1 of 18
Contact
Awareness
“I’ve heard about the project”
Understanding
2
3
4
5
6
7
Engagement
“I want to know more about the project”
Acceptance
“The project is going to happen”
Commitment
“I want to help make the implementation work”
Internalisation
“It’s the way we do things here”
1
LevelofCommitment
Time
Stakeholder Management
2 of 18
What is Stakeholder Management?
Stakeholder Management is forming and maintaining relationships with stakeholders and
influencing them in order to achieve an objective – or at least not undermine it
An objective might be identifying new opportunities, winning a bid or delivering a project
A Stakeholder is any person or group with interest in or impacted by the objective
– either positively or negatively
Stakeholder Management is two-way communication and incorporation of feedback to:
build and sustain appropriate levels of commitment to the objective
identify and mitigate resistance
Who are the most important stakeholders?
Those who can stop you achieving the objective
3 of 18
The Business Network
Objective
Stakeholder
Management
Budget
Owners
UsersPartners
Account
Management
Project
Delivery
BidCaptureCampaign
Influence to
achieve an
objective
Gather
intelligence to
inform a bid
Managing
stakeholders common
to an organisation
Delivering a
winning bid
Delivering a
successful
outcome
Keeping all
stakeholders
on board
Miller Heiman:
Economic Buyer
4 of 18
When is Stakeholder Management done?
Stakeholder Management starts as soon as the objective is agreed
and continues until the objective has been achieved
A pre-defined approach should include:
A process of stakeholder identification, analysis and on-going monitoring to drive the
actions required to build appropriate levels of support and deal with any issues
Key messages around business rationale, benefits, transition plans & impacts
Stakeholder Management roles and responsibilities
5 of 18
Why do Stakeholder Management?
Stakeholders may significantly influence the success or otherwise of achieving the objective
Stakeholders will have a variety of understandings, expectations and levels of commitment
So it is vital to understand:
Who are the interested parties?
What is their reaction to the objective?
What is their role within the interested community?
What are their current and future levels of commitment?
What level of power and influence do they have?
Who or what influences the stakeholder?
Stakeholder Management will enable effective time management
6 of 18
Stakeholder Management Process
Identify
Name each stakeholder and determine their interest in the
objective and what information they will require
Assess
Understand the level of interest, influence and commitment of
the stakeholder to appropriately manage them
Plan
Record the required level of engagement, any change needed and
name of the gatekeeper in a Stakeholder Management Plan
Create a Stakeholder Map to visualise groupings and relationships
Act
Engage with stakeholders as planned
Regularly review and update the Stakeholder Management Plan
7 of 18
Identify Stakeholders
Stakeholders can be individuals, groups, functions or organisations and fall into categories:
Those groups or individuals impacted by the objective
Those whose involvement is essential
Those able to influence the outcome
Those who just need to be kept informed
requiring communications but not themselves impacted by the objective
The Gatekeeper is the main point of contact who will manage each stakeholder
All contact should be co-ordinated through the gatekeeper
There may other colleagues who play a supporting role
It may be necessary or desirable to manage a stakeholder indirectly
– perhaps by managing someone who has influence over them
8 of 18
Identify Possible Stakeholders
Objective
Business
Development
Division
Heads
Executive
Support
Groups
Engineering
Groups
Commercial
Procurement
Executive
Requirement
Owners
Users
Business
Development
Commercial
Executive
Operational
Commercial
Standards
General
Public
Lobbyists
Groups
Internal
External Customers
Suppliers
Partners
9 of 18
Assess: Where are they on the Commitment Curve
Where they are now
Where we need them in 5 weeks
Contact
Awareness
“I’ve heard about the project”
Understanding
2
3
4
5
6
7
Where we need them in 3 weeks
Engagement
“I want to know more about the project”
Acceptance
“The project is going to happen”
Commitment
“I want to help make the implementation work”
Internalisation
“It’s the way we do things here”
1
LevelofCommitment
Time
Visualise where stakeholders are now and where we want to get them to in the future
10 of 18
Assess: Analyse for each Stakeholder
How are they affected?
What are the changes they will face?
What are the benefits and disadvantages to them?
What is their reaction?
ChangeDrivers
Where are they now on the commitment curve? How do we know?
What are our concerns?
What are their concerns?
What issues do they have?
Where do we want them on the commitment curve?
How will we know when they are there? What will we be seeing / hearing?
What do we need them to do?
Do they have any requirements of us?
RequirementsConcernsActions
How do we get them up the commitment curve?
Who owns the actions?
When do we need to contact them?
What contact has there been to date?
Who has been speaking to them?
What category stakeholder are they?
Impacted – Involved – Influencers – Keep Informed
Supporter – Opponent – Enthusiast – Neutral – Unknown
Light Touch or Firm Control
To build commitment
and surface resistance
in the required timescale
11 of 18
Plan: Stakeholder Map
Internal
ObjectiveName – Project Manager
+5D H
Name – Technical Authority
+5D H
Users
Customer
Gatekeeper
User – Function – details
+2U M
Prime
Gatekeeper
P Rime – Prime PM – details
+2D H
Name – System Architect
+5D H
Gatekeeper
Name – Customer PM – details
+5E H
Sub
Contractors
P Rime
S Contractor – SC PM – details
+2T M
Stakeholder Template
Stakeholder – Title, Location
Gatekeeper
U M +2
12 of 18
Plan: Stakeholder Management Plan
Stakeholder Analysis
Project Name: ProjectID ProjectName
Stakeholder Marker(s) & Influencer(s) Change Drivers Rating
How
Affected
Commitment Curve
#
Buying
Influence
Name Title Location Role
Degree
of
Influence
Mode
Gatekeeper
(Gatekeeper
Supporter)
Stakeholder
Influencer(s)
Key Wins & Results
Benefits &
Disadvantages
-5 to +5
Involve
Inform
Impacted
Influencer
Now Desired By When
Customer
1 Y I L
2 Y E M
Macro to copy selected Stakeholder data
(those selected as Buying Influence in column 2)
to Miller Heiman (MH) Blue Sheet
for Single Sales Objective Analysis
Place the
Stakeholder on the
Commitment Curve
Decide how the
Stakeholder is affected
MH Rating for the
Stakeholder
+5 (Enthusiastic Advocate) to
-5 (Antagonistic Anti-Sponsor)
MH Buying
Influence Role
E/U/T/C/D/I
MH Mode
G/T/EK/OC
Main Point
of Contact
MH Wins
& Results
13 of 18
Plan: Level of Control
Firm Control
Stakeholders whose engagement requires very tight co-ordination and control
Light Touch
Stakeholders who don’t require tight control
Contact or communication
with a Stakeholder where
not the Gatekeeper:
ASK the Gatekeeper first
Contact
Process
Gatekeeper authorises and
provides current status of
the relationship from their
information and Stakeholder
Management Plan
Contact the Stakeholder,
document any significant
outcome and send to
Gatekeeper
Contact or communication
with a Stakeholder where
not the Gatekeeper
Contact
Process
Refer to Stakeholder Plan to
obtain latest position
Optional: Ask Gatekeeper for
their view on current status
of the relationship
Contact Stakeholder and
inform Gatekeeper of
significant outcomes
14 of 18
Plan: Gatekeepers
Lead Stakeholder engagement maintaining an overview of current relationship status
Act as the co-ordination point for liaison with Stakeholders, pre-authorising contact with
Stakeholders in the Firm Control category
Identify and implement the activities necessary to build the required levels of Stakeholder
support and buy-in
Record all analysis and regularly update the Stakeholder Management Plan to provide a
complete history of contacts and significant responses
Highlight issues as they arise and identify actions to address them
Escalate serious Stakeholder issues & risks as required
Communicate consistent, clear and agreed messages
15 of 18
Act: Flagging Stakeholders - Examples
There are issues or concerns present for which no resolution is currently identified
Stakeholder has refused to sign off material
Stakeholder has the power to delay the project and is deemed likely to do so
Stakeholder is communicating negative messages about the project
Stakeholder not at the required point on the commitment curve but unlikely to delay progress
Stakeholder raised issues or concerns which are being managed, unresolved to date, but can be resolved
Stakeholder not signed-off or seen material on schedule but no reason to believe they will raise issues
Insufficient contact to enable Gatekeeper to make reliable status assessment – status unknown
Stakeholder has seen and approved all relevant material for the current stage of the project
All Stakeholder issues addressed to their satisfaction at this stage
Stakeholder at the required point on the commitment curve for this stage of the project
16 of 18
Act: Validation & Maintenance
Has the whole lifecycle and every aspect of the programme been considered?
e.g. all technical, managerial and organisational impacts
All appropriate reporting lines covered for the Stakeholders identified?
Avoid ‘black holes’ i.e. ensure an awareness at all appropriate levels
Does everyone understand the content of the Stakeholder Management Plan?
Is it clear, specific and unambiguous?
Actions sufficient to build required commitment and surface resistance in the timescale?
How will progress along the commitment curve be measured?
What will Stakeholders be saying and doing at each stage?
Do the actions focus on priority Stakeholders in relation to timing of impact?
17 of 18
Cautions
Stakeholder Management Plan content must comply with Data Protection Legislation
Data protection legislation entitles individuals access to information recorded about them
Only record fact, not assumptions or perceptions
18 of 18
Author Profile
In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m
project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP,
the Roke Engineering Process, also managing the engineering tools to support it.
After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer,
I moved into project management for 14 years, at Siemens and Roke Manor Research.
Successfully delivering Roke’s most challenging whole lifecycle product developments
on time and under budget led to a role as Director and board member for 6 years.
In 2013 I returned to hands-on project management as Programme Director at
Cambridge Consultants, founder member of the Cambridge Science Park.
Creator of the APM corporate accredited PM Excellence Programme,
I chaired a quarterly PM forum to share best practice and built a
supportive PM community. I coached seven PMs to RPP, five to PQ,
and all passed APMP.
These investments in PM professionalism led to a turn-around and
annual improvement in project results across a 400 project portfolio
and delivered an above budget performance in five consecutive years
with profits totalling £7.9m above budget.
Passionate advocate of PM professionalism, Fellow of the APM and
the IET and author of articles published in Project and PM Today.
Professional Development
Winning Project Work
Planning
Estimating
Risk Management
Earned Value Management
Change Control
Stakeholder Management
3 Steps to Professional Project Management: Case Study
ProjectManagementTopics

Weitere ähnliche Inhalte

Was ist angesagt?

Stakeholder engagement and management
Stakeholder engagement and managementStakeholder engagement and management
Stakeholder engagement and managementSimon Misiewicz
 
Stakeholder management - a short introduction
Stakeholder management - a short introduction Stakeholder management - a short introduction
Stakeholder management - a short introduction Vincenzo Capozzoli
 
Lecture Five - Stakeholders, external and internal
Lecture Five - Stakeholders, external and internal Lecture Five - Stakeholders, external and internal
Lecture Five - Stakeholders, external and internal Innovation Forum Publishing
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
Project Stakeholder Engagement
Project Stakeholder EngagementProject Stakeholder Engagement
Project Stakeholder EngagementMark Ritchie
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Agus Suhanto
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewAnand Bobade
 
Stakeholder analysis scm
Stakeholder analysis scmStakeholder analysis scm
Stakeholder analysis scmADRIANFRANKLIN5
 
4 Steps for Improved Stakeholder Engagement
4 Steps for Improved Stakeholder Engagement4 Steps for Improved Stakeholder Engagement
4 Steps for Improved Stakeholder EngagementBrightWork
 
Project stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela AnyomiProject stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela AnyomiNelson Mandela Anyomi
 

Was ist angesagt? (20)

Stakeholder engagement and management
Stakeholder engagement and managementStakeholder engagement and management
Stakeholder engagement and management
 
Stakeholder Engagement
Stakeholder EngagementStakeholder Engagement
Stakeholder Engagement
 
Stakeholder management - a short introduction
Stakeholder management - a short introduction Stakeholder management - a short introduction
Stakeholder management - a short introduction
 
Stakeholder management
Stakeholder managementStakeholder management
Stakeholder management
 
Lecture Five - Stakeholders, external and internal
Lecture Five - Stakeholders, external and internal Lecture Five - Stakeholders, external and internal
Lecture Five - Stakeholders, external and internal
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
Project Stakeholder Engagement
Project Stakeholder EngagementProject Stakeholder Engagement
Project Stakeholder Engagement
 
Stakeholder Engagement vs Stakeholder Management
Stakeholder Engagement vs Stakeholder ManagementStakeholder Engagement vs Stakeholder Management
Stakeholder Engagement vs Stakeholder Management
 
Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6Project Stakeholder Management - PMBOK6
Project Stakeholder Management - PMBOK6
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management Overview
 
Stakeholder analysis scm
Stakeholder analysis scmStakeholder analysis scm
Stakeholder analysis scm
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Project Stakeholder Management
Project Stakeholder ManagementProject Stakeholder Management
Project Stakeholder Management
 
4 Steps for Improved Stakeholder Engagement
4 Steps for Improved Stakeholder Engagement4 Steps for Improved Stakeholder Engagement
4 Steps for Improved Stakeholder Engagement
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela AnyomiProject stakeholder management by Nelson Mandela Anyomi
Project stakeholder management by Nelson Mandela Anyomi
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Stakeholder Analysis
Stakeholder AnalysisStakeholder Analysis
Stakeholder Analysis
 
Program Management
Program ManagementProgram Management
Program Management
 
Stakeholder management
Stakeholder managementStakeholder management
Stakeholder management
 

Ähnlich wie Stakeholder Management

Health Systems Identifying and Managing Stakeholders
Health Systems Identifying and Managing Stakeholders Health Systems Identifying and Managing Stakeholders
Health Systems Identifying and Managing Stakeholders Alaa Hamed
 
10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.pptItcHcm1
 
Module 18 - Stakeholder Management.pptx
Module 18 - Stakeholder Management.pptxModule 18 - Stakeholder Management.pptx
Module 18 - Stakeholder Management.pptxcaniceconsulting
 
What is the Risk in Steering Committee?
What is the Risk in Steering Committee?What is the Risk in Steering Committee?
What is the Risk in Steering Committee?Christine Aykac
 
Project Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docxProject Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docxZiyad Zaidi
 
ISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsMichael Punzo
 
ISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsMichael Punzo
 
Best_Practices_Managing_Stakeholder_Expectations
Best_Practices_Managing_Stakeholder_ExpectationsBest_Practices_Managing_Stakeholder_Expectations
Best_Practices_Managing_Stakeholder_ExpectationsPatricia J. Williams, PMP
 
2.13 stakeholder management 1
2.13  stakeholder management 12.13  stakeholder management 1
2.13 stakeholder management 1reddvise
 
Stakeholder management presentation
Stakeholder management presentationStakeholder management presentation
Stakeholder management presentationSusan Mansfield
 
Stakeholder engagement and management
Stakeholder engagement and managementStakeholder engagement and management
Stakeholder engagement and managementAndre Knipe
 
Stakeholder Analysis
Stakeholder AnalysisStakeholder Analysis
Stakeholder AnalysisAsraHafeez
 
Understanding and Engaging Stakeholders through Stakeholder Analysis
Understanding and Engaging Stakeholders through Stakeholder AnalysisUnderstanding and Engaging Stakeholders through Stakeholder Analysis
Understanding and Engaging Stakeholders through Stakeholder AnalysisCIToolkit
 
Project stakeholder management
Project stakeholder managementProject stakeholder management
Project stakeholder managementSaad Al Jabri
 

Ähnlich wie Stakeholder Management (20)

1610818657077 stakeholder pp ppt
1610818657077 stakeholder pp ppt1610818657077 stakeholder pp ppt
1610818657077 stakeholder pp ppt
 
Stakeholders
StakeholdersStakeholders
Stakeholders
 
Health Systems Identifying and Managing Stakeholders
Health Systems Identifying and Managing Stakeholders Health Systems Identifying and Managing Stakeholders
Health Systems Identifying and Managing Stakeholders
 
10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt10. PMP Project Stakeholder Management.ppt
10. PMP Project Stakeholder Management.ppt
 
Module 18 - Stakeholder Management.pptx
Module 18 - Stakeholder Management.pptxModule 18 - Stakeholder Management.pptx
Module 18 - Stakeholder Management.pptx
 
What is the Risk in Steering Committee?
What is the Risk in Steering Committee?What is the Risk in Steering Committee?
What is the Risk in Steering Committee?
 
Project Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docxProject Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docx
 
ISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectations
 
ISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectations
 
Best_Practices_Managing_Stakeholder_Expectations
Best_Practices_Managing_Stakeholder_ExpectationsBest_Practices_Managing_Stakeholder_Expectations
Best_Practices_Managing_Stakeholder_Expectations
 
Stakeholders Analysis
Stakeholders AnalysisStakeholders Analysis
Stakeholders Analysis
 
2.13 stakeholder management 1
2.13  stakeholder management 12.13  stakeholder management 1
2.13 stakeholder management 1
 
Stakeholder management _1
Stakeholder management _1Stakeholder management _1
Stakeholder management _1
 
Stakeholder management presentation
Stakeholder management presentationStakeholder management presentation
Stakeholder management presentation
 
Stakeholder engagement and management
Stakeholder engagement and managementStakeholder engagement and management
Stakeholder engagement and management
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
Stakeholder Analysis
Stakeholder AnalysisStakeholder Analysis
Stakeholder Analysis
 
Understanding and Engaging Stakeholders through Stakeholder Analysis
Understanding and Engaging Stakeholders through Stakeholder AnalysisUnderstanding and Engaging Stakeholders through Stakeholder Analysis
Understanding and Engaging Stakeholders through Stakeholder Analysis
 
Project stakeholder management
Project stakeholder managementProject stakeholder management
Project stakeholder management
 
Stakeholder Communication
Stakeholder CommunicationStakeholder Communication
Stakeholder Communication
 

Mehr von Russell Taylor BEng CEng FAPM FIET (7)

Change Control
Change ControlChange Control
Change Control
 
Winning Project Work
Winning Project WorkWinning Project Work
Winning Project Work
 
Planning
PlanningPlanning
Planning
 
Estimating
EstimatingEstimating
Estimating
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PM Professional Development
PM Professional DevelopmentPM Professional Development
PM Professional Development
 

Kürzlich hochgeladen

Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 

Kürzlich hochgeladen (16)

Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 

Stakeholder Management

  • 1. 1 of 18 Contact Awareness “I’ve heard about the project” Understanding 2 3 4 5 6 7 Engagement “I want to know more about the project” Acceptance “The project is going to happen” Commitment “I want to help make the implementation work” Internalisation “It’s the way we do things here” 1 LevelofCommitment Time Stakeholder Management
  • 2. 2 of 18 What is Stakeholder Management? Stakeholder Management is forming and maintaining relationships with stakeholders and influencing them in order to achieve an objective – or at least not undermine it An objective might be identifying new opportunities, winning a bid or delivering a project A Stakeholder is any person or group with interest in or impacted by the objective – either positively or negatively Stakeholder Management is two-way communication and incorporation of feedback to: build and sustain appropriate levels of commitment to the objective identify and mitigate resistance Who are the most important stakeholders? Those who can stop you achieving the objective
  • 3. 3 of 18 The Business Network Objective Stakeholder Management Budget Owners UsersPartners Account Management Project Delivery BidCaptureCampaign Influence to achieve an objective Gather intelligence to inform a bid Managing stakeholders common to an organisation Delivering a winning bid Delivering a successful outcome Keeping all stakeholders on board Miller Heiman: Economic Buyer
  • 4. 4 of 18 When is Stakeholder Management done? Stakeholder Management starts as soon as the objective is agreed and continues until the objective has been achieved A pre-defined approach should include: A process of stakeholder identification, analysis and on-going monitoring to drive the actions required to build appropriate levels of support and deal with any issues Key messages around business rationale, benefits, transition plans & impacts Stakeholder Management roles and responsibilities
  • 5. 5 of 18 Why do Stakeholder Management? Stakeholders may significantly influence the success or otherwise of achieving the objective Stakeholders will have a variety of understandings, expectations and levels of commitment So it is vital to understand: Who are the interested parties? What is their reaction to the objective? What is their role within the interested community? What are their current and future levels of commitment? What level of power and influence do they have? Who or what influences the stakeholder? Stakeholder Management will enable effective time management
  • 6. 6 of 18 Stakeholder Management Process Identify Name each stakeholder and determine their interest in the objective and what information they will require Assess Understand the level of interest, influence and commitment of the stakeholder to appropriately manage them Plan Record the required level of engagement, any change needed and name of the gatekeeper in a Stakeholder Management Plan Create a Stakeholder Map to visualise groupings and relationships Act Engage with stakeholders as planned Regularly review and update the Stakeholder Management Plan
  • 7. 7 of 18 Identify Stakeholders Stakeholders can be individuals, groups, functions or organisations and fall into categories: Those groups or individuals impacted by the objective Those whose involvement is essential Those able to influence the outcome Those who just need to be kept informed requiring communications but not themselves impacted by the objective The Gatekeeper is the main point of contact who will manage each stakeholder All contact should be co-ordinated through the gatekeeper There may other colleagues who play a supporting role It may be necessary or desirable to manage a stakeholder indirectly – perhaps by managing someone who has influence over them
  • 8. 8 of 18 Identify Possible Stakeholders Objective Business Development Division Heads Executive Support Groups Engineering Groups Commercial Procurement Executive Requirement Owners Users Business Development Commercial Executive Operational Commercial Standards General Public Lobbyists Groups Internal External Customers Suppliers Partners
  • 9. 9 of 18 Assess: Where are they on the Commitment Curve Where they are now Where we need them in 5 weeks Contact Awareness “I’ve heard about the project” Understanding 2 3 4 5 6 7 Where we need them in 3 weeks Engagement “I want to know more about the project” Acceptance “The project is going to happen” Commitment “I want to help make the implementation work” Internalisation “It’s the way we do things here” 1 LevelofCommitment Time Visualise where stakeholders are now and where we want to get them to in the future
  • 10. 10 of 18 Assess: Analyse for each Stakeholder How are they affected? What are the changes they will face? What are the benefits and disadvantages to them? What is their reaction? ChangeDrivers Where are they now on the commitment curve? How do we know? What are our concerns? What are their concerns? What issues do they have? Where do we want them on the commitment curve? How will we know when they are there? What will we be seeing / hearing? What do we need them to do? Do they have any requirements of us? RequirementsConcernsActions How do we get them up the commitment curve? Who owns the actions? When do we need to contact them? What contact has there been to date? Who has been speaking to them? What category stakeholder are they? Impacted – Involved – Influencers – Keep Informed Supporter – Opponent – Enthusiast – Neutral – Unknown Light Touch or Firm Control To build commitment and surface resistance in the required timescale
  • 11. 11 of 18 Plan: Stakeholder Map Internal ObjectiveName – Project Manager +5D H Name – Technical Authority +5D H Users Customer Gatekeeper User – Function – details +2U M Prime Gatekeeper P Rime – Prime PM – details +2D H Name – System Architect +5D H Gatekeeper Name – Customer PM – details +5E H Sub Contractors P Rime S Contractor – SC PM – details +2T M Stakeholder Template Stakeholder – Title, Location Gatekeeper U M +2
  • 12. 12 of 18 Plan: Stakeholder Management Plan Stakeholder Analysis Project Name: ProjectID ProjectName Stakeholder Marker(s) & Influencer(s) Change Drivers Rating How Affected Commitment Curve # Buying Influence Name Title Location Role Degree of Influence Mode Gatekeeper (Gatekeeper Supporter) Stakeholder Influencer(s) Key Wins & Results Benefits & Disadvantages -5 to +5 Involve Inform Impacted Influencer Now Desired By When Customer 1 Y I L 2 Y E M Macro to copy selected Stakeholder data (those selected as Buying Influence in column 2) to Miller Heiman (MH) Blue Sheet for Single Sales Objective Analysis Place the Stakeholder on the Commitment Curve Decide how the Stakeholder is affected MH Rating for the Stakeholder +5 (Enthusiastic Advocate) to -5 (Antagonistic Anti-Sponsor) MH Buying Influence Role E/U/T/C/D/I MH Mode G/T/EK/OC Main Point of Contact MH Wins & Results
  • 13. 13 of 18 Plan: Level of Control Firm Control Stakeholders whose engagement requires very tight co-ordination and control Light Touch Stakeholders who don’t require tight control Contact or communication with a Stakeholder where not the Gatekeeper: ASK the Gatekeeper first Contact Process Gatekeeper authorises and provides current status of the relationship from their information and Stakeholder Management Plan Contact the Stakeholder, document any significant outcome and send to Gatekeeper Contact or communication with a Stakeholder where not the Gatekeeper Contact Process Refer to Stakeholder Plan to obtain latest position Optional: Ask Gatekeeper for their view on current status of the relationship Contact Stakeholder and inform Gatekeeper of significant outcomes
  • 14. 14 of 18 Plan: Gatekeepers Lead Stakeholder engagement maintaining an overview of current relationship status Act as the co-ordination point for liaison with Stakeholders, pre-authorising contact with Stakeholders in the Firm Control category Identify and implement the activities necessary to build the required levels of Stakeholder support and buy-in Record all analysis and regularly update the Stakeholder Management Plan to provide a complete history of contacts and significant responses Highlight issues as they arise and identify actions to address them Escalate serious Stakeholder issues & risks as required Communicate consistent, clear and agreed messages
  • 15. 15 of 18 Act: Flagging Stakeholders - Examples There are issues or concerns present for which no resolution is currently identified Stakeholder has refused to sign off material Stakeholder has the power to delay the project and is deemed likely to do so Stakeholder is communicating negative messages about the project Stakeholder not at the required point on the commitment curve but unlikely to delay progress Stakeholder raised issues or concerns which are being managed, unresolved to date, but can be resolved Stakeholder not signed-off or seen material on schedule but no reason to believe they will raise issues Insufficient contact to enable Gatekeeper to make reliable status assessment – status unknown Stakeholder has seen and approved all relevant material for the current stage of the project All Stakeholder issues addressed to their satisfaction at this stage Stakeholder at the required point on the commitment curve for this stage of the project
  • 16. 16 of 18 Act: Validation & Maintenance Has the whole lifecycle and every aspect of the programme been considered? e.g. all technical, managerial and organisational impacts All appropriate reporting lines covered for the Stakeholders identified? Avoid ‘black holes’ i.e. ensure an awareness at all appropriate levels Does everyone understand the content of the Stakeholder Management Plan? Is it clear, specific and unambiguous? Actions sufficient to build required commitment and surface resistance in the timescale? How will progress along the commitment curve be measured? What will Stakeholders be saying and doing at each stage? Do the actions focus on priority Stakeholders in relation to timing of impact?
  • 17. 17 of 18 Cautions Stakeholder Management Plan content must comply with Data Protection Legislation Data protection legislation entitles individuals access to information recorded about them Only record fact, not assumptions or perceptions
  • 18. 18 of 18 Author Profile In my board role I led a team of 22 Project Managers and 5 Quality Engineers, and ensured Roke’s £79m project portfolio delivered better than budget profit. I set-up and ran a virtual PMO and created REP, the Roke Engineering Process, also managing the engineering tools to support it. After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer, I moved into project management for 14 years, at Siemens and Roke Manor Research. Successfully delivering Roke’s most challenging whole lifecycle product developments on time and under budget led to a role as Director and board member for 6 years. In 2013 I returned to hands-on project management as Programme Director at Cambridge Consultants, founder member of the Cambridge Science Park. Creator of the APM corporate accredited PM Excellence Programme, I chaired a quarterly PM forum to share best practice and built a supportive PM community. I coached seven PMs to RPP, five to PQ, and all passed APMP. These investments in PM professionalism led to a turn-around and annual improvement in project results across a 400 project portfolio and delivered an above budget performance in five consecutive years with profits totalling £7.9m above budget. Passionate advocate of PM professionalism, Fellow of the APM and the IET and author of articles published in Project and PM Today. Professional Development Winning Project Work Planning Estimating Risk Management Earned Value Management Change Control Stakeholder Management 3 Steps to Professional Project Management: Case Study ProjectManagementTopics