SlideShare ist ein Scribd-Unternehmen logo
1 von 38
Downloaden Sie, um offline zu lesen
2/26/2013
1
CHAPTER 2
Load Characteristics
1Dr.A.Arunagiri
2
The load characteristic plays an important role in
 determiningthe totalpowerand energyrequirementsof the system
 planningthe installedcapacityof a powerplant
 selectionof suitablegeneratingcapacityfor eachunit of the plant..
Load Characteristics
Someof the termsin connectionwith the load characteristicsare explained
below
Demand
The demand of a system is the load at the receiving terminals
(usually in kW or kVA) averaged over a suitable specific interval
of time of shortduration. Dr.A.Arunagiri
2/26/2013
2
3
Demand Interval
It is the periodover whichthe load is averaged.
Load Curves of a Generating Station
The totalpowerrequirementof a generationstationcan be estimatedusingthis
curves
Load Curve (or Chronological Load
Curve)
It represents the load in its time sequence. As shown this curve is obtained by
plotting the station load along Y-axis and the time when it occurs along X-axis.
Usually, it is plotted for one day by taking average load based on the time
interval t, which is usually an hour. The area under the curve represents the
totalenergyconsumedby the load in one day.
Dr.A.Arunagiri
4
6AM 12N 6PM 11PM 6AM
15kW
20kW
10kW
5kW
2kW
Time
0 5 11 17 24
15kW
20kW
10kW
5kW
2kW
Time in hr
Load curve Load-duration curve
Load-Duration Curve
It represents the same data (i.e. load versus time) but the ordinates are
rearranged in magnitude sequence (not time sequence). Here, the greatest
load is plotted on the left, lesser load towards the right and the least load
on the extremeright,as Shown.Dr.A.Arunagiri
2/26/2013
3
5
The areas under the load curve and load duration curve are equal and each
represents the total units consumed during a day of 24 hours. The load –
duration curves can be daily, weekly, monthly and annual. Sometimes the
plotsare done in per unit values.
The total load supplied by a generating station is normally divided into
threeparts:
 Base load
 Intermediateload
 Peak load
The base load is the load below which the demand never falls and is
supplied 100% of the time. The peak load occurs for about 15% of the
time. The intermediate load represents the remaining load region in the
load curve.These typesof loadsare shownin the next figure.Dr.A.Arunagiri
6
Base load Base load
Intermediate load
Intermediate load
Peak loadPeak load
Time Time
Load-duration curve
Load curve
Dr.A.Arunagiri
2/26/2013
4
7Dr.A.Arunagiri
Actual Load Curve
8Dr.A.Arunagiri
2/26/2013
5
It is the sum of continuous ratings of all the
equipments connected to supply system.
Connected load
9Dr.A.Arunagiri
Maximum Demand
It is the greatest demand of load on the power
station during a given period.
10Dr.A.Arunagiri
2/26/2013
6
Demand Factor
It is the ratio of maximum demand on the power station to
its connected load
Demand Factor = Maximum Demand
Connected Load
11Dr.A.Arunagiri
The value of demand factor is usually less than 1. It
is expected because maximum demand on the power
station is generally less than the connected load. If
the maximum demand on the power station is 80 MW
and the connected load is 100 MW,
then demand factor = 80/100 = 0.8. The knowledge
of demand factor is vital in determining the capacity
of the plant equipment.
12Dr.A.Arunagiri
2/26/2013
7
Average Load
It is the average of loads occurring on the power
station in a given period (day or month or year) is
known as average load or average demand.
13Dr.A.Arunagiri
14Dr.A.Arunagiri
2/26/2013
8
Load Factor
The ratio of average load to the maximum
demand during a given period is known as
Load Factor
15Dr.A.Arunagiri
Diversity Factor
It is the ratio of sum of individual maximumIt is the ratio of sum of individual maximum
demands to the maximum demand on the powerdemands to the maximum demand on the power
stationstation
16Dr.A.Arunagiri
2/26/2013
9
Capacity Factor
It is the ratio of actual energy produced to the
maximum possible energy that could have been
produced during a given period.
17Dr.A.Arunagiri
18Dr.A.Arunagiri
2/26/2013
10
Plant Use Factor
It is the ratio of KWhr generated to the product of
plant capacity and the number of hours for which the
plant was in operation
19Dr.A.Arunagiri
Load Duration Curve
When the load elements of a load curve are
arranged in the order of descending magnitudes,
the curve thus obtained is called a load duration
curve
20Dr.A.Arunagiri
2/26/2013
11
21Dr.A.Arunagiri
Problem:
1.The maximum demand on power station
is 100 MW . If the annual load factor
is 40%, calculte the total energy
generated in a year.
(Ans:3504*10^5kwhr)
22Dr.A.Arunagiri
2/26/2013
12
2 A generating station has a connected load of
43MW and a maximum demand of 20 MW, the units
generated being 61500000KWhr per annum. Caculate the
(i) the demand factor (0.465)
(ii) the load factor(35.1%)
23Dr.A.Arunagiri
Time Consumer1 Consumer2 Consumer3
12 midnight
to
8 A.M
No load 200W No load
8 A.M to 2 P.M 600W No load 200W
2 P.M to 4
P.M
200W 1000W 1200W
4 P.M to 10
P.M
800W No load No load
10 P.M to
midnight
No load 200W 200W
Thedaily demands of three consumers are given below
24Dr.A.Arunagiri
2/26/2013
13
Plot the load curve and find
(i) load factor of individual consumer
45.8%,16.7%13.8%
(ii) diversity factor(1.25)
(iii) load factor of the station (29.1%)
25Dr.A.Arunagiri
The power station has the following daily load cycle:
Time in
Hours
6 - 8 8-12 12-16 16-20 20-24 24-6
Load in
MW
20 40 60 20 50 20
Plot the load curve and load duration curve also calculate
the energy generated perday (840000kwhr)
26Dr.A.Arunagiri
2/26/2013
14
27
High value of diversity factor means that more consumers
can be supplied for a given station maximum demand and
so lower prices can be offered to consumer. Usually,
domestic load gives higher value of diversity factor than
industrial load.
Example 1
Assume that there are 6 residential consumers
connected to a distribution transformer. The connected
load per consumer is 9.0 kW. The demand factor and
diversity factor of the group of 6 residential consumers
are 0.65 and 1.1 respectively. Calculate the (coincident)
maximum demand on the transformer.
Dr.A.Arunagiri
28
Therefore, maximum demand of each consumer is 9xDFi
= 9x0.65 = 5.85 kW
loadconnectedtotal
consumereachofdemandmaximum
Solution
Demand factor of each consumer, DFi =
loadwholetheofdemandmaximum
demandsmaximumindividualofsum
factorDiversity 
loadwholetheofdemandmaximum
685.5
1.1


Therefore, the maximum demand on the transformer is
5.86x6/1.1 = 31.9 kW
Dr.A.Arunagiri
2/26/2013
15
29
Significance of Load Factor
Load factor is, in fact, an index to the proportion of the
whole time a generator plant or system is being worked to
its full capacity. The generating equipment has to be
selected on the basis of the maximum power demand that
is likely to be imposed on it. However, it seldom happens
that the generating equipment is loaded to its maximum
load during all the 8,760 hours of a year. But whether the
equipment is being worked to its full capacity or not, there
are certain charges (like interest, depreciation, taxes,
insurance, part of staff salaries etc.) which are adding up
continuously. In other word, the equipment is costing
money to its owner whether working or idle. The equipment
earns profit only during those hours when it is fully loaded
and the more it is fully loaded the more is the profit to the
owner. Dr.A.Arunagiri
30
Hence, from the point view of economics it is desirable
to obtain high load factors. If the load factor is poor i.e.
kWh of electrical energy produced is small, then charge
per kWh would obviously be high. But if load factor is
high i.e. the number of kWh generated is large, then cost
of production and hence charge per kWh are reduced
because now the fixed charges are distributed over a
large number of units of energy.
Dr.A.Arunagiri
2/26/2013
16
31
Connected load Factor
This factor relates only to the receiving equipment and
is defined as the ratio of the average power input to the
connected load.
loadconnected
inputpoweraverage
factorloadConnected 
factor)Demand(factor)(Load
loadconnected
demandmax.
demandmax.
inputpoweraverage
factorloadConnected


Dr.A.Arunagiri
32
Example 3
A consumer has the following load-schedule for a day:
From midnight to 6.00a.m. = 200W
From 6.00a.m to 12.00 noon = 3000W
From 12.00 noon to 1.00p.m = 100W
From 1.00p.m to 4.00p.m = 4000W
From 4.00p.m to 9.00p.m = 2000W
From 9.00p.m to midnight = 1000W
Find the load factor.
Solution
2/26/2013
17
33
Example 4
A generating station has a connected load of 43 MW and
a maximum demand of 20 MW. The total annual energy
generated by the station is 61,500,000 kWh (Units).
Calculate the load factor, demand factor and connected
load factor.
Solution
Dr.A.Arunagiri
34
Example 5
A power station has a load cycle as under::
260MW for 6hr; 200MW for 8hr; 160MW for 4hr; 100MW
for 6hr.
If the power station is equipped with 4 generating sets of
75MW each, calculate the load factor and the capacity
factor from the above data.
Solution
Dr.A.Arunagiri
2/26/2013
18
35Dr.A.Arunagiri
Economics of Power
Generation
The art Of determining the per unit (i.e. one kWh) cost of
production of electrical energy is known as economics of
power generation
36Dr.A.Arunagiri
2/26/2013
19
The economics of power generation has
assumed a great importance in this fast
developing power plant engineering. A
consumer will use electric power only if it is
supplied at reasonable rate. Therefore, power
engineers have to find convenient methods to
produce electric power as cheap as possible so
that consumers are tempted to use electrical
methods
37Dr.A.Arunagiri
Definition Of Terms
(i) Interest. The Cost Of Use of money is
known as interest
A power station is constructed by investing
a. huge capital. This money is generally
borrowed from banks or other financial
institutions and the supply company has to
pay the annual interest .
38Dr.A.Arunagiri
2/26/2013
20
Therefore, while calculating the cost of
production of electrical energy, the interest
payable on the capital investment must be
included. The rate of interest depends upon
market position and other factors, and may
vary from 4% to 8% per annum.
39Dr.A.Arunagiri
(ii) Depreciation
The decrease in the value of the power plant
equipment and building due to constant use is
known as depreciation.
40Dr.A.Arunagiri
2/26/2013
21
In actual practice, every power station has a useful
life ranging from fifty to sixty years. From the time
the power station is installed, its equipment steadily
deteriorates due to wear and tear so that there is a
gradual reduction in the value of the plant. This
reduction in the value of plant every year is known as
annual depreciation. Due to depreciation, the plant has
to be replaced by the new one after its useful life.
Therefore, suitable amount must be set aside every
year so that by the time the plant retires, the
collected amount by way of depreciation equals the
cost of replacement.
41Dr.A.Arunagiri
Cost of Electrical Energy
The total cost of electrical energy
generated can be divided into three
parts, namely;
(i) Fixed cost;
(ii) Semi-fixed cost;
(iii) Running or operating cost.
42Dr.A.Arunagiri
2/26/2013
22
Fixed Cost
It is the cost which is independent of maximum
demand and units generated.
43Dr.A.Arunagiri
The fixed cost is due to the annual cost of central
organization, interest on capital cost of land and
salaries of high officials. The annual expenditure on
the central organization and salaries of high officials
is fixed since it has to be met whether the plant has
high or low maximum demand or it generates less or
more units. Further, the capital investment on the
land is fixed and hence the amount of interest is
also fixed.
44Dr.A.Arunagiri
2/26/2013
23
Semi-fixed cost
It is the cost which depends upon maximum demand,
but is independent of units generated.
45Dr.A.Arunagiri
Running cost
It is the cost which depends only upon the
number of units generated.
46Dr.A.Arunagiri
2/26/2013
24
The running cost is on account of annual cost
of fuel, lubricating oil, maintenance, repairs
and salaries of operating staff. Since these
charges depend upon the energy output, the
running cost is directly proportional to the
number of units generated by the station. In
other words, if the power station generates
more units, it will have higher running cost
47Dr.A.Arunagiri
Expressions for Cost of
Electrical Energy
The overall annual cost of electrical energy generated
by a power station can be expressed in two forms ie
three part form and two part form.
48Dr.A.Arunagiri
2/26/2013
25
Three part form
In this method, the overall annual costof
electrical energy generated is divided into
three
parts ie fixed cost, semi-fixed cost and
running cost
49Dr.A.Arunagiri
Total annual cost of energy =
Fixed cost+Semi fixed cost+Running cost
Constant+Proportional to max. demand+Pro­portional to
kWh generated.
RM(a+b kW+c kWh)
50Dr.A.Arunagiri
2/26/2013
26
wherea = annual fixed cost independent of maximum
demand and energy output
b = a constant which when multiplied by maximum
demand on the station gives annual semi fixed cost
c= a constant which when multiplied by KWhr
output per annum gives the annual running cost
51Dr.A.Arunagiri
Two part form
It is sometimes convenient to give the
annual cost of energy in two part form. In this case,
the annual cost of energy is divided into two parts ie a
fixed sum per kW of maximum demand plus a running
charge per unit of energy. The expression for the
annual cost of
energy then becomes
Total annual cost of energy
= RM(A kW+B kWh)
52Dr.A.Arunagiri
2/26/2013
27
where A = a constant which when multiplied by maximum
kW, demand on the station gives the annual cost
of the first part.
B =
53Dr.A.Arunagiri
a constant which when multiplied by KWhr
output per annum gives the annual running cost
PROBLEM
54
A generating station has a maximum demand of 50,000 kW. Calculate the
cost per unit generated from the following data :
Capital cost = SR 95 * 106;
Annual load factor = 40%
Annual cost of fuel and oil = SR 9 ×*106
Taxes, wages and salaries etc. = SR 7·5*× 106
Interest and depreciation = 12% (16 Halala)
Dr.A.Arunagiri
2/26/2013
28
Problem
Dr.A.Arunagiri 55
A generating station has an installed capacity of
50,000 kW and delivers 220 ×10^6units per annum. If
the annual fixed charges are SR 160 per kW installed
capacity and running charges are 4 halala per kWh,
determine the cost per unit generated.(7.64)
Dr.A.Arunagiri 56
2/26/2013
29
Problem
Dr.A.Arunagiri 57
A generating plant has a maximum capacity of 100 kW and costs
SR 1,60,000. The annual fixed charges are 12% consisting of 5%
intererst, 5% depreciation and 2% taxes. Find the fixed charges
per kWh if the load factor is
(i) 100% and (ii) 50%.( HALALA 2.19,4.38)
Problem
Dr.A.Arunagiri 58
Estimate the generating cost per kWh delivered from a
generating station from the following data :
Plant capacity = 50 MW ;Annual load factor = 40%
Capital cost = 12 millions;
annual cost of wages, taxation etc. = Rs 0.4 lmillion;
cost of fuel,lubrication, maintenance etc. = 1·0
halala/kWh generated.
Interest 5% per annum, depreciation 6%per annum of
initial value. (2)
2/26/2013
30
Problem
Dr.A.Arunagiri 59
Dr.A.Arunagiri 60
2/26/2013
31
Load and Loss Factor Relationship
61
While calculating the energy cost the cost of power loss also
must be taken into account.
THERE are two type of losses:
•Fixed Loss ( No load loss)
•Variable loss (Load losses)
Dr.A.Arunagiri
62
No load losses:
Since these are essentially constant , extra generating
equipments must be provided to supply the additional
demand at peak hours. Efficient base –load units(from
hydro capacity , thermal or nuclear) can supply these
losses most of the time. Hence the perunit
demand/energy cost for these is low.
Load Losses:
These losses constitute two losses
Demand loss
Energy loss
Dr.A.Arunagiri
2/26/2013
32
63
Load diversity complicates the evaluation of the demand based
cost of peak load losses. The distribution system peak loading
may not coincide with the total system(generation) peak.
In these losses, the demand cost depends upon peak
responsibility factor(k) which is the ratio of distribution systems
load at the time of total system peak to its peak load. It generally
varies between 0.2 and 0.8 for distribution system and 0.8 and
0.95 for transmission systems.
Dr.A.Arunagiri
Dr.A.Arunagiri 64
If a distribution has P kw loss at its peak load, then k2P
will be the loss at the time of total system peak, the
cost of which is demand based. Therefore k2P kw
losses demand must be provided by the generating
equipments.
2/26/2013
33
Dr.A.Arunagiri 65
For energy based losses the loss factor is important.
It is the ratio of the energy loss in the system during
a given time period to the energy loss that would
result if the system peak loss had persisted
throughout that period.
Load and losses factors relationship:
66
Loss factor = (Load factor)1.732
Or another thumb rule isOne empirical formula is
Loss factor = c (Load factor) + (1-c) (Load factor)2
Where c= 0.3 for transmission system and 0.15 for distribution systems. These two
relations are considered accurate if the minimum demand during the period does
not fall below 0.2 pu of the peak demand.
Dr.A.Arunagiri
One empirical formula is
2/26/2013
34
Dr.A.Arunagiri 67
In case the system load factor Lf Is below 0.8 the following
relation is more accurate:
22
)(273.0 KLLL ffs 
K is the minimum demand in pu of peak demand
Ls is loss factor
Lf is load factor
Total losses per annum = Loss factor* Maximum losses
based on continuous peak current
68
2
8.02.0 ffs LLL 
2
7.03.0 ffs LLL 
2
84.016.0 ffs LLL 
2
8.02.0 ffs LLL 
•In terms of British experience , this the Losses factor fits relationship:
•The Americanexperience gives:
For urban areas
For rural areas
•The Australians use:
Dr.A.Arunagiri
2/26/2013
35
Example
Dr.A.Arunagiri 69
In a power utility the energy consumption per year
is 5000 GWhr with the maximum and minimum
demands of 1000 and 100 MW respectively. Find the
loss factor and the typical empirical relation.
Solution
Dr.A.Arunagiri 70
Yearly load factor = AD/MD = 0.57
K is the minimum demand in pu of peak demand
K = 100/1000=0.10
3852.0
)(273.0 22

 KLLL ffs
Loss factor = c (Load factor) + (1-c) (Load factor)2
0.3852= c (Load factor) + (1-c) (Load factor)2
C=0.25
The empirical relation will be
Loss factor = 0.25(Load factor) + (0.75) (Load factor)2
2/26/2013
36
Load Growth
Dr.A.Arunagiri 71
.
The demand estimation is the starting point for planning
the future electric power supply. The consistency of
demand growth over the years has led to numerous
attempts to fit mathematical curves to this trend. One of
the simplest method is
where a is the average per unit growth rate, P is the
demand in year t, and P0 is
the given demand at year t0.
Definition of some basic concepts in statistics:
Dr.A.Arunagiri 72
n
yi
n
yii

'
n
yi 

2
2
)( 

 


2
exp
)(
]/
2
1
[ 22


y
yf
•Mean value
•Weighted mean
•Variance (standard deviation)
•Normaldistribution
2/26/2013
37
Problem
Dr.A.Arunagiri 73
A 2.5MVAR, 11KV, capacitor bank has been commissioned at a
33/11KV, 10MVA transformersubstationhaving the following data:
33KV line length is 35 KM and conductor resistance is 0.584Ω/KM,
Load factor = 0.65.
Find saving in losses and sparing of system capacity after installation
of the capacitors
Without Capacitors With Capacitors
Peak load 8000KW 8000KW
Voltage 10.4KV 11.4KV
Power Factor 0.846 0.99
Peak current on
11KV
525A 409A
Peak current on
33KV
175A 136.3A
Solution
Dr.A.Arunagiri 74
2/26/2013
38
Dr.A.Arunagiri 75
Dr.A.Arunagiri 76

Weitere ähnliche Inhalte

Was ist angesagt?

Commercial load estimation for electrical
Commercial load estimation for electricalCommercial load estimation for electrical
Commercial load estimation for electricalasmjewel
 
Distribution systems
Distribution systemsDistribution systems
Distribution systemsSURAJ PRASAD
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesRaja Adapa
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomHussain Ali
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parametersfiraoltemesgen1
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power systemPreet_patel
 
EE8701 - HVE - Insulation coordination
EE8701 - HVE - Insulation coordinationEE8701 - HVE - Insulation coordination
EE8701 - HVE - Insulation coordinationKarthikeyanK816516
 
Power quality notes unit 1
Power quality notes unit  1 Power quality notes unit  1
Power quality notes unit 1 Dilip kumar
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curvesGPERI
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakersKabilesh K
 
Power system stability
Power system stabilityPower system stability
Power system stabilityBalaram Das
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal schedulingASHIRBAD BARIK
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power systemBalaram Das
 
Methods of Voltage Control
Methods of Voltage ControlMethods of Voltage Control
Methods of Voltage ControlYashvi Mehta
 

Was ist angesagt? (20)

Commercial load estimation for electrical
Commercial load estimation for electricalCommercial load estimation for electrical
Commercial load estimation for electrical
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission Lines
 
Swing equation
Swing equationSwing equation
Swing equation
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcom
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
Pashen's law
Pashen's lawPashen's law
Pashen's law
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
 
EE8701 - HVE - Insulation coordination
EE8701 - HVE - Insulation coordinationEE8701 - HVE - Insulation coordination
EE8701 - HVE - Insulation coordination
 
Power quality notes unit 1
Power quality notes unit  1 Power quality notes unit  1
Power quality notes unit 1
 
Static var compensator
Static var compensatorStatic var compensator
Static var compensator
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Power system stability
Power system stabilityPower system stability
Power system stability
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
 
An Overview Of Power Quality
An Overview Of Power QualityAn Overview Of Power Quality
An Overview Of Power Quality
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
Methods of Voltage Control
Methods of Voltage ControlMethods of Voltage Control
Methods of Voltage Control
 
Facts controller
Facts controllerFacts controller
Facts controller
 

Andere mochten auch

Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curveCraZzy Shubh
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesAzfar Rasool
 
ELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYAmeen San
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 
Stepper motor
Stepper motor Stepper motor
Stepper motor Ameen San
 
PLC Counters
PLC CountersPLC Counters
PLC CountersAmeen San
 
PLC arithmatic functions
PLC arithmatic functionsPLC arithmatic functions
PLC arithmatic functionsAmeen San
 
PLC application
PLC applicationPLC application
PLC applicationAmeen San
 
Group 7 load forecasting&harmonics final ppt
Group   7 load forecasting&harmonics final pptGroup   7 load forecasting&harmonics final ppt
Group 7 load forecasting&harmonics final pptRahul Sharma
 
Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)
Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)
Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)Mohammad Usman Javed Sial
 
Receiving end circle diagram
Receiving end circle diagram Receiving end circle diagram
Receiving end circle diagram GPERI
 
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkMET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkIbrahim AboKhalil
 
PLC data types and addressing
PLC data types and addressingPLC data types and addressing
PLC data types and addressingAmeen San
 
economics of power generation
economics of power generationeconomics of power generation
economics of power generationjagniyant
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generationAFAQAHMED JAMADAR
 
PLC Traffic Light Control
PLC Traffic Light ControlPLC Traffic Light Control
PLC Traffic Light ControlAmeen San
 
Load Demand Forecasting
Load Demand ForecastingLoad Demand Forecasting
Load Demand ForecastingAman Mehra
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatchDeepak John
 

Andere mochten auch (20)

Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curves
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
 
ELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGY
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
Stepper motor
Stepper motor Stepper motor
Stepper motor
 
PLC Counters
PLC CountersPLC Counters
PLC Counters
 
PLC arithmatic functions
PLC arithmatic functionsPLC arithmatic functions
PLC arithmatic functions
 
PLC application
PLC applicationPLC application
PLC application
 
Group 7 load forecasting&harmonics final ppt
Group   7 load forecasting&harmonics final pptGroup   7 load forecasting&harmonics final ppt
Group 7 load forecasting&harmonics final ppt
 
Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)
Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)
Tutorial solution of Thermal Power station (Principles of power system Vk-Mehta)
 
Receiving end circle diagram
Receiving end circle diagram Receiving end circle diagram
Receiving end circle diagram
 
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkMET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
 
PLC data types and addressing
PLC data types and addressingPLC data types and addressing
PLC data types and addressing
 
economics of power generation
economics of power generationeconomics of power generation
economics of power generation
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
PLC Traffic Light Control
PLC Traffic Light ControlPLC Traffic Light Control
PLC Traffic Light Control
 
Load Demand Forecasting
Load Demand ForecastingLoad Demand Forecasting
Load Demand Forecasting
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
diversity
diversitydiversity
diversity
 

Ähnlich wie Load Characteristics

Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfTheBlank5
 
Economics of Power Generation(3) h.pdf
Economics of Power Generation(3)           h.pdfEconomics of Power Generation(3)           h.pdf
Economics of Power Generation(3) h.pdfMahamad Jawhar
 
SodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptSodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptswathisriranjani1
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxFelcherLayugan
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Power System Operation
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docxArpitaBanik8
 
Load on power system
Load on power systemLoad on power system
Load on power systemv Kalairajan
 
Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelIRJET Journal
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curvesSwapnil Gadgune
 
Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curvesSwapnil Gadgune
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsBalamurugan Subburaj
 
Grid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata PatnaikGrid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata PatnaikDr.Priyabrata Patnaik
 
Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Prof.Nagnath Khandekar
 

Ähnlich wie Load Characteristics (20)

Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Economics of Power Generation(3) h.pdf
Economics of Power Generation(3)           h.pdfEconomics of Power Generation(3)           h.pdf
Economics of Power Generation(3) h.pdf
 
SodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptSodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.ppt
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
 
Ch01-ESR-L01.pdf
Ch01-ESR-L01.pdfCh01-ESR-L01.pdf
Ch01-ESR-L01.pdf
 
Load on power system
Load on power systemLoad on power system
Load on power system
 
load on power system
 load on power system load on power system
load on power system
 
Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curves
 
Copy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdfCopy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdf
 
Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curves
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Ch01-ESR-L02.pdf
Ch01-ESR-L02.pdfCh01-ESR-L02.pdf
Ch01-ESR-L02.pdf
 
EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
 
Grid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata PatnaikGrid integration of renewable energy-Priyabrata Patnaik
Grid integration of renewable energy-Priyabrata Patnaik
 
Ah36200203
Ah36200203Ah36200203
Ah36200203
 
Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration
 

Mehr von Ameen San

PLC Internal Relays
PLC Internal RelaysPLC Internal Relays
PLC Internal RelaysAmeen San
 
PLC Intro to programming
PLC Intro to programmingPLC Intro to programming
PLC Intro to programmingAmeen San
 
PLC Logic Circuits
PLC Logic CircuitsPLC Logic Circuits
PLC Logic CircuitsAmeen San
 
PLC input and output devices
PLC input and output devices PLC input and output devices
PLC input and output devices Ameen San
 
PLC Applications
PLC ApplicationsPLC Applications
PLC ApplicationsAmeen San
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the LightningAmeen San
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit BreakersAmeen San
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering EconomyAmeen San
 
Accounting & financial decisions
Accounting & financial decisionsAccounting & financial decisions
Accounting & financial decisionsAmeen San
 
Ratio analysis
Ratio  analysisRatio  analysis
Ratio analysisAmeen San
 
Depreciation methods
Depreciation methodsDepreciation methods
Depreciation methodsAmeen San
 
Income statement
Income statementIncome statement
Income statementAmeen San
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingAmeen San
 
Time value of money
Time value of moneyTime value of money
Time value of moneyAmeen San
 
Cash flow statement
Cash flow statementCash flow statement
Cash flow statementAmeen San
 
Forms of business organizations
Forms of business organizationsForms of business organizations
Forms of business organizationsAmeen San
 
مهارات الحوار والاقناع
مهارات الحوار والاقناعمهارات الحوار والاقناع
مهارات الحوار والاقناعAmeen San
 

Mehr von Ameen San (20)

PLC Timers
PLC TimersPLC Timers
PLC Timers
 
PLC Internal Relays
PLC Internal RelaysPLC Internal Relays
PLC Internal Relays
 
PLC Intro to programming
PLC Intro to programmingPLC Intro to programming
PLC Intro to programming
 
PLC Logic Circuits
PLC Logic CircuitsPLC Logic Circuits
PLC Logic Circuits
 
PLC input and output devices
PLC input and output devices PLC input and output devices
PLC input and output devices
 
PLC Applications
PLC ApplicationsPLC Applications
PLC Applications
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
 
Protection
ProtectionProtection
Protection
 
Relays
RelaysRelays
Relays
 
Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Accounting & financial decisions
Accounting & financial decisionsAccounting & financial decisions
Accounting & financial decisions
 
Ratio analysis
Ratio  analysisRatio  analysis
Ratio analysis
 
Depreciation methods
Depreciation methodsDepreciation methods
Depreciation methods
 
Income statement
Income statementIncome statement
Income statement
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Time value of money
Time value of moneyTime value of money
Time value of money
 
Cash flow statement
Cash flow statementCash flow statement
Cash flow statement
 
Forms of business organizations
Forms of business organizationsForms of business organizations
Forms of business organizations
 
مهارات الحوار والاقناع
مهارات الحوار والاقناعمهارات الحوار والاقناع
مهارات الحوار والاقناع
 

Kürzlich hochgeladen

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 

Kürzlich hochgeladen (20)

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 

Load Characteristics

  • 1. 2/26/2013 1 CHAPTER 2 Load Characteristics 1Dr.A.Arunagiri 2 The load characteristic plays an important role in  determiningthe totalpowerand energyrequirementsof the system  planningthe installedcapacityof a powerplant  selectionof suitablegeneratingcapacityfor eachunit of the plant.. Load Characteristics Someof the termsin connectionwith the load characteristicsare explained below Demand The demand of a system is the load at the receiving terminals (usually in kW or kVA) averaged over a suitable specific interval of time of shortduration. Dr.A.Arunagiri
  • 2. 2/26/2013 2 3 Demand Interval It is the periodover whichthe load is averaged. Load Curves of a Generating Station The totalpowerrequirementof a generationstationcan be estimatedusingthis curves Load Curve (or Chronological Load Curve) It represents the load in its time sequence. As shown this curve is obtained by plotting the station load along Y-axis and the time when it occurs along X-axis. Usually, it is plotted for one day by taking average load based on the time interval t, which is usually an hour. The area under the curve represents the totalenergyconsumedby the load in one day. Dr.A.Arunagiri 4 6AM 12N 6PM 11PM 6AM 15kW 20kW 10kW 5kW 2kW Time 0 5 11 17 24 15kW 20kW 10kW 5kW 2kW Time in hr Load curve Load-duration curve Load-Duration Curve It represents the same data (i.e. load versus time) but the ordinates are rearranged in magnitude sequence (not time sequence). Here, the greatest load is plotted on the left, lesser load towards the right and the least load on the extremeright,as Shown.Dr.A.Arunagiri
  • 3. 2/26/2013 3 5 The areas under the load curve and load duration curve are equal and each represents the total units consumed during a day of 24 hours. The load – duration curves can be daily, weekly, monthly and annual. Sometimes the plotsare done in per unit values. The total load supplied by a generating station is normally divided into threeparts:  Base load  Intermediateload  Peak load The base load is the load below which the demand never falls and is supplied 100% of the time. The peak load occurs for about 15% of the time. The intermediate load represents the remaining load region in the load curve.These typesof loadsare shownin the next figure.Dr.A.Arunagiri 6 Base load Base load Intermediate load Intermediate load Peak loadPeak load Time Time Load-duration curve Load curve Dr.A.Arunagiri
  • 5. 2/26/2013 5 It is the sum of continuous ratings of all the equipments connected to supply system. Connected load 9Dr.A.Arunagiri Maximum Demand It is the greatest demand of load on the power station during a given period. 10Dr.A.Arunagiri
  • 6. 2/26/2013 6 Demand Factor It is the ratio of maximum demand on the power station to its connected load Demand Factor = Maximum Demand Connected Load 11Dr.A.Arunagiri The value of demand factor is usually less than 1. It is expected because maximum demand on the power station is generally less than the connected load. If the maximum demand on the power station is 80 MW and the connected load is 100 MW, then demand factor = 80/100 = 0.8. The knowledge of demand factor is vital in determining the capacity of the plant equipment. 12Dr.A.Arunagiri
  • 7. 2/26/2013 7 Average Load It is the average of loads occurring on the power station in a given period (day or month or year) is known as average load or average demand. 13Dr.A.Arunagiri 14Dr.A.Arunagiri
  • 8. 2/26/2013 8 Load Factor The ratio of average load to the maximum demand during a given period is known as Load Factor 15Dr.A.Arunagiri Diversity Factor It is the ratio of sum of individual maximumIt is the ratio of sum of individual maximum demands to the maximum demand on the powerdemands to the maximum demand on the power stationstation 16Dr.A.Arunagiri
  • 9. 2/26/2013 9 Capacity Factor It is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period. 17Dr.A.Arunagiri 18Dr.A.Arunagiri
  • 10. 2/26/2013 10 Plant Use Factor It is the ratio of KWhr generated to the product of plant capacity and the number of hours for which the plant was in operation 19Dr.A.Arunagiri Load Duration Curve When the load elements of a load curve are arranged in the order of descending magnitudes, the curve thus obtained is called a load duration curve 20Dr.A.Arunagiri
  • 11. 2/26/2013 11 21Dr.A.Arunagiri Problem: 1.The maximum demand on power station is 100 MW . If the annual load factor is 40%, calculte the total energy generated in a year. (Ans:3504*10^5kwhr) 22Dr.A.Arunagiri
  • 12. 2/26/2013 12 2 A generating station has a connected load of 43MW and a maximum demand of 20 MW, the units generated being 61500000KWhr per annum. Caculate the (i) the demand factor (0.465) (ii) the load factor(35.1%) 23Dr.A.Arunagiri Time Consumer1 Consumer2 Consumer3 12 midnight to 8 A.M No load 200W No load 8 A.M to 2 P.M 600W No load 200W 2 P.M to 4 P.M 200W 1000W 1200W 4 P.M to 10 P.M 800W No load No load 10 P.M to midnight No load 200W 200W Thedaily demands of three consumers are given below 24Dr.A.Arunagiri
  • 13. 2/26/2013 13 Plot the load curve and find (i) load factor of individual consumer 45.8%,16.7%13.8% (ii) diversity factor(1.25) (iii) load factor of the station (29.1%) 25Dr.A.Arunagiri The power station has the following daily load cycle: Time in Hours 6 - 8 8-12 12-16 16-20 20-24 24-6 Load in MW 20 40 60 20 50 20 Plot the load curve and load duration curve also calculate the energy generated perday (840000kwhr) 26Dr.A.Arunagiri
  • 14. 2/26/2013 14 27 High value of diversity factor means that more consumers can be supplied for a given station maximum demand and so lower prices can be offered to consumer. Usually, domestic load gives higher value of diversity factor than industrial load. Example 1 Assume that there are 6 residential consumers connected to a distribution transformer. The connected load per consumer is 9.0 kW. The demand factor and diversity factor of the group of 6 residential consumers are 0.65 and 1.1 respectively. Calculate the (coincident) maximum demand on the transformer. Dr.A.Arunagiri 28 Therefore, maximum demand of each consumer is 9xDFi = 9x0.65 = 5.85 kW loadconnectedtotal consumereachofdemandmaximum Solution Demand factor of each consumer, DFi = loadwholetheofdemandmaximum demandsmaximumindividualofsum factorDiversity  loadwholetheofdemandmaximum 685.5 1.1   Therefore, the maximum demand on the transformer is 5.86x6/1.1 = 31.9 kW Dr.A.Arunagiri
  • 15. 2/26/2013 15 29 Significance of Load Factor Load factor is, in fact, an index to the proportion of the whole time a generator plant or system is being worked to its full capacity. The generating equipment has to be selected on the basis of the maximum power demand that is likely to be imposed on it. However, it seldom happens that the generating equipment is loaded to its maximum load during all the 8,760 hours of a year. But whether the equipment is being worked to its full capacity or not, there are certain charges (like interest, depreciation, taxes, insurance, part of staff salaries etc.) which are adding up continuously. In other word, the equipment is costing money to its owner whether working or idle. The equipment earns profit only during those hours when it is fully loaded and the more it is fully loaded the more is the profit to the owner. Dr.A.Arunagiri 30 Hence, from the point view of economics it is desirable to obtain high load factors. If the load factor is poor i.e. kWh of electrical energy produced is small, then charge per kWh would obviously be high. But if load factor is high i.e. the number of kWh generated is large, then cost of production and hence charge per kWh are reduced because now the fixed charges are distributed over a large number of units of energy. Dr.A.Arunagiri
  • 16. 2/26/2013 16 31 Connected load Factor This factor relates only to the receiving equipment and is defined as the ratio of the average power input to the connected load. loadconnected inputpoweraverage factorloadConnected  factor)Demand(factor)(Load loadconnected demandmax. demandmax. inputpoweraverage factorloadConnected   Dr.A.Arunagiri 32 Example 3 A consumer has the following load-schedule for a day: From midnight to 6.00a.m. = 200W From 6.00a.m to 12.00 noon = 3000W From 12.00 noon to 1.00p.m = 100W From 1.00p.m to 4.00p.m = 4000W From 4.00p.m to 9.00p.m = 2000W From 9.00p.m to midnight = 1000W Find the load factor. Solution
  • 17. 2/26/2013 17 33 Example 4 A generating station has a connected load of 43 MW and a maximum demand of 20 MW. The total annual energy generated by the station is 61,500,000 kWh (Units). Calculate the load factor, demand factor and connected load factor. Solution Dr.A.Arunagiri 34 Example 5 A power station has a load cycle as under:: 260MW for 6hr; 200MW for 8hr; 160MW for 4hr; 100MW for 6hr. If the power station is equipped with 4 generating sets of 75MW each, calculate the load factor and the capacity factor from the above data. Solution Dr.A.Arunagiri
  • 18. 2/26/2013 18 35Dr.A.Arunagiri Economics of Power Generation The art Of determining the per unit (i.e. one kWh) cost of production of electrical energy is known as economics of power generation 36Dr.A.Arunagiri
  • 19. 2/26/2013 19 The economics of power generation has assumed a great importance in this fast developing power plant engineering. A consumer will use electric power only if it is supplied at reasonable rate. Therefore, power engineers have to find convenient methods to produce electric power as cheap as possible so that consumers are tempted to use electrical methods 37Dr.A.Arunagiri Definition Of Terms (i) Interest. The Cost Of Use of money is known as interest A power station is constructed by investing a. huge capital. This money is generally borrowed from banks or other financial institutions and the supply company has to pay the annual interest . 38Dr.A.Arunagiri
  • 20. 2/26/2013 20 Therefore, while calculating the cost of production of electrical energy, the interest payable on the capital investment must be included. The rate of interest depends upon market position and other factors, and may vary from 4% to 8% per annum. 39Dr.A.Arunagiri (ii) Depreciation The decrease in the value of the power plant equipment and building due to constant use is known as depreciation. 40Dr.A.Arunagiri
  • 21. 2/26/2013 21 In actual practice, every power station has a useful life ranging from fifty to sixty years. From the time the power station is installed, its equipment steadily deteriorates due to wear and tear so that there is a gradual reduction in the value of the plant. This reduction in the value of plant every year is known as annual depreciation. Due to depreciation, the plant has to be replaced by the new one after its useful life. Therefore, suitable amount must be set aside every year so that by the time the plant retires, the collected amount by way of depreciation equals the cost of replacement. 41Dr.A.Arunagiri Cost of Electrical Energy The total cost of electrical energy generated can be divided into three parts, namely; (i) Fixed cost; (ii) Semi-fixed cost; (iii) Running or operating cost. 42Dr.A.Arunagiri
  • 22. 2/26/2013 22 Fixed Cost It is the cost which is independent of maximum demand and units generated. 43Dr.A.Arunagiri The fixed cost is due to the annual cost of central organization, interest on capital cost of land and salaries of high officials. The annual expenditure on the central organization and salaries of high officials is fixed since it has to be met whether the plant has high or low maximum demand or it generates less or more units. Further, the capital investment on the land is fixed and hence the amount of interest is also fixed. 44Dr.A.Arunagiri
  • 23. 2/26/2013 23 Semi-fixed cost It is the cost which depends upon maximum demand, but is independent of units generated. 45Dr.A.Arunagiri Running cost It is the cost which depends only upon the number of units generated. 46Dr.A.Arunagiri
  • 24. 2/26/2013 24 The running cost is on account of annual cost of fuel, lubricating oil, maintenance, repairs and salaries of operating staff. Since these charges depend upon the energy output, the running cost is directly proportional to the number of units generated by the station. In other words, if the power station generates more units, it will have higher running cost 47Dr.A.Arunagiri Expressions for Cost of Electrical Energy The overall annual cost of electrical energy generated by a power station can be expressed in two forms ie three part form and two part form. 48Dr.A.Arunagiri
  • 25. 2/26/2013 25 Three part form In this method, the overall annual costof electrical energy generated is divided into three parts ie fixed cost, semi-fixed cost and running cost 49Dr.A.Arunagiri Total annual cost of energy = Fixed cost+Semi fixed cost+Running cost Constant+Proportional to max. demand+Pro­portional to kWh generated. RM(a+b kW+c kWh) 50Dr.A.Arunagiri
  • 26. 2/26/2013 26 wherea = annual fixed cost independent of maximum demand and energy output b = a constant which when multiplied by maximum demand on the station gives annual semi fixed cost c= a constant which when multiplied by KWhr output per annum gives the annual running cost 51Dr.A.Arunagiri Two part form It is sometimes convenient to give the annual cost of energy in two part form. In this case, the annual cost of energy is divided into two parts ie a fixed sum per kW of maximum demand plus a running charge per unit of energy. The expression for the annual cost of energy then becomes Total annual cost of energy = RM(A kW+B kWh) 52Dr.A.Arunagiri
  • 27. 2/26/2013 27 where A = a constant which when multiplied by maximum kW, demand on the station gives the annual cost of the first part. B = 53Dr.A.Arunagiri a constant which when multiplied by KWhr output per annum gives the annual running cost PROBLEM 54 A generating station has a maximum demand of 50,000 kW. Calculate the cost per unit generated from the following data : Capital cost = SR 95 * 106; Annual load factor = 40% Annual cost of fuel and oil = SR 9 ×*106 Taxes, wages and salaries etc. = SR 7·5*× 106 Interest and depreciation = 12% (16 Halala) Dr.A.Arunagiri
  • 28. 2/26/2013 28 Problem Dr.A.Arunagiri 55 A generating station has an installed capacity of 50,000 kW and delivers 220 ×10^6units per annum. If the annual fixed charges are SR 160 per kW installed capacity and running charges are 4 halala per kWh, determine the cost per unit generated.(7.64) Dr.A.Arunagiri 56
  • 29. 2/26/2013 29 Problem Dr.A.Arunagiri 57 A generating plant has a maximum capacity of 100 kW and costs SR 1,60,000. The annual fixed charges are 12% consisting of 5% intererst, 5% depreciation and 2% taxes. Find the fixed charges per kWh if the load factor is (i) 100% and (ii) 50%.( HALALA 2.19,4.38) Problem Dr.A.Arunagiri 58 Estimate the generating cost per kWh delivered from a generating station from the following data : Plant capacity = 50 MW ;Annual load factor = 40% Capital cost = 12 millions; annual cost of wages, taxation etc. = Rs 0.4 lmillion; cost of fuel,lubrication, maintenance etc. = 1·0 halala/kWh generated. Interest 5% per annum, depreciation 6%per annum of initial value. (2)
  • 31. 2/26/2013 31 Load and Loss Factor Relationship 61 While calculating the energy cost the cost of power loss also must be taken into account. THERE are two type of losses: •Fixed Loss ( No load loss) •Variable loss (Load losses) Dr.A.Arunagiri 62 No load losses: Since these are essentially constant , extra generating equipments must be provided to supply the additional demand at peak hours. Efficient base –load units(from hydro capacity , thermal or nuclear) can supply these losses most of the time. Hence the perunit demand/energy cost for these is low. Load Losses: These losses constitute two losses Demand loss Energy loss Dr.A.Arunagiri
  • 32. 2/26/2013 32 63 Load diversity complicates the evaluation of the demand based cost of peak load losses. The distribution system peak loading may not coincide with the total system(generation) peak. In these losses, the demand cost depends upon peak responsibility factor(k) which is the ratio of distribution systems load at the time of total system peak to its peak load. It generally varies between 0.2 and 0.8 for distribution system and 0.8 and 0.95 for transmission systems. Dr.A.Arunagiri Dr.A.Arunagiri 64 If a distribution has P kw loss at its peak load, then k2P will be the loss at the time of total system peak, the cost of which is demand based. Therefore k2P kw losses demand must be provided by the generating equipments.
  • 33. 2/26/2013 33 Dr.A.Arunagiri 65 For energy based losses the loss factor is important. It is the ratio of the energy loss in the system during a given time period to the energy loss that would result if the system peak loss had persisted throughout that period. Load and losses factors relationship: 66 Loss factor = (Load factor)1.732 Or another thumb rule isOne empirical formula is Loss factor = c (Load factor) + (1-c) (Load factor)2 Where c= 0.3 for transmission system and 0.15 for distribution systems. These two relations are considered accurate if the minimum demand during the period does not fall below 0.2 pu of the peak demand. Dr.A.Arunagiri One empirical formula is
  • 34. 2/26/2013 34 Dr.A.Arunagiri 67 In case the system load factor Lf Is below 0.8 the following relation is more accurate: 22 )(273.0 KLLL ffs  K is the minimum demand in pu of peak demand Ls is loss factor Lf is load factor Total losses per annum = Loss factor* Maximum losses based on continuous peak current 68 2 8.02.0 ffs LLL  2 7.03.0 ffs LLL  2 84.016.0 ffs LLL  2 8.02.0 ffs LLL  •In terms of British experience , this the Losses factor fits relationship: •The Americanexperience gives: For urban areas For rural areas •The Australians use: Dr.A.Arunagiri
  • 35. 2/26/2013 35 Example Dr.A.Arunagiri 69 In a power utility the energy consumption per year is 5000 GWhr with the maximum and minimum demands of 1000 and 100 MW respectively. Find the loss factor and the typical empirical relation. Solution Dr.A.Arunagiri 70 Yearly load factor = AD/MD = 0.57 K is the minimum demand in pu of peak demand K = 100/1000=0.10 3852.0 )(273.0 22   KLLL ffs Loss factor = c (Load factor) + (1-c) (Load factor)2 0.3852= c (Load factor) + (1-c) (Load factor)2 C=0.25 The empirical relation will be Loss factor = 0.25(Load factor) + (0.75) (Load factor)2
  • 36. 2/26/2013 36 Load Growth Dr.A.Arunagiri 71 . The demand estimation is the starting point for planning the future electric power supply. The consistency of demand growth over the years has led to numerous attempts to fit mathematical curves to this trend. One of the simplest method is where a is the average per unit growth rate, P is the demand in year t, and P0 is the given demand at year t0. Definition of some basic concepts in statistics: Dr.A.Arunagiri 72 n yi n yii  ' n yi   2 2 )(       2 exp )( ]/ 2 1 [ 22   y yf •Mean value •Weighted mean •Variance (standard deviation) •Normaldistribution
  • 37. 2/26/2013 37 Problem Dr.A.Arunagiri 73 A 2.5MVAR, 11KV, capacitor bank has been commissioned at a 33/11KV, 10MVA transformersubstationhaving the following data: 33KV line length is 35 KM and conductor resistance is 0.584Ω/KM, Load factor = 0.65. Find saving in losses and sparing of system capacity after installation of the capacitors Without Capacitors With Capacitors Peak load 8000KW 8000KW Voltage 10.4KV 11.4KV Power Factor 0.846 0.99 Peak current on 11KV 525A 409A Peak current on 33KV 175A 136.3A Solution Dr.A.Arunagiri 74