Introduction to Machine Learning Unit-3 for II MECH
Â
SEWAGE TREATMENT PLANT,LUCKNOW
1. Presentation On
SEWAGE TREATMENT
PLANT,LUCKNOW
SHASWAT MISHRA
B.TECH (CIVIL)
111000138
AERIAL VIEW OF 345 MLD STP UASB AT BHARWARA
2. SEWAGE TREATMENT PLANT
⢠Constructed at a cost of around Rs360 crore, the STP has three channels
each of 113mld. The channels are fed by the Gwari pumping station in
Gomtinagar drawing sewage from two subsidiary pumping stations each
situated on two major canals â Kukrail canal and Ghiasuddin Haider
canal.
⢠The two pumping stations would pump their sewage to the Main Pumping
Station (MPS) in Gwari culvert that will further pump the sewage to the
STP in Bharwara. The STP will produce 400 cubic metres of methane gas
per hour, which will generate 1,200-1,500 KW electricity that will be used
to run the plant. Work on the Rs169-crore STP project had started in 2008
3. GENERAL OUTLINES OF SEWAGE
TREATMENT
Sewage treatment, or domestic
wastewater treatment, is the process of
removing contaminants from wastewater,
both runoff(effluents)and domestic. It
includes physical, chemical and
biological processes to remove physical,
chemical and biological contaminants. Its
objective is to produce a waste stream (or
treated )and a solid waste or sludge
suitable for discharge or reuse back into
the environment.
Industrial sources of wastewater often require
specialized treatment processes the sewage
treatment involves three stages,
called primary, secondary and tertiary
treatment .First, the solids are separated from
the wastewater stream. Then dissolved
biological matter is progressively converted
into a solid mass by using indigenous, water-borne
microorganisms. Finally, the biological
solids are neutralized then disposed of or re-used,
and the treated water may be disinfected
chemically or physically (for example by
lagoons and micro-filtration).The final
effluent can be discharged into a
stream, river , bay, lagoon or wetland, or it can
be used for the irrigation of a golf course,
green way or park.
5. WASTEWATER TREATMENT TECHNOLOGIES
SUSPENDED GROWTH
PROCESSES
In suspended growth processes the
microorganisms responsible for treatment are
maintained in liquid suspension by
appropriate mixing methods. Many
suspended growth processes used in
municipal and industrial wastewater
treatment are operated with a positive
dissolved oxygen concentration (aerobic).
The most common suspended growth process
used for municipal wastewater treatment is
the Activated Sludge Process.
ATTACHED GROWTH
PROCESSES
In attached growth processes, the
microorganisms responsible for the
conversion of organic material or
nutrients are attached on inert
packing material.
The major methods for wastewater
treatment are listed below:
â˘Activated sludge systems
â˘Aerated lagoon
â˘Aerobic granular reactor
⢠Aerobic treatment system
â˘Anaerobic clarigester
â˘Anaerobic digestion
⢠API oil-water separator
⢠Anaerobic lagoon
⢠Bead Filter
6. CHARACTERISTICS OF WASTEWATER
Constituent Concentration, mg/l
Strong Medium Weak
Total solids 1200 700 350
Dissolved solids (TDS) 850 500 250
Suspended solids 350 200 100
Nitrogen (as N) 85 40 20
Phosphorus (as P) 20 10 6
Chloride1 100 50 30
Alkalinity (as CaCO3) 200 100 50
Grease 150 100 50
BOD5* 300 200 100
1 The amounts of TDS and chloride should be increased by the concentrations of these
constituents in the carriage water.
*BOD5 is the biochemical oxygen demand at 20°Cover 5 days and is a measure of the
biodegradable organic matter in the wastewater.
7. IMPORTANT FACTS OF SEWAGE
TREATMENT PLANT
Around 85% of the land area of Lucknow City is situated on the Central Ganga alluvial plain,
and stretches across both banks of the Gomti River
Gross available water supply of about 490 MLD â of which around 240 MLD is derived from
up to 500 tube wells and 250 MLD from river Gomti.
â˘CisâGomti side are comparatively lower than the areas on Transâ Gomti side.
â˘Gomti River flows from NW to SE through the heart of the city.
â˘26 drains join the river, 14 drains from cisâGomti and 12 drains from transâGomti side.
â˘Out of 14 cisâGomti side drains, 12 drains are located in the upstream and 2 are located
into downstream of Barrage.
â˘All of the 12 TransâGomti drains merge into river Gomti in the upstream of Barrage.
The total project cost for the overall projects is estimated at Rs. 2054.63 crore with the bulk
Of investments proposed in Phase 2 of the JNNURM.
There is a provision of Rs. 625.97 Crores in PhaseâI (2006â11) and Rs. 1428.67 Crores in
PhaseâII (2012â2031) of City Development Plan of Lucknow
8.
9. SEWAGE DISTRICTS
⢠The overall sewerage scheme consists of 4 separate Sewerage Districts each with its
own (planned) treatment plant:
⢠a) District I: Chowk, Hardoi Road, Cambell Road and Dubagga etc. area conveying
sewage to existing Daulatganj STP
⢠b) District II: Amausi area and Sarojini Nagar area conveying sewage to proposed
Khwajapur STP
⢠c) District III: Total TransâGomti side including Indira Nagar, Gomti Nagar and Sitapur
road areas conveying sewage to Bharwara STP which is sanctioned under Gomti Action
Plan PhaseâII and in process of construction.
⢠d) District IV: Cis Gomti side conveying sewage to proposed Mastemau STP
10. FINE SCREEN CHAMBER
⢠The function of the bar screen is to prevent entry of solid particles/ articles above a
certain size; such as plastic cups, paper dishes, polythene bags, condoms and
sanitary napkins into the STP. (If these items are allowed to enter the STP, they clog
and damage the STP pumps, and cause stoppage of the plant.) The screening is
achieved by placing a screen made out of vertical bars, placed across the sewage
flow.
11. AERATION TANK
⢠The Aeration tank (together with the settling tank/ clarifier that follows) is at the
heart of the treatment system. The bulk of the treatment is provided here,
employing microbes/bacteria for the process. The main function of the Aeration
tank is to maintain a high population level of microbes. This mixture is called
MLSS (Mixed Liquor Suspended Solids) The mixed liquor is passed on to the
clarifier tank, where the microbes are made to settle at the bottom. The settled
microbes are recycled back to the aeration tank. Thus they are retained for a
long period within the system
12. OPERATIONAL SEWAGE TREATMENT
PLANT
STP CAPACITY TECHNOLOGY DRAINS
LENGTH OF TRUNK
AND BRANCH SEWER
LINES
DAULATGANJ
STP
42+14=56
MLD
FAB
WASTEWATER
FROM GAUGHAT,
SARKATA
NAGARIA-TREATED
WASTEWATER IS
DISCHARGED IN
RIVER GOMTI
THROUGH
SARKATA NALA
339 KM
BHARWARA
STP
345 MLD UASB 860 KM
401 MLD
13. TERTIARY TREATMENT
Tertiary treatment provides a final stage to raise the effluent quality before it is
discharged to the receiving environment (sea, river, lake, ground, etc.). More than
one tertiary treatment process may be used at any treatment plant. If disinfection is
practiced, it is always the final process. It is also called "effluent polishing"
Filtration-
Sand filtration removes much of the residual suspended matter. Filtration over activated
carbon, also called carbon adsorption, removes residual toxins.
Lagooning-
Lagooning provides settlement and further biological improvement through storage in large
man-made ponds or lagoons. These lagoons are highly aerobic and colonization by native
macrophytes.
Disinfection-
The purpose of disinfection in the treatment of waste water is to substantially reduce the
number of microorganisms in the water to be discharged back into the environment for the later
use of drinking, bathing, irrigation, etc.
16. CONCLUSION
1. Both of the existing sewage treatment plants are working properly and the results of treated water are
observed as per the central pollution control board norms. It has been observed that 100 % of the waste
water generated is not treated; thus more plants are required.
2. More foam was observed at site during the visit in the final polishing ponds of the UASB reactor.
Antifoaming agents are available in the market to remove the foam, and should be used.
3. Due to the inefficient sewerage network, highly diluted sewage is received at the Bharwara plant due to
which there is insignificant biogas generation which could otherwise be used for power generation; hence,
cost recovery.
4. All treated water is disposed into the Gomti River. The treated water may be used for industrial and
irrigation purposes.
5. Several important Water Quality Parameters like Faecal Coliform, Sulphate, Oil and Grease are not
measured on a regular basis.
6. For a particular location i.e. fixed land cost, the LCC of the FAB and UASB reactors increases with the
capacity of the STP but the LCC is lower for the UASB reactor up to a particular value of the STPâs
capacity; however, the rate of increase is greater for the UASB reactor.
7. Due to the low LCC of the UASB based Bharwara STP, it is better for a city like Lucknow.