Its integrated why wont you use it - 10 must do tactics to help companies roll out integrated p6 solutions - Oracle Primavera P6 Collaborate 14
1. REMINDER
Check in on the
COLLABORATE mobile app
It's integrated!
Why won't you use it?
Michael Lepage
Managing Partner
PlannerTuts Online Training
www.plannertuts.com
10 Must-Do Tactics to Help
Companies Roll-out Integrated
Primavera P6 Solutions
Session ID#: #15422
2. Primavera P6 ELearning
for the Enterprise
Blended Learning & Support
Guided Curriculum
Scalable for 100s of users
Experienced Instructors
-- an online Library of
Primavera P6 Learning.
7. What happened?
■ We got caught up in the thrill of integrating 2 systems
■ And forgot about the end user.
8. What happened?
■ We got caught up in the thrill of integrating 2 systems
■ And forgot about the end user.
9. 10 Must-Do Tactics to help
companies roll-out integrated
Primavera P6 solutions
10. Let Your Users Have a Voice
Most often, users will support something
they are involved in. Get them involved.
Engage them on the “WHY”
Ask for open and honest feedback.
Let them speak, complain and be
heard.
You don’t have to fix everything, just
listening is most important.
Gather Anonymous Feedback
11. Break it Up
“Wisely, and slow. They stumble that
run fast.” -Shakespeare
• Deliver pieces incrementally over a
reasonable period of time
• Allow users to learn and integrate each piece
• Refine and make corrections as you go
• Agile principles
• Rapid delivery
• Changing requirements
• Feedback from business often
12. Have a Measurable Business Goal
(one that users will want to rally behind)
Make it meaningful for users, not just
sponsors
Track it and report on it
eg:
Reduce Month-End Report Prep Time by
50%
Eliminate Excel Spreadsheets
Reduce Redundant Reporting to 0
13. Pilot First, Evaluate, Then Rollout.
• Use a Pilot period. Prove it out.
• Use real projects
• Use lower-priority projects
• Define Success Criteria
• Let the Pilot team Evaluate the
system from a user’s
perspective
17. Don’t just provide training, provide a
Learning Path for your users after training.
Self-Paced Learning
(Videos, Tutorials, Workshops,
Documentation, etc.)
Virtual Training
(Screen sharing + a Live Training
Environment)
Simulations
(A Simulation of the software presented
in Flash)
18. Beware the “System of Record”
What are the User implications for having a System of Record for cost or schedule
information?
What workaround will users have to execute to work?
SAP
WBS
Actual Costs
Resources
Primavera P6
Activities
Resource Assignments
Budgeted Costs
19. Don’t Bend to the Tech Gods
SAP team forced Users to have 2 projects in
Primavera P6
Capital Costs
Expense Costs
User were forced to work with 2 projects
instead of 1 in P6.
Find technology solutions that work for all
departments involved
Go to BATTLE for your users
20. Make time for people to Engage with the
new integrated system
“I’m already swamped. Now I
have to learn this new system.
There’s no time left to do my
work.”
21. Provide incentives. You can make it Fun.
Give users a challenge to earn a
prize
The first user to figure out how
to import WBS data from SAP
and show me their report goes
mini-putting.
Get them engaged.
They will help each other.
22. Execs – be a Project Scheduler for a Day
Use the solution yourself for a full day,
alongside other users.
Engage with users, ask for help and feedback.
Volunteer to be someone’s assistant scheduler
for a day
Really understand issues, problems and pain
points.
Dazzle them with your commitment to people.