Basic terms
• Dock: the enclosed area provided for berthing ships
to keep them afloat at a uniform level to facilitate
loading and unloading is called the dock.
• Harbour: The sheltered area of the sea in which
vessels could be launched, built or repaired, or could
seek refuge during storm time and provide loading
and unloading facilities of cargo and passengers is
called harbour.
Harbour
• It is a sheltered area
• Used for loading and unloading of cargo
• Vessels are also built, repair and launch
• It protects ships naturally or artificially from fury of
sea
• Ships, boats, and barges can seek shelter from
stormy weather, in navigable waters well protected
naturally or artificially
• Situated along sea shore or river estuary or lake or
canal connected to sea
Classification of harbour
• Artificial harbour
Man-made harbour
Deliberately constructed break waters, sea walls ,
jetties, and also dredging is done there
Requires maintenance by periodic dredging
Ex. Madras harbour
Artificial harbour
Natural harbour
• It is protected form storms and waves by
prominence of land
• Consist of part of body of water which is protected
and deep enough for anchorage
Docks & harbors construction
Semi- natural harbours
• The ones who are protected on sides by land and
require man- made protection only at entrance
• Ex. Vishakhapatnum port
Docks & harbors construction
Classification based on function to be
performed
1. Harbor of refuge- used for ships in storms or
emergency condition.
good anchorage and safe and easy access from
the sea.
2. Commercial harbor- Facilities for loading and
unloading of cargo are provided.
Harbour of refuge
Commercial harbour
3. Fishery harbor- For loading unloading the catch .
It should have refrigeration stores with plenty of
storing space for preserving catch.
4. Military harbor or navel base harbours- This
harbor is meant for accommodating naval crafts and
serves as a supply deport.
The layout of this type of harbor is greatly
influenced by its location.
Fishery harbour
Military harbour
Planning for harbour
The planning of harbor should be carried out after
collecting the necessary information of the existing
features at the proposed site.
The following important facts should be studied:
 To carry out a thorough survey of the neighborhood
including the fore shore and depths of water in the
vicinity is necessary.
The nature of the harbor, whether sheltered or not
should be studied.
The existence of sea insects which undermine the
foundation should be studied.
The problem of silting or erosion of coast line should
be studied carefully.
To ascertain the character of the ground, borings
and soundings should be taken.
To know the probable surface conditions on land,
borings on land should also be made. It will be help
full in locating the harbor works correctly.
The natural metrological phenomenon should be
studied at site with respect to frequency of storms,
rainfall, range of tides, maximum and minimum
temperatures, direction and intensity of winds,
humidity, direction and velocity of currents etc.
Requirements of a good harbour
• The depth of a harbor should be sufficient for every
type of visiting ships.
• The bottom of harbor should provide secured
anchorage to hold the ships against high winds.
• To prevent destructive wave action, break water are
provided.
• The entrance of a harbor should be wide enough to
provide the easy passage of ships.
Harbor area required depends upon the following
factors:
 Size and number of ships to be accommodated in the
harbor at a time
 Length and width needed for movement of ships to
and from berths.
 Type of cargo carried.
To make the harbor useful for operating and
dispatching ships, the water depth in the entrance,
approach channel and harbor basin should be
sufficient even at the low water spring tide.
• It is very important i.e. the location and alignment
of elements such as entrance, approach channel,
turning basin, break water, wharves, jetties and
docks etc. will ensure easy maneuverability and
additional navigation facilities.
• The main faction of a harbor is to provide a safe and
suitable accommodation to the vessels needing
refuge, supplies, repairs, refueling or transfer of
cargo and passengers.
Selection of site
• Availability of cheap land & construction material.
• Natural protection from waves & winds
• Transport & communication facilities
• Industrial development of the locality
• Sea bed, sub soil & foundation conditions
• Avability of electrical energy
• Defense & strategic aspects
• Traffic potentiality of harbour
Features of harbour
• Break water
• Docks
• Entrance channel
• Jetty
• Light house
• Berthing Basin
• Turning Basin
• Pier Head
• Wharves
Breakwaters
• Breakwater are the structures constructed to enclose
the harbours to protect them from the effect of wind
generated waves by reflecting and dissipating their
force or energy.
• Helps to use the area thus enclosed as a safe
anchorage for ships and to facilitate loading and
unloading of water by means of wave breakers.
• Height depends upon the its purpose, extent of
enclosed water area and nature of existing shipping
work.
• Generally the height of breakwater is kept as
equivalent to 1.2 to 1.25 times the waves expected.
• It also helps to prevent beach erosion
• The most common breakwater used has a core of
small rocks or rubble with a covering of large rocks
to keep the core from being washed away.
• It may be small structures, placed one to three
hundred feet offshore in relatively shallow water
• Breakwater either fixed or floating- choice depend
on normal water depth & tidal range
• Its construction is usually parallel or perpendicular
to the coast
Docks & harbors construction
Docks & harbors construction
Docks
• Docks are enclosed areas for berthing the ships to
keep them afloat at a uniform level to facilitate
loading and unloading cargo.
• A marine structure for berthing of vessels for
loading and unloading cargo and passengers.
• Necessary for discharging of the cargo
• As ships require a number of days for discharging
cargo, during which period they need a uniform
water level.
• If ship is subjected to a vertical movement by the
tides, great inconvenience will be felt in lifting the
cargo from the ship and special arrangement will be
needed for lifting the cargo
• Docks can be classified into following two
categories:
 Wet docks.
 Dry docks.
Wet docks-
• Docks required for berthing of ships or vessels to
facilitate the loading and unloading of passengers
and cargo are called wet docks.
• These are also known as harbor docks.
 Dry docks
• The docks used for repairs of ships are known as
dry docks.
• It is long excavated chamber, having side walls, a
semi circular end wall and a floor.
• The open end of the chamber is provided with a gate
and acts as the entrance to the dock.
ENTRANCE CHANNEL
• Depth and width are kept more at entrance
• Width depends upon density of traffic and no. of
entrances
JETTIES
• A narrow structure projecting from the shore
into the water with berths one or both sides and
sometimes at the end also.
• These are structures in the form of piles
projections.
• Built from the shore to the deep water.
• They may be constructed in the sea or in a
navigable river.
• The jetties extend from the shore to the deep sea
to receive the ship.
Docks & harbors construction
BERTHING AND TURNING BASINS
• Berthing basins are used for the parking of ships
• While turning for the turning of ships
PIER HEAD
• The structure provided at the tip of break water
• Such as light house
THANK YOU

Weitere ähnliche Inhalte

Was ist angesagt?

Docks, Harbour and Ports
Docks, Harbour and PortsDocks, Harbour and Ports
Docks, Harbour and PortsArbaz Kazi
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611VATSAL PATEL
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623VATSAL PATEL
 
Docks and their classification
Docks and their classificationDocks and their classification
Docks and their classificationLatif Hyder Wadho
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623VATSAL PATEL
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623VATSAL PATEL
 
Vertical wall type breakwaters
Vertical wall type breakwatersVertical wall type breakwaters
Vertical wall type breakwatersVikas Patre
 
Ports and harbours
Ports and harboursPorts and harbours
Ports and harboursMohan Sai G
 
Harbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT MysoreHarbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT MysoreShankaregowda Mandya
 
Breakwaters and types
Breakwaters and types Breakwaters and types
Breakwaters and types M Aamer Raza
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623VATSAL PATEL
 
H & d ppt 05 wet docks
H & d ppt 05 wet docksH & d ppt 05 wet docks
H & d ppt 05 wet docksHasna Hassan
 
Chapter 5 coastal structures
Chapter  5 coastal structuresChapter  5 coastal structures
Chapter 5 coastal structuresMohsin Siddique
 
Classification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxClassification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxJAYA LAKSHMI ATHRAM
 

Was ist angesagt? (20)

Docks, Harbour and Ports
Docks, Harbour and PortsDocks, Harbour and Ports
Docks, Harbour and Ports
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
Harbour
HarbourHarbour
Harbour
 
Docks and their classification
Docks and their classificationDocks and their classification
Docks and their classification
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
Docks and Harbors.pptx
Docks and Harbors.pptxDocks and Harbors.pptx
Docks and Harbors.pptx
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
Vertical wall type breakwaters
Vertical wall type breakwatersVertical wall type breakwaters
Vertical wall type breakwaters
 
Ports and harbours
Ports and harboursPorts and harbours
Ports and harbours
 
Harbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT MysoreHarbour engineering by Shankaregowda MIT Mysore
Harbour engineering by Shankaregowda MIT Mysore
 
Breakwaters and types
Breakwaters and types Breakwaters and types
Breakwaters and types
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
 
H & d ppt 05 wet docks
H & d ppt 05 wet docksH & d ppt 05 wet docks
H & d ppt 05 wet docks
 
Chapter 5 coastal structures
Chapter  5 coastal structuresChapter  5 coastal structures
Chapter 5 coastal structures
 
Classification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptxClassification of port and harbour ppt.pptx
Classification of port and harbour ppt.pptx
 
Harbours Engineering
 Harbours Engineering  Harbours Engineering
Harbours Engineering
 
Navigational aids
Navigational aidsNavigational aids
Navigational aids
 
Breakwaters
BreakwatersBreakwaters
Breakwaters
 
Airpot design
Airpot designAirpot design
Airpot design
 

Ähnlich wie Docks & harbors construction

harbour-160808044336.ppt
harbour-160808044336.pptharbour-160808044336.ppt
harbour-160808044336.pptRishi Nath
 
Presentation (1).pptx
Presentation (1).pptxPresentation (1).pptx
Presentation (1).pptxManaliGujar1
 
Harbour 160808044336 (1)
Harbour 160808044336 (1)Harbour 160808044336 (1)
Harbour 160808044336 (1)ArunKumar7403
 
Ports, Harbours & Docks.pptx
Ports, Harbours & Docks.pptxPorts, Harbours & Docks.pptx
Ports, Harbours & Docks.pptxAnujyadav514462
 
195925358-Harbour-and-Jetty-Structures (1).ppt
195925358-Harbour-and-Jetty-Structures (1).ppt195925358-Harbour-and-Jetty-Structures (1).ppt
195925358-Harbour-and-Jetty-Structures (1).pptMridulHasan15
 
Ports&harbor, some of its parts and modern facilities
Ports&harbor, some of its parts and modern facilitiesPorts&harbor, some of its parts and modern facilities
Ports&harbor, some of its parts and modern facilitiesKristel Rejean Ramos
 
Horbour & Dock Engineerin
Horbour & Dock EngineerinHorbour & Dock Engineerin
Horbour & Dock Engineerinjamalkhan619
 
Harbor_Classification 27.11.2022.docx
Harbor_Classification 27.11.2022.docxHarbor_Classification 27.11.2022.docx
Harbor_Classification 27.11.2022.docxgksaha2007
 
CHAPTER - 2. HARBOUR PLANNING.pptx
CHAPTER - 2. HARBOUR PLANNING.pptxCHAPTER - 2. HARBOUR PLANNING.pptx
CHAPTER - 2. HARBOUR PLANNING.pptxjaswanthyadav12
 
Marine civil engineering and Gujarat
Marine civil engineering and GujaratMarine civil engineering and Gujarat
Marine civil engineering and Gujaratadhyaru19
 
harborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdfharborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdfjaswanthyadav12
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623VATSAL PATEL
 
Nautical and engineering terms and concepts .pptx
Nautical and engineering terms and concepts .pptxNautical and engineering terms and concepts .pptx
Nautical and engineering terms and concepts .pptxdevmarineacademy
 
Ports and Great Lakes.pptx
Ports and Great Lakes.pptxPorts and Great Lakes.pptx
Ports and Great Lakes.pptxAndrewPruett3
 

Ähnlich wie Docks & harbors construction (20)

harbour-160808044336.ppt
harbour-160808044336.pptharbour-160808044336.ppt
harbour-160808044336.ppt
 
Presentation (1).pptx
Presentation (1).pptxPresentation (1).pptx
Presentation (1).pptx
 
Harbour 160808044336 (1)
Harbour 160808044336 (1)Harbour 160808044336 (1)
Harbour 160808044336 (1)
 
Ports, Harbours & Docks.pptx
Ports, Harbours & Docks.pptxPorts, Harbours & Docks.pptx
Ports, Harbours & Docks.pptx
 
195925358-Harbour-and-Jetty-Structures (1).ppt
195925358-Harbour-and-Jetty-Structures (1).ppt195925358-Harbour-and-Jetty-Structures (1).ppt
195925358-Harbour-and-Jetty-Structures (1).ppt
 
Berthing structures
Berthing structuresBerthing structures
Berthing structures
 
Habour and dock engineering
Habour and dock engineeringHabour and dock engineering
Habour and dock engineering
 
Ports&harbor, some of its parts and modern facilities
Ports&harbor, some of its parts and modern facilitiesPorts&harbor, some of its parts and modern facilities
Ports&harbor, some of its parts and modern facilities
 
Horbour & Dock Engineerin
Horbour & Dock EngineerinHorbour & Dock Engineerin
Horbour & Dock Engineerin
 
Harbor_Classification 27.11.2022.docx
Harbor_Classification 27.11.2022.docxHarbor_Classification 27.11.2022.docx
Harbor_Classification 27.11.2022.docx
 
Waterways
WaterwaysWaterways
Waterways
 
harbor types and site selection
harbor types and site selectionharbor types and site selection
harbor types and site selection
 
CHAPTER - 2. HARBOUR PLANNING.pptx
CHAPTER - 2. HARBOUR PLANNING.pptxCHAPTER - 2. HARBOUR PLANNING.pptx
CHAPTER - 2. HARBOUR PLANNING.pptx
 
Marine civil engineering and Gujarat
Marine civil engineering and GujaratMarine civil engineering and Gujarat
Marine civil engineering and Gujarat
 
M3_IE_D&HE.pdf
M3_IE_D&HE.pdfM3_IE_D&HE.pdf
M3_IE_D&HE.pdf
 
harborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdfharborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdf
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
 
Nautical and engineering terms and concepts .pptx
Nautical and engineering terms and concepts .pptxNautical and engineering terms and concepts .pptx
Nautical and engineering terms and concepts .pptx
 
RAHE UNIT 5.pptx
RAHE UNIT 5.pptxRAHE UNIT 5.pptx
RAHE UNIT 5.pptx
 
Ports and Great Lakes.pptx
Ports and Great Lakes.pptxPorts and Great Lakes.pptx
Ports and Great Lakes.pptx
 

Kürzlich hochgeladen

EPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptxEPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptxJoseeMusabyimana
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderjuancarlos286641
 
solar wireless electric vechicle charging system
solar wireless electric vechicle charging systemsolar wireless electric vechicle charging system
solar wireless electric vechicle charging systemgokuldongala
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide LaboratoryBahzad5
 
Design of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxDesign of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxYogeshKumarKJMIT
 
nvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxnvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxjasonsedano2
 
Basic Principle of Electrochemical Sensor
Basic Principle of  Electrochemical SensorBasic Principle of  Electrochemical Sensor
Basic Principle of Electrochemical SensorTanvir Moin
 
Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...sahb78428
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
Multicomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdfMulticomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdfGiovanaGhasary1
 
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Apollo Techno Industries Pvt Ltd
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Projectreemakb03
 
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchrohitcse52
 
Modelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsModelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsYusuf Yıldız
 
me3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Ame3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Akarthi keyan
 
A Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationA Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationMohsinKhanA
 
Dev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingDev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingMarian Marinov
 

Kürzlich hochgeladen (20)

EPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptxEPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptx
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entender
 
solar wireless electric vechicle charging system
solar wireless electric vechicle charging systemsolar wireless electric vechicle charging system
solar wireless electric vechicle charging system
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
計劃趕得上變化
計劃趕得上變化計劃趕得上變化
計劃趕得上變化
 
Design of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxDesign of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptx
 
nvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxnvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptx
 
Basic Principle of Electrochemical Sensor
Basic Principle of  Electrochemical SensorBasic Principle of  Electrochemical Sensor
Basic Principle of Electrochemical Sensor
 
Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Litature Review: Research Paper work for Engineering
Litature Review: Research Paper work for EngineeringLitature Review: Research Paper work for Engineering
Litature Review: Research Paper work for Engineering
 
Multicomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdfMulticomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdf
 
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Project
 
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
 
Modelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovationsModelling Guide for Timber Structures - FPInnovations
Modelling Guide for Timber Structures - FPInnovations
 
me3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Ame3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part A
 
Lecture 4 .pdf
Lecture 4                              .pdfLecture 4                              .pdf
Lecture 4 .pdf
 
A Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationA Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software Simulation
 
Dev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingDev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & Logging
 

Docks & harbors construction

  • 1. DOCKS & HARBOURS CONSTRUCTION Presentation by – Madhura S. Deshpande 1427002
  • 2. Basic terms • Dock: the enclosed area provided for berthing ships to keep them afloat at a uniform level to facilitate loading and unloading is called the dock. • Harbour: The sheltered area of the sea in which vessels could be launched, built or repaired, or could seek refuge during storm time and provide loading and unloading facilities of cargo and passengers is called harbour.
  • 3. Harbour • It is a sheltered area • Used for loading and unloading of cargo • Vessels are also built, repair and launch • It protects ships naturally or artificially from fury of sea • Ships, boats, and barges can seek shelter from stormy weather, in navigable waters well protected naturally or artificially • Situated along sea shore or river estuary or lake or canal connected to sea
  • 4. Classification of harbour • Artificial harbour Man-made harbour Deliberately constructed break waters, sea walls , jetties, and also dredging is done there Requires maintenance by periodic dredging Ex. Madras harbour
  • 6. Natural harbour • It is protected form storms and waves by prominence of land • Consist of part of body of water which is protected and deep enough for anchorage
  • 8. Semi- natural harbours • The ones who are protected on sides by land and require man- made protection only at entrance • Ex. Vishakhapatnum port
  • 10. Classification based on function to be performed 1. Harbor of refuge- used for ships in storms or emergency condition. good anchorage and safe and easy access from the sea. 2. Commercial harbor- Facilities for loading and unloading of cargo are provided.
  • 12. 3. Fishery harbor- For loading unloading the catch . It should have refrigeration stores with plenty of storing space for preserving catch. 4. Military harbor or navel base harbours- This harbor is meant for accommodating naval crafts and serves as a supply deport. The layout of this type of harbor is greatly influenced by its location.
  • 14. Planning for harbour The planning of harbor should be carried out after collecting the necessary information of the existing features at the proposed site. The following important facts should be studied:  To carry out a thorough survey of the neighborhood including the fore shore and depths of water in the vicinity is necessary. The nature of the harbor, whether sheltered or not should be studied. The existence of sea insects which undermine the foundation should be studied.
  • 15. The problem of silting or erosion of coast line should be studied carefully. To ascertain the character of the ground, borings and soundings should be taken. To know the probable surface conditions on land, borings on land should also be made. It will be help full in locating the harbor works correctly. The natural metrological phenomenon should be studied at site with respect to frequency of storms, rainfall, range of tides, maximum and minimum temperatures, direction and intensity of winds, humidity, direction and velocity of currents etc.
  • 16. Requirements of a good harbour • The depth of a harbor should be sufficient for every type of visiting ships. • The bottom of harbor should provide secured anchorage to hold the ships against high winds. • To prevent destructive wave action, break water are provided. • The entrance of a harbor should be wide enough to provide the easy passage of ships.
  • 17. Harbor area required depends upon the following factors:  Size and number of ships to be accommodated in the harbor at a time  Length and width needed for movement of ships to and from berths.  Type of cargo carried. To make the harbor useful for operating and dispatching ships, the water depth in the entrance, approach channel and harbor basin should be sufficient even at the low water spring tide.
  • 18. • It is very important i.e. the location and alignment of elements such as entrance, approach channel, turning basin, break water, wharves, jetties and docks etc. will ensure easy maneuverability and additional navigation facilities. • The main faction of a harbor is to provide a safe and suitable accommodation to the vessels needing refuge, supplies, repairs, refueling or transfer of cargo and passengers.
  • 19. Selection of site • Availability of cheap land & construction material. • Natural protection from waves & winds • Transport & communication facilities • Industrial development of the locality • Sea bed, sub soil & foundation conditions • Avability of electrical energy • Defense & strategic aspects • Traffic potentiality of harbour
  • 20. Features of harbour • Break water • Docks • Entrance channel • Jetty • Light house • Berthing Basin • Turning Basin • Pier Head • Wharves
  • 21. Breakwaters • Breakwater are the structures constructed to enclose the harbours to protect them from the effect of wind generated waves by reflecting and dissipating their force or energy. • Helps to use the area thus enclosed as a safe anchorage for ships and to facilitate loading and unloading of water by means of wave breakers. • Height depends upon the its purpose, extent of enclosed water area and nature of existing shipping work.
  • 22. • Generally the height of breakwater is kept as equivalent to 1.2 to 1.25 times the waves expected. • It also helps to prevent beach erosion • The most common breakwater used has a core of small rocks or rubble with a covering of large rocks to keep the core from being washed away.
  • 23. • It may be small structures, placed one to three hundred feet offshore in relatively shallow water • Breakwater either fixed or floating- choice depend on normal water depth & tidal range • Its construction is usually parallel or perpendicular to the coast
  • 26. Docks • Docks are enclosed areas for berthing the ships to keep them afloat at a uniform level to facilitate loading and unloading cargo. • A marine structure for berthing of vessels for loading and unloading cargo and passengers. • Necessary for discharging of the cargo • As ships require a number of days for discharging cargo, during which period they need a uniform water level.
  • 27. • If ship is subjected to a vertical movement by the tides, great inconvenience will be felt in lifting the cargo from the ship and special arrangement will be needed for lifting the cargo • Docks can be classified into following two categories:  Wet docks.  Dry docks.
  • 28. Wet docks- • Docks required for berthing of ships or vessels to facilitate the loading and unloading of passengers and cargo are called wet docks. • These are also known as harbor docks.
  • 29.  Dry docks • The docks used for repairs of ships are known as dry docks. • It is long excavated chamber, having side walls, a semi circular end wall and a floor. • The open end of the chamber is provided with a gate and acts as the entrance to the dock.
  • 30. ENTRANCE CHANNEL • Depth and width are kept more at entrance • Width depends upon density of traffic and no. of entrances
  • 31. JETTIES • A narrow structure projecting from the shore into the water with berths one or both sides and sometimes at the end also. • These are structures in the form of piles projections. • Built from the shore to the deep water. • They may be constructed in the sea or in a navigable river. • The jetties extend from the shore to the deep sea to receive the ship.
  • 33. BERTHING AND TURNING BASINS • Berthing basins are used for the parking of ships • While turning for the turning of ships