SlideShare a Scribd company logo
1 of 47
 Introduction
 Protection of transformers
 Protection of generators
 Protection of transmission and distribution
lines
 Bus protection
A part of the system protected by a certain protective
scheme is called as protective zone or zone of
protection.
The entire part of a power system is covered by several
protective zones and no part of the system is left
unprotected.
The protective zones are shown in figure.
Overlapping of zones is done to ensure safety of each
element in the system.
Primary Protection –This is the first protection to act. This is
responsible to protect power system element from all types of
faults .If primary protection fails, then back up protection comes
into action and removes the faulty part from healthy system.
Backup Protection- This protection comes into action when primary
protection fails.
If due to some reason (such as fault in CT,PT,trip circuit etc.) the
primary protection fails to operate, there should be additional
protection to take care of fault otherwise the fault will not be
cleared and may damage the equipments .
The maintenance and testing work is carried on primary protection
system. Then primary protection is not operative due to
maintenance work. Then back up protection acts as main
protection.
If fault occurs beyond C region ,Circuit breaker of C region operates
as primary protection.
In the meanwhile relays at B and A may also start operating.
They ar given time lag.
If breaker at C does not operate then after 0.6 seconds breaker at B
will operate and act as backup protection.
Breaker at A will operate if breaker at B fails to operate.
In this way back up protection is provided.
 When earth current flows through earth return path,
the fault is called earth fault. The earth faults are
frequent. So earth fault protection is important.
 Residual Earth Fault Relay:
 When earth fault does not take place, the sum of three
secondary currents of CT is zero i.e. IR +IY+IB =0
 The sum of all these currents is called residual current.
When earth fault develops, the sum of three currents is
not zero, the residual current flows through earth fault
relay.
 This protection is also called unrestricted earth fault
protection.
It consists of a domed vessel. There are two mercury switches.
The upper mercury switch is attached to a float. The lower
mercury switch is attached to a flap and the mechanism is
hinged as shown in figure.
Alarm contacts are brought to upper mercury switch and trip
contacts are brought to lower mercury switch.
The upper mercury switch operates during incipient(less sever
faults like overloads) faults and the lower mercury switch
operates in case of severe faults.
When the fault current flows through earth return path, the
fault is called earth fault. The earth faults are frequent.
So earth fault protection is important.
Residual earth fault relay-
When earth fault does not take place, the sum of the three
currents of CT is zero.
IR+IY+IB=0
The sum of these currents is called residual current. When
earth fault develops, the sum of three currents is not
zero, the residual current flows through earth fault
relay.
This protection is also called unrestricted earth fault
protection. In other scheme, the relay is connected in the
neutral wire of the transformer.
RESIDUAL EARTH FAULT
RELAY
RELAY IN NEUTRAL
WIRE
This scheme is used for multi
turn alternators.
For multi turn alternators, the
winding of each phase is
divided into two equal
sections (S1 and S2) as
shown in figure.
Two identical CTs are connected
in respective windings. The
CT secondary are connected
in phase opposition and a
relay R is connected in CT
secondary loop.
Distance protection scheme uses distance relay. The relay
operation is based on the impedance (or
distance)between the relay and point of fault. This
scheme of protection does not require any pilot wire.
The voltage element of impedance receives supply from
PT secondary and current element receives supply
from CT secondary.
Bus bar Protection by Over Current Relays
Protection
Protection
Protection
Protection
Protection

More Related Content

What's hot

Current Transformer and Potential Transformer
Current Transformer and Potential TransformerCurrent Transformer and Potential Transformer
Current Transformer and Potential TransformerRidwanul Hoque
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Rahul Ruddra
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protectionSaifUrrehman183
 
Alternator protection
Alternator protectionAlternator protection
Alternator protectionjawaharramaya
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Protective relay
Protective relay Protective relay
Protective relay Uday Wankar
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Transformer protection
Transformer protectionTransformer protection
Transformer protectionjawaharramaya
 
Tripping and control of impulse generators
Tripping and control of impulse generatorsTripping and control of impulse generators
Tripping and control of impulse generatorsFariza Zahari
 
Power System Protection Technique: A Review
Power System Protection Technique: A ReviewPower System Protection Technique: A Review
Power System Protection Technique: A Reviewsahid raja khan
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptxMuhd Hafizi Idris
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars PremanandDesai
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)Rohini Haridas
 

What's hot (20)

Current Transformer and Potential Transformer
Current Transformer and Potential TransformerCurrent Transformer and Potential Transformer
Current Transformer and Potential Transformer
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
BREAKDOWN IN GASES
BREAKDOWN IN GASESBREAKDOWN IN GASES
BREAKDOWN IN GASES
 
distance relay
distance relaydistance relay
distance relay
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Protective relay
Protective relay Protective relay
Protective relay
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Thyristor
ThyristorThyristor
Thyristor
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
 
Protective relaying
Protective relayingProtective relaying
Protective relaying
 
Tripping and control of impulse generators
Tripping and control of impulse generatorsTripping and control of impulse generators
Tripping and control of impulse generators
 
Power System Protection Technique: A Review
Power System Protection Technique: A ReviewPower System Protection Technique: A Review
Power System Protection Technique: A Review
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)
 
Relays
RelaysRelays
Relays
 

Viewers also liked

KoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloud
KoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloudKoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloud
KoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloudTobias Koprowski
 
Primry & backup protection
Primry & backup protectionPrimry & backup protection
Primry & backup protectionqasmi100
 
ELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYAmeen San
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load CharacteristicsAmeen San
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 
Basic electrical comp upload1
Basic electrical comp upload1Basic electrical comp upload1
Basic electrical comp upload1Ganesh Kumar
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the LightningAmeen San
 
Electrical components 8
Electrical components 8Electrical components 8
Electrical components 8RIFFAT_ZAHID
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Distance Relay:->Mho relay
Distance Relay:->Mho relayDistance Relay:->Mho relay
Distance Relay:->Mho relaymohan_K_M
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Kamran Gillani
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarBhushan Kumbhalkar
 
protection and relay scheme
protection and relay schemeprotection and relay scheme
protection and relay schemeinfosaneeshss
 
Power system protection
Power system protectionPower system protection
Power system protectionAnu Priya
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protectionBinit Das
 
Hume Discover - Adam Hornsey
Hume Discover - Adam HornseyHume Discover - Adam Hornsey
Hume Discover - Adam HornseyPLVNICT
 

Viewers also liked (20)

KoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloud
KoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloudKoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloud
KoprowskiT_SQLRelay2014#5_Newcastle_FromPlanToBackupToCloud
 
Primry & backup protection
Primry & backup protectionPrimry & backup protection
Primry & backup protection
 
ELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGY
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
Types of relay
Types of relayTypes of relay
Types of relay
 
Basic electrical comp upload1
Basic electrical comp upload1Basic electrical comp upload1
Basic electrical comp upload1
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
 
Protection basic
Protection basicProtection basic
Protection basic
 
Electrical components 8
Electrical components 8Electrical components 8
Electrical components 8
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Distance Relay:->Mho relay
Distance Relay:->Mho relayDistance Relay:->Mho relay
Distance Relay:->Mho relay
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)Power System Protection (Primary & Backup)
Power System Protection (Primary & Backup)
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkar
 
protection and relay scheme
protection and relay schemeprotection and relay scheme
protection and relay scheme
 
Power system protection
Power system protectionPower system protection
Power system protection
 
Relay
RelayRelay
Relay
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
Hume Discover - Adam Hornsey
Hume Discover - Adam HornseyHume Discover - Adam Hornsey
Hume Discover - Adam Hornsey
 

Similar to Protection

4_Differential Protection_rar(1).pdf
4_Differential Protection_rar(1).pdf4_Differential Protection_rar(1).pdf
4_Differential Protection_rar(1).pdfLiewChiaPing
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protectionDinesh Sharma
 
Introduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basicsIntroduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basicsMd. Rashedul Islam
 
TOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptxTOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptxMartMantilla1
 
SGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSHIVANICHAUUHAN1
 
Generator Transformer Protections.
Generator Transformer  Protections.Generator Transformer  Protections.
Generator Transformer Protections.Nischal Popat
 
Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...ijtsrd
 
EE6702 Protection and Switchgear
EE6702 Protection and SwitchgearEE6702 Protection and Switchgear
EE6702 Protection and Switchgearrmkceteee
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power systemArvind Nathan
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear johny renoald
 
Power System Faults and Protection System
Power System Faults and Protection SystemPower System Faults and Protection System
Power System Faults and Protection SystemHarshalJain48
 
substation protection basics.ppt
substation protection basics.pptsubstation protection basics.ppt
substation protection basics.pptSalim Palayi
 
Generator protection
Generator protectionGenerator protection
Generator protectionChetan Patil
 
47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptxThien Phan Bản
 
Electrical interview-questions-answers
Electrical interview-questions-answersElectrical interview-questions-answers
Electrical interview-questions-answersRaghavendra Kiran
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptxRahaf Waheep
 
Switchgear and protection 3
Switchgear and protection 3Switchgear and protection 3
Switchgear and protection 3Md Irshad Ahmad
 

Similar to Protection (20)

4_Differential Protection_rar(1).pdf
4_Differential Protection_rar(1).pdf4_Differential Protection_rar(1).pdf
4_Differential Protection_rar(1).pdf
 
PSG UNIT I.pdf
PSG UNIT I.pdfPSG UNIT I.pdf
PSG UNIT I.pdf
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
Introduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basicsIntroduction to system_protection-_protection_basics
Introduction to system_protection-_protection_basics
 
TOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptxTOPIC 6.2- Power System Faults and Protection System.pptx
TOPIC 6.2- Power System Faults and Protection System.pptx
 
SGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptx
 
Generator Transformer Protections.
Generator Transformer  Protections.Generator Transformer  Protections.
Generator Transformer Protections.
 
Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...
 
EE6702 Protection and Switchgear
EE6702 Protection and SwitchgearEE6702 Protection and Switchgear
EE6702 Protection and Switchgear
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power system
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Power System Faults and Protection System
Power System Faults and Protection SystemPower System Faults and Protection System
Power System Faults and Protection System
 
substation protection basics.ppt
substation protection basics.pptsubstation protection basics.ppt
substation protection basics.ppt
 
Generator protection
Generator protectionGenerator protection
Generator protection
 
Neutral grounding
Neutral groundingNeutral grounding
Neutral grounding
 
47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx
 
Electrical interview-questions-answers
Electrical interview-questions-answersElectrical interview-questions-answers
Electrical interview-questions-answers
 
BASIC ELECTRICAL EMERSON EDUARDO RODRIGUES
BASIC ELECTRICAL EMERSON EDUARDO RODRIGUESBASIC ELECTRICAL EMERSON EDUARDO RODRIGUES
BASIC ELECTRICAL EMERSON EDUARDO RODRIGUES
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptx
 
Switchgear and protection 3
Switchgear and protection 3Switchgear and protection 3
Switchgear and protection 3
 

More from Ameen San

Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationAmeen San
 
Stepper motor
Stepper motor Stepper motor
Stepper motor Ameen San
 
PLC application
PLC applicationPLC application
PLC applicationAmeen San
 
PLC arithmatic functions
PLC arithmatic functionsPLC arithmatic functions
PLC arithmatic functionsAmeen San
 
PLC data types and addressing
PLC data types and addressingPLC data types and addressing
PLC data types and addressingAmeen San
 
PLC Counters
PLC CountersPLC Counters
PLC CountersAmeen San
 
PLC Traffic Light Control
PLC Traffic Light ControlPLC Traffic Light Control
PLC Traffic Light ControlAmeen San
 
PLC Internal Relays
PLC Internal RelaysPLC Internal Relays
PLC Internal RelaysAmeen San
 
PLC Intro to programming
PLC Intro to programmingPLC Intro to programming
PLC Intro to programmingAmeen San
 
PLC Logic Circuits
PLC Logic CircuitsPLC Logic Circuits
PLC Logic CircuitsAmeen San
 
PLC input and output devices
PLC input and output devices PLC input and output devices
PLC input and output devices Ameen San
 
PLC Applications
PLC ApplicationsPLC Applications
PLC ApplicationsAmeen San
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit BreakersAmeen San
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering EconomyAmeen San
 
Accounting & financial decisions
Accounting & financial decisionsAccounting & financial decisions
Accounting & financial decisionsAmeen San
 
Ratio analysis
Ratio  analysisRatio  analysis
Ratio analysisAmeen San
 
Depreciation methods
Depreciation methodsDepreciation methods
Depreciation methodsAmeen San
 
Income statement
Income statementIncome statement
Income statementAmeen San
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingAmeen San
 

More from Ameen San (20)

Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
 
Stepper motor
Stepper motor Stepper motor
Stepper motor
 
PLC application
PLC applicationPLC application
PLC application
 
PLC arithmatic functions
PLC arithmatic functionsPLC arithmatic functions
PLC arithmatic functions
 
PLC data types and addressing
PLC data types and addressingPLC data types and addressing
PLC data types and addressing
 
PLC Counters
PLC CountersPLC Counters
PLC Counters
 
PLC Traffic Light Control
PLC Traffic Light ControlPLC Traffic Light Control
PLC Traffic Light Control
 
PLC Timers
PLC TimersPLC Timers
PLC Timers
 
PLC Internal Relays
PLC Internal RelaysPLC Internal Relays
PLC Internal Relays
 
PLC Intro to programming
PLC Intro to programmingPLC Intro to programming
PLC Intro to programming
 
PLC Logic Circuits
PLC Logic CircuitsPLC Logic Circuits
PLC Logic Circuits
 
PLC input and output devices
PLC input and output devices PLC input and output devices
PLC input and output devices
 
PLC Applications
PLC ApplicationsPLC Applications
PLC Applications
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Accounting & financial decisions
Accounting & financial decisionsAccounting & financial decisions
Accounting & financial decisions
 
Ratio analysis
Ratio  analysisRatio  analysis
Ratio analysis
 
Depreciation methods
Depreciation methodsDepreciation methods
Depreciation methods
 
Income statement
Income statementIncome statement
Income statement
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 

Recently uploaded

US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Recently uploaded (20)

US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

Protection

  • 1.
  • 2.  Introduction  Protection of transformers  Protection of generators  Protection of transmission and distribution lines  Bus protection
  • 3.
  • 4. A part of the system protected by a certain protective scheme is called as protective zone or zone of protection. The entire part of a power system is covered by several protective zones and no part of the system is left unprotected. The protective zones are shown in figure. Overlapping of zones is done to ensure safety of each element in the system.
  • 5. Primary Protection –This is the first protection to act. This is responsible to protect power system element from all types of faults .If primary protection fails, then back up protection comes into action and removes the faulty part from healthy system. Backup Protection- This protection comes into action when primary protection fails. If due to some reason (such as fault in CT,PT,trip circuit etc.) the primary protection fails to operate, there should be additional protection to take care of fault otherwise the fault will not be cleared and may damage the equipments . The maintenance and testing work is carried on primary protection system. Then primary protection is not operative due to maintenance work. Then back up protection acts as main protection.
  • 6.
  • 7. If fault occurs beyond C region ,Circuit breaker of C region operates as primary protection. In the meanwhile relays at B and A may also start operating. They ar given time lag. If breaker at C does not operate then after 0.6 seconds breaker at B will operate and act as backup protection. Breaker at A will operate if breaker at B fails to operate. In this way back up protection is provided.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.  When earth current flows through earth return path, the fault is called earth fault. The earth faults are frequent. So earth fault protection is important.  Residual Earth Fault Relay:  When earth fault does not take place, the sum of three secondary currents of CT is zero i.e. IR +IY+IB =0  The sum of all these currents is called residual current. When earth fault develops, the sum of three currents is not zero, the residual current flows through earth fault relay.  This protection is also called unrestricted earth fault protection.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20. It consists of a domed vessel. There are two mercury switches. The upper mercury switch is attached to a float. The lower mercury switch is attached to a flap and the mechanism is hinged as shown in figure. Alarm contacts are brought to upper mercury switch and trip contacts are brought to lower mercury switch. The upper mercury switch operates during incipient(less sever faults like overloads) faults and the lower mercury switch operates in case of severe faults.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26. When the fault current flows through earth return path, the fault is called earth fault. The earth faults are frequent. So earth fault protection is important. Residual earth fault relay- When earth fault does not take place, the sum of the three currents of CT is zero. IR+IY+IB=0 The sum of these currents is called residual current. When earth fault develops, the sum of three currents is not zero, the residual current flows through earth fault relay. This protection is also called unrestricted earth fault protection. In other scheme, the relay is connected in the neutral wire of the transformer.
  • 28.
  • 29.
  • 30. This scheme is used for multi turn alternators. For multi turn alternators, the winding of each phase is divided into two equal sections (S1 and S2) as shown in figure. Two identical CTs are connected in respective windings. The CT secondary are connected in phase opposition and a relay R is connected in CT secondary loop.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38. Distance protection scheme uses distance relay. The relay operation is based on the impedance (or distance)between the relay and point of fault. This scheme of protection does not require any pilot wire. The voltage element of impedance receives supply from PT secondary and current element receives supply from CT secondary.
  • 39.
  • 40.
  • 41.
  • 42. Bus bar Protection by Over Current Relays