2013 FEDCON SUMMIT
Government Contract Disruptions, Delays
and Changes

Presented By:

David L. Hayden
Smith, Anderson, Blount, Dorsett,
Mitchell & Jernigan, LLP

&
Paulanne Page
(Team Leader, NCMBC)
AGENDA
•
•
•
•
•

2

Captain Phillips and the Maersk Alabama
Disruption-What is the impact
Delay-When is it compensatory?
Change Orders
Questions
Disruptions
Example: Differing Site Conditions (DSC)
• FAR 52.236-2
– Allows equitable adjustment if contractor provides
prompt, written notice of DSC
– Ensure clause is in contract or remedy not available
– Type I DSC (Relies on contract representations)
– Type II DSC (Unusual & unknown physical conditions)

3
TYPE I DSC
• FAR 52.236-2(a)(1) Contractor must prove:
– Contract implicitly or explicitly indicated particular site
condition
– Reasonable interpretation and reliance by contractor
on site conditions
– Latent or subsurface conditions differed materially
from those indicated in contract
– Costs were attributable solely to differing site
conditions.

4
TYPE II DSC
• FAR 52.236-2 (a)(2) Contractor must prove:
– Conditions encountered were unusual physical
conditions that were unknown at the time of contract
– The conditions differed materially from those
ordinarily encountered
•
•
•
•

5

Acts of nature after contract award are not DSC
Contractor cannot create its own DSC
Contractor may not recover if reasonably discoverable
It is harder to show Type II vs. Type I DSC
Delays Due to Suspension of Work
FAR 52.242-14: The KO may suspend, interrupt, or delay
work for the government’s convenience
• Delay is compensable if:
– It is unreasonable
– The KO orders it
– The contractor has not caused the suspension by its negligence
or failure to perform
– The cost of performance increases because of KO order

• See also FAR 42.13 Suspension of Work, Stop-Work
Orders, and Government Delay of Work

6
Delays Due to Suspension of Work
• Contractor may be entitled to a performance period
extension even if the delay is reasonable.
• Profit is not recoverable
• Delay costs limited to 20 days unless contractor notifies
the Government (KO)
• Is delay due to federal government shutdown
unreasonable?
Connor Bros. Const. Co., Inc. v. Geren, 550 f.3d 1368 (Fed. Cir. 2008)

7
Loss of Efficiency
• Disruption caused by government changes and/or delays
may cause a loss of efficiency to the contractor
• Contractor may recover for loss of efficiency if it can
show:
– Increased cost
– Government was responsible
Luria Bros. & Co. v. United States, 177 Ct. Cl. 676, 369 F.2d 701 (1966)

8
TYPES OF DELAY/DISRUPTION
• Excusable – delay is not the result of actions or inactions
by either party at contract.
• Delay arises from unforeseeable causes beyond the
control and without the fault or negligence of the
Contractor.
(FAR 52.249-10 -- Default (Fixed-Price Construction)
• Inexcusable – delay caused by the contractor
• Examples include failure to coordinate work, too few
workers, and low productivity.
DELAY/DISRUPTION = CHANGE ORDER?
• Compensatory – a delay caused by actions or inactions by one of
the contracted parties that results in financial injury to the other party
at contract.
• The burden of proving a compensable delay is borne by the
contractor.
• Government caused delays = equitable adjustment/claim
• The contractor must prove the extent of the governmentcaused delay, and its increased costs, to prove its injury, and
there was no concurrent delay.
• Contractor caused delays = liquidated damages
• The Government must prove the extent of contractor caused
delay, and there was no concurrent delay.
CHANGE ORDERS
•

Differing site conditions.

•

Regulatory changes.

•

Owner changes.
– Scope added/deleted during construction.
– Late design changes.
– Changes in Owner-provide equipment.

•

Information missing from the contract documents, ambiguities, errors
and omissions

•

Schedule delays and revisions.

•

Adverse Weather – Normal and Severe
CHANGE ORDERS
• Changes may have both cost and schedule impacts.
• Dealing with changes promptly will have the least
amount of impact on the budget and schedule.

• Delaying resolution can increase costs, jobsite friction,
extend the completion of the project and result in a
dispute.
CHANGE ORDER
• Most Contracts do not
spell out a formal
“Contractor Change
Request” process.

• If the Contractor wants to
submit a change request
it needs to follow the
“claims” process defined
in the contract to request
a change.
CHANGE ORDERS
• Compensatory – a delay caused by actions or inactions by one of
the contracted parties that results in financial injury to the other party
at contract.
• The burden of proving a compensable delay is borne by the
contractor
• Government caused delays = equitable adjustment/claim
• The contractor must prove the extent of the governmentcaused delay, and its increased costs, to prove its injury, and
there was no concurrent delay.
• Contractor caused delays = liquidated damages
• The Government must prove the extent of contractor caused
delay, and there was no concurrent delay.
EXAMPLE: ADVERSE WEATHER
•
•
•
•
•
•
•
•
•

Non Compensable
Notification to Government
UPDATED Schedule – CPM (Monthly)
Extends Contract Completion
Calendar Work Days per Week – 5 or 7
Scheduled CP Activities – 50% production
Daily Reports (Temp, Winds, Humidity)
Fragnet of Impact entered into schedule
Analysis of As-Planned to As-Built
Questions?
Paulanne Page
pagep@ncmbc.us
(910) 330-8560

David Hayden
dhayden@smithlaw.com
(919) 821-6755

Weitere ähnliche Inhalte

Ähnlich wie FEDCON Summit: Change Orders & Contract Disruptions/Delays

Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptNesrElhandasa1
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction ProjectMelissa Brumback
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractSHKLaw
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 

Ähnlich wie FEDCON Summit: Change Orders & Contract Disruptions/Delays (20)

Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Making Changes on the Construction Project
 Making Changes on the Construction Project Making Changes on the Construction Project
Making Changes on the Construction Project
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 

Mehr von NC Military Business Center

Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14NC Military Business Center
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsNC Military Business Center
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysNC Military Business Center
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction OpportunitiesNC Military Business Center
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsNC Military Business Center
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...NC Military Business Center
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceNC Military Business Center
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...NC Military Business Center
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelNC Military Business Center
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsNC Military Business Center
 

Mehr von NC Military Business Center (20)

Camp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach EventCamp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach Event
 
MCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach EventMCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach Event
 
Spawar slides
Spawar slidesSpawar slides
Spawar slides
 
Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction Projects
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction Opportunities
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
 
FEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations EastFEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations East
 
FEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for ContractorsFEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for Contractors
 
FEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private VenturesFEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private Ventures
 
FEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming ArrangementsFEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming Arrangements
 
FEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans AffairsFEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans Affairs
 
Medical Technologies
Medical TechnologiesMedical Technologies
Medical Technologies
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
 
Ground Vehicle and Robotics
Ground Vehicle and RoboticsGround Vehicle and Robotics
Ground Vehicle and Robotics
 

Kürzlich hochgeladen

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 

Kürzlich hochgeladen (20)

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 

FEDCON Summit: Change Orders & Contract Disruptions/Delays

  • 1. 2013 FEDCON SUMMIT Government Contract Disruptions, Delays and Changes Presented By: David L. Hayden Smith, Anderson, Blount, Dorsett, Mitchell & Jernigan, LLP & Paulanne Page (Team Leader, NCMBC)
  • 2. AGENDA • • • • • 2 Captain Phillips and the Maersk Alabama Disruption-What is the impact Delay-When is it compensatory? Change Orders Questions
  • 3. Disruptions Example: Differing Site Conditions (DSC) • FAR 52.236-2 – Allows equitable adjustment if contractor provides prompt, written notice of DSC – Ensure clause is in contract or remedy not available – Type I DSC (Relies on contract representations) – Type II DSC (Unusual & unknown physical conditions) 3
  • 4. TYPE I DSC • FAR 52.236-2(a)(1) Contractor must prove: – Contract implicitly or explicitly indicated particular site condition – Reasonable interpretation and reliance by contractor on site conditions – Latent or subsurface conditions differed materially from those indicated in contract – Costs were attributable solely to differing site conditions. 4
  • 5. TYPE II DSC • FAR 52.236-2 (a)(2) Contractor must prove: – Conditions encountered were unusual physical conditions that were unknown at the time of contract – The conditions differed materially from those ordinarily encountered • • • • 5 Acts of nature after contract award are not DSC Contractor cannot create its own DSC Contractor may not recover if reasonably discoverable It is harder to show Type II vs. Type I DSC
  • 6. Delays Due to Suspension of Work FAR 52.242-14: The KO may suspend, interrupt, or delay work for the government’s convenience • Delay is compensable if: – It is unreasonable – The KO orders it – The contractor has not caused the suspension by its negligence or failure to perform – The cost of performance increases because of KO order • See also FAR 42.13 Suspension of Work, Stop-Work Orders, and Government Delay of Work 6
  • 7. Delays Due to Suspension of Work • Contractor may be entitled to a performance period extension even if the delay is reasonable. • Profit is not recoverable • Delay costs limited to 20 days unless contractor notifies the Government (KO) • Is delay due to federal government shutdown unreasonable? Connor Bros. Const. Co., Inc. v. Geren, 550 f.3d 1368 (Fed. Cir. 2008) 7
  • 8. Loss of Efficiency • Disruption caused by government changes and/or delays may cause a loss of efficiency to the contractor • Contractor may recover for loss of efficiency if it can show: – Increased cost – Government was responsible Luria Bros. & Co. v. United States, 177 Ct. Cl. 676, 369 F.2d 701 (1966) 8
  • 9. TYPES OF DELAY/DISRUPTION • Excusable – delay is not the result of actions or inactions by either party at contract. • Delay arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. (FAR 52.249-10 -- Default (Fixed-Price Construction) • Inexcusable – delay caused by the contractor • Examples include failure to coordinate work, too few workers, and low productivity.
  • 10. DELAY/DISRUPTION = CHANGE ORDER? • Compensatory – a delay caused by actions or inactions by one of the contracted parties that results in financial injury to the other party at contract. • The burden of proving a compensable delay is borne by the contractor. • Government caused delays = equitable adjustment/claim • The contractor must prove the extent of the governmentcaused delay, and its increased costs, to prove its injury, and there was no concurrent delay. • Contractor caused delays = liquidated damages • The Government must prove the extent of contractor caused delay, and there was no concurrent delay.
  • 11. CHANGE ORDERS • Differing site conditions. • Regulatory changes. • Owner changes. – Scope added/deleted during construction. – Late design changes. – Changes in Owner-provide equipment. • Information missing from the contract documents, ambiguities, errors and omissions • Schedule delays and revisions. • Adverse Weather – Normal and Severe
  • 12. CHANGE ORDERS • Changes may have both cost and schedule impacts. • Dealing with changes promptly will have the least amount of impact on the budget and schedule. • Delaying resolution can increase costs, jobsite friction, extend the completion of the project and result in a dispute.
  • 13. CHANGE ORDER • Most Contracts do not spell out a formal “Contractor Change Request” process. • If the Contractor wants to submit a change request it needs to follow the “claims” process defined in the contract to request a change.
  • 14. CHANGE ORDERS • Compensatory – a delay caused by actions or inactions by one of the contracted parties that results in financial injury to the other party at contract. • The burden of proving a compensable delay is borne by the contractor • Government caused delays = equitable adjustment/claim • The contractor must prove the extent of the governmentcaused delay, and its increased costs, to prove its injury, and there was no concurrent delay. • Contractor caused delays = liquidated damages • The Government must prove the extent of contractor caused delay, and there was no concurrent delay.
  • 15. EXAMPLE: ADVERSE WEATHER • • • • • • • • • Non Compensable Notification to Government UPDATED Schedule – CPM (Monthly) Extends Contract Completion Calendar Work Days per Week – 5 or 7 Scheduled CP Activities – 50% production Daily Reports (Temp, Winds, Humidity) Fragnet of Impact entered into schedule Analysis of As-Planned to As-Built
  • 16. Questions? Paulanne Page pagep@ncmbc.us (910) 330-8560 David Hayden dhayden@smithlaw.com (919) 821-6755