SlideShare ist ein Scribd-Unternehmen logo
1 von 26
TUNNEL ENGINEERING
SUBMITTED BY:-
Mohammad Iqbal
Regd no:- 0721211027
Civil Engineering
7th Semester
OEC,BBSR
INTRODUCTION
 Tunnels are underground passages used for
transportation. They could be used for carrying
freights and passengers, water, sewage, etc.
 The methods involved are underground operations
known as tunnel driving and the surface is not
disturbed
 It is understood that first tunnel was constructed by
Egyptians and Babylonians about 4000 years ago. It
was built to connect two buildings in Babylon. The
length, width, and height of this tunnel were 910
m, 360 cm, 450 cm respectively.
THAMES TUNNEL(LONDON)
ADVANTAGES OF TUNNELING
 Tunnels are more economical than open cuts beyond
certain depths
 Tunnels avoid disturbing or interfering with surface life
and traffic during construction
 Tunnels prove to be cheaper than bridges or open cuts to
carry public utility services like water, sewer and gas
 if tunnels are provided with easy gradients, the cost of
hauling is decreased
 In case of aerial warfare and bombing of cities, the
tunnels would grant better protection as compared to
bridges
ECONOMIES OF TUNNELING
 In general it depends on relative cost of open tunnel
vs tunelling some aspects are given below.
 Nature of soil, particularly in deep cutting, with the
consequent side slopes and volume of excavation
 If the soil is hard rock, the open cut could be of steep
slope, involving much less volume of excavation and
may prove cheaper
 The requirements of fill in the neighborhood also
largely influence the choice. If a large amount of
material is needed for the nearby fill, an open cut
may be justified
SELECTION OF ROUTE OF TUNNEL
 Alignment restraints: Underground space is a
heterogeneous mass and in addition, problems like
water table, position of fractured rocks etc. are to be
tackled. A through detailed inspection and evaluation
of the existing alignment restraints of underground
space should therefore be made & correlated with the
tunneling technology to be adopted for the project
 Environmental considerations: The site of tunnel
should be selected in such a way that the least
difficulty is experienced for various environmental
factors such as disposal of exhaust
gas, groundwater, muck, etc.
TUNNELLING THROUGH ROCK
 Full face method: The full face method is adopted only
for small tunnels whose dimensions do not exceed
about 3 m. The vertical columns are fixed at suitable
height. A series of drillholes about 10 mm to 40 mm
diameter are drilled at about 1200 mm centres.
 Heading & bench system: This is the method usually
adopted for all railway tunnels. The heading is the top
portion which will be 3700 mm to 4600 mm ahead of
the bottom portion known as bench.
 Cantilever car dump method: This arrangement
consists of two plate girders about 23 m long and fixed
at 1800 mm centres. A belt conveyor fitted with a
number of jacks is running on these plate girders, the
ends of which project beyond full face of the bench.
TUNNELLING THROUGH ROCKS
(CONTD)
 Drift system: In this system, a drift is first
driven of appropriate size, usually of 3000 mm
by 3000 mm. The drillholes are provided all
round the drift in entire cross section of tunnel.
 Pilot tunnel method: The pilot tunnel which is
first driven to full size is connected to the
centre-line of the main tunnel, can be started
from a number of holes. The pilot tunnel also
helps in removal of muck and the lighting and
ventilation of the main tunnel
ANCIENT METHOD OF DIGGING
TUNNEL THROUGH ROCKS
TUNNELLING THROUGH SOFT
GROUND
 Forepoling method: In this method, a frame in the
shape A is prepared and placed near the face of the
tunnel covered with suitable planks. The poles are then
inserted at top and continued to a depth upto which
they can be easily taken up. The forepoling is an old
method and it can be used successfully for carrying out
tunnelling operations through ground
 Needle beam method : This method is useful when the
soil is hard enough to stand for few minutes. A small
drift is prepared for inserting a needle beam consisting
of two I-girders and bolted together with a wooden
block in the centre.
TUNNELLING THROUGH SOFT
GROUND (CONTD)
 Five-piece set method: In this method, the widening
of the tunnel is carried out by using a set of timbering
consisting of five pieces.
 Liner plates method: In this method, the timbering is
replaced by pressed steel plates of standard sizes. The
advantages of this method are: They are light, Easy to
handle, Larger than timber pieces, require less
number of joints, They are fire-proof, They can be
erected by unskilled labour .
METHODS OF TUNNELLING
THROUGH SUB-AQUEOUS STRATA
 Shield tunnelling: A shield is a movable frame and it
is used to support the face of the tunnel. The
excavation & lining of tunnel can be carried out under
protection of shield
 Plenum process or compressed air tunnelling: In this
process, the use is made of compressed air to prevent
the collapse of sides and the top of the tunnel.
Theoretically 0.003 N/mm² air pressure is equivalent
to 305 mm of head of water. But practically 0.0035
N/mm² pressure will be required.
DRAINAGE OF TUNNELS
 Sumps & pumps: The sumps connected by a pipe line
are provided at a distance of about 300 m & water is
pumped from one sump to another until it is thrown
out of tunnel opening
 Grouting: The above method cannot be used, if water
is percolating from the top of the tunnel. In such
cases, the grouting is adopted to make the seams
water-tight.
 Pilot tunnel: In cases where pilot tunnel at a lower
level than the main tunnel is constructed parallel to it
for drainage of water
LIGHTING OF TUNNELS
 The situations which demand adequate light can be
obstructions in tunnel, drilling & mucking
zones, bottoms of shaft, storage points, pumping
stations, underground repair shops
 The spacing of lights will depend on various factors
such as tunnel dimensions, size of light source, nature
of rock surface
 The common types of lights used in tunnelling work
are acetylene gas lighting, electric lighting & lanterns
USE OF ELECTRIC LIGHTING
SHAFTS & MUCKING
 Shafts: The shafts are used for ventilation after
the construction of tunnel. They are also useful
to accommodate the pipes of fans during
construction work
 Mucking: In case of tunnelling through
rocks, the blasted rock or earth has to be
removed from the tunnel. This process is
known as mucking
A SHAFT IN TUNNEL
VENTILATION OF TUNNELS
 Blow-in method: In this method fresh air is
forced by a fan through a pipe & is supplied
near face. This method has the advantage that
a positive supply of fresh air is guaranteed
where it is required.
 Exhaust method: In this method the foul air is
pulled out through a pipe & is exhausted by a
fan. This sets up a current of fresh air to enter
the tunnel. This method has the advantage that
the foul air is kept out from working place.
INSIDE OF A TUNNEL
A TRANSIT RAILWAY TUNNEL
LINING OF TUNNELS
 The lining will be required in practically all
the tunnels to give a finishing touch to the
tunnel cross-section. Most common materials
used as lining are stones, bricks, cement
concrete, rubber & pre-cast pipes.
 In rocky ground, the lining can be carried out
in any one of following ways:
 Invert first and then sides & top
 Side walls first and then arch section and
then invert
 Full section in one operation
TYPES OF LINING MATERIALS
SHAPE & SIZE OF TUNNELS
 The size of the tunnel is determined by its utility. For
irrigation purpose, the tunnel is generally designed to
run full & if lining is of concrete, the velocity is taken
as 366 cm/sec. In case of road tunnels, it will depend
no. of traffic lanes & in case of railway tunnels, it
will depend on the no. of lines & type of gauge.
 The shape of tunnel is determined by the material of
which the cross-section is built & material through
which the tunnel is bored.
CROSS SECTION OF A TUNNEL
MAINTENANCE OF RAILWAY
TUNNELS
 The slopes of portals at entry & exit should be
checked.
 It should be seen whether the masonry has
crushed, cracked or deteriorated.
 The track through the tunnel should be in line and
level.
 The dimensions of tunnel should conform to original
dimensions.
 The lining of tunnel should be examined & checked if
it is in a satisfactory condition.
  Tunnel engineering

Weitere ähnliche Inhalte

Was ist angesagt?

Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railwayRAMPRASAD KUMAWAT
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian RailwayArbaz Kazi
 
Basics of Transportation Engineering
Basics of Transportation EngineeringBasics of Transportation Engineering
Basics of Transportation Engineeringkajol panchal
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway EngineeringLatif Hyder Wadho
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modulesbhalinder singh
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Railssrinivas2036
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and railsDeven Diran
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingssrinivas2036
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
 

Was ist angesagt? (20)

PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Cbr test
Cbr testCbr test
Cbr test
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian Railway
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Cross section of road
Cross section of roadCross section of road
Cross section of road
 
Well foundation
Well foundationWell foundation
Well foundation
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Basics of Transportation Engineering
Basics of Transportation EngineeringBasics of Transportation Engineering
Basics of Transportation Engineering
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modules
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and rails
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 

Andere mochten auch

Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnelspartha sharma
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpointishict
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machinerutuldave
 
Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Pirpasha Ujede
 
Top Down and Bottom Up Design Model
Top Down and Bottom Up Design ModelTop Down and Bottom Up Design Model
Top Down and Bottom Up Design ModelAbdul Rahman Sherzad
 
2 handouts-lecture-7
2  handouts-lecture-72  handouts-lecture-7
2 handouts-lecture-7Saleem Malik
 
Water cycle and water budget
Water cycle and water budgetWater cycle and water budget
Water cycle and water budgetMohsin Siddique
 
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway trackmohitjain123
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of RailwaySouvik Mondal
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the trackT.Naga Anusha
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingshiranrathva
 
Introduction to ground water hydrology
Introduction to ground water hydrologyIntroduction to ground water hydrology
Introduction to ground water hydrologyMohsin Siddique
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Hossam Shafiq II
 

Andere mochten auch (20)

Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpoint
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 
Top down
Top down Top down
Top down
 
Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing Geophysical methods of soil/Foundation testing
Geophysical methods of soil/Foundation testing
 
Geo-Physical Investigations
Geo-Physical InvestigationsGeo-Physical Investigations
Geo-Physical Investigations
 
Top Down and Bottom Up Design Model
Top Down and Bottom Up Design ModelTop Down and Bottom Up Design Model
Top Down and Bottom Up Design Model
 
Presentation on geophysical methods
Presentation on geophysical methodsPresentation on geophysical methods
Presentation on geophysical methods
 
2 handouts-lecture-7
2  handouts-lecture-72  handouts-lecture-7
2 handouts-lecture-7
 
Floods
FloodsFloods
Floods
 
Water cycle and water budget
Water cycle and water budgetWater cycle and water budget
Water cycle and water budget
 
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway track
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Introduction to ground water hydrology
Introduction to ground water hydrologyIntroduction to ground water hydrology
Introduction to ground water hydrology
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
 

Ähnlich wie Tunnel engineering

Ähnlich wie Tunnel engineering (20)

Tunneling
Tunneling Tunneling
Tunneling
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
3 tunnel
3 tunnel3 tunnel
3 tunnel
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
ALEEM MALIK
ALEEM MALIKALEEM MALIK
ALEEM MALIK
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Seminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptxSeminar Underground Construction PPT.pptx
Seminar Underground Construction PPT.pptx
 
Sewer Appurtenances
Sewer AppurtenancesSewer Appurtenances
Sewer Appurtenances
 
Tunnel PDF.pdf
Tunnel PDF.pdfTunnel PDF.pdf
Tunnel PDF.pdf
 
Tunnelling Methods.pdf
Tunnelling Methods.pdfTunnelling Methods.pdf
Tunnelling Methods.pdf
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
 

Tunnel engineering

  • 1. TUNNEL ENGINEERING SUBMITTED BY:- Mohammad Iqbal Regd no:- 0721211027 Civil Engineering 7th Semester OEC,BBSR
  • 2. INTRODUCTION  Tunnels are underground passages used for transportation. They could be used for carrying freights and passengers, water, sewage, etc.  The methods involved are underground operations known as tunnel driving and the surface is not disturbed  It is understood that first tunnel was constructed by Egyptians and Babylonians about 4000 years ago. It was built to connect two buildings in Babylon. The length, width, and height of this tunnel were 910 m, 360 cm, 450 cm respectively.
  • 4. ADVANTAGES OF TUNNELING  Tunnels are more economical than open cuts beyond certain depths  Tunnels avoid disturbing or interfering with surface life and traffic during construction  Tunnels prove to be cheaper than bridges or open cuts to carry public utility services like water, sewer and gas  if tunnels are provided with easy gradients, the cost of hauling is decreased  In case of aerial warfare and bombing of cities, the tunnels would grant better protection as compared to bridges
  • 5. ECONOMIES OF TUNNELING  In general it depends on relative cost of open tunnel vs tunelling some aspects are given below.  Nature of soil, particularly in deep cutting, with the consequent side slopes and volume of excavation  If the soil is hard rock, the open cut could be of steep slope, involving much less volume of excavation and may prove cheaper  The requirements of fill in the neighborhood also largely influence the choice. If a large amount of material is needed for the nearby fill, an open cut may be justified
  • 6. SELECTION OF ROUTE OF TUNNEL  Alignment restraints: Underground space is a heterogeneous mass and in addition, problems like water table, position of fractured rocks etc. are to be tackled. A through detailed inspection and evaluation of the existing alignment restraints of underground space should therefore be made & correlated with the tunneling technology to be adopted for the project  Environmental considerations: The site of tunnel should be selected in such a way that the least difficulty is experienced for various environmental factors such as disposal of exhaust gas, groundwater, muck, etc.
  • 7. TUNNELLING THROUGH ROCK  Full face method: The full face method is adopted only for small tunnels whose dimensions do not exceed about 3 m. The vertical columns are fixed at suitable height. A series of drillholes about 10 mm to 40 mm diameter are drilled at about 1200 mm centres.  Heading & bench system: This is the method usually adopted for all railway tunnels. The heading is the top portion which will be 3700 mm to 4600 mm ahead of the bottom portion known as bench.  Cantilever car dump method: This arrangement consists of two plate girders about 23 m long and fixed at 1800 mm centres. A belt conveyor fitted with a number of jacks is running on these plate girders, the ends of which project beyond full face of the bench.
  • 8. TUNNELLING THROUGH ROCKS (CONTD)  Drift system: In this system, a drift is first driven of appropriate size, usually of 3000 mm by 3000 mm. The drillholes are provided all round the drift in entire cross section of tunnel.  Pilot tunnel method: The pilot tunnel which is first driven to full size is connected to the centre-line of the main tunnel, can be started from a number of holes. The pilot tunnel also helps in removal of muck and the lighting and ventilation of the main tunnel
  • 9. ANCIENT METHOD OF DIGGING TUNNEL THROUGH ROCKS
  • 10. TUNNELLING THROUGH SOFT GROUND  Forepoling method: In this method, a frame in the shape A is prepared and placed near the face of the tunnel covered with suitable planks. The poles are then inserted at top and continued to a depth upto which they can be easily taken up. The forepoling is an old method and it can be used successfully for carrying out tunnelling operations through ground  Needle beam method : This method is useful when the soil is hard enough to stand for few minutes. A small drift is prepared for inserting a needle beam consisting of two I-girders and bolted together with a wooden block in the centre.
  • 11. TUNNELLING THROUGH SOFT GROUND (CONTD)  Five-piece set method: In this method, the widening of the tunnel is carried out by using a set of timbering consisting of five pieces.  Liner plates method: In this method, the timbering is replaced by pressed steel plates of standard sizes. The advantages of this method are: They are light, Easy to handle, Larger than timber pieces, require less number of joints, They are fire-proof, They can be erected by unskilled labour .
  • 12. METHODS OF TUNNELLING THROUGH SUB-AQUEOUS STRATA  Shield tunnelling: A shield is a movable frame and it is used to support the face of the tunnel. The excavation & lining of tunnel can be carried out under protection of shield  Plenum process or compressed air tunnelling: In this process, the use is made of compressed air to prevent the collapse of sides and the top of the tunnel. Theoretically 0.003 N/mm² air pressure is equivalent to 305 mm of head of water. But practically 0.0035 N/mm² pressure will be required.
  • 13. DRAINAGE OF TUNNELS  Sumps & pumps: The sumps connected by a pipe line are provided at a distance of about 300 m & water is pumped from one sump to another until it is thrown out of tunnel opening  Grouting: The above method cannot be used, if water is percolating from the top of the tunnel. In such cases, the grouting is adopted to make the seams water-tight.  Pilot tunnel: In cases where pilot tunnel at a lower level than the main tunnel is constructed parallel to it for drainage of water
  • 14. LIGHTING OF TUNNELS  The situations which demand adequate light can be obstructions in tunnel, drilling & mucking zones, bottoms of shaft, storage points, pumping stations, underground repair shops  The spacing of lights will depend on various factors such as tunnel dimensions, size of light source, nature of rock surface  The common types of lights used in tunnelling work are acetylene gas lighting, electric lighting & lanterns
  • 15. USE OF ELECTRIC LIGHTING
  • 16. SHAFTS & MUCKING  Shafts: The shafts are used for ventilation after the construction of tunnel. They are also useful to accommodate the pipes of fans during construction work  Mucking: In case of tunnelling through rocks, the blasted rock or earth has to be removed from the tunnel. This process is known as mucking
  • 17. A SHAFT IN TUNNEL
  • 18. VENTILATION OF TUNNELS  Blow-in method: In this method fresh air is forced by a fan through a pipe & is supplied near face. This method has the advantage that a positive supply of fresh air is guaranteed where it is required.  Exhaust method: In this method the foul air is pulled out through a pipe & is exhausted by a fan. This sets up a current of fresh air to enter the tunnel. This method has the advantage that the foul air is kept out from working place.
  • 19. INSIDE OF A TUNNEL
  • 21. LINING OF TUNNELS  The lining will be required in practically all the tunnels to give a finishing touch to the tunnel cross-section. Most common materials used as lining are stones, bricks, cement concrete, rubber & pre-cast pipes.  In rocky ground, the lining can be carried out in any one of following ways:  Invert first and then sides & top  Side walls first and then arch section and then invert  Full section in one operation
  • 22. TYPES OF LINING MATERIALS
  • 23. SHAPE & SIZE OF TUNNELS  The size of the tunnel is determined by its utility. For irrigation purpose, the tunnel is generally designed to run full & if lining is of concrete, the velocity is taken as 366 cm/sec. In case of road tunnels, it will depend no. of traffic lanes & in case of railway tunnels, it will depend on the no. of lines & type of gauge.  The shape of tunnel is determined by the material of which the cross-section is built & material through which the tunnel is bored.
  • 24. CROSS SECTION OF A TUNNEL
  • 25. MAINTENANCE OF RAILWAY TUNNELS  The slopes of portals at entry & exit should be checked.  It should be seen whether the masonry has crushed, cracked or deteriorated.  The track through the tunnel should be in line and level.  The dimensions of tunnel should conform to original dimensions.  The lining of tunnel should be examined & checked if it is in a satisfactory condition.