INTRODUCTION
:
 For the different construction activities like





Brick work above 5 ft
Surface finishing works like plastering, painting, walling etc.
Renovation, repair and alteration works.
Roof and slab pouring

Some temporary nature supports and structures are required like





Formwork
(Supporting Structure)
Scaffoldings (arrangement for working plate forms)
Shoring
(supporting method for unsafe structure)
Underpinning (Method of strengthening an existing structure’s
footing)
WHAT IS
FORMWORK:

Formwork are temporary structures that are built
to support parts or the whole of a permanent structure
until it is self-supporting.

Formwork means the surface, support and framing
used to define the shape of concrete until it is selfsupporting.
Design Requirements:
•Strength
•Speedy erection and dismantling
•Tightness of joints
•Rigidity
•Reuse
•Ease of handling
Classification Criteria for
Formwork :oClassification according to size
oClassification according to the location of use
oClassification according to materials of construction
oClassification according to nature of operation
oClassification according to brand name of the product
TYPES OF WALL
FORMWORK
(Based on nature of operation)

 JUMP FORM
 SLIP FORM
 TUNNEL FORM
JUMP FORM:


Generally, jump form systems comprise the
formwork and working platforms for cleaning/fixing of
the formwork, steel fixing and concreting.
Jump form, often described as climbing form. It is
suitable for construction of multi-floor vertical concrete
elements in high-rise structures, such as shear walls, core
walls, lift shafts, stair shafts and bridge pylons.



It is a highly productive system designed to increase
speed and efficiency while minimizing labor and time.
TYPES OF JUMP
FORMWORK
Normal jump/climbing form
Guided-climbing jump form
Self-climbing jump form
WALL FORMING – JUMP FORM
SELF CLIMBING JUMP FORM
PROCESS EFFICIENCY :
 Fast construction can be achieved by careful planning of the
construction process. Crane availability is critical for normal jump
form.
 Self-climbing formwork cuts down the requirement for crane time
considerably. By allowing the crane to be used for other
construction work this may reduce the total number of cranes
needed on site.
 The formwork is independently supported, so the shear walls and
core walls can be completed ahead of the rest of the main building
structure. This can help to provide stability to the main structure
during its construction and can have the beneficial effect of taking
the jump form core off the project critical path.
CONTINUED…
 High quality surface finishes are possible.
 Climbing forms can be designed to operate in high winds (when
the use of a crane is less viable). This allows construction work to
be carried out at reduced risk from adverse weather.
 The highly engineered nature of jump form systems allows quick
and precise adjustment of the formwork in all planes.
 Some formwork systems can be used at an inclined angle, which
is particularly useful on bridge pylons or where walls vary in
thickness.
 A small but skilled workforce is required on site.
 It is easier to plan construction activities due to the repetitive
nature of the work.
SAFETY :
 Working platforms, guard rails, and ladders are built into the
completed units of market-leading formwork systems. Complete
wind-shield protection on platform edges is also possible.
 Self-climbing formwork systems are provided with integral freefall braking devices.
 The completed formwork assembly is robust and provides a stable
working platform.
 The reduced use of scaffolding and temporary work platforms
results in less congestion on site.
 The setting rate of concrete in those parts of the structure
supporting the form is critical in determining the rate at which
construction can safely proceed.
 The repetitive nature of the work means that site operatives can
quickly become familiar with health and safety aspects of their
job. Formwork suppliers provide materials and resources to help
train the labour force.
SUSTAINABILITY
FEATURES :
 The formwork system is easy to clean and reuse with little
formwork waste generated compared to traditional formwork.
 Climbing formwork systems offer simplicity, safety and cost
effectiveness for certain high-rise building structures.
 The repetitive nature of the work, combined with the engineered
nature of the formwork, allows fine tuning of the construction
operations, which in turn leads to minimal concrete wastage.
 Many repeated uses of formwork are possible before maintenance
or replacement is needed, the number of uses depending on the
quality of the surface finish of concrete specified.
CONSIDERATIONS :


Jump form is typically used on buildings of 5 storey's or
more; fully self-climbing systems are generally used on structures
with more than 20 floor levels.



Assembly and lifting operations for self-climbing formwork
systems require personnel to be comprehensively trained to ensure
competence.



The raising operation must be carefully planned and
coordinated, and access to the working area during lifting should
be restricted to essential personnel.
REFERENCES
:
“FORMWORK FOR MODERN, EFFICIENT
CONCRETE CONSTRUCTION” BY Rohan Rupasinghe
and Éanna Nolan, BRE
WWW.YOUTUBE.COM
HTTP://EN.WIKIPEDIA.ORG
?
Formwork Presentation: Jump Forms Explained

Weitere ähnliche Inhalte

Was ist angesagt?

Slipform construction
Slipform constructionSlipform construction
Slipform constructiontivar rose
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildingsKarthik Suresh
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise BuildingsPrasad Thanthratey
 
Composite structure of concrete and steel.
Composite structure of concrete and steel.Composite structure of concrete and steel.
Composite structure of concrete and steel.Suhailkhan204
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studiesSoumitra Smart
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildingsAnas Adel
 
ADVANCE FORMWORK SYSTEM
ADVANCE FORMWORK SYSTEMADVANCE FORMWORK SYSTEM
ADVANCE FORMWORK SYSTEMDeepak Verma
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsGrace Henry
 
modular coordination
modular coordinationmodular coordination
modular coordinationShailja km
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formworkchaitanyakrsk
 
LOAD BEARING WALL
LOAD BEARING WALLLOAD BEARING WALL
LOAD BEARING WALLwan izzati
 
Precast construction
Precast constructionPrecast construction
Precast constructionDivya Vishnoi
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building constructionAditya Sanyal
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 

Was ist angesagt? (20)

Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Damp proofing
Damp proofingDamp proofing
Damp proofing
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
Shell structure
Shell structureShell structure
Shell structure
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
High rise building
High rise buildingHigh rise building
High rise building
 
Composite structure of concrete and steel.
Composite structure of concrete and steel.Composite structure of concrete and steel.
Composite structure of concrete and steel.
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
ADVANCE FORMWORK SYSTEM
ADVANCE FORMWORK SYSTEMADVANCE FORMWORK SYSTEM
ADVANCE FORMWORK SYSTEM
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
modular coordination
modular coordinationmodular coordination
modular coordination
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
LOAD BEARING WALL
LOAD BEARING WALLLOAD BEARING WALL
LOAD BEARING WALL
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building construction
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 

Andere mochten auch

Doka self climbing system
Doka self climbing systemDoka self climbing system
Doka self climbing systemKuldeep Pandit
 
Climbing formwork
Climbing formworkClimbing formwork
Climbing formworkArnas Aidil
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
CONCERTE JUMP FORM BUILDING CONSTRUCTION
CONCERTE JUMP FORM BUILDING CONSTRUCTION CONCERTE JUMP FORM BUILDING CONSTRUCTION
CONCERTE JUMP FORM BUILDING CONSTRUCTION Thomas Smith
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab constructiontivar rose
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueSandeep Jain
 
1.pocket book vario
1.pocket book vario1.pocket book vario
1.pocket book varionugrohoery83
 
Doka Corporate Presentation 2016
Doka Corporate Presentation 2016Doka Corporate Presentation 2016
Doka Corporate Presentation 2016Doka
 
PERI UP Presentation 11-18-15
PERI UP Presentation 11-18-15PERI UP Presentation 11-18-15
PERI UP Presentation 11-18-15Billy Touvell
 
Pt. pks medan centre point
Pt. pks   medan centre pointPt. pks   medan centre point
Pt. pks medan centre pointDarwis Sutriadi
 
A presentation on Formwork
A presentation on FormworkA presentation on Formwork
A presentation on FormworkEsri India
 
Mechanised construction
Mechanised constructionMechanised construction
Mechanised constructionMANUJ sinh
 

Andere mochten auch (20)

Doka self climbing system
Doka self climbing systemDoka self climbing system
Doka self climbing system
 
Climbing formwork
Climbing formworkClimbing formwork
Climbing formwork
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork
FormworkFormwork
Formwork
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
CONCERTE JUMP FORM BUILDING CONSTRUCTION
CONCERTE JUMP FORM BUILDING CONSTRUCTION CONCERTE JUMP FORM BUILDING CONSTRUCTION
CONCERTE JUMP FORM BUILDING CONSTRUCTION
 
Formwork
FormworkFormwork
Formwork
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
 
ASPA_Product Brochure
ASPA_Product BrochureASPA_Product Brochure
ASPA_Product Brochure
 
1.pocket book vario
1.pocket book vario1.pocket book vario
1.pocket book vario
 
Doka Corporate Presentation 2016
Doka Corporate Presentation 2016Doka Corporate Presentation 2016
Doka Corporate Presentation 2016
 
PERI UP Presentation 11-18-15
PERI UP Presentation 11-18-15PERI UP Presentation 11-18-15
PERI UP Presentation 11-18-15
 
Pt. pks medan centre point
Pt. pks   medan centre pointPt. pks   medan centre point
Pt. pks medan centre point
 
A presentation on Formwork
A presentation on FormworkA presentation on Formwork
A presentation on Formwork
 
Mechanised construction
Mechanised constructionMechanised construction
Mechanised construction
 

Ähnlich wie Formwork Presentation: Jump Forms Explained

Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptxAnanthakumar75
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork adarshkaushik6
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptxssuserc0bf9b
 
Building construction report
Building construction  reportBuilding construction  report
Building construction reportAprajeeta Singh
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentationsomitra bhardwaj
 
Building Technology 1 (P1)
Building Technology 1 (P1)Building Technology 1 (P1)
Building Technology 1 (P1)Nicole Foo
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfGourhariBiswas1
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimneyAxay Sharma
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction TechnologyDarshit
 
Construction Technology
Construction TechnologyConstruction Technology
Construction TechnologySwapnilGorade1
 
Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...
Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...
Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...IJERA Editor
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
 

Ähnlich wie Formwork Presentation: Jump Forms Explained (20)

Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptx
 
Table formwork
Table formwork Table formwork
Table formwork
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Building construction report
Building construction  reportBuilding construction  report
Building construction report
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Building Technology 1 (P1)
Building Technology 1 (P1)Building Technology 1 (P1)
Building Technology 1 (P1)
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Slip form
Slip formSlip form
Slip form
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...
Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...
Study of Strength of RC Shear Wall at Different Location on Multi-Storied Res...
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 

Mehr von Pranay Kumar Tode

Hindu Temple Architecture | History of Architecture
Hindu Temple Architecture | History of ArchitectureHindu Temple Architecture | History of Architecture
Hindu Temple Architecture | History of ArchitecturePranay Kumar Tode
 
Maratha Architecture | History of Architecture
Maratha Architecture | History of ArchitectureMaratha Architecture | History of Architecture
Maratha Architecture | History of ArchitecturePranay Kumar Tode
 
Landscape and design elements in an institutional campus.
Landscape and design elements in an institutional campus.Landscape and design elements in an institutional campus.
Landscape and design elements in an institutional campus.Pranay Kumar Tode
 
How to write architectural thesis
How to write architectural thesisHow to write architectural thesis
How to write architectural thesisPranay Kumar Tode
 

Mehr von Pranay Kumar Tode (8)

Hindu Temple Architecture | History of Architecture
Hindu Temple Architecture | History of ArchitectureHindu Temple Architecture | History of Architecture
Hindu Temple Architecture | History of Architecture
 
Maratha Architecture | History of Architecture
Maratha Architecture | History of ArchitectureMaratha Architecture | History of Architecture
Maratha Architecture | History of Architecture
 
Floor and slabs
Floor and slabsFloor and slabs
Floor and slabs
 
Landscape and design elements in an institutional campus.
Landscape and design elements in an institutional campus.Landscape and design elements in an institutional campus.
Landscape and design elements in an institutional campus.
 
How to write a cv or resume
How to write a cv or resumeHow to write a cv or resume
How to write a cv or resume
 
How to write architectural thesis
How to write architectural thesisHow to write architectural thesis
How to write architectural thesis
 
Placing column layout
Placing  column layoutPlacing  column layout
Placing column layout
 
The architects act, 1972
The architects act, 1972The architects act, 1972
The architects act, 1972
 

Kürzlich hochgeladen

BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 

Kürzlich hochgeladen (20)

BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 

Formwork Presentation: Jump Forms Explained

  • 2. CONTENTS : 1. INTRODUCTION TO fORm wORk 2. DesIgN ReqUIRemeNTs 3. ClassIfICaTION CRITeRIa 4. JUmp fORm 5. TYpes Of JUmp fORm 6. pROCess effICIeNCY 7. safeTY & sUsTaINaBle feaTURes 8. CONsIDeRaTIONs 9. RefeReNCes
  • 3. INTRODUCTION :  For the different construction activities like     Brick work above 5 ft Surface finishing works like plastering, painting, walling etc. Renovation, repair and alteration works. Roof and slab pouring Some temporary nature supports and structures are required like     Formwork (Supporting Structure) Scaffoldings (arrangement for working plate forms) Shoring (supporting method for unsafe structure) Underpinning (Method of strengthening an existing structure’s footing)
  • 4. WHAT IS FORMWORK:  Formwork are temporary structures that are built to support parts or the whole of a permanent structure until it is self-supporting.  Formwork means the surface, support and framing used to define the shape of concrete until it is selfsupporting.
  • 5. Design Requirements: •Strength •Speedy erection and dismantling •Tightness of joints •Rigidity •Reuse •Ease of handling
  • 6. Classification Criteria for Formwork :oClassification according to size oClassification according to the location of use oClassification according to materials of construction oClassification according to nature of operation oClassification according to brand name of the product
  • 7. TYPES OF WALL FORMWORK (Based on nature of operation)  JUMP FORM  SLIP FORM  TUNNEL FORM
  • 8. JUMP FORM:  Generally, jump form systems comprise the formwork and working platforms for cleaning/fixing of the formwork, steel fixing and concreting. Jump form, often described as climbing form. It is suitable for construction of multi-floor vertical concrete elements in high-rise structures, such as shear walls, core walls, lift shafts, stair shafts and bridge pylons.  It is a highly productive system designed to increase speed and efficiency while minimizing labor and time.
  • 9. TYPES OF JUMP FORMWORK Normal jump/climbing form Guided-climbing jump form Self-climbing jump form
  • 10. WALL FORMING – JUMP FORM
  • 12. PROCESS EFFICIENCY :  Fast construction can be achieved by careful planning of the construction process. Crane availability is critical for normal jump form.  Self-climbing formwork cuts down the requirement for crane time considerably. By allowing the crane to be used for other construction work this may reduce the total number of cranes needed on site.  The formwork is independently supported, so the shear walls and core walls can be completed ahead of the rest of the main building structure. This can help to provide stability to the main structure during its construction and can have the beneficial effect of taking the jump form core off the project critical path.
  • 13. CONTINUED…  High quality surface finishes are possible.  Climbing forms can be designed to operate in high winds (when the use of a crane is less viable). This allows construction work to be carried out at reduced risk from adverse weather.  The highly engineered nature of jump form systems allows quick and precise adjustment of the formwork in all planes.  Some formwork systems can be used at an inclined angle, which is particularly useful on bridge pylons or where walls vary in thickness.  A small but skilled workforce is required on site.  It is easier to plan construction activities due to the repetitive nature of the work.
  • 14. SAFETY :  Working platforms, guard rails, and ladders are built into the completed units of market-leading formwork systems. Complete wind-shield protection on platform edges is also possible.  Self-climbing formwork systems are provided with integral freefall braking devices.  The completed formwork assembly is robust and provides a stable working platform.  The reduced use of scaffolding and temporary work platforms results in less congestion on site.  The setting rate of concrete in those parts of the structure supporting the form is critical in determining the rate at which construction can safely proceed.  The repetitive nature of the work means that site operatives can quickly become familiar with health and safety aspects of their job. Formwork suppliers provide materials and resources to help train the labour force.
  • 15. SUSTAINABILITY FEATURES :  The formwork system is easy to clean and reuse with little formwork waste generated compared to traditional formwork.  Climbing formwork systems offer simplicity, safety and cost effectiveness for certain high-rise building structures.  The repetitive nature of the work, combined with the engineered nature of the formwork, allows fine tuning of the construction operations, which in turn leads to minimal concrete wastage.  Many repeated uses of formwork are possible before maintenance or replacement is needed, the number of uses depending on the quality of the surface finish of concrete specified.
  • 16. CONSIDERATIONS :  Jump form is typically used on buildings of 5 storey's or more; fully self-climbing systems are generally used on structures with more than 20 floor levels.  Assembly and lifting operations for self-climbing formwork systems require personnel to be comprehensively trained to ensure competence.  The raising operation must be carefully planned and coordinated, and access to the working area during lifting should be restricted to essential personnel.
  • 17. REFERENCES : “FORMWORK FOR MODERN, EFFICIENT CONCRETE CONSTRUCTION” BY Rohan Rupasinghe and Éanna Nolan, BRE WWW.YOUTUBE.COM HTTP://EN.WIKIPEDIA.ORG