SlideShare a Scribd company logo
1 of 72
Classification of Towers based
on
1)No. of
Circuits
a. Single circuits towers
b. DC/SC towers
c. DC towers
d. MC towers
2)AOD
a) Suspension/Tangent towers <2°
b) Small angle towers 2 ° -15 °
c) Medium angle towers 15 ° -30 °
d) Large Angle towers 30 ° -60 °
e) Dead end towers >60 °
f) Transposition towers(4Xarms)
g) Special towers – JC, MC, NB, NBMC
h) Pole mounted termination towers
i) Mono poles
SC DC/SC
(B/B)
MC
(B/B)
NB (B/B)
A P/D(4.2) K(8) 0° (1.3)
B R(7.15) L(8.7) 30° (1.31)
C&D S(7.75) M(11.5) 60°
(3.174)
Bot Xarm
Ht
Bot Xarm
ht
12.283 12.35 12.3
Total
Height
Total
height
27.381 38.46 27.1
132
KV
Note: All in meters
L&T TSP M/C NB
A AV/AS X 0°
B BS Y 30°
C CS(8) Z(17) 60° (3.3)
D(11)
BotXarm Ht 16.85 19.085 17.45 11.79
Total Ht 33.5 38.035 51.4 29
220 KV
Note: All in mesters
NB MCNB(220KV) MCNB(132KV)
120m 250m 300m
60° 0, 30 & 60 Deg 0°, 30° & 60°
2.2 5.4 3.936
14 13.1 12.15
Special towers
Mono pole
180m
0°, 30° & 60°
Bot Xarm Ht 15.8
For river crossing suspension towers only
Height(m) Base
width
(B/B) (m)
Bot
Xram(m)
Wt.
(MT)
Full JC 88.2 12.38 69 32.5
Trunk
JC
72.15 10.4 52.5 28.9
JC
 +3m
 +6m
 +9m
 +12m
 +18m
 +25m
 +30m
Tower extensions:
Generally extensions are added to the tower at Bottom section .
Cage Extension is added at cage for dead end towers, the extension
Will be of 3m & 5m
 Normal span: 320m for Panther
 350m for Zebra and L&T
towers
 380m for Moose and TSP
towers
 950m for JC
 Actual span
 Wind span
 Weight span: Left wt. span & Right wt.
span
 Equivalent span
 Negative span
SPANS:
Erection
a) Setting of stubs:
Template
B/B & diagonal at Template top
B/B & diagonal at stub top Ram bus shape
Stub cleats with B&N 2 each
Extra cleats to avoid failure of foundation
due to tower falling.
Threads to bisect
LP&AP
Template height at centre point & joining of
2 threads
Probe setting
b) After 14 days of curing
Built-up method:- This method consist of erection of
towers member by member. The 4 main leg members of
first section of the tower are first erected and guyed of. The
cross braces then assembled. For assembling second section
a light gin pole is placed on top of the corner legs for
raising the second section of the tower. Afterwards the gin
pole is shifted to top of second section leg to raise third
section this process is continued till complete tower is
erected.
Section method :-
Major sections of the tower are assembled on the
ground and same are erected as units.
Either mobile crane or gin pole of 10m long is
used.
Ground assembly(Proto) :-
This method consist of assembling the tower on
ground and erecting it as a complete unit. The
complete tower is assembled in line wise position
to allow Xarms to fitted. After assembly is
completed tower is picked up from ground with
the help of crane and carried to is location and
set on its foundation.
This method is not is useful when the towers are
large and heavy and the locations are difficult.
Helicopter method :-
In this method the tower is erected in section.
Bottom section is first lifted on to the stub and
then the upper section is lifted and bolted to first
section and the process is repeated till the tower
is erected. Some times complete assembled tower
is raised with the help of helicopter. This method
is adopted when approach is impossible.
oTower parts – 86 Microns
oBolt & Nuts - 45 Microns
Galvanization :
MS tower parts to Galvanized tower parts
Galvanization Procedure
1 2 3 54 6 7 8
1. Decreasing Bath Hard HCL
2. Pickling HCL
3. Rinsing Water
4. Fluxing Ammonia and Zinc Chloride
5. Hot plate
6. Zinc batch
7. Dychromizing
8. Finishing & Filling
Tightening of B&N
The bolts & nuts are used to join the tower parts
The bolts are of 16mm diameter and 20mm diameter
The length of bolts are various from 35mm to 80mm
multiple of 5mm
17.5mm/21.5mm dia hole is provided on tower part for
fixing bolt & nut
Spring washers - 16 x 3.5 mm- to tighten the bolt&nut
Flat washers 4, 5, 6, 8, 10,20 and 25mm to fill up gaps
between the tower parts
Check for tight of B&N using torque wrench
The threads of bolts projecting out side shall be
punched at 3 positions and do half round welding
to
ensure that nuts are not loosened in course of time
and avoid theft of angles.
Zinc epoxy painting is applied on welded portion to
avoid rusting.
Tower verticality :- 1 in 360
Slenderness Ratio = Effective length of members / Radius
of gyration
SR gives Resistance of any member to
bending
SR for leg members - 150
Tension members - 350
Grounding : -
pipe earthing –Tower foot Resistance<15
ohm
CP earthing - 15 – 30 m of 7/8 or 7/9
SWG
galvanized steel wire
50x6mm flat of 1.5m length is used & flat
should be buried at 0.6m below the ground
level.
 Earthing pipe is of 25mm dia, 3050 meters
length GI pipe with holes.
Explain practice of coke and salt, betonite
powder
earthing is provided for D leg only
For Railway crossing double earthing is
to be provided.
Normally earth pipe is placed vertically
& in difficult places earth pipe placed in
slant position with prior approval.
A pit of 300mm dia and 3.2m depth is
excavated to place earth pipes.
Tower Accessories: -
Danger boards
Number plate
Phase plate
Anti Climbing Device
Step bolts 16x175 mm
Antiperch / Bird guards for suspension towers
Hanger rods
i) NO TOWER SHALL BE ERECTED ON FOUNDATION
BEFORE 10 DAYS AFTER CONCRETING.
ii) CHECK THE CORRECTNESS OF DIAGONAL AND
LEVEL OF THE STUB OF THE FOUNDATION.
iii) TOWERS ARE TO BE ERECTED AS PER ERECTION
DRAWING
iv) ASSEMBLY OF TOWER PARTS SHALL BE MADE AS
PER MARK NUMBER WISE ENGRAVED ON THE
TOWER MEMBER CORRESPONDING TO NUMBER IN
THE ERECTION DRAWING.
v) SPECIAL CARE SHALL BE TAKEN IN SELECTION OF
MARK NUMBER FOR TRANSVERSE AND
LONGITUDINAL FACE OF THE SQUARE BASE TOWER.
vi) ANY BUCKLING, DAMAGE TO STEEL MEMBER,
DAMAGE TO GALVANIZING SHALL BE AVOIDED
vii) NO MEMBER SHALL BE SUBJECTED TO UNDUE
STRESS.
viii) REASON CAN BE: (i) DEFECTIVE FABRICATION.
(ii) DEFECTIVE FOUNDATION.
(iii) DEFECTIVE ERECTION
METHOD.
viii) COLLECT MATERIAL FROM STORE TALLYING WITH
BOM.
ix) PREFERABLY TRANSPORT COMPLETE TOWER OR
COMPLETE SECTION.
x) THE TOWER MEMBER AT LOCATION SHALL BE KEPT
ON GROUND SERIALLY ACCORDING TO THE NEED
FOR FOLLOWING UP ERECTION SEQUENCE.
TOWER ERECTION
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
CROW BARS
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
CROW BARS
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
CROW BARS
DERRICK
DERRICK TYING ROPE
20mm POLY
PROPYLENE
ROPE
CROW BARS
i) WHILE LOADING AND UNLOADING THE TOWER PARTS,
CARE SHOULD BE TAKEN FOR STACKING
SYSTEMATICALLY.
ii) HANDLE THE TOWER PARTS CAREFULLY. WHILE
HANDLING THEM WEAR SUITABLE GLOVES.
iii) ESTABLISH CLEAR SIGNAL/COMMUNICATION
BETWEEN THE PERSONS WORKING ON THE TOP AND
THE PEOPLE SUPPLYING TOWER PARTS, WATCHING
GUYS PULLING ETC SPECIAL CARE SHALL BE TAKEN
FOR R.C. TOWER.
iv) ALL LIFTING TOOLS AND TACKLES SHOULD BE LOAD
TESTED AS PER STANDARD.
vi) ENSURE THE DERRICK USED BEFORE TOWER
ERECTION HAS BEEN CHECKED FOR ADEQUATE
STRENGTH / SIZE.
vii) KEEP WATCH ON ALL GUYS USED DURING ERECTION
ANY SLIPPAGE/FAILURE IF THE GUY CAN CAUSE
ACCIDENT.
viii) POLYPROPYLENE ROPE FROM 20MM TO 25MM SIZE
SHOULD BE USED FOR GUYING & LIFTING.
ix) AFTER 5 OPERATIONS CHECK THE CONDITION OF THE
ROPE. IF WORN OUT THEN REJECT.
xi) ALL TOWER MEMBERS TO BE FITTED WITH
APPROPRIATE SIZE OF NUTS & BOLTS OF THE SECTION
ERECTED BEFORE THE ERECTION IS TAKEN UP FOR THE
NEXT SECTION.
xii) AVOID ALL TOWER ERECTION IN RAINY DAY.
xiii) HEAVILY CLOUDY DAYS AVOID ALL TYPE TOWER
ERECTION. STOP TOWER ERECTION OF R.C.TOWER.
xiv) IN CASE OF HEAVY WIND OR APPROACHING STORM
STOP ALL TOWER ERECTION. EVERY ONE SHOULD BE
AWAY FROM THE TOWER.
xv) PPE LIKE HELMET, SAFETY BELT OF PROPER QUALITY IS
USED.
xvi) FOR CLIMBING TOWER USE SAFETY BELT WHICH CAN BE
FITTED TO THE TOWER.
Conductor Amps Kg/KM AL59 INVAR
Panther 489 974 734 Amp. Double
Panther
30+7/3.00
Zebra 737 1621 930 Amp. Double
Zebra
54+7/3.18
Moose 840 1998 54+7/3.53
LINE MATERIALS
1.Conductors
AAAC- Less wt., more sag, & more current carrying capacity
ACSR- More wt., less sag, & less current carrying capacity
I. Total No. of wires = 3N(N+1)+1 ; Where N= No. of layers
Layer No. of
wires
Total
Centre 1 1
1st
6 7
2nd
12 19
3rd
18 37
II. Lay Ratio = Lay/OD ; Where OD = Outer diameter=(2N+1)d;
where d= Dia of single strand
18 wires 10 – 12
12 wires 12 -14
6 wires 13 -18
2.Earth wire: Shielding angle 10 – 30 °
7/3.66 → 7/3.15
Weight /KM 575 428 Kg/KM
3. Insulators: 70 KN, 120KN and 160
KN
Voltag
e
Suspension Angle
132KV 9Nos 10Nos
220KV 13Nos 14Nos
400KV 23Nos 24Nos
132÷√3 = 76.2 KV ≈ 80 KV ÷ 11 = 8 Nos + 1 extra = 9 Nos
220÷√3 = 127 KV ÷ 11 = 12 Nos + 1 extra = 13 Nos
400÷√3 = 230.95 KV ÷ 11 = 21 Nos + 1 extra = 22 Nos or Say 23
a) Porcelain Insulators :- Ball and Socket
Long rod
b) SRC Insulators :- Silicon Rubber Composite
FRP rod with sheds, fiber resin plastic rod
Insulator hoisting
Suspension insulators shall be used upto deviations of 2
degrees on all tangent type towers on the line and strain
insulators on all angle type towers.
For ensuring insulation co-ordination the suspension or tension
strings on approach and terminal towers near the station ends
upto a length of 1.5 Km shall be provided with adjustable arcing
horns on tower side and fixed arcing horns on line side, keeping
the arcing gap as may be stipulated by the Engineer at site.
Insulator strings shall be assembled on the ground. These shall
be cleaned and examined before hoisting. All accessories shall
be properly fitted.
Those having glazing defects exceeding half centimeter square
shall not be used.
For suspension towers 70 KN insulators are hoisted
with Aerial rollers. The Aerial rollers are like single
sleeve pulley .Before hoisting of insulators the M pins
should be checked thoroughly for their opening so that
the insulation will not detached during stringing.
4. SSH for conductor:- PA rods 11 – 14 Nos; where PA=
Preformed Armoured Rods
5. STH for conductor 6. DSH for conductor
7. DTH for conductor 8. SSH for earth wire
9. STH for earth wire
10. 4R stock bridge vibration dampers (1.2 – 1.3m)
11. MS joint for conductor
12. MS joint for earth wire
13. Repair sleeves
CORRECT METHODSWRONG METHOD
i) SELECT CONTINUOUS STRETCH AND STARTING TYPE OF
TOWER FOR STRINGING WITH ADEQUATE CARE.
ii) PREPARE DRUM SCHEDULE FOR CONDUCTOR WITH CARE TO
REDUCE WASTAGE.
iii) SELECT PROPERLY THE PLACEMENT SCHEDULE FOR
TENSIONER AND PULLER.
iv) SELECT THE PLACE CAREFULLY FOR PLACEMENT OF
TENSIONER AND PULLER TAKING SITE CONDITION INTO
CONSIDERATION.
v) CHECK CORRECTNESS OF ERECTED TOWER AS PER
DRAWING AND SPECIFICATION FOR ALL TOWERS.
vi) CHECK COMPLETION OF EARTHING AND RECORD TOWER
FOOTING RESISTANCE OF EACH LOCATION.
vii) ALL TREES ENROUTE THE LINE SHOULD BE CLEARED AND
REMOVED FROM THE TRAVELLING PATH OF CONDUCTOR.
viii) CERTIFY AFTER VERIFICATION JOINTLY.
STRINGING
a)Paving out of conductor
b)Rough sag
c)Final tension / stringing
METHOD
 SLACK OR LAY OUT METHOD.
 PAYING BY TENSIONER PULLER.
T&P required :-
Tractor/Tensioner
Turn table (5T or 10T)
Conductor socks
Automatic come along clamp for conductor and earth wire
20mm and 25mm D shackles
Wooden packs
Ground rollers
Aerial rollers
Crowbars
Hacksaw blade
Cutting pliers
Screw driver
Spanners
1. Generally drum lengths are
Panther 2KM
Zebra 1KM
Moose 1KM
Earth wire 2KM
2. Place the conductor drum on TURN TABLE & unwind it.
3. Pull the end of conductor over ground rollers and
passing
through Aerial rollers at suspension towers reach the
next cut point tower using tractor/ tensioner.4. Make up the end of conductor to the cut point tower with STH/DTH
5. Follow the same procedure for balance conductors
and earth wire
Rough sag
T&P required:-
Rough sag leads
Steel ropes 10mm, 12mm, 15mm and 16mm
Come along clamp (7 bolts)
Slings (20mm)
4 Sheave pulley
2 Sheave pulley
Single Sheave pulley
Manila ropes 12mm, 16mm, 18mm and 20mm
Single and double end socks
Turn buckle
D shakles 20 mm
Dead man 1to 1.2 m
6. By connecting the other end to LEPTY do the rough sag by
pulling with tractor/tensioner and see that conductors
are lifted In all spans by hand height.
7. Common problem is BARD CAGING
LEPTY made with steel rope of 12mm of 200m and
400m lengths with four sheave pulleys on either end.
Final tension /Stringing
T&P required:-
1. Leg winch
2. Sag boards
3. 100 MT joint compressor with die sets
suitable for panther, Zebra Moose and earth
wire.
4. Earth wire flat clamps
5. D shackles 16mm/25mm
6. Binoculars
7. Tractor / Tension puller
8. Travelling speed will be 5 – 8 KM per hour.
9. if speed is low causes swinging of traveler and insulator
hardware and higher speed cause damage.
10. Tension load will be around 2000 – 2500
Kgs
11. For 3rd
crossarm stringing tension will be 500
Kgs
12. For 400 KV pilot wire and tensioner is used. First pilot
wire will be passed through the entire reach with Tractor.
Conductor is winded on Tensioner. Pilot wire is knotted to
conductor. The other end of pilot wire is connected to
Puller.slowly puller load applied and tensioner is
releasing the conductor without any problem and make up
at this with STH. Once paving is completed again load
Tensioner till sag point and guyed. Then by Lepty and
Tractor make marking and cater the end.
13. Measurement of sag with equal supports use sag boards
between the two towers of sag span
14. Measurement of sag where supports are at different height
or single spans. Use Dynamo meter for tension readings
15. Sagging section length should not exceed 5KM or 15 spans
16. Physical measurement of ground clearance on roads and
important places.
A A
A
1.50M LONG ISMB 200
BACK FILLED EARTH
STEEL ROPE OF 20MM DIA
DETAIL – ‘A’
100MM
300MM
1100MM
150MM
BACK FILLED EARTH
1.50M LONG ISMB 200
STEEL ROPE OF 20MM DIA
DETAIL – ‘A’
100MM
300MM
1100MM
150MM
A A
A
TOOLS & PLANT REQUIRED PER CONDUCTOR
1. 20mm dia wire Rope Slings 40m length - 1 No.
2. 20mm 'D' Shakles - 2 Nos
3. Come along Clamp (Bolted Type) - 1 No.
4. 20mm Sling 10m length - 1 No.
5. Deadmen wood (1000mm-1200mm long)- 1 No.
DETAIL – ‘B’
2.00M LONG ISMB 200
BACK FILLED EARTH
STEEL ROPE OF 20MM DIA
100MM
300MM
1600MM
250MM
40m Approx.
Excavated pit for Anchoring of Conductor
TENSION TOWER
SUSPENSION TOWER SUSPENSION TOWER
B
DETAIL – ‘C’
2.00M LONG ISMB 200
BACK FILLED EARTH
STEEL ROPE OF 20MM DIA
100MM
300MM
2100MM
250MM
C
NOTE: Sling size = 20mm. Depending upon the
Tension load rope size should be selected which
is dependent on no of conductors type and the
tension applied during the sagging.
Arrangement should be capable of 1.5 times of
the total tension load.
IMPROPER
GUYING
ARRANGEMENT
RAIL PIECE
BACK FILLED
EARTH
STEEL ROPE
RAIL PIECE
BACK FILLED
EARTH
HOOK
HOOK
STEEL ROPE
HOOK
PROPER
GUYING
ARRANGEMENT
PROPER
GUYING
ARRANGEMENT
After stringing ensure the following
Any departures from the correct sag in any span
does not exceed 4 percent.
The sag of any conductor does not depart by
more than 3% from the mean sag of all the
conductors in the same span subject of a
maximum of 150mm.
i) BACK TENSION OF BOTH THE TENSION TOWERS OF SAG SECTION IS MOST
IMPORTANT. PROVIDE BACK TENSION BY PAID OUT CONDUCTOR OF THE
NEXT ADJACENT SECTION OF BOTH TENSION TOWERS.
ii) BACK TENSION ON THE TOWER WITH GUY WIRE SHOULD BE AVOIDED.
iii) IF REQUIRED PREPARE A SCHEME AND GOT IT APPROVED BY THE
TECHNICAL CELL.
iv) GUY WIRE CAPACITY SHOULD BE 1½ TIMES OF MAXIMUM TENSION OF THE
CONDUCTORS.
v) INSPECT THOROUGHLY THE CONDITION OF GUY WIRES BEFORE USED.
vi) GUY FIXING ANGLE SHOULD BE BETWEEN 45
o
TO 50
o
TO THE VERTICAL.
vii) GUY BLOCKING ARRANGEMENT SHOULD BE VERY CAREFULLY DONE.
viii) RESPONSIBLE PERSONS SHOULD BE DEPLOYED DURING ENTIRE SAGGING
OPERATION.
ix) MEN ON BACK STAY SHOULD BE PROVIDED WITH APPROPRIATE WHISTLE
AND COMMUNICATION.
x) MEN ON BACK STAY SHOULD BE IN CONSTANT TOUCH WITH FINAL
SAGGING PERSON.
xi) ANY WHISTLE OR COMMUNICATION FROM THE PERSON AT BACK STAY,
STRINGING SHOULD BE STOPPED.
xii) IF NECESSARY CONDUCTOR SHOULD BE RELEASED TO DE-TENSION.
xiii) FINAL SAGGING SHOULD BE DONE AS PER APPROVED SAG TENSION CHART.
xiv) ANY CHANGES IN THE SECTION, SPAN MADE DURING THE CONSTRUCTION
THE SAG TENSION CHART SHOULD BE GOT CORRECTED.
xv) THE PERSON IN-CHARGE OF FINAL SAGGING SHOULD HAVE COPIES OF FINAL
PROFILES, SAG TENSION CHART, FINAL TOWER SCHEDULE, SAG TEMPLATE,
PROPER RECORDING REGISTER, FORMATS, ALL DRAWINGS OF HARDWARE
AND ACCESSORIES.
xvi) TWO THERMOMETERS SHOULD BE CLAMPED ON THE TOWER IN ADVANCE ON
THE SAG SPAN.
xvii) TEMPERATURE SHOULD BE CONSTANTLY MONITORED.
xviii) NECESSARY CORRECTION OF SAG BOARD SHOULD BE DONE BEFORE FINAL
MARKING OF CONDUCTOR.
xix) ADEQUATE AND PROPER COMMUNICATION SHOULD BE AVAILABLE AT ALL
POINTS CONTROLLING SAG AND BACK TENSION POINT.
xi) ALL EQUIPMENT SHOULD BE LOAD TESTED BEFORE FINAL SAGGING
OPERATION PLANNED.
xii) USE SUITABLE DYNAMOMETERS TO CROSS CHECK SAG, SHORTER
SPAN, HILLY TERRAIN.
xiii) CHECK CONSTANTLY EVENNESS OF THE BUNDLE CONDUCTOR.
xiv) KEEP CONSTANT CHECK ON THE MOVEMENT OF AERIAL ROLLER TO
ENSURE INTERMEDIATE SPAN ALSO REACHED TO DESIRED SAG.
xv) IN CASE ANY CONDUCTOR IS PULLED ABOVE SAG IN THE SAG SPAN
THEN RELEASE BOTH THE CONDUCTORS TO BRING DOWN BELOW SAG
AND BRING EVENNESS AND THEN RE-SAGGED.
xvi) AVOID FINAL SAGGING IN WINDY DAYS, OTHER WISE ALLOWANCE IS TO
BE GIVEN FOR UPLIFT.
xvii) ALLOWANCE GIVING IS NOT DESIRABLE SINCE IT DEPENDS ON THE
WIND AND EXPERIENCE.
xviii) SPECIFIC CARE SHOULD BE TAKEN IN MEASURING FINALLY SAGGED
CONDUCTOR BEFORE CUTTING & COMPRESSING THE DEAD END
CLAMP.
i) KEEP THE CONDUCTOR FINALLY SAGGED FOR 48HRS ON
ROLLER.
ii) AGAIN CHECK THE SAG AND RE-ADJUST IT IF NECESSARY.
iii) KEEP SUSPENSION STRING ABSOLUTE VERTICAL.
iv) PLUMB MARK THE CONDUCTOR BEFORE REMOVING ROLLER BY
MEANS OF A PLUMB OR PLUMB MARKER MADE FOR SPECIFIC
PURPOSE.
v) THEN THE CONDUCTOR SHOULD BE LIFTED BY MEANS OF A
SUITABLE LIFTING DEVICE.
vi) LIFTING DEVICE MAY CONSIST OF ONE OR TWO HOOKS
DEPENDING UPON NUMBER OF CONDUCTORS.
vii) AFTER LIFTING THE CONDUCTOR FIX PREFORMED ARMOUR
RODS.
viii) TAKE 2 OR 3 RODS ON EACH SIDE OF THE CENTRE MARK SUCH
THAT THE HAND WILL NOT BE MORE THAN ONE OR TWO PITCH
LENGTHS AWAY FROM THE CENTRE MARK.
ix) THE CENTRE MARK OF THE RODS SHOULD BE LOCATED AT THE
CENTRE MARK OF THE CONDUCTOR SUPPORT.
x) APPLY THE RODS BY ROTATING ABOUT CONDUCTOR CONTINUING
FROM 1 OR 2 PITCH LENGTH OF EITHER SIDE OF THE CENTRE.
xi) FIX ARMOUR ROD APPLYING SPIRAL MOTION OF THE HANDS UNTIL
THEIR ENDS ARE SNAPPED INTO POSITION.
xii) FIX SUSPENSION STRING OVER ARMOUR ROD THEN RELEASE THE
LOAD.
xiii) CHECK THE INSULATOR ASSEMBLY IS IN PLUMB.
xiv) INSTALL VIBRATOR DAMPERS OR SPACER DAMPERS AS PER
DRAWING at 1.2 to 1.3 m
xv) IF VIBRATION DAMPERS ARE USED THEN FIX THE LINE SPACER
IMMEDIATELY THERE AFTER.
i) ALLOW THE FINALLY SAGGED CONDUCTOR FOR 48HRS TO TAKE
CARE THE CREEPAGE OR MINOR SAG ERROR DUE TO MOVEMENT OF
AERIAL ROLLER.
ii) LIFTING DEVICE SHOULD BE FIXED IN SUCH A MANNER SO THAT
LIFTING LOAD IS TRANSFERRED TO TOWER BODY.
iii) AVOID POINTED LIFTING LOAD ON THE TIP OF CROSS ARM.
iv) LIFTING HOOK SHOULD HAVE A RUBBER OR NEOPRENE LINING.
v) MATCH THE CENTRE OF THE ARMOUR ROD WITH CENTRE MARK OF
THE SUSPENSION POINT.
vi) FIX VIBRATION DAMPERS OR SPACER DAMPER IMMEDIATELY SINCE
THE CONDUCTOR AT FULL LOAD / CRITICAL TENSION.
vii) FIX LINE SPACER IMMEDIATELY FOR BUNDLE CONDUCTOR TO AVOID
CLASHING OF CONDUCTOR.
i) MEASURE THE EXACT JUMPER LENGTH REQUIRED
FOR EACH TENSION TOWER.
ii) CHECK THE JUMPER DEPTH, ANGLE AS GIVEN IN THE
ELECTRICAL CLEARANCE DIAGRAM.
iii) PRESS THE JUMPER CONE AND FIX ON THE TOWER.
iv) WHILE FIXING JUMPER THE CONDUCTOR SHOULD BE
EARTHED PREFERABLY ON BOTH THE SIDES.
v) IN CASE OF BUNDLE CONDUCTOR RIGID SPACER
SHOULD BE FIXED AS PER THE RECOMMENDATIONS
OF MANUFACTURER.
Statutory Inspection
points:
S. No.
Location No.
Type of tower
Chimney
Coping
Missing bolt &
nuts
HR weld
Insulators
Arcing horns
Jumper bolt &
nuts
Jumpers
Vibration
Conductor
Earth wire
Earth wire bonds
Number plates
Danger boards
Phase plates
Step bolt & nuts
Protection wall
Ground
clearance
Tree clearance
Other remarks
Transmission Line Towers and details

More Related Content

What's hot (20)

Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
Transmission line Project
Transmission line ProjectTransmission line Project
Transmission line Project
 
tower spotting
tower spottingtower spotting
tower spotting
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
 
Design of Transmission Tower
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission Tower
 
design of tower
design of towerdesign of tower
design of tower
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
Presentation1
Presentation1Presentation1
Presentation1
 
Method statement for transmission line (lanco)
Method statement for transmission line (lanco)Method statement for transmission line (lanco)
Method statement for transmission line (lanco)
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
Acsr moose conductor
Acsr moose conductorAcsr moose conductor
Acsr moose conductor
 
Survey & ts for ehv lines
Survey & ts for ehv linesSurvey & ts for ehv lines
Survey & ts for ehv lines
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Earthing system
Earthing system   Earthing system
Earthing system
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Underground cables vs overhead lines
Underground cables vs overhead linesUnderground cables vs overhead lines
Underground cables vs overhead lines
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable Selection
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 

Viewers also liked

Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableLeonardo ENERGY
 
Struktur Baja Metode LRFD
Struktur Baja Metode LRFDStruktur Baja Metode LRFD
Struktur Baja Metode LRFDMuhammad Umari
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
Power transmission(ppt)
Power transmission(ppt)Power transmission(ppt)
Power transmission(ppt)zeeshan715
 

Viewers also liked (8)

Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power Cable
 
Struktur Baja Metode LRFD
Struktur Baja Metode LRFDStruktur Baja Metode LRFD
Struktur Baja Metode LRFD
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Types of insulator
Types of insulatorTypes of insulator
Types of insulator
 
Conductors
ConductorsConductors
Conductors
 
Conductor types and sizes
Conductor types and sizesConductor types and sizes
Conductor types and sizes
 
Power transmission(ppt)
Power transmission(ppt)Power transmission(ppt)
Power transmission(ppt)
 
INSULATORS AND ITS TYPES
INSULATORS AND ITS TYPESINSULATORS AND ITS TYPES
INSULATORS AND ITS TYPES
 

Similar to Transmission Line Towers and details

01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Thorne & Derrick International
 
Offshore platform slot recovery process
Offshore platform slot recovery processOffshore platform slot recovery process
Offshore platform slot recovery processKamel Elsayed
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling - 00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling - Adam Guo
 
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Patrice Adjei
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Stainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docxStainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docxtoramansor
 
A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...nasina balasubrahmayam
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...IRJET Journal
 
Destressing in LWR Track.pptx
Destressing in LWR Track.pptxDestressing in LWR Track.pptx
Destressing in LWR Track.pptxhanu chandran
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSSaritaJoshi5
 
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app689198f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891AkashPatel747
 
Rail, sleepers fittings.ppt
Rail, sleepers  fittings.pptRail, sleepers  fittings.ppt
Rail, sleepers fittings.pptAdityaDubewar2
 
Coupler (08102015)
Coupler (08102015)Coupler (08102015)
Coupler (08102015)Khairul Amri
 
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 CablesThorne & Derrick International
 

Similar to Transmission Line Towers and details (20)

01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
 
Offshore platform slot recovery process
Offshore platform slot recovery processOffshore platform slot recovery process
Offshore platform slot recovery process
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling - 00 flexible drill pipe usr -ultra short radius drilling -
00 flexible drill pipe usr -ultra short radius drilling -
 
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Stainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docxStainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docx
 
A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
IRJET- Parametric Study of RC Deck Slab Bridge with Varying Thickness: Techni...
 
Destressing in LWR Track.pptx
Destressing in LWR Track.pptxDestressing in LWR Track.pptx
Destressing in LWR Track.pptx
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Dismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONSDismantling of existing ROB, CSB Nagpur, AFCONS
Dismantling of existing ROB, CSB Nagpur, AFCONS
 
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app689198f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
98f5ce56 bca9-41ef-b8c9-095d7bf17a1c-151202050517-lva1-app6891
 
Rail, sleepers fittings.ppt
Rail, sleepers  fittings.pptRail, sleepers  fittings.ppt
Rail, sleepers fittings.ppt
 
Coupler (08102015)
Coupler (08102015)Coupler (08102015)
Coupler (08102015)
 
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
1. Heat Shrink Cable Termination (HV) - 11kV 33kV 3 Core XLPE BS6622 Cables
 

Recently uploaded

System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESNarmatha D
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 

Recently uploaded (20)

Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIES
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 

Transmission Line Towers and details

  • 1.
  • 2. Classification of Towers based on 1)No. of Circuits a. Single circuits towers b. DC/SC towers c. DC towers d. MC towers
  • 3. 2)AOD a) Suspension/Tangent towers <2° b) Small angle towers 2 ° -15 ° c) Medium angle towers 15 ° -30 ° d) Large Angle towers 30 ° -60 ° e) Dead end towers >60 ° f) Transposition towers(4Xarms) g) Special towers – JC, MC, NB, NBMC h) Pole mounted termination towers i) Mono poles
  • 4. SC DC/SC (B/B) MC (B/B) NB (B/B) A P/D(4.2) K(8) 0° (1.3) B R(7.15) L(8.7) 30° (1.31) C&D S(7.75) M(11.5) 60° (3.174) Bot Xarm Ht Bot Xarm ht 12.283 12.35 12.3 Total Height Total height 27.381 38.46 27.1 132 KV Note: All in meters
  • 5. L&T TSP M/C NB A AV/AS X 0° B BS Y 30° C CS(8) Z(17) 60° (3.3) D(11) BotXarm Ht 16.85 19.085 17.45 11.79 Total Ht 33.5 38.035 51.4 29 220 KV Note: All in mesters
  • 6. NB MCNB(220KV) MCNB(132KV) 120m 250m 300m 60° 0, 30 & 60 Deg 0°, 30° & 60° 2.2 5.4 3.936 14 13.1 12.15 Special towers
  • 7. Mono pole 180m 0°, 30° & 60° Bot Xarm Ht 15.8
  • 8. For river crossing suspension towers only Height(m) Base width (B/B) (m) Bot Xram(m) Wt. (MT) Full JC 88.2 12.38 69 32.5 Trunk JC 72.15 10.4 52.5 28.9 JC
  • 9.  +3m  +6m  +9m  +12m  +18m  +25m  +30m Tower extensions: Generally extensions are added to the tower at Bottom section . Cage Extension is added at cage for dead end towers, the extension Will be of 3m & 5m
  • 10.  Normal span: 320m for Panther  350m for Zebra and L&T towers  380m for Moose and TSP towers  950m for JC  Actual span  Wind span  Weight span: Left wt. span & Right wt. span  Equivalent span  Negative span SPANS:
  • 11. Erection a) Setting of stubs: Template B/B & diagonal at Template top B/B & diagonal at stub top Ram bus shape Stub cleats with B&N 2 each Extra cleats to avoid failure of foundation due to tower falling. Threads to bisect LP&AP Template height at centre point & joining of 2 threads Probe setting
  • 12. b) After 14 days of curing Built-up method:- This method consist of erection of towers member by member. The 4 main leg members of first section of the tower are first erected and guyed of. The cross braces then assembled. For assembling second section a light gin pole is placed on top of the corner legs for raising the second section of the tower. Afterwards the gin pole is shifted to top of second section leg to raise third section this process is continued till complete tower is erected.
  • 13. Section method :- Major sections of the tower are assembled on the ground and same are erected as units. Either mobile crane or gin pole of 10m long is used. Ground assembly(Proto) :- This method consist of assembling the tower on ground and erecting it as a complete unit. The complete tower is assembled in line wise position to allow Xarms to fitted. After assembly is completed tower is picked up from ground with the help of crane and carried to is location and set on its foundation. This method is not is useful when the towers are large and heavy and the locations are difficult.
  • 14. Helicopter method :- In this method the tower is erected in section. Bottom section is first lifted on to the stub and then the upper section is lifted and bolted to first section and the process is repeated till the tower is erected. Some times complete assembled tower is raised with the help of helicopter. This method is adopted when approach is impossible.
  • 15. oTower parts – 86 Microns oBolt & Nuts - 45 Microns Galvanization : MS tower parts to Galvanized tower parts Galvanization Procedure 1 2 3 54 6 7 8 1. Decreasing Bath Hard HCL 2. Pickling HCL 3. Rinsing Water 4. Fluxing Ammonia and Zinc Chloride 5. Hot plate 6. Zinc batch 7. Dychromizing 8. Finishing & Filling
  • 16. Tightening of B&N The bolts & nuts are used to join the tower parts The bolts are of 16mm diameter and 20mm diameter The length of bolts are various from 35mm to 80mm multiple of 5mm 17.5mm/21.5mm dia hole is provided on tower part for fixing bolt & nut Spring washers - 16 x 3.5 mm- to tighten the bolt&nut Flat washers 4, 5, 6, 8, 10,20 and 25mm to fill up gaps between the tower parts Check for tight of B&N using torque wrench
  • 17. The threads of bolts projecting out side shall be punched at 3 positions and do half round welding to ensure that nuts are not loosened in course of time and avoid theft of angles. Zinc epoxy painting is applied on welded portion to avoid rusting.
  • 18. Tower verticality :- 1 in 360 Slenderness Ratio = Effective length of members / Radius of gyration SR gives Resistance of any member to bending SR for leg members - 150 Tension members - 350
  • 19. Grounding : - pipe earthing –Tower foot Resistance<15 ohm CP earthing - 15 – 30 m of 7/8 or 7/9 SWG galvanized steel wire 50x6mm flat of 1.5m length is used & flat should be buried at 0.6m below the ground level.  Earthing pipe is of 25mm dia, 3050 meters length GI pipe with holes. Explain practice of coke and salt, betonite powder
  • 20. earthing is provided for D leg only For Railway crossing double earthing is to be provided. Normally earth pipe is placed vertically & in difficult places earth pipe placed in slant position with prior approval. A pit of 300mm dia and 3.2m depth is excavated to place earth pipes.
  • 21. Tower Accessories: - Danger boards Number plate Phase plate Anti Climbing Device Step bolts 16x175 mm Antiperch / Bird guards for suspension towers Hanger rods
  • 22. i) NO TOWER SHALL BE ERECTED ON FOUNDATION BEFORE 10 DAYS AFTER CONCRETING. ii) CHECK THE CORRECTNESS OF DIAGONAL AND LEVEL OF THE STUB OF THE FOUNDATION. iii) TOWERS ARE TO BE ERECTED AS PER ERECTION DRAWING iv) ASSEMBLY OF TOWER PARTS SHALL BE MADE AS PER MARK NUMBER WISE ENGRAVED ON THE TOWER MEMBER CORRESPONDING TO NUMBER IN THE ERECTION DRAWING. v) SPECIAL CARE SHALL BE TAKEN IN SELECTION OF MARK NUMBER FOR TRANSVERSE AND LONGITUDINAL FACE OF THE SQUARE BASE TOWER. vi) ANY BUCKLING, DAMAGE TO STEEL MEMBER, DAMAGE TO GALVANIZING SHALL BE AVOIDED
  • 23. vii) NO MEMBER SHALL BE SUBJECTED TO UNDUE STRESS. viii) REASON CAN BE: (i) DEFECTIVE FABRICATION. (ii) DEFECTIVE FOUNDATION. (iii) DEFECTIVE ERECTION METHOD. viii) COLLECT MATERIAL FROM STORE TALLYING WITH BOM. ix) PREFERABLY TRANSPORT COMPLETE TOWER OR COMPLETE SECTION. x) THE TOWER MEMBER AT LOCATION SHALL BE KEPT ON GROUND SERIALLY ACCORDING TO THE NEED FOR FOLLOWING UP ERECTION SEQUENCE.
  • 24. TOWER ERECTION DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE CROW BARS DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE CROW BARS DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE CROW BARS DERRICK DERRICK TYING ROPE 20mm POLY PROPYLENE ROPE CROW BARS
  • 25.
  • 26.
  • 27. i) WHILE LOADING AND UNLOADING THE TOWER PARTS, CARE SHOULD BE TAKEN FOR STACKING SYSTEMATICALLY. ii) HANDLE THE TOWER PARTS CAREFULLY. WHILE HANDLING THEM WEAR SUITABLE GLOVES. iii) ESTABLISH CLEAR SIGNAL/COMMUNICATION BETWEEN THE PERSONS WORKING ON THE TOP AND THE PEOPLE SUPPLYING TOWER PARTS, WATCHING GUYS PULLING ETC SPECIAL CARE SHALL BE TAKEN FOR R.C. TOWER. iv) ALL LIFTING TOOLS AND TACKLES SHOULD BE LOAD TESTED AS PER STANDARD.
  • 28. vi) ENSURE THE DERRICK USED BEFORE TOWER ERECTION HAS BEEN CHECKED FOR ADEQUATE STRENGTH / SIZE. vii) KEEP WATCH ON ALL GUYS USED DURING ERECTION ANY SLIPPAGE/FAILURE IF THE GUY CAN CAUSE ACCIDENT. viii) POLYPROPYLENE ROPE FROM 20MM TO 25MM SIZE SHOULD BE USED FOR GUYING & LIFTING. ix) AFTER 5 OPERATIONS CHECK THE CONDITION OF THE ROPE. IF WORN OUT THEN REJECT.
  • 29. xi) ALL TOWER MEMBERS TO BE FITTED WITH APPROPRIATE SIZE OF NUTS & BOLTS OF THE SECTION ERECTED BEFORE THE ERECTION IS TAKEN UP FOR THE NEXT SECTION. xii) AVOID ALL TOWER ERECTION IN RAINY DAY. xiii) HEAVILY CLOUDY DAYS AVOID ALL TYPE TOWER ERECTION. STOP TOWER ERECTION OF R.C.TOWER. xiv) IN CASE OF HEAVY WIND OR APPROACHING STORM STOP ALL TOWER ERECTION. EVERY ONE SHOULD BE AWAY FROM THE TOWER. xv) PPE LIKE HELMET, SAFETY BELT OF PROPER QUALITY IS USED. xvi) FOR CLIMBING TOWER USE SAFETY BELT WHICH CAN BE FITTED TO THE TOWER.
  • 30.
  • 31.
  • 32. Conductor Amps Kg/KM AL59 INVAR Panther 489 974 734 Amp. Double Panther 30+7/3.00 Zebra 737 1621 930 Amp. Double Zebra 54+7/3.18 Moose 840 1998 54+7/3.53 LINE MATERIALS 1.Conductors
  • 33. AAAC- Less wt., more sag, & more current carrying capacity ACSR- More wt., less sag, & less current carrying capacity I. Total No. of wires = 3N(N+1)+1 ; Where N= No. of layers Layer No. of wires Total Centre 1 1 1st 6 7 2nd 12 19 3rd 18 37
  • 34. II. Lay Ratio = Lay/OD ; Where OD = Outer diameter=(2N+1)d; where d= Dia of single strand 18 wires 10 – 12 12 wires 12 -14 6 wires 13 -18
  • 35. 2.Earth wire: Shielding angle 10 – 30 ° 7/3.66 → 7/3.15 Weight /KM 575 428 Kg/KM 3. Insulators: 70 KN, 120KN and 160 KN Voltag e Suspension Angle 132KV 9Nos 10Nos 220KV 13Nos 14Nos 400KV 23Nos 24Nos
  • 36. 132÷√3 = 76.2 KV ≈ 80 KV ÷ 11 = 8 Nos + 1 extra = 9 Nos 220÷√3 = 127 KV ÷ 11 = 12 Nos + 1 extra = 13 Nos 400÷√3 = 230.95 KV ÷ 11 = 21 Nos + 1 extra = 22 Nos or Say 23 a) Porcelain Insulators :- Ball and Socket Long rod b) SRC Insulators :- Silicon Rubber Composite FRP rod with sheds, fiber resin plastic rod
  • 37. Insulator hoisting Suspension insulators shall be used upto deviations of 2 degrees on all tangent type towers on the line and strain insulators on all angle type towers. For ensuring insulation co-ordination the suspension or tension strings on approach and terminal towers near the station ends upto a length of 1.5 Km shall be provided with adjustable arcing horns on tower side and fixed arcing horns on line side, keeping the arcing gap as may be stipulated by the Engineer at site. Insulator strings shall be assembled on the ground. These shall be cleaned and examined before hoisting. All accessories shall be properly fitted. Those having glazing defects exceeding half centimeter square shall not be used.
  • 38. For suspension towers 70 KN insulators are hoisted with Aerial rollers. The Aerial rollers are like single sleeve pulley .Before hoisting of insulators the M pins should be checked thoroughly for their opening so that the insulation will not detached during stringing.
  • 39. 4. SSH for conductor:- PA rods 11 – 14 Nos; where PA= Preformed Armoured Rods 5. STH for conductor 6. DSH for conductor 7. DTH for conductor 8. SSH for earth wire 9. STH for earth wire 10. 4R stock bridge vibration dampers (1.2 – 1.3m) 11. MS joint for conductor 12. MS joint for earth wire 13. Repair sleeves
  • 41. i) SELECT CONTINUOUS STRETCH AND STARTING TYPE OF TOWER FOR STRINGING WITH ADEQUATE CARE. ii) PREPARE DRUM SCHEDULE FOR CONDUCTOR WITH CARE TO REDUCE WASTAGE. iii) SELECT PROPERLY THE PLACEMENT SCHEDULE FOR TENSIONER AND PULLER. iv) SELECT THE PLACE CAREFULLY FOR PLACEMENT OF TENSIONER AND PULLER TAKING SITE CONDITION INTO CONSIDERATION. v) CHECK CORRECTNESS OF ERECTED TOWER AS PER DRAWING AND SPECIFICATION FOR ALL TOWERS. vi) CHECK COMPLETION OF EARTHING AND RECORD TOWER FOOTING RESISTANCE OF EACH LOCATION. vii) ALL TREES ENROUTE THE LINE SHOULD BE CLEARED AND REMOVED FROM THE TRAVELLING PATH OF CONDUCTOR. viii) CERTIFY AFTER VERIFICATION JOINTLY.
  • 42.
  • 43. STRINGING a)Paving out of conductor b)Rough sag c)Final tension / stringing
  • 44. METHOD  SLACK OR LAY OUT METHOD.  PAYING BY TENSIONER PULLER.
  • 45. T&P required :- Tractor/Tensioner Turn table (5T or 10T) Conductor socks Automatic come along clamp for conductor and earth wire 20mm and 25mm D shackles Wooden packs Ground rollers Aerial rollers Crowbars Hacksaw blade Cutting pliers Screw driver Spanners
  • 46. 1. Generally drum lengths are Panther 2KM Zebra 1KM Moose 1KM Earth wire 2KM 2. Place the conductor drum on TURN TABLE & unwind it. 3. Pull the end of conductor over ground rollers and passing through Aerial rollers at suspension towers reach the next cut point tower using tractor/ tensioner.4. Make up the end of conductor to the cut point tower with STH/DTH 5. Follow the same procedure for balance conductors and earth wire
  • 47.
  • 48. Rough sag T&P required:- Rough sag leads Steel ropes 10mm, 12mm, 15mm and 16mm Come along clamp (7 bolts) Slings (20mm) 4 Sheave pulley 2 Sheave pulley Single Sheave pulley Manila ropes 12mm, 16mm, 18mm and 20mm Single and double end socks Turn buckle D shakles 20 mm Dead man 1to 1.2 m
  • 49. 6. By connecting the other end to LEPTY do the rough sag by pulling with tractor/tensioner and see that conductors are lifted In all spans by hand height. 7. Common problem is BARD CAGING LEPTY made with steel rope of 12mm of 200m and 400m lengths with four sheave pulleys on either end.
  • 50. Final tension /Stringing T&P required:- 1. Leg winch 2. Sag boards 3. 100 MT joint compressor with die sets suitable for panther, Zebra Moose and earth wire. 4. Earth wire flat clamps 5. D shackles 16mm/25mm 6. Binoculars 7. Tractor / Tension puller
  • 51. 8. Travelling speed will be 5 – 8 KM per hour. 9. if speed is low causes swinging of traveler and insulator hardware and higher speed cause damage. 10. Tension load will be around 2000 – 2500 Kgs 11. For 3rd crossarm stringing tension will be 500 Kgs 12. For 400 KV pilot wire and tensioner is used. First pilot wire will be passed through the entire reach with Tractor. Conductor is winded on Tensioner. Pilot wire is knotted to conductor. The other end of pilot wire is connected to Puller.slowly puller load applied and tensioner is releasing the conductor without any problem and make up at this with STH. Once paving is completed again load Tensioner till sag point and guyed. Then by Lepty and Tractor make marking and cater the end.
  • 52. 13. Measurement of sag with equal supports use sag boards between the two towers of sag span 14. Measurement of sag where supports are at different height or single spans. Use Dynamo meter for tension readings 15. Sagging section length should not exceed 5KM or 15 spans 16. Physical measurement of ground clearance on roads and important places.
  • 53. A A A 1.50M LONG ISMB 200 BACK FILLED EARTH STEEL ROPE OF 20MM DIA DETAIL – ‘A’ 100MM 300MM 1100MM 150MM
  • 54. BACK FILLED EARTH 1.50M LONG ISMB 200 STEEL ROPE OF 20MM DIA DETAIL – ‘A’ 100MM 300MM 1100MM 150MM A A A
  • 55. TOOLS & PLANT REQUIRED PER CONDUCTOR 1. 20mm dia wire Rope Slings 40m length - 1 No. 2. 20mm 'D' Shakles - 2 Nos 3. Come along Clamp (Bolted Type) - 1 No. 4. 20mm Sling 10m length - 1 No. 5. Deadmen wood (1000mm-1200mm long)- 1 No. DETAIL – ‘B’ 2.00M LONG ISMB 200 BACK FILLED EARTH STEEL ROPE OF 20MM DIA 100MM 300MM 1600MM 250MM 40m Approx. Excavated pit for Anchoring of Conductor TENSION TOWER SUSPENSION TOWER SUSPENSION TOWER B
  • 56. DETAIL – ‘C’ 2.00M LONG ISMB 200 BACK FILLED EARTH STEEL ROPE OF 20MM DIA 100MM 300MM 2100MM 250MM C NOTE: Sling size = 20mm. Depending upon the Tension load rope size should be selected which is dependent on no of conductors type and the tension applied during the sagging. Arrangement should be capable of 1.5 times of the total tension load.
  • 57. IMPROPER GUYING ARRANGEMENT RAIL PIECE BACK FILLED EARTH STEEL ROPE RAIL PIECE BACK FILLED EARTH HOOK HOOK STEEL ROPE HOOK PROPER GUYING ARRANGEMENT PROPER GUYING ARRANGEMENT
  • 58.
  • 59.
  • 60. After stringing ensure the following Any departures from the correct sag in any span does not exceed 4 percent. The sag of any conductor does not depart by more than 3% from the mean sag of all the conductors in the same span subject of a maximum of 150mm.
  • 61. i) BACK TENSION OF BOTH THE TENSION TOWERS OF SAG SECTION IS MOST IMPORTANT. PROVIDE BACK TENSION BY PAID OUT CONDUCTOR OF THE NEXT ADJACENT SECTION OF BOTH TENSION TOWERS. ii) BACK TENSION ON THE TOWER WITH GUY WIRE SHOULD BE AVOIDED. iii) IF REQUIRED PREPARE A SCHEME AND GOT IT APPROVED BY THE TECHNICAL CELL. iv) GUY WIRE CAPACITY SHOULD BE 1½ TIMES OF MAXIMUM TENSION OF THE CONDUCTORS. v) INSPECT THOROUGHLY THE CONDITION OF GUY WIRES BEFORE USED. vi) GUY FIXING ANGLE SHOULD BE BETWEEN 45 o TO 50 o TO THE VERTICAL. vii) GUY BLOCKING ARRANGEMENT SHOULD BE VERY CAREFULLY DONE. viii) RESPONSIBLE PERSONS SHOULD BE DEPLOYED DURING ENTIRE SAGGING OPERATION. ix) MEN ON BACK STAY SHOULD BE PROVIDED WITH APPROPRIATE WHISTLE AND COMMUNICATION. x) MEN ON BACK STAY SHOULD BE IN CONSTANT TOUCH WITH FINAL SAGGING PERSON.
  • 62. xi) ANY WHISTLE OR COMMUNICATION FROM THE PERSON AT BACK STAY, STRINGING SHOULD BE STOPPED. xii) IF NECESSARY CONDUCTOR SHOULD BE RELEASED TO DE-TENSION. xiii) FINAL SAGGING SHOULD BE DONE AS PER APPROVED SAG TENSION CHART. xiv) ANY CHANGES IN THE SECTION, SPAN MADE DURING THE CONSTRUCTION THE SAG TENSION CHART SHOULD BE GOT CORRECTED. xv) THE PERSON IN-CHARGE OF FINAL SAGGING SHOULD HAVE COPIES OF FINAL PROFILES, SAG TENSION CHART, FINAL TOWER SCHEDULE, SAG TEMPLATE, PROPER RECORDING REGISTER, FORMATS, ALL DRAWINGS OF HARDWARE AND ACCESSORIES. xvi) TWO THERMOMETERS SHOULD BE CLAMPED ON THE TOWER IN ADVANCE ON THE SAG SPAN. xvii) TEMPERATURE SHOULD BE CONSTANTLY MONITORED. xviii) NECESSARY CORRECTION OF SAG BOARD SHOULD BE DONE BEFORE FINAL MARKING OF CONDUCTOR. xix) ADEQUATE AND PROPER COMMUNICATION SHOULD BE AVAILABLE AT ALL POINTS CONTROLLING SAG AND BACK TENSION POINT.
  • 63. xi) ALL EQUIPMENT SHOULD BE LOAD TESTED BEFORE FINAL SAGGING OPERATION PLANNED. xii) USE SUITABLE DYNAMOMETERS TO CROSS CHECK SAG, SHORTER SPAN, HILLY TERRAIN. xiii) CHECK CONSTANTLY EVENNESS OF THE BUNDLE CONDUCTOR. xiv) KEEP CONSTANT CHECK ON THE MOVEMENT OF AERIAL ROLLER TO ENSURE INTERMEDIATE SPAN ALSO REACHED TO DESIRED SAG. xv) IN CASE ANY CONDUCTOR IS PULLED ABOVE SAG IN THE SAG SPAN THEN RELEASE BOTH THE CONDUCTORS TO BRING DOWN BELOW SAG AND BRING EVENNESS AND THEN RE-SAGGED. xvi) AVOID FINAL SAGGING IN WINDY DAYS, OTHER WISE ALLOWANCE IS TO BE GIVEN FOR UPLIFT. xvii) ALLOWANCE GIVING IS NOT DESIRABLE SINCE IT DEPENDS ON THE WIND AND EXPERIENCE. xviii) SPECIFIC CARE SHOULD BE TAKEN IN MEASURING FINALLY SAGGED CONDUCTOR BEFORE CUTTING & COMPRESSING THE DEAD END CLAMP.
  • 64.
  • 65.
  • 66. i) KEEP THE CONDUCTOR FINALLY SAGGED FOR 48HRS ON ROLLER. ii) AGAIN CHECK THE SAG AND RE-ADJUST IT IF NECESSARY. iii) KEEP SUSPENSION STRING ABSOLUTE VERTICAL. iv) PLUMB MARK THE CONDUCTOR BEFORE REMOVING ROLLER BY MEANS OF A PLUMB OR PLUMB MARKER MADE FOR SPECIFIC PURPOSE. v) THEN THE CONDUCTOR SHOULD BE LIFTED BY MEANS OF A SUITABLE LIFTING DEVICE. vi) LIFTING DEVICE MAY CONSIST OF ONE OR TWO HOOKS DEPENDING UPON NUMBER OF CONDUCTORS. vii) AFTER LIFTING THE CONDUCTOR FIX PREFORMED ARMOUR RODS. viii) TAKE 2 OR 3 RODS ON EACH SIDE OF THE CENTRE MARK SUCH THAT THE HAND WILL NOT BE MORE THAN ONE OR TWO PITCH LENGTHS AWAY FROM THE CENTRE MARK.
  • 67. ix) THE CENTRE MARK OF THE RODS SHOULD BE LOCATED AT THE CENTRE MARK OF THE CONDUCTOR SUPPORT. x) APPLY THE RODS BY ROTATING ABOUT CONDUCTOR CONTINUING FROM 1 OR 2 PITCH LENGTH OF EITHER SIDE OF THE CENTRE. xi) FIX ARMOUR ROD APPLYING SPIRAL MOTION OF THE HANDS UNTIL THEIR ENDS ARE SNAPPED INTO POSITION. xii) FIX SUSPENSION STRING OVER ARMOUR ROD THEN RELEASE THE LOAD. xiii) CHECK THE INSULATOR ASSEMBLY IS IN PLUMB. xiv) INSTALL VIBRATOR DAMPERS OR SPACER DAMPERS AS PER DRAWING at 1.2 to 1.3 m xv) IF VIBRATION DAMPERS ARE USED THEN FIX THE LINE SPACER IMMEDIATELY THERE AFTER.
  • 68. i) ALLOW THE FINALLY SAGGED CONDUCTOR FOR 48HRS TO TAKE CARE THE CREEPAGE OR MINOR SAG ERROR DUE TO MOVEMENT OF AERIAL ROLLER. ii) LIFTING DEVICE SHOULD BE FIXED IN SUCH A MANNER SO THAT LIFTING LOAD IS TRANSFERRED TO TOWER BODY. iii) AVOID POINTED LIFTING LOAD ON THE TIP OF CROSS ARM. iv) LIFTING HOOK SHOULD HAVE A RUBBER OR NEOPRENE LINING. v) MATCH THE CENTRE OF THE ARMOUR ROD WITH CENTRE MARK OF THE SUSPENSION POINT. vi) FIX VIBRATION DAMPERS OR SPACER DAMPER IMMEDIATELY SINCE THE CONDUCTOR AT FULL LOAD / CRITICAL TENSION. vii) FIX LINE SPACER IMMEDIATELY FOR BUNDLE CONDUCTOR TO AVOID CLASHING OF CONDUCTOR.
  • 69.
  • 70. i) MEASURE THE EXACT JUMPER LENGTH REQUIRED FOR EACH TENSION TOWER. ii) CHECK THE JUMPER DEPTH, ANGLE AS GIVEN IN THE ELECTRICAL CLEARANCE DIAGRAM. iii) PRESS THE JUMPER CONE AND FIX ON THE TOWER. iv) WHILE FIXING JUMPER THE CONDUCTOR SHOULD BE EARTHED PREFERABLY ON BOTH THE SIDES. v) IN CASE OF BUNDLE CONDUCTOR RIGID SPACER SHOULD BE FIXED AS PER THE RECOMMENDATIONS OF MANUFACTURER.
  • 71. Statutory Inspection points: S. No. Location No. Type of tower Chimney Coping Missing bolt & nuts HR weld Insulators Arcing horns Jumper bolt & nuts Jumpers Vibration Conductor Earth wire Earth wire bonds Number plates Danger boards Phase plates Step bolt & nuts Protection wall Ground clearance Tree clearance Other remarks

Editor's Notes

  1. FINAL
  2. FINAL
  3. FINAL
  4. FINAL
  5. FINAL
  6. FINAL
  7. FINAL
  8. FINAL
  9. FINAL
  10. FINAL
  11. FINAL
  12. FINAL
  13. FINAL
  14. FINAL
  15. FINAL
  16. FINAL
  17. FINAL
  18. FINAL
  19. FINAL
  20. FINAL
  21. FINAL
  22. FINAL
  23. FINAL
  24. FINAL
  25. FINAL
  26. FINAL
  27. FINAL
  28. FINAL
  29. FINAL