dig Pack & Schedule
1. Based on spoil balance and Range diagrams adjust the lowwall crest elevations for the
design and build the new spoil from this changed lowwall crest line.
2. Export the Pre dig DTM with Pre-strip removed, dragline design, Coal seam roof & floor
into DXF format and then import all of them into 3d-dig.
3. Create the approximate blast profile in 3d-dig from the sections and blast the material
with the historical swell factor of the area and then start digging using dragline with a
dig swell of 5%.
4. Follow the sequence discussed during the spoil balance step and finish the dig.
5. Export the volumes (lcm) from 3d-dig and convert them to bcm to make a schedule with
the given dragline KPIs. Supply the schedule to the medium term scheduler.
EP07 - DL Micro Schedule 17-Mar-16
Blocks Design Extra
Volume Delay D N D N D N D N D N D N D N D
17 17 18 18 19 19 20 20 21 21 22 22 23 23 24
DL Walk in to the main pass dig2,734,192 2,734,192 0 - 1 0 0.0 17-Mar AM 17-Mar AM 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 WALK 0 0 - 1 0 1.0 1.0 17-Mar AM 17-Mar PM 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 13 KEY 82,017 82,017 2,200 9.41 1 41,387 4.0 17-Mar PM 19-Mar AM 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0
DE01 12 KEY 115,026 115,026 2,200 9.41 1 41,387 5.6 19-Mar AM 22-Mar AM 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0
DE01 11 KEY 18,309 18,309 2,200 9.41 1 41,387 0.9 22-Mar AM 22-Mar PM 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0
DE01 11 KEY 119,942 119,942 2,200 9.41 1 41,387 5.8 22-Mar PM 25-Mar PM 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1
DE01 10 KEY 61,154 61,154 2,200 9.41 1 41,387 3.0 25-Mar PM 27-Mar AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 WALK - 0 0 - 1 0 1.0 1.0 27-Mar AM 27-Mar PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 13 BLKS 60,987 60,987 2,400 9.41 1 45,149 2.7 27-Mar PM 28-Mar PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 12 BLKS 115,214 115,214 2,400 9.41 1 45,149 5.1 28-Mar PM 31-Mar AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 11 BLKS 179,376 179,376 2,400 9.41 1 45,149 7.9 31-Mar AM 4-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 10 BLKS 20,205 20,205 2,400 9.41 1 45,149 0.9 4-Apr AM 4-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 9 OHAND 29,035 29,035 2,200 9.41 1 41,387 1.4 4-Apr PM 5-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 10 OHAND 64,959 64,959 2,200 9.41 1 41,387 3.1 5-Apr PM 7-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 WALK - 0 0 - 1 0 1.0 1.0 7-Apr AM 7-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 10 KEY 70,976 70,976 2,200 9.41 1 41,387 3.4 7-Apr PM 9-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 9 KEY 120,140 120,140 2,200 9.41 1 41,387 5.8 9-Apr AM 12-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 8 KEY 124,754 124,754 2,200 9.41 1 41,387 6.0 12-Apr AM 15-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 7 KEY 27,548 27,548 2,200 9.41 1 41,387 1.3 15-Apr AM 15-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 WALK - 0 0 - 1 0 1.0 1.0 15-Apr PM 16-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 10 BLKS 158,808 158,808 2,400 9.41 1 45,149 7.0 16-Apr AM 19-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 9 BLKS 175,458 175,458 2,400 9.41 1 45,149 7.8 19-Apr PM 23-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 8 BLKS 64,493 64,493 2,400 9.41 1 45,149 2.9 23-Apr PM 25-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 DELAY - 0 0 - 1 0 0.5 0.5 25-Apr AM 25-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 7 KEY 142,541 142,541 2,200 9.41 1 41,387 6.9 25-Apr PM 28-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 6 KEY 93,369 93,369 2,200 9.41 1 41,387 4.5 28-Apr PM 1-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 6 OHAND 8,711 8,711 2,200 9.41 1 41,387 0.4 1-May AM 1-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 5 OHAND 56,735 56,735 2,200 9.41 1 41,387 2.7 1-May AM 2-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 4 OHAND 79,089 79,089 2,200 9.41 1 41,387 3.8 2-May PM 4-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 DELAY - 0 0 - 1 0 0.5 0.5 4-May PM 4-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 4 KEY 98,412 98,412 2,200 9.41 1 41,387 4.8 4-May PM 7-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 5 KEY 157,313 157,313 2,200 9.41 1 41,387 7.6 7-May AM 11-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 6 KEY 61,187 61,187 2,200 9.41 1 41,387 3.0 11-May AM 12-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 WALK - 0 0 - 1 0 1.0 1.0 12-May PM 13-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 8 BLKS 54,428 54,428 2,400 9.41 1 45,149 2.4 13-May AM 14-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 7 BLKS 106,578 106,578 2,400 9.41 1 45,149 4.7 14-May AM 16-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 6 BLKS 150,998 150,998 2,400 9.41 1 45,149 6.7 16-May PM 20-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
DE01 5 BLKS 116,430 116,430 2,400 9.41 1 45,149 5.2 20-May AM 22-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
S S M
Week-12
bcm/day
Duration
(Shifts)
Start date End date
T FType
(K/T/B)
Left
Vol.(bcm)
Rate
(bcm/hr)
Op.
Hrs/Shift
# Eq.
T W
Wall Plan
1. Prepare a wall plan with all the information showing the plan, sections, volumes, check
list, dig sequence, faults, low spots, coal access and Sign-off. Make copies one for
machine, one for production and one for tech-services. Sample wall plan is given below.
Exporting the design into Titronics
1. Export the design into DXF under ACTIVE layer name.
2. Export the triangle file of the design into DXF with FINAL layer name.
3. Export other lines like block lines, text, chop line, misfires, sump location, etc into DXF
under STATIC layer name.
4. Create a long section line along highwall toe. The RL of this line should be at the lowest
RL of the design. Export this line into DXF with CENTRELINELONG layer name.
5. Create a cross section line in the centre of the design. The RL of the line should be
more than the maximum RL of the design, i.e. this line should be above the design
triangle. Export this line into DXF with CENTRELINECROSS layer name.
6. Open the Leica translator and open the ACTIVE dxf file first. Then overlay all other dxf
files on top of this. Don’t save it as dozer file, if you save it first as dozer file then all the
layers in Leica translator will be copied under one layer and if you create map file after
this then dragline doesn’t distinguish between the different layers. Hence, create a map
file first then create the dozer file.
7. When you create the map file the text becomes horizontal, which will be rectified by
editing the map file in notepad and replace the number besides “P” with the actual
angle read from the design software. The text in the map file will be saved in the last, so
edit for each text with correct text angle and then save.
8. Upload the file into IMS (Titronics) and check with the machine for both plan view and
section view.
Execution of the dig
1. Conduct the pre-dig meeting and discuss the plan with the operators to get
the inputs and sequence modifications.
2. Make pit tour on the first day of each crew start to explain the plan for the
week and any short term changes and sequence modifications and discuss
the alternate options to improve the performance.
3. Take lots of photos and create a diary to record all the events in the dig, which
will be useful for the next dig in the same location for better planning and
execution. Learn from the mistakes you made.
4. Involve the operators in the planning process for the next dig and plan for the
next dig while the current dig is under execution to make the plan more robust
and pool proof.
5. Communicate with the other team members about the progress and share the
experiences.
Things to monitor for dragline to follow
1. Do not rip into coal with dragline teeth.
2. Take assistance of dozer in cleaning the top of coal to minimise
the coal loss.
3. Do not over dig or under cut highwall outside the design limits.
4. Expose the coal edge and lowwall toe without forming the skew-
ramps at the base of the lowwall.
5. Always maintain the lowwall berm as per the design.
6. Follow the bench elevations as indicated in the dig pack.
7. Always maintain the LV access to dragline and away from it.
Reconciliation
1. After the dig is finished, prepare reconciliation sheet comparing the plan Vs
actuals listing
1. KPIs
2. Prime and Rehandle volumes.
3. Coal tonnes & losses.
4. Blasting data.
5. Geo-technical issues.
6. Water management issues.
7. Highwall and lowwall profiles.
8. Major delays.
2. Request drill and blast for the floor treatment, if required.
Thanks…

Weitere ähnliche Inhalte

Was ist angesagt?

In pit crushing and conveying in surface mines
In pit crushing and conveying  in surface minesIn pit crushing and conveying  in surface mines
In pit crushing and conveying in surface minesSafdar Ali
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in miningEder Reyes
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drillpavan kumar
 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)sou_suk_sou
 
Haul road design
Haul road designHaul road design
Haul road designVR M
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesaashutosh chhirolya
 
Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesAnurag Jha
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentationAlex Demidov
 
Armoured face conveyor
Armoured face conveyorArmoured face conveyor
Armoured face conveyorAnkit Narain
 
Blasting concepts (1)
Blasting concepts (1)Blasting concepts (1)
Blasting concepts (1)Safdar Ali
 
Bord Pillar
Bord PillarBord Pillar
Bord PillarVR M
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methodsTayyab Anwar
 
Subsidence control in coal mines
Subsidence control in coal minesSubsidence control in coal mines
Subsidence control in coal minesSunil Varma
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit miningSATYANARAYANA I
 

Was ist angesagt? (20)

In pit crushing and conveying in surface mines
In pit crushing and conveying  in surface minesIn pit crushing and conveying  in surface mines
In pit crushing and conveying in surface mines
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in mining
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drill
 
Pillar design in coal mines
Pillar design in coal minesPillar design in coal mines
Pillar design in coal mines
 
SURFACE MINERS
SURFACE MINERSSURFACE MINERS
SURFACE MINERS
 
Concept of oc mine planning & design(final)
Concept  of oc mine planning & design(final)Concept  of oc mine planning & design(final)
Concept of oc mine planning & design(final)
 
Haul road design
Haul road designHaul road design
Haul road design
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
 
Opencast mining machineries
Opencast mining machineriesOpencast mining machineries
Opencast mining machineries
 
Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast mines
 
depllaring in coal mines
depllaring in coal minesdepllaring in coal mines
depllaring in coal mines
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
 
Armoured face conveyor
Armoured face conveyorArmoured face conveyor
Armoured face conveyor
 
Blasting concepts (1)
Blasting concepts (1)Blasting concepts (1)
Blasting concepts (1)
 
Bord Pillar
Bord PillarBord Pillar
Bord Pillar
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
 
Roof supports in coal mines
Roof supports in coal minesRoof supports in coal mines
Roof supports in coal mines
 
Shovel and Dumper Combinatio by Auqib Javed.pptx
Shovel and Dumper Combinatio by Auqib Javed.pptxShovel and Dumper Combinatio by Auqib Javed.pptx
Shovel and Dumper Combinatio by Auqib Javed.pptx
 
Subsidence control in coal mines
Subsidence control in coal minesSubsidence control in coal mines
Subsidence control in coal mines
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
 

Andere mochten auch

Working with Dragline
Working with DraglineWorking with Dragline
Working with DraglineVR M
 
Dragline exclavator
Dragline exclavatorDragline exclavator
Dragline exclavatorVivek Kumar
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliTauhid Mohammad
 
Excavating Equipments
Excavating EquipmentsExcavating Equipments
Excavating EquipmentsTulsi Makwana
 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Construction Tech. and Mgmt., VNIT Nagpur
 
Mining Methods
Mining MethodsMining Methods
Mining MethodsVR M
 
Shovel excavator
Shovel excavatorShovel excavator
Shovel excavatorathulya cs
 
Bucket wheel excavator
Bucket wheel excavatorBucket wheel excavator
Bucket wheel excavatorVR M
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialVR M
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc minesSATYANARAYANA I
 
Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design FundasVR M
 

Andere mochten auch (20)

Working of dragline
Working of draglineWorking of dragline
Working of dragline
 
Working with Dragline
Working with DraglineWorking with Dragline
Working with Dragline
 
Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)
 
Dragline exclavator
Dragline exclavatorDragline exclavator
Dragline exclavator
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauli
 
Excavating Equipments
Excavating EquipmentsExcavating Equipments
Excavating Equipments
 
Power shovel
Power shovelPower shovel
Power shovel
 
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
Excavators: Power Shovel, Backhoe an Front Shovel (by Faisal VA and Karthik V)
 
Dragline rus
Dragline rusDragline rus
Dragline rus
 
Mining Methods
Mining MethodsMining Methods
Mining Methods
 
Shovel excavator
Shovel excavatorShovel excavator
Shovel excavator
 
types of excavators
types of excavatorstypes of excavators
types of excavators
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
Dlbal
DlbalDlbal
Dlbal
 
Bucket wheel excavator
Bucket wheel excavatorBucket wheel excavator
Bucket wheel excavator
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 
Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
 
Types of excavating tools and machine
Types of excavating tools and machineTypes of excavating tools and machine
Types of excavating tools and machine
 

Ähnlich wie Dragline Planning

Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)John Latilla
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling ManagementMojrian Web
 
Anchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldAnchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldJose V.Taboada
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Rajesh Prasad
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2Tee Joanne
 
Site surveying-report-2
Site surveying-report-2Site surveying-report-2
Site surveying-report-2Shane Ah
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)AMIT PAYAL
 
Design Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisDesign Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisMichael Masi, Jr. Eng.
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverterRidhoIrawan12
 

Ähnlich wie Dragline Planning (20)

Capitulo 02 grupo 01
Capitulo 02 grupo 01Capitulo 02 grupo 01
Capitulo 02 grupo 01
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
 
Training PPT
Training PPTTraining PPT
Training PPT
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling Management
 
Anchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldAnchois 1- Oil&Gas Field
Anchois 1- Oil&Gas Field
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2
 
Site surveying-report-2
Site surveying-report-2Site surveying-report-2
Site surveying-report-2
 
CONTINIOUS BRIDGE.pptx
CONTINIOUS BRIDGE.pptxCONTINIOUS BRIDGE.pptx
CONTINIOUS BRIDGE.pptx
 
ICDE2006, Singapore
ICDE2006, SingaporeICDE2006, Singapore
ICDE2006, Singapore
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Tes p-122.08-r0
Tes p-122.08-r0Tes p-122.08-r0
Tes p-122.08-r0
 
Design Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisDesign Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost Analysis
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
Project 2b (1) (2)
Project 2b  (1) (2)Project 2b  (1) (2)
Project 2b (1) (2)
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 

Mehr von VR M

Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling processVR M
 
Energy - India (11th Plan)
Energy - India (11th Plan)Energy - India (11th Plan)
Energy - India (11th Plan)VR M
 
Methods of extraction in Opencast mine
Methods of extraction in Opencast mineMethods of extraction in Opencast mine
Methods of extraction in Opencast mineVR M
 
Vulcan tutorial 01
Vulcan tutorial 01Vulcan tutorial 01
Vulcan tutorial 01VR M
 
Project Management (PMP Material)
Project Management (PMP Material)Project Management (PMP Material)
Project Management (PMP Material)VR M
 
Bolter miner @ Russia
Bolter miner @ RussiaBolter miner @ Russia
Bolter miner @ RussiaVR M
 
Longwall AFC changing - innovation
Longwall AFC changing - innovationLongwall AFC changing - innovation
Longwall AFC changing - innovationVR M
 
Statutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineStatutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineVR M
 
Top ten in world
Top ten in worldTop ten in world
Top ten in worldVR M
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining TechnologyVR M
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectVR M
 
Mine communication sysetms
Mine communication sysetmsMine communication sysetms
Mine communication sysetmsVR M
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersVR M
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesVR M
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidenceVR M
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road aheadVR M
 
Design of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of RamagundamDesign of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of RamagundamVR M
 
Longwall exp india-expectations
Longwall exp india-expectationsLongwall exp india-expectations
Longwall exp india-expectationsVR M
 
Future Longwalls in India
Future Longwalls in IndiaFuture Longwalls in India
Future Longwalls in IndiaVR M
 
Caving behaviour in Longwall
Caving behaviour in LongwallCaving behaviour in Longwall
Caving behaviour in LongwallVR M
 

Mehr von VR M (20)

Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling process
 
Energy - India (11th Plan)
Energy - India (11th Plan)Energy - India (11th Plan)
Energy - India (11th Plan)
 
Methods of extraction in Opencast mine
Methods of extraction in Opencast mineMethods of extraction in Opencast mine
Methods of extraction in Opencast mine
 
Vulcan tutorial 01
Vulcan tutorial 01Vulcan tutorial 01
Vulcan tutorial 01
 
Project Management (PMP Material)
Project Management (PMP Material)Project Management (PMP Material)
Project Management (PMP Material)
 
Bolter miner @ Russia
Bolter miner @ RussiaBolter miner @ Russia
Bolter miner @ Russia
 
Longwall AFC changing - innovation
Longwall AFC changing - innovationLongwall AFC changing - innovation
Longwall AFC changing - innovation
 
Statutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mineStatutory clearances required to start a greenfield captive opencast coal mine
Statutory clearances required to start a greenfield captive opencast coal mine
 
Top ten in world
Top ten in worldTop ten in world
Top ten in world
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
 
Legal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining projectLegal flow schemes for a greenfield mining project
Legal flow schemes for a greenfield mining project
 
Mine communication sysetms
Mine communication sysetmsMine communication sysetms
Mine communication sysetms
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidence
 
Longwall - The road ahead
Longwall - The road aheadLongwall - The road ahead
Longwall - The road ahead
 
Design of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of RamagundamDesign of Longwall for 2 seam of Ramagundam
Design of Longwall for 2 seam of Ramagundam
 
Longwall exp india-expectations
Longwall exp india-expectationsLongwall exp india-expectations
Longwall exp india-expectations
 
Future Longwalls in India
Future Longwalls in IndiaFuture Longwalls in India
Future Longwalls in India
 
Caving behaviour in Longwall
Caving behaviour in LongwallCaving behaviour in Longwall
Caving behaviour in Longwall
 

Kürzlich hochgeladen

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 

Kürzlich hochgeladen (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 

Dragline Planning

  • 2. Dragline setup Highwall Crest Highwall Toe Lowwall berm Lowwall Crest Lowwall Toe Coal edge KEY Spoil Toe Spoil Cable boat DL Cable LV Park up Direction of dig DL boom radius + 30m DL boom radius Exclusion zone BLOCK TOP OF COALDe coaled area Call up Sign
  • 4. Dragline Planning Process 1. It starts with Review of the recons of the previous strips considering the below points. • Dragline performance in the last strip – Prime, Rehandle, KPIs. • Geological conditions – model variations with actual survey. • Geological disturbances – faults, folds, intrusions, etc. • Geotechnical structures – joint planes, highwall & lowwall stability, failures, if any. • Water management – low points, sump & pump locations. • Drill and blast access. • Coal access. • Light vehicle access & cable access. • Cable interactions. • Dragline dig sequence. • Spoil fit issues. • Floor treatment – Ex. Floor blasting, Tuff push, etc • Dragline entry and exit into the pit. • Cast profiles.
  • 5. Dragline Planning Process 2. Review the Geo-technical design parameters for highwall and lowwall for angles and identify the potential areas of concerns. The general profile of the dragline is as shown below. TOPO Dragline designPrime 10m 10m 370 700 Presplit highwall Highwall angle HWC HWT CE LWT LWC ST SC ST 370 Lowwall angle Spoil angle SPOIL Lowwall berm SC Max dump height=45m Max dig depth=45m Dragline horizon HWC – Highwall Crest HWT – Highwall Toe CE – Coal Edge LWT – Lowwall Toe LWC – Lowwall Crest ST – Spoil Toe SC – Spoil Crest LEGEND
  • 6. Dragline Planning Process 2. Take the coal edge from the previous strip on floor of coal and offset it by 3m and then normalise the line. If seam thick ness is more than 5m then reduce the offset distance. As the seam thickness is 10m in this mine, so there is no offset from the floor Coal edge. Hence normalise the coal edge line to get rid of all the kinks in the line before projecting up to lowwall crest. Coal edge line on Floor of Coal – As indicated by Survey 3m-Offset Normalised line without many kinks Project this line Project this line with Lowwall batter angle to a certain RL initially, may be 100m high from the current coal edge RL. Then create a triangle surface (call LW_37Batter) with these two lines to generate the Lowwall batter profile, which will be used later to create Lowwall Toe & Crest lines. PLAN SECTION HWT-FloorofCoal Coaledge-FOC Offsetline-normalised ProjectedtocertainRL 370 LW batter angle Highwall Toe line on FOC- mostly taken from the medium term designs Strip width=60m
  • 7. Dragline Planning Process 3. Project the highwall Toe to the current Topo with the highwall batter angle. The highwall batter angle is recommended by the Geo-tech analysis with a minimum factor of safety 1.2. In a highly faulted areas, it is recommended to have a softwall batter of 45 degrees rather than a presplit wall with 65 or 70 degree batter. Do the same for endwall. 4. As the dragline exposes to top of coal so create the highwall toe line on TOC and also take the coal edge line of the previous strip on the lowwall side from the actual survey. Create the contours of the top of coal within this polygon. SECTION HWT HWCHWC CE TOPO Softwall – 450 Presplit wall – 650 to 700 CE Previous strip highwall
  • 8. Dragline Planning Process 5. Offset the Coal edge line on TOC by 50m towards lowwall and create a triangle using CE-TOC and offset line which will intersect with the lowwall batter profile created earlier. The intersection of these two triangles will give you the lowwall toe line. HWC HWT - TOC TOC Contours CE - TOC CE - FOC CE – TOC – Offset by 50m Triangle with CE-TOC and 50m offset line Triangle with CE-TOC and 50m offset line Lowwall batter profile SECTION HWC HWT - TOC CE - TOC CE - FOC CE – TOC – Offset by 50m Triangle with line-1 & 2 (Surface-2) LWT Line Intersection between Surface -1 & 2 will give the Lowwall Toe line. Lowwall Toe 1 2 Section line
  • 9. Dragline Planning Process SECTION HWC HWT - TOC CE - TOC CE - FOC LWT Project the HWT-TOC line 90 degrees at a distance equal to max dig depth of DL = 45m Offset this line by 200m towards lowwall Triangle surface with line-1 & 2 (Surface-2) 1 2 Intersection between Surface -1 & 2 will give the Lowwall Crest line. Lowwall Crest 6. To create the lowwall crest line, project the Highwall Toe line at 90 degrees vertical to an height equal to maximum dig depth of the dragline which is 45m in this case and offset it by 200m towards lowwall. Generate the triangle with these two lines and create an intersection line between this triangle and lowwall batter profile to give you the lowwall crest line.
  • 10. Dragline Planning Process 7. Then the remaining portion of the design process is to create the spoil. 1. Offset the lowwall crest line by 10m towards lowwall (which is the lowwall berm width, it is different for different mines as recommended by the geo-tech analysis) which is the spoil toe line. 2. Project this line at Spoil batter angle (which is 37 degrees – natural angle of repose, this is also given by Geo-tech) to the maximum dump height of the dragline which is 45m in this case which gives the spoil crest line. 3. Then offset this line by 10m towards lowwall to give you the flat top of spoil & 4. Project down at 37 degrees to the topo to complete the design. SECTION HWC TOPO CE HWT LWC ST SC SC ST LWT 1 2 3 4
  • 11. Sample Dragline design HWC HWT - TOC CE - TOC LWT LWC ST SC SC ST SOFTWALL – 450 HIGHWALL BATTER PRESPLIT WALL – 700 HIGHWALL BATTER LOWEST POINT Create the triangle file from the design and find out the prime and spoil volumes for each block to do the spoil balance. At this stage get the Geo-tech approval of the design before start working on sections and 3d-dig for the sequence and schedule.
  • 12. ● The dragline horizon in this cross section can be calculated using the following formula: 𝑆𝑝𝑜𝑖𝑙 𝐴𝑟𝑒𝑎 1.25 ÷ 𝑆𝑡𝑟𝑖𝑝 𝑊𝑖𝑑𝑡ℎ = 𝐷𝑟𝑎𝑔𝑙𝑖𝑛𝑒 𝐻𝑜𝑟𝑖𝑧𝑜𝑛 Dragline horizon - Volumes Dragline Horizon Strip Width Spoil Area Pre-strip A B A = Prime = Topo – Design surface (find out for each block, this is in bcm) B = Spoil = Design surface – Topo (find out for each block, this is in lcm. Divide by swell to convert to bcm)
  • 13. Spoil Balance Fill the spoil balance sheet with Prime, Spoil room, Top of coal RLs, Seam dips, Highwall, Lowwall batters, lowwall berm width, Spoil strike lengths, etc. Which populates the spoil fit condition in each block. Then play with the Key, elevated and double elevated bench elevations to make the spoil to fit. Sample sheet is shown below. Based on the bench elevations decide the sequence of digging and ramp locations between the benches. Think of the cable and LV access all the time.
  • 14. Range Diagrams Based on the spoil balance sheet, cut the sections in each block for every 100m to find out the approximate cast volumes, dozer push volumes, dragline prime and rehandle volumes. As this is based on the 2D plane, it is difficult to predict the rehandles in cases like rolling the bridges and crossing the central ramps, etc.
  • 15. Range Diagrams Range diagrams can be done using different software like Vulcan, Minescape, Drag sim, etc. A sample range diagram done using Minescape is shown below.
  • 16. 3d-dig – Dig Pack & Schedule 1. Based on spoil balance and Range diagrams adjust the lowwall crest elevations for the design and build the new spoil from this changed lowwall crest line. 2. Export the Pre dig DTM with Pre-strip removed, dragline design, Coal seam roof & floor into DXF format and then import all of them into 3d-dig. 3. Create the approximate blast profile in 3d-dig from the sections and blast the material with the historical swell factor of the area and then start digging using dragline with a dig swell of 5%. 4. Follow the sequence discussed during the spoil balance step and finish the dig. 5. Export the volumes (lcm) from 3d-dig and convert them to bcm to make a schedule with the given dragline KPIs. Supply the schedule to the medium term scheduler. EP07 - DL Micro Schedule 17-Mar-16 Blocks Design Extra Volume Delay D N D N D N D N D N D N D N D 17 17 18 18 19 19 20 20 21 21 22 22 23 23 24 DL Walk in to the main pass dig2,734,192 2,734,192 0 - 1 0 0.0 17-Mar AM 17-Mar AM 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 WALK 0 0 - 1 0 1.0 1.0 17-Mar AM 17-Mar PM 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 13 KEY 82,017 82,017 2,200 9.41 1 41,387 4.0 17-Mar PM 19-Mar AM 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 DE01 12 KEY 115,026 115,026 2,200 9.41 1 41,387 5.6 19-Mar AM 22-Mar AM 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 DE01 11 KEY 18,309 18,309 2,200 9.41 1 41,387 0.9 22-Mar AM 22-Mar PM 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 DE01 11 KEY 119,942 119,942 2,200 9.41 1 41,387 5.8 22-Mar PM 25-Mar PM 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 DE01 10 KEY 61,154 61,154 2,200 9.41 1 41,387 3.0 25-Mar PM 27-Mar AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 WALK - 0 0 - 1 0 1.0 1.0 27-Mar AM 27-Mar PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 13 BLKS 60,987 60,987 2,400 9.41 1 45,149 2.7 27-Mar PM 28-Mar PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 12 BLKS 115,214 115,214 2,400 9.41 1 45,149 5.1 28-Mar PM 31-Mar AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 11 BLKS 179,376 179,376 2,400 9.41 1 45,149 7.9 31-Mar AM 4-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 10 BLKS 20,205 20,205 2,400 9.41 1 45,149 0.9 4-Apr AM 4-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 9 OHAND 29,035 29,035 2,200 9.41 1 41,387 1.4 4-Apr PM 5-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 10 OHAND 64,959 64,959 2,200 9.41 1 41,387 3.1 5-Apr PM 7-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 WALK - 0 0 - 1 0 1.0 1.0 7-Apr AM 7-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 10 KEY 70,976 70,976 2,200 9.41 1 41,387 3.4 7-Apr PM 9-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 9 KEY 120,140 120,140 2,200 9.41 1 41,387 5.8 9-Apr AM 12-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 8 KEY 124,754 124,754 2,200 9.41 1 41,387 6.0 12-Apr AM 15-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 7 KEY 27,548 27,548 2,200 9.41 1 41,387 1.3 15-Apr AM 15-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 WALK - 0 0 - 1 0 1.0 1.0 15-Apr PM 16-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 10 BLKS 158,808 158,808 2,400 9.41 1 45,149 7.0 16-Apr AM 19-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 9 BLKS 175,458 175,458 2,400 9.41 1 45,149 7.8 19-Apr PM 23-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 8 BLKS 64,493 64,493 2,400 9.41 1 45,149 2.9 23-Apr PM 25-Apr AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 DELAY - 0 0 - 1 0 0.5 0.5 25-Apr AM 25-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 7 KEY 142,541 142,541 2,200 9.41 1 41,387 6.9 25-Apr PM 28-Apr PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 6 KEY 93,369 93,369 2,200 9.41 1 41,387 4.5 28-Apr PM 1-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 6 OHAND 8,711 8,711 2,200 9.41 1 41,387 0.4 1-May AM 1-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 5 OHAND 56,735 56,735 2,200 9.41 1 41,387 2.7 1-May AM 2-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 4 OHAND 79,089 79,089 2,200 9.41 1 41,387 3.8 2-May PM 4-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 DELAY - 0 0 - 1 0 0.5 0.5 4-May PM 4-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 4 KEY 98,412 98,412 2,200 9.41 1 41,387 4.8 4-May PM 7-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 5 KEY 157,313 157,313 2,200 9.41 1 41,387 7.6 7-May AM 11-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 6 KEY 61,187 61,187 2,200 9.41 1 41,387 3.0 11-May AM 12-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 WALK - 0 0 - 1 0 1.0 1.0 12-May PM 13-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 8 BLKS 54,428 54,428 2,400 9.41 1 45,149 2.4 13-May AM 14-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 7 BLKS 106,578 106,578 2,400 9.41 1 45,149 4.7 14-May AM 16-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 6 BLKS 150,998 150,998 2,400 9.41 1 45,149 6.7 16-May PM 20-May AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 DE01 5 BLKS 116,430 116,430 2,400 9.41 1 45,149 5.2 20-May AM 22-May PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 S S M Week-12 bcm/day Duration (Shifts) Start date End date T FType (K/T/B) Left Vol.(bcm) Rate (bcm/hr) Op. Hrs/Shift # Eq. T W
  • 17. Wall Plan 1. Prepare a wall plan with all the information showing the plan, sections, volumes, check list, dig sequence, faults, low spots, coal access and Sign-off. Make copies one for machine, one for production and one for tech-services. Sample wall plan is given below.
  • 18. Exporting the design into Titronics 1. Export the design into DXF under ACTIVE layer name. 2. Export the triangle file of the design into DXF with FINAL layer name. 3. Export other lines like block lines, text, chop line, misfires, sump location, etc into DXF under STATIC layer name. 4. Create a long section line along highwall toe. The RL of this line should be at the lowest RL of the design. Export this line into DXF with CENTRELINELONG layer name. 5. Create a cross section line in the centre of the design. The RL of the line should be more than the maximum RL of the design, i.e. this line should be above the design triangle. Export this line into DXF with CENTRELINECROSS layer name. 6. Open the Leica translator and open the ACTIVE dxf file first. Then overlay all other dxf files on top of this. Don’t save it as dozer file, if you save it first as dozer file then all the layers in Leica translator will be copied under one layer and if you create map file after this then dragline doesn’t distinguish between the different layers. Hence, create a map file first then create the dozer file. 7. When you create the map file the text becomes horizontal, which will be rectified by editing the map file in notepad and replace the number besides “P” with the actual angle read from the design software. The text in the map file will be saved in the last, so edit for each text with correct text angle and then save. 8. Upload the file into IMS (Titronics) and check with the machine for both plan view and section view.
  • 19. Execution of the dig 1. Conduct the pre-dig meeting and discuss the plan with the operators to get the inputs and sequence modifications. 2. Make pit tour on the first day of each crew start to explain the plan for the week and any short term changes and sequence modifications and discuss the alternate options to improve the performance. 3. Take lots of photos and create a diary to record all the events in the dig, which will be useful for the next dig in the same location for better planning and execution. Learn from the mistakes you made. 4. Involve the operators in the planning process for the next dig and plan for the next dig while the current dig is under execution to make the plan more robust and pool proof. 5. Communicate with the other team members about the progress and share the experiences.
  • 20. Things to monitor for dragline to follow 1. Do not rip into coal with dragline teeth. 2. Take assistance of dozer in cleaning the top of coal to minimise the coal loss. 3. Do not over dig or under cut highwall outside the design limits. 4. Expose the coal edge and lowwall toe without forming the skew- ramps at the base of the lowwall. 5. Always maintain the lowwall berm as per the design. 6. Follow the bench elevations as indicated in the dig pack. 7. Always maintain the LV access to dragline and away from it.
  • 21. Reconciliation 1. After the dig is finished, prepare reconciliation sheet comparing the plan Vs actuals listing 1. KPIs 2. Prime and Rehandle volumes. 3. Coal tonnes & losses. 4. Blasting data. 5. Geo-technical issues. 6. Water management issues. 7. Highwall and lowwall profiles. 8. Major delays. 2. Request drill and blast for the floor treatment, if required.