SlideShare a Scribd company logo
1 of 127
Download to read offline
ERECTION
                   MANUAL

                              STEAM TURBINE
                                  500 MW
                               (KWU DESIGN)




                    DOCUMENT NO. TS-T1-08




       Bharat Heavy Electricals Limited
                          POWER SECTOR
                      TECHNICAL SERVICES (HQ)
                                   NOIDA




Bharat Heavy Electricals Limited                T1-08-0801G
Rev 00, 7-98                                      Page No. 1
FOREWORD



I am glad that Power Sector - Technical Services ( Head Quarters),
Noida has brought out this erection manual of 500 MW steam
turbine (KWU design) being produced by BHEL. This manual lays
emphasis on site optimisation techniques which aims at uniform
erection practices, improvement in quality, reduction in time cycle
and saving in cost.




I am sure, this manual will form the basis for site erection activities
so that the organisation can derive      full benefit out of this. It is
needless to emphasize that upgrading of technology is a continuous
process and we have to review our methods of working and make
suitable changes, wherever required.




                                                      (K P Mathur)
New Delhi                                          Executive Director
                                                     (PEM & TS)




Bharat Heavy Electricals Limited                            T1-08-0801G
Rev 00, 7-98                                                  Page No. 2
PREFACE
The Erection Manual for 500 MW Steam Turbine (KWU design)
manufactured by BHEL      for Thermal Power Stations has been
prepared by a team of BHEL engineers having long experience in
Erection & Commissioning, Design, Quality control of steam turbines.
This dedicated team has been drawn from regional erection group,
designed department of manufacturing units, PS-Q & TS-HQ,
Noida.

The manual carries general description of steam turbine, erection
procedure, special instruction, general instructions, and various other
technical instructions with an intention to establish an uniform
approach for erection of steam turbine.

The Erection Manual provides broad based guide line for erection of
steam turbine.     Product standard, technical circulars & BHEL
drawings for the specific project will precede the instructions and
guidelines furnished in this manual. Project specific document will be
generated by region concerned. This document is generated as a
standard Erection Manual for 500 MW fixed pedestal type steam
turbine with spring loaded foundation.

The work done by TASK FORCE is commendable. Feed-back and
suggestions are welcome for the improvement of this Erection
Manual to bringing down the cycle time with quality.

BHEL reserves the right to suggest alternative            procedure    if
necessity arises at site due to local site conditions .


                                                    (BABOO RAM)
NOIDA                                     GENERAL MANAGER(TS&Q)

SNO   DESCRIPTION                                INSTRUCTION NO




Bharat Heavy Electricals Limited                             T1-08-0801G
Rev 00, 7-98                                                   Page No. 3
1     TECHNICAL DATA                         T 1- 08-0101G

2     INSTRUCTION FOR HANDLING AND           T 1-08-0202G
      STORAGE OF TURBINE
3     ERECTION SEQUENCE                      T 1-08-0303G

4     ERECTION PROCEDURE                     T 1-08-0404G

5     GROUTING PROCEDURE                     T 1- 08-0505G

6     ASSEMBLY OF IP MODULE AT SITE          T 1-08-0606G

7     SEALING AND ANTISEIZING COMPOUNDS      T 1-08-0707G

8     CRITICAL ACTIVITIES                    T 1-08-0808G

9     SPRING LOADED FOUNDATION               T 1- 08-0909G

10    ERECTION OF PIPING                     T 1-08-1010G

11    SPECIFICATION FOR GAS HEATING DEVICE   T 1-08-1111G

12    SPECIFICATION FOR BREECH NUT HEATING   T 1-08-1212G
      DEVICE
13    SPECIFICATION FOR THERMAL INSULATION   T1-08-1313 G




Bharat Heavy Electricals Limited                             T1-08-0801G
Rev 00, 7-98                                                   Page No. 4
The following codification system is used for numbering of instructions and the
codification of Log Sheets is as per FQA document.

  XX        X     -       XX            XX        XX      X
 Alpha    Numeric        Numeric       Numeric   Numeric Alpha

                                                                  Type of
                                                                  Instruction


                                                      System Instruction No



                                                      System Designation



                                                 Rating of Main Equipment



                                                 Type of Manual



                                                 Product Code

1.1 PRODUCT CODE

            B           Boiler
            BA          Boiler Aux.
            T           Turbine
            TA          Turbine Aux.
            G           Generator
            GA          Generator Aux
            P           Power Plant Piping
            CI          C&I
1.2 TYPE OF MANUAL

            1           Erection
            2           Commissioning
            3           Service

Bharat Heavy Electricals Limited                                         T1-08-0801G
Rev 00, 7-98                                                               Page No. 5
1.3 RATING OF MAIN EQUIPMENT

           01        200/210 MW
           02        120 MW
           03        110 MW
           04         60 MW
           05          30 MW
           06        100 MW
           07        235 MW
           08        500 MW             KWU Design
           09        210 MW             KWU Design
           10        120 MW             KWU Design
           11         60 MW             KWU Design
           12          70 MW            KWU Design
           13        Industrial Units
           14        210 MW             Tower Type Concrete Pylem
           15        210 MW             Tower Type Steel Structure
           16        500 MW             Tower Type Once through
           17        250 MW
           18        CCP




Bharat Heavy Electricals Limited                              T1-08-0801G
Rev 00, 7-98                                                    Page No. 6
1.4 SYSTEM DESIGNATION

            SNO      DESCRIPTION
             1.      TECHNICAL DATA
             2.      INSTRUCTION FOR HANDLING AND STORAGE
                     OF TURBINE
             3.      ERECTION SEQUENCE
             4.      ERECTION PROCEDURE
             5.      GROUTING PROCEDURE
             6.      ASSEMBLY OF IP MODULE AT SITE
             7.      SEALING AND ANTISEIZING COMPOUNDS
             8.      CRITICAL ACTIVITIES
             9.      SPRING LOADED FOUNDATION
             10.     ERECTION OF PIPING
             11.     SPECIFICATION FOR GAS HEATING DEVICE
             12.     SPECIFICATION FOR BREECH NUT HEATING
                     DEVICE
             13.     SPECIFICATION FOR THERMAL INSULATION




1.5 TYPE OF INSTRUCTION
            G           General
            T           Technical
            L           Log Sheet
            C           Check List




Bharat Heavy Electricals Limited                            T1-08-0801G
Rev 00, 7-98                                                  Page No. 7
LOAD
RATED                                                                  500 MW

MAX. UNDER VALVE WIDE OPEN (VWO) CONDITION                               524.2


CONSTRUCTION
THREE CYLINDER REHEAT CONDENSING TURBINE                               500 MW

SINGLE FLOW HP TURBINE WITH 17 REACTION STAGES            TYPE       H30-100-2

DOUBLE FLOW IP TURBINE WITH 12 REACTION STAGES PER        TYPE         M30-63
FLOW

DOUBLE FLOW LP TURBINE WITH 6 REACTION STAGES PER         TYPE        N30-2X10
FLOW

2 MAIN STOP AND CONTROL VALVES                            TYPE         EV320-1

2 REHEAT STOP AND CONTROL VALVES                          TYPE           IV560

1 SWING CHECK VALVE IN COLD REHEAT LINE                                 DN-800
                                                          MAKE   BHEL,TIRUCHY

2 BYPASS STOP AND CONTROL VALVES                                       DN-320



EXTRACTION SWING CHECK VALVES :

EXTRACTION-1     : NO VALVE                                                   -

EXTRACTION-2     : 1 SWING CHECK VALVE WITH ACTUATOR                    DN-800
                                                          MAKE   BHEL,TIRUCHY

EXTRACTION-3     : 1 SWING CHECK VALVE WITH ACTUATOR                    DN-500
                   &                                      MAKE   BHEL,TIRUCHY
                   1 SWING CHECK VALVE WITHOUT
                   ACTUATOR

EXTRACTION-4.1   : 2 SWING CHECK VALVE WITH ACTUATOR                    DN-500
                                                          MAKE   BHEL,TIRUCHY

EXTRACTION-4.2   : 2 SWING CHECK VALVE WITH ACTUATOR             DN-500
                                                          MAKE   BHEL,TIRUCHY

EXTRACTION-5     : 1 SWING CHECK VALVE WITH ACTUATOR                    DN-400
                   &                                      MAKE   BHEL,TIRUCHY
                   1 SWING CHECK VALVE WITHOUT ACTUATOR

EXTRACTION-6     : NO VALVE

SPEED
RATED SPEED                                                             50.0 /S


Bharat Heavy Electricals Limited                                   T1-08-0801G
Rev 00, 7-98                                                         Page No. 8
SPEED LIMITATION IN LOAD & STATION AUX. LOAD                                524.2
                                              OPERATION          :                     51.5 /S
                           MAX. SPEED, NO TIME LIMITATION        :                     47.5 /S
                           MIN. SPEED, NO TIME LIMITATION

PERMISSIBLE FOR A MAXIMUM OF 2 HRS. DURING THE LIFE OF           :                  47.5 /S
LP BLADING                               SPEED                   :            51.5 TO 60 /S
BELOW
                                         SPEED
ABOVE

SPEED EXECUTION RANGE AT OPERATION WITHOUT LOAD*                 :           6.7 TO 47.5 /S

STANDARD OVER SPEED TRIP SETTING                                 :                MAX. 55.5 /s


 * THIS SPEED RANGE SHOULD BE PASSED THROUGH IN ONE
   SMOOTH OPERATION TO AVOID ENDANGERING THE
   BLADES DUE TO RESONANCE

STEAM PRESSURES
                                       RATED*       LONG TIME        SHORT TIME
                                                    OPERATION        OPERATION

INITIAL STEAM                           166.7           166.7              20.7          BAR

BEFORE 1st HP DRUM STAGE                154.4           163.4          169.9             BAR

HP CYLINDER EXHAUST                      44.9           52.0           57.4**            BAR

IP CYLINDER STOP VALVE INLET             40.3           46.7           55.2**            BAR

EXTRACTION 6                             44.9           52.0               57.4          BAR

EXTRACTION 5                             17.5           22.2               22.2          BAR

EXTRACTION 4                              7.2            8.7               8.7           BAR

EXTRACTION 3                             2.58            3.2               3.2           BAR

EXTRACTION 2                            1.329           1.66               1.66          BAR

EXTRACTION 1                            0.257           0.41               0.41          BAR

LP CYLINDER EXHAUST                     0.1013           0.3               0.3           BAR


* THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACK
 PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS.

** THE SAFETY VALVES MUST BE SET SO THAT THESE SHORT TIME VALUES ARE NOT EXCEEDED.


LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT.

SHORT TIME OPERATION : PERMISSIBLE MOMENTARY VALUE. THE AGGREGATE DURATION OF
                      SUCH SWINGS MUST NOT EXCEED 12 HOURS IN ANY ONE YEAR.

ALL PRESSURES ARE ABSOLUTE PRESSURES


 Bharat Heavy Electricals Limited                                                 T1-08-0801G
 Rev 00, 7-98                                                                       Page No. 9
LOW VACUUM TRIP, STANDARD SETTING
HYDRAULIC LOW VACUUM TRIP                             :         0.3   BAR

ELECTRICAL LOW VACUUM TRIP                            :         0.3   BAR

HYDRAULIC LOW VACUUM TRIP BYPASS OPERATION            :         0.6   BAR




SEAL STEAM SUPPLY SYSTEM
PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC)     :         35    MBAR




AXIAL SHIFT
                ALARM                                TRIP

               * 0.5 mm                             * 1 mm


* DIRECTION OF ROTATION
  ANTI CLOCK WISE WHEN VIEWED FROM FRONT PEDESTAL TOWARDS THE
  GENERATOR




Bharat Heavy Electricals Limited                                T1-08-0801G
Rev 00, 7-98                                                     Page No. 10
STEAM TEMPERATURES
                                        RATED    LONG TIME     400 h     80 h PER
                                         VAL.      VALUE       PER        ANNUM
                                       ANNUAL     (WITHIN     ANNUM      MAX. 15
                                        MEAN      ANNUAL                  MIN IN
                                        VALUE      MEAN                 INDIVIDUA
                                                    VAL.)                 L CASE
                                                                                    O
INITIAL STEAM                           536.0      546.O       552.O      566.0         C
                                                                                    O
IP CYLINDER STOP VALVE INLET            536.0      546.3       552.0      566.0         C



                                       RATED      LONG       80 h PER      IN
                                       VALVE *    TIME        ANNUM     SPECIAL
                                                 OPERATI     MAX. 15     CASES
                                                   ON         MIN IN     AT NO
                                                             INDIVIDU    LOAD
                                                             AL CASE
                                                                                    O
HP CYLINDER EXHAUST                     340.0      360.0      440.0      500.0**    C
                                                                                    O
EXTRACTION 6                            340.0      360.0      440.0      500.0**    C
                                                                                    O
EXTRACTION 5                            413.9      421.9      459.9                 C
                                                                                    O
EXTRACTION 4                            292.1      304.1      346.4                 C
                                                                                    O
EXTRACTION 3                            187.3      195.3      242.3                 C
                                                                                    O
EXTRACTION 2                            128.3      139.3      184.3                 C
                                                                                    O
EXTRACTION 1                            66.5       86.5       136.5                 C
                                                                                    O
LP CYLINDER EXHAUST                     46.1       70.0        70.0                 C


       LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME
       LIMIT.

*      THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR
       BACK PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM
       CONDITIONS.

**    ONLY VALID FOR THE NO LOAD PERIOD WITH HIGH REHEAT PRESSURE AFTER
      TRIP-OUT FROM FULL LOAD OPERATION. FOR INDIVIDUAL CASE APPROX. 15
      MINUTES

       THE TURBINE IS IMMEDIATELY RE-LOADED OR THE BOILER IMMEDIATELY
       REDUCED TO MINIMUM LOAD IF NO LOAD OPERATION IS MAINTAINED.




    Bharat Heavy Electricals Limited                                        T1-08-0801G
    Rev 00, 7-98                                                             Page No. 11
CASING TEMPERATURES
WALL TEMPERATURES                                          ALARM         MACHINE MUST BE
                                                             AT           SHUT DOWN AT
                                                                                                     O
HP TURBINE CASING EXHAUST                                       480               500                  C
                                                                                                     O
OUTER CASING OF LP CYLINDER                                     90                110                  C

PERMISSIBLE DIFFERENTIAL TEMP. BETWEEN PARALLEL STEAM SUPPLY LINES :
                                                                                                 O
                                                            •     NO TIME LIMITATION         : 17 C
                                                                                                 O
                                                            •     SHORT TIME PERIOD (15 MIN.) : 28 C

IN THE HOTTEST LINE THE LIMITATIONS INDICATED FOR INITIAL STEAM & REHEAT TEMP. MUST NOT BE EXCEEDED.
                                                     O
SPRAY WATER TO LP TURBINE MUST BE SWITCHED ON AT 90 C.

TEMPERATURES DIFFERENCE                                    ALARM         MACHINE MUST BE
                                                             AT           SHUT DOWN AT
                                                                                                     O
DIFFERENCE BETWEEN UPPER & LOWER                             * 90                * 100                 C
CASING HALVES HP TURBINE. MIDDLE
                                                                                                     O
LP TURBINE. FRONT                                            * 30                 * 45                 C
                                                                                                     O
LP TURBINE. REAR                                             * 30                 * 45                 C

FEEDWATER HEATER OUT OF SERVICE
OPERATION WITH FEEDWATER HEATER OUT OF SERVICE                           MAIN STEAM           LOAD
                                                                         FLOW Kg/s             MW

EXTRACTION A6 = 0                                                              395             500

EXTRACTION A5 = 0                                                              421             500

EXTRACTION A3 = 0                                                              423             500

EXTRACTION A2 = 0                                                              425             500

EXTRACTION A1 = 0                                                              423             500

EXTRACTION A6, A5 = 0                                                          400             525

OUTPUT LIMIT DURING TESTING WITH AUTOMATIC TURBINE TESTER
TESTING OF MAIN STEAM STOP & CONTROL VALVE                                     400             MW

TESTING OF HRH STEAM STOP & CONTROL VALVE                                   200 - 500          MW

MOTORING :
MOTORING IS THE CONDITION IN WHICH THE TURBINE IS DRIVEN BY THE GENERATOR AT
RATED SPEED WITH THE STOP & CONTROL VALVES CLOSED. IN THIS OPERATING MODE,
CERTAIN TURBINE COMPONENTS ARE HEATED UP BY WINDAGE POWER IN THE BLADING.
TO PREVENT HEAT-UP BEYOND PERMISSIBLE TEMPERATURES, MOTORING MUST NOT BE
ALLOWED TO CONTINUE FOR LONGER THAN ONE MINUTE. IF THE CONDENSER LOW
VACUUM LIMIT OF 0.3 BAR IS EXCEEDED, MOTORING MUST NOT BE ALLOWED TO CONTINUE
FOR MORE THAN 4 SECONDS.




 Bharat Heavy Electricals Limited                                                        T1-08-0801G
 Rev 00, 7-98                                                                             Page No. 12
BEARING TEMPERATURES
                                                 ALARM      MACHINE MUST BE
                                                   AT        SHUT DOWN AT
                                                                                    O
OPERATION TEMPERATURE BELOW 75 OC                   90             120              C
                                                                                    O
OPERATION TEMPERATURE 75 TO 85 OC                  100             120              C
                                                                                    O
OPERATION TEMPERATURE 85 TO 90OC                   110             120              C
                                                                                    O
OPERATION TEMPERATURE ABOVE 90OC                   115             120              C

VIBRATION
                                ABSOLUTE BEARING         ABSOLUTE SHAFT
                                HOUSING VIBRATION           VIBRATION

STANDARD ALARM SETTING                                     30 µ m ABOVE         µm
                                                          NORMAL LEVEL*

MAXIMUM ALARM SETTING                    35                      120            µm

LIMIT VALUE FOR TRIPPING                 45                      200            µm
* THE NORMAL LEVEL IS REPRODUCIBLE VIBRATIONAL BEHAVIOUR TYPICAL FOR THE MACHINE AND
  DEPENDENT ON THE OPERATING CONDITIONS, VIBRATION READINGS INDICATED IN CONTROL
  ROOM ARE HALF PEAK. THE ABOVE VALUES ARE ALSO GIVEN IN HALF PEAK.

WEIGHTS
HP TURBINE, COMPLETELY ASSEMBLED                                   :     94.6   T
IP TURBINE. TOP HALF OUTER CASING                                  :     25.7   T
IP TURBINE, TOP HALF INNER CASING, COMPLETE WITH BLADING           :     15.5   T
LP TURBINE. TOP HALF OUTER CASING COMPLETE                         :     42.6   T
LP CYLINDER, TOP HALF OUTER SHELL OF INNER CASING, COMPLETE        :     38.5   T
WITH BLADING, STATIONARY BLADE CARRIERS & DIFFUSER

HP TURBINE ROTOR, COMPLETE WITH BLADING                            :     16.3   T
IP TURBINE ROTOR, COMPLETE WITH BLADING                            :     23.1   T
LP TURBINE ROTOR, COMPLETE WITH BLADING                            :     85.8   T
MAIN STOP & CONTROL VALVE, COMPLETE WITH SERVO MOTORS,             :     20.9   T
WITHOUT BEND & PIPE SECTION
REHEAT STOP & CONTROL VALVE, COMPLETE WITH SERVO                   :     32.2   T
MOTORS, WITHOUT BEND & PIPE SECTION

ALL WEIGHTS HAVE BEEN CALCULATED WITH SAFETY ALLOWANCES. SLINGS
CHOSEN MUST PROVIDE SUFFICIENT SECURITY.




Bharat Heavy Electricals Limited                                          T1-08-0801G
Rev 00, 7-98                                                               Page No. 13
OIL SUPPLY
MAIN OIL TANK, RATED CAPACITY                           :   25/40      Cu . M
Ist OIL FILLING (ESTIMATED)                             :   47.5       Cu . M
FLUSHING OIL QUANTITY (ESTIMATED)                       :   28.5       Cu . M
OIL COOLER FOR OPERATION, NUMBER                        :    1         NO.
OIL COOLER FOR RESERVE, NUMBER                          :     I        NO.
OIL TEMP. AT COOLER OUTLET, UNIT IN OPERATION
                                            MIN.        :    38
                                                                         O
                                            NORMAL      :    45           C
                                            MAX.        :    47

OIL TEMP. AT COOLER OUTLET, UNIT SHUT DOWN
                                                                         O
                                               MAX.     :    75           C
TEMP. RISE OF OIL IN BEARINGS
                                                                         O
                                               NORMAL   :    20           C
                                               MAX.     :    25

ESTIMATED OIL REQUIREMENTS OF BEARINGS :
BEARING 1(HP TURBINE, FRONT PEDESTAL)                   :    0.8       dm3/S
BEARING 2                                               :   15.4       dm3/S
BEARING 3                                               :    4.1       dm3/S
BEARING 4                                               :    8.6       dm3/S
GENERATOR FRONT BEARING                                 :   7.92       dm3/S
GENERATOR REAR BEARING                                  :   7.92       dm3/S
EXCITER BEARING                                         :   0.70       dm3/S
1 DUPLEX OIL FILTER FOR BEARING OIL (FULL FLOW)         :   200         mm
DUPLEX OIL FILTER . TYPE - 2.62.9. SIZE 355/750. MAKE   :   BOLL & KIRCH
FILTRATION PARTICLE SIZE OF DUPLEX FILTER ELEMENT       :    37         µm
FILTRATION PARTICLE SIZE OF MAIN OIL TANK FILTER        :   250         µm
ELEMENT
SAFETY VALVE IN JACKING OIL SYSTEM, SETTING             :   200         BAR
MAX.
PRESSURE LIMITING VALVE IN JACKING OIL SYSTEM,          :   100         BAR
SETTING
1 DUPLEX OIL FILTER FOR JACKING OIL                     :    25         mm
FILTRATION PARTICLE SIZE OF JACKING OIL FILTER          :    37         µm




Bharat Heavy Electricals Limited                                    T1-08-0801G
Rev 00, 7-98                                                         Page No. 14
OIL PUMPS
               MAIN OIL     AUXILIARY        DC         JACKING
                PUMP        OIL PUMP     EMERGENCY      OIL PUMP
                                          OIL PUMP

QUANTITY           1                2        1       AC : 2          DC : 1

MAKER            BHEL              KSB      KSB         TUSHAKO

TYPE          97.22 dm3/S    ETA-150-     ETA-100-        SDF80
                              50VVL        33VVL

CAPACITY          75           89.25        30                1.53            dm3/s
(RATED)

DISCHARGE         8.6              6.2      2.3               178             BAR
PRESSURE
(GAUGE)

SPEED             50           24.75        24.3          49.42                /s

DRIVE          TURBINE      AC MOTOR     DC MOTOR     AC          DC
                                                     MOTOR       MOTOR




Bharat Heavy Electricals Limited                                         T1-08-0801G
Rev 00, 7-98                                                              Page No. 15
CONTROL FLUID SUPPLY
CONTROL FLUID TANK, RATED CAPACITY                           :     10/16      Cu . M

Ist FLUID FILLING (ESTIMATED)                                :       15       Cu . M

FLUSHING FLUID QUANTITY (ESTIMATED)                          :       10       Cu . M

CONTROL FLUID COOLER FOR OPERATION, NUMBER                   :       1        NO.

CONTROL FLUID COOLER FOR RESERVE, NUMBER                     :       I        NO.

CONTROL FLUID MAINTENANCE EQUIPMENT :
GEAR PUMP
                                        MANUFACTURER         :        STEIMEL
                                        TYPE                 :       BGK 2-24R

FLUID FLOW                                                   :      0.28      dm3/S

GAUGE PRESSURE                                               :      3.06          at

SPEED                                                        :       25           S-1

MOTOR POWER                                                  :      0.75          KW

2 EARTH FILTERS
                                        MANUFACTURER         :        ROTRING
                                        TYPE                 :        PYG5-350

EARTH FILLING MESH                                           :      140           Kg

1 FINE MESH FILTER
                                        MANUFACTURER         :       ROTRING
                                        TYPE                 :     S-1800-14-TUY

FILTRATION PARTICLE SIZE                                     :      3-5           µm

FILTER MATERIAL                                              :           COTTON


CONTROL FLUID SUPPLY SYSTEM

A FIRE RESISTANT FLUID IS USED FOR THE CONTROL SYSTEM




SCOPE
        The document covers all steam turbine components and provides the handling,
        inspection and storage instructions for large steam turbine components at site.
        A strict adherence to these instructions is necessary to avoid damages during
        handling and storage at site.
Bharat Heavy Electricals Limited                                           T1-08-0801G
Rev 00, 7-98                                                                Page No. 16
HANDLING OF EQUIPMENT :
In any kind of rigging work it is necessary to strictly observe the safety precautions,
      since even the slightest negligence and non observance of the rules may result
      in accidents, which may cause damage to equipment or injury to men.
The site for the rigging work involving lifting and conveying of loads should be well
     lighted. The loads must not be lifted unless the crane operator can see clearly
     the signals given by the rigger.
The positions where the slings are to be put, are marked on the packages and on
      the drawings. While lifting/handling these packages/equipment, the slings
      should only be put at the proper places.
The slings of the proper sizes and lengths should only be used for handling the
      equipment/packages. The angle between the two arms of the sling at the
      crane hook should be small (depending upon the dia of the sling) so as to have
      proper loading of the sling.
The turbine rotors and cylinder covers (in assembled condition are lifted by the
     use of special lifting devices supplied by BHEL. The use of these lifting
     devices facilitates correct slinging and maintain horizontal position of the
     components. These devices, after use, should be properly stored and
     conserved so as to ensure that they do not get damaged during storage.
     Before using them, they should be thoroughly inspected.
The work related to handling of the loads (packages or equipment) by crane or by
     other hoisting mechanism should be entrusted to trained riggers only. If
     the rigger/operator is not sure of the weight of the item/package (load) to
     be handled, he must ask for the required information before handling the
     equipment.


The rigger and the crane operator should see that the hook and the ropes of the
      crane occupy vertical position, before hoisting the load. Dragging of the load
      by slanting ropes is not allowed. The center of gravity of the load should be
      aligned with the vertical axis of the crane hook.
The eye bolts, 'D' shackles, turn buckles, and wire ropes of suitable sizes should
     only be used for handling of the equipment. Before using, they should be
     thoroughly inspected to their full threads, so as to avoid any chance of
     slipping then the load comes on them.
Before giving a signal to lift the load, the rigger must check and ensure that there are
      no loose parts or tools on the load, which might fall during lifting. Then the load
      must be lifted 100 or 200 mm high for checking the uniformity             of sling
      tensioning and reliability of lashing. If it is necessary to rearrange the sling
      lengths, the load must be lowered and then the slings rearranged.
Before horizontal conveyance of the load the rigger must see that the load has been
      lifted to a height at least 0.5 M above the tallest object, on the path of the load.

 Bharat Heavy Electricals Limited                                           T1-08-0801G
 Rev 00, 7-98                                                                Page No. 17
While the load is being conveyed, the rigger must accompany it and see
        that it is not moved above any person. Prior to lowering the load the rigger
        should examine the ground on which the load will be, lowered and make sure
        that these is no risk of falling or slipping of the load.
If any one of the personnel present during lifting or lowering of the load detects some
      defect of the crane or sling of notices some conditions jeopardizing the lifting or
      lowering operation, he must give a signal for emergency grounding of the
      package or components.
Smooth lifting and transportation of equipment must be ensured. Shocks and jerks
     should be avoided.
All   lifting devices, slings must be   properly   conserved after   use and periodically
          inspected and tested.
In the turbines having diaphragms, it is prohibited to handle diaphragms by putting
      slings in between the blades. For handling the welded diaphragms, special
      lifting devices is supplied by BHEL and the cast diaphragms are handled
      by putting the eye bolts, for which the provision of threads holes have been
      made in the diaphragms.
While handling the bearings, it is prohibited to put the sling across the rabbit surface of
      the bearings. Threaded holes have been provided; in which the eye bolts have
      to be put for handling of the bearings.
While handling the cylinders, it must be ensured that the slings or any other material
      does not get rubbed at their horizontal and vertical parting planes or at any
      other machined surface.
The handling of the long components such as longitudinal girder, endwall etc. should
      be done with extra care. When they are placed on the floor, in addition to the
      end supports, few extra supports at the intermediate positions must be provided.
 While handling LP rotor with free standing blades, care must be taken to ensure that no
       force is exerted on the free standing blades to avoid collapsing of clamping
       pieces under blade root.

MARKINGS ON PACKING CASES
Various symbols are marked on the packing cases as per 0456.001 to facilitate
      storage and handling of the crates and protection of equipment inside.

INSPECTION
Before storing the equipment it should be opened for visual examination or the
      internal packing, protective coating and condition of the equipment. Any
      damage to packing and conservation should be immediately rectified.
It    is necessary to carryout first inspection within three weeks of arrival of the
         consignment. Thereafter, all the equipment should be inspected once in every
         three months to insure that the conservation is intact. During rainy season, the
         inspection should be done once in a month. At any time, if any original

 Bharat Heavy Electricals Limited                                            T1-08-0801G
 Rev 00, 7-98                                                                 Page No. 18
conservation is found damaged, it should be reconserved as per                relevant
       conservation instructions No. ST 33004.
While inspecting the packages containing rotors, special care should be taken to check
       the journals. In case of slightest sign of pitting on the journals and thrust
       collar, immediate steps for rectification should be taken and equipment
       reconserved as per relevant conservation instructions.

STORAGE
All steam turbine equipment should be accommodated in the designated place of
      storage immediately after arrival at destination. This is very essential particularly
      during the rainy season.


Store houses fall into the following categories


        TYPE OF                                CONDITIONS
         STORE        TEMP.       RELATIVE                  ARRANGEMENT
         HOUSE                    HUMIDITY

           'P'         +50 C        < 70 %      Totally enclosed, rain proof, ventilated
                        to                      and dry with cemented floor.
                       500 C

           'Q'         upto             -       Roofed area with walls (of brick /
                       500 C                    asbestos/ GI sheet ) around and
                                                cemented / pucca hard floor.

           'R'           -             -        Raised platform with shed of asbestos /
                                                GI sheet / water proof tarapaulin.

           'S'           -             -        Raised Platform.




 Bharat Heavy Electricals Limited                                            T1-08-0801G
 Rev 00, 7-98                                                                 Page No. 19
The   platforms and store-houses should be built up in conformity with the fire
      prevention rules and standards. Complete storage area especially the ‘R’ & ‘S’
      catagory must be adequately fenced & protected against theft & pilferage.
These store houses and areas around them should have proper drainage facility for
     the sub-soil, surface and rain water. The water should not be allowed to stand
     or get accumulated in these areas, especially where the material has been
     stored.
Store house should be provided with proper ventilation facilities.
Level should be maintained for all the packages and equipment and should be
      uniformly supported to avoid distortion. The long packages should be
      supported at intermediate places also, so as to avoid sagging during storage.
Store houses should preferably be equipped with proper lifting devices to ensure
      normal handling of equipment.
Small and medium size parts can be kept on shelves with proper identification tags.
Packages upto 5 tones can be placed on upon the other upto 2.5m in height using
     required number of wooden spacers 50 mm thick. In doing so, lighter
     packages would be laid upon heavier once to avoid any damage to lower
     packages.
Articles weighing more than 5 tones should be laid in a single tier.
For heavier components under ‘Q’, the roof/walls may be constructed/fabricated after
      placement of the component on cemented/pucca hard floor.




 Bharat Heavy Electricals Limited                                        T1-08-0801G
 Rev 00, 7-98                                                             Page No. 20
STORAGE OF STEAM TURBINE COMPONENTS
   SNO.          DESCRIPTION OF THE COMPONENT      TYPE OF
                                                   STORAGE
    1.     FOUNDATION BOLT                            Q
    2.     EMBEDDED PARTS (ADDITIONAL)                R
    3.     COMPONENTS OF BASE PLATE ASSLY.            Q
    4.     BASE PLATE LP CASING                       R
    5.     LP OUTER CASIONG                           R
    6.     LONGITUDINAL GIRDER (LEFT & RIGHT)         R
    7.     LP FRONT WALL (TS&GS)                      R
    8.     LP SHAFT SEALING (FRONT & REAR)            Q
    9.     AUXILIARIES OF TURBINE                     Q
    10.    HP/IP BEARING PEDESTAL                     Q
    11.    HP/IP BEARING PEDESTAL ASSEMBLY PARTS      Q
    12.    IP/LP PEDESTAL ASSEMBLY                    Q
    13.    LP/GEN. PEDESTAL                           Q
    14.    BEARING PEDESTAL PARTS                     Q
    15.    FRONT BEARING PEDESTAL                     Q
    16.    LIFTING BEAM                               R
    17.    LP CASING EXTRACTION A1                    R
    18.    LP EXTRACTION A2                           R
    19.    LP EXTRACTION A3                           R
    20.    LP EXTRACTION PIPE SHEATHING               R
    21.    INNER GUIDE PLATE DIFFUSER                 R
    22.    DIFFUSER (UPPER & LOWER HALVES)            R
    23.    LP INNER-OUTER CASING (VH)                 Q
    24.    LP INNER CASING ASSEMBLY (LH & VH)         Q
    25.    HEATING DEVICE                             Q
    26.    LP CASING ASSEMBLY                         Q
    27.    LP INNER CASING ASSEMBLY (FASTENER)        Q
    28.    INNER GUIDE PLATE DIFFUSER (GS)            R
    29.    LP ROTOR                                   Q
    30.    IP TURBINE                                 Q

Bharat Heavy Electricals Limited                   T1-08-0801G
Rev 00, 7-98                                        Page No. 21
31.   IP TURBINE PARTS                         Q
    32.   IP INLET PIPES                           Q
    33.   HP TURBINE                               Q
    34.   HP INLET ASSEMBLY                        Q
    35.   HP EXHAUST ELBOW                         Q
    36.   HPT RELATED PARTS                        Q
    37.   FRAME FOR SUSPENSION (ESV)               R
    38.   SUSPENSION OF VALVE (ESV)                Q
    39.   ESV & CV CASING WITH VALVE               Q
    40.   ESV SERVOMOTORS WITH LIMIT SWITCH        Q
    41.   HP CONTROL VALVE SERVOMOTORS             Q
    42.   SUSPENSION OF VALVE (IV)                 Q
    43.   IV & CV CASING WITH VALVE                Q
    44.   IV SERVOMOTORS WITH LIMIT SWITCH         Q
    45.   IP CONTROL VALVE SERVOMOTORS             Q
    46.   FRAME FOR SUSPENSION (IV)                R
    47.   IV SERVOMOTORS WITH LIMIT SWITCH         Q
    48.   STEAM BLOWING & HYD. TEST DEVICE         Q
    49.   TOOLS FOR GOVERNING SYSTEM               Q
    50.   SUSPENSION OF LPB VALVE                  Q
    51.   WATER INJECTION VALVES                   Q
    52.   CHEST LPB WITH STOP & CONTROL VALVE      q
    53.   LPB STOP VALVE SERVOMOTOR                Q
    54.   LPB CONTROL VALVES SERVOMOTORS           Q
    55.   INJR. FOR SUCTION PIPE NB 350            R
    56.   INJR. FOR SUCTION PIPE NB 300            R
    57.   MAIN OIL TANK                            R
    58.   MAIN OIL TANK & NOZZLE ASSEMBLY          R
    59.   OIL STRAINER                             Q
    60.   LEVEL MONITOR INSTALLATION               Q
    61.   INSTRUMENTS                              Q
    62.   LEAKAGE / DIRTY FLUID TANK               R
    63.   VARIABLE ORIFICES & THROTTLE             Q

Bharat Heavy Electricals Limited                T1-08-0801G
Rev 00, 7-98                                     Page No. 22
64.   CONTROL FLUID TANK                              R
    65.   CONTROL FLUID TANK NOZZLE ARRANGEMENT           R
    66.   EXPANSION TANK                                  R
    67.   FILTER & PR. DAMPING DEVICES                    Q
    68.   CROSS AROUND PIPE                               R
    69.   SUPPORT FOR CAP                                 R
    70.   CHANGE OVER VALVE                               R
    71.   RATING & MONOGRAM PLATES                        Q
    72.   OIL STRIPER                                     R
    73.   HOUSING FOR HRH STEAM STRAINER                  R
    74.   HOUSING FOR MAIN STEAM STRAINER                 R
    75.   MS & HRH STR.HSG GASKET                         Q
    76.   STEAM STRAINER MS                               Q
    77.   STEAM STRAINER HRH                              Q
    78.   COMPENSATOR                                     Q
    79.   TURBINE CONTROL LPB / SUPPLY RACK               Q
    80.   TEMPERATURE & PRESSURE CONNECTIONS              Q
    81.   PR. TRANSMITTERS BAR. PROBES THERMOCOUPLES      Q
    82.   TRANSMITTERS & JUNCTION BOXES                   Q




Bharat Heavy Electricals Limited                       T1-08-0801G
Rev 00, 7-98                                            Page No. 23
STORAGE & PRESERVATION OF COMPONENTS OF
       TURBOGENERATOR, EXCITER AND SYSTEMS
   SNO.          DESCRIPTION OF THE COMPONENT        TYPE OF
                                                     STORAGE
    1.    EMBEDDED PARTS                                R
    2.    FOUNDATION PARTS                              R
    3.    WOUND STATOR WITH GAS COOLERS                 Q
    4.    TURNION FOOT PLATES                           Q
    5.    ROTOR                                         Q
    6.    ASSEMBLY OF PIPE CONTROL FOR GAS COOLERS      R
    7.    END SHIELDS                                   Q
    8.    FAN SHIELD, GEN VVIEW HEADER ASSEMBLY         R
    9.    TERMINAL BUSHING AND HEADER ASSEMBLY          Q
    10.   BEARING WITH BRUSH GEAR                       Q
    11.   SEAL BODY                                     Q
    12.   TEMP. CONNECTION                              Q
    13.   CASING FOR TURNIONS                           R
    14.   ERECTION MATERIALS                            Q
    15.   ERECTION DEVICES                              R
    16.   SHAFT SEALS                                   Q
    17.   SEAL RINGS                                    Q
    18.   ADOPTING RING                                 Q
    19.   AUXILIARY BEARING                             Q
    20.   CENTRIFUGAL FAN                               Q
    21.   CARBON DIOXIDE VAPOURISER                     Q
    22.   FILTER O.C.P.                                 Q
    23.   EXPANSION TANK                                R
    24.   OIL SEPARATOR                                 R
    25.   PRE CHAMBER                                   R
    26.   S.O.S.T.                                      R
    27.   SEAL OIL UNIT                                 Q
    28.   HYDROGEN DISTRIBUTION                         R
    29.   CARBON DIOXIDE DISTRIBUTION                   R
    30.   VALVES FOR AUXILIARY SYSTEMS                  P
    31.   GAS UNITS                                     Q
    32.   FLEXIBLE LEADS                                Q
     STORAGE & PRESERVATION OF COMPONENTS OF
                 HEAT EXCHANGERS

   SNO.          DESCRIPTION OF THE COMPONENT        TYPE OF
                                                     STORAGE
   PRODUCT : CONDENSER

Bharat Heavy Electricals Limited                     T1-08-0801G
Rev 00, 7-98                                          Page No. 24
1.    BOTTOM PLATE                            S
    2.    LOWER DOM WALL                          S
    3.    SIDE WALL                               S
    4.    WATER CHAMBER                           Q
    5.    UPPER DOM WALL                          S
    6.    STIFFENING PIPES                        S
    7.    STIFFENING RODS                         S
    8.    TUBE SUPPORT PLATE                      R
    9.    WATER BOX                               R
    10.   AIR EXTRACTION PIPING                   R
    11.   HOTWELL                                 S
    12.   SPRING ELEMENTS                         R
    13.   LOOSE ITEMS                             Q
    14.   INSTRUMENTS                             Q
    15.   CONDENSER TUBES (STAINLESS STEEL)       R
    16.   CONDENSER TUBES (NON-FERROUS)           Q
    17.   VACUUM PUMP                             Q
    18.   EJECTOR                                 R
    19.   AIR MEASURING DEVICE                    Q

   PRODUCT : HEATER
   1.     GLAND STEAM CONDENSER               R
   2.     STAND PIPE                          Q
   3.     INSTRUMENTS                         Q
   4.     DRAIN COOLER                        R
   5.     L.P.HEATERS                         R
          PRODUCT : COOLER
   1.     OIL COOLER                          R
   2.     CONTROL FLUID COOLER                R
   3.     STATOR WATER COOLER                 R
   4.     HYDROGEN COOLER                     Q
   5.     EXCITER AIR COOLER                  Q
   6.     INSTRUMENTS / LOOSE ITEM            Q




Bharat Heavy Electricals Limited              T1-08-0801G
Rev 00, 7-98                                   Page No. 25
MAXIMUM PERMISSIBLE LOADING FOR WIRE ROPES IN KG.
 NOMINAL        SINGLE              DOUBLE CORD WITH INCLUDED ANGLE OF
DIA (d) OF       CORD
ROPES mm                            0o        45o        90o        120o

    9             522              1044       965        738        522

    12           1170              2340       2070      1580        1170

    18           2150              4300       4000      3060        2150

    24           3850              7700       2100      5400        3850

    30           6200              12400     11500      8800        6200

    36           9000              18000     16600      12700       9000

    42           12200             24400     22600      17300      12200

    48           16000             32000     29500      22600      16000

    54           20200             40400     37300      28500      20200

    60           24900             49800     46000      35200      24900

    66           30100             60200     55700      42600      30100

    72           35800             71600     66200      50700      35800

    78           42100             84200     77700      59500      42100

    84           48800             97600     90200      69000      48800

    90           56000         112000        103500     79200      56000

    96           63700         127400        117700     90000      63700

   102           71900         143800        132900    101700      71900

   108           81000         162000        149700    114500      81000

   114           89900         179800        166100    127100      89900

   120           99700         199400        184300    141100      99700




Bharat Heavy Electricals Limited                                T1-08-0801G
Rev 00, 7-98                                                     Page No. 26
ERECTION SEQUENCE

         (For 500 MW Fixed pedestal type Turbine with spring loaded foundation)

1. Cleaning and checking of Turbine and Generator foundations as per the transverse

    and longitudinal axis including their elevation.

2. Prepare and install LP base plates, HP front pedestal, HP rear pedestal, LP front

    pedestal, LP rear pedestal along with their anchor bolts and anchor plates.

3. Provisionally    align and level all the pedestal and LP base          plates as per the

    transverse and longitudinal axis including their elevation.

4. Matching of anchor plates of pedestal and LP base plates to ensure their perfect

    seating.

5. Finally align and level HP front, HP rear, LP front and LP rear pedestals along with

    LP base plates as per the transverse and longitudinal axis including their elevation

    and catenary as per the design.

6. Prepare and install steel bars for LP casing centralising keys in foundation slab as

    per the required center line .

7. Weld locating ring of LP front pedestal and steel bars of LP front and LP rear

    centralising keys.

8. Prepare shuttering and grouting of the pedestals and LP base plates including

    anchor plates of HP rear pedestal.

9. Prepare, install, align/ level both the LP girder along with their carrier plates.

10. Prepare , install and assemble LP front and rear end walls with the LP girders.

11. Level / align LP outer casing lower half as per the transverse and longitudinal axis

    of the machine.

12. Install permanent packers of LP outer casing including their radial and axial keys.

13. Prepare and install LP inner outer casing along with gusset plates in position

 Bharat Heavy Electricals Limited                                              T1-08-0801G
 Rev 00, 7-98                                                                   Page No. 27
14. Align LP inner outer casing lower half and level it. Install LP casing parting plane

    platform .

15. Prepare and install LP front and LP rear lower half shaft seals housing and align it

    provisionally.

16. Prepare and install LP rotor along with their bellows in position.

17. Align LP rotor radially and axially in position and record free run out of rotor.

18. Record/ Ensure radial and axial clearances of the LP casing including rotor float

    including fitting of final axial keys of the LP inner casing .

19. Box up LP inner inner casing and heat tighten the parting plane bolts.

20. Box up LP inner outer casing .

21. Prepare and place HP module in position on temporary packers.

22. Transfer the load of HP rotor on bearings from the transport device and align it

    radially and axially.

23. Check free run out of HP rotor on journal and coupling face including its float.

24. Prepare and place IP module in position on temporary packers. (In case IP module

    is sent to site in disassembled condition, refer Instruction T1-08-0606G.

25. Loading of IP rear end of the shaft on bearing and removal of transport device.

26. Provisionally align HP , IP and LP rotor .

27. Couple HP / IP rotor on temporary Bolts and align rotor / casing radially and axially.

28. Record/ Ensure IP rotor float by shifting HP casing axially.

29. Conduct Horn drop test of HP casing without any radial and axial keys and pipe

    lines.

30. Conduct Horn drop test of IP casing without IP inlet upper half pipe lines.

31. Assembly of breech nut of HP casing and Main Steam Stop & Control valve

    assembly.


 Bharat Heavy Electricals Limited                                              T1-08-0801G
 Rev 00, 7-98                                                                   Page No. 28
32. Erection of Reheat Stop & Control valve assembly.

33. Weld IP inlet upper half pipe and record Horn drop values without radial-axial keys.

34. Alignment of HP/IP/LP rotors and their coupling on temporary bolts including its

    couple runout.

35. Swing check of HP rotor on its front end with temporary alternate bolt tightened on

    HP/IP coupling .

36. MOP alignment and its doweling.

37. Reaming/honing of HP/IP and LP/IP coupling including fitting of final coupling bolts.

38. Fixing of axial position of shaft and assembly of thrust bearing including its colour

    matching.

39. Roll check of HP/IP casing and fixing of radial and axial keys of the casing (Casing

    final packers need not to be put at this stage).

40. Assembly of bearings and checking of all clearances including fittings of side pads

    of bearing, yoke keys etc.

41. Turbovisory works in all the pedestal i.e. assembly and calibration of thrust bearing

    axial   shift, LP rotor expansions pick up, Hall generator and thermocouples of

    bearing .

42. Preparations of the bearing for oil flushing.

43. Oil flushing of the machine and normalizing the bearing after oil flushing.

44. Preparation and floating of TG deck as per Instruction No. T1-08-0909G.

45. Decoupling of HP / IP, LP/IP, LP/Gen., Gen./Exciter coupling and rechecking of

    alignment/catenary after floating of TG deck spring.

46. Final tightening of HP/IP, IP/LP , LP/Generator and Generator / Exciter coupling

    after correcting the alignment including their couple run out and swing check of rotor

    on HP Front and exciter rotor.


 Bharat Heavy Electricals Limited                                            T1-08-0801G
 Rev 00, 7-98                                                                 Page No. 29
47. Checking /Correction of LP shaft seal clearance after floating of TG deck with CW

    pump in operation and water in the hot well of condenser upto operating level.

48. Roll check of HP, IP casing in up and down direction only with TG deck in floating

    condition and CW pump in operation including water in hot well upto normal level.

49. Assembly of final packers of the HP, IP casing after completing the roll check in up

    and down direction.

50. Recording of final Horn drop of HP and IP casing after completing the welding of

    HP inlet, HP exhaust , IP inlet and Cross around piping.

51. Preparation and boxing up of LP casing after competing the full Roll check of LP

    casing and fitting of final casing packers and radial keys.

52. Barring gear.




 Bharat Heavy Electricals Limited                                           T1-08-0801G
 Rev 00, 7-98                                                                Page No. 30
CHECKING OF FOUNDATION BEFORE CASTING
Customer to provide, center line and elevation point.

Check positioning of all the inserts and fixed points with respect to center line
     in transverse and longitudinal direction as per BHEL Hardwar drawings.

Check elevation of all points.

Check verticality of all the pipe sleeves with the help of plumb.

Ensure proper locking of all the insert and fixed points before grouting.

Ensure leveling on the fixed points of LP girder and LP rear pedestal.

Preserve machined surfaces of all the fixed points against any damages due to
      Improper handling.

Ensure proper flatness of the bottom seating plate of all the inserts.

Ensure proper stiffeners in all the vertical and horizontal embedment provided
     for various purposes like hangers and supports etc.

Ensure proper cleaning of the area before casting.

Remove all unwanted material.

      NOTE: In case of spring loaded TG deck refer Installation Instruction
              No. T1-08-0909G prior to positioning of inserts etc.

CHECKS DURING CASTING/POURING OF CONCRETE
Casting of foundationTG deck should be carried out immediately after
      inspection of the foundationTG deck i.e. within 3-4 days after final
      inspection to avoid any disturbance to the inserts and fixed point.

Ensure no disturbance to the insert etc. during pouring of concrete while
     vibrators are used.




Bharat Heavy Electricals Limited                                         T1-08-0801G
Rev 00, 7-98                                                              Page No. 31
About 15-20 mm extra concrete may be left on top on all the pedestals and LP
     base plate area for chipping/cleaning purpose at a later date.

Close all the pipe sleeve from top to avoid entry of concrete inside. Alternately
      the pipe sleeve should be filled with sand.

CHECKING OF FOUNDATION AFTER CASTING
Clean complete foundation and remove all shuttering etc.

Ensure there is no loose concrete layer in the region where the pedestal and
     base plates are to be laid. No repair should be done in this region without
     consulting the turbine erection engineer.

Cover all the opening before checking any dimensional measurement to
     avoid any accident.

Establish a suitable longitudinal axis considering the fixed point of the LP rear
      pedestal and various pipe sleeves / inserts.

Establish a transverse axis as 90 degree with the help of the odolite.

Measure pitching/elevation of all the inserts and fixed points.

Measure elevation of all foundation on different pedestal and LP base plate area.

Check level of LP rear pedestal fixed points and if required correction may
     be carried out.

PREPARATION OF FOUNDATION FOR PLACEMENT OF
   PEDESTALS AND BASE PLATES:
Foundation are to be cleaned and loose concrete are to be chipped off.

Maintain elevation of foundation to ensure correct thickness of non-shrink
      grout.

A reference point for elevation in respect of machine center line (equivalent to LP
      rear pedestal) is to be maintained at a proper place. This point is to be
      preserved with proper protection. For making reference point a one side
      ground plate of about 200 x300 x20 mm may be used. This may be
      welded on a I-beam near Generator. The ground position of the plate is
      to be kept on top side and all elevation are to be transferred from this
      point with the help of water level jar. A correct elevation reading is to
      be punched on this plate. This reference point is to be used only during the
      turbine erection period.

Clean and deburr piping sleeves of the foundation on ID/OD       of the pipe.

Ensure all corners of the foundation remains perfect during chipping of extra
     concrete of foundation.



Bharat Heavy Electricals Limited                                       T1-08-0801G
Rev 00, 7-98                                                            Page No. 32
PLACEMENT OF PEDESTALS
Open and clean the pedestal.

Ensure there is no paint/oil on bottom face of the pedestal sole plate.

Ensure there is no paint on inside surface or the pedestal and if required sand
     blasting may be carried out at site.

Ensure correct fitting/clearance of locating rings of LP rear pedestal.

The half bore error of pedestals is punched by manufacturing unit however in
      case it is not there, measure and punch half bore error of pedestal in
      left/right side of the pedestal. If the error is nil then this may be
      punched as zero-zero.

Ensure that the pedestal parting plane is feeler tight after tightening all the
     parting plane bolts. If required, colour matching may be carried out but
     scraping/cutting is to be done on upper half cover only.

Check proper colour contact of spherical/cylindrical supports of the bearing
     with the pedestal.




Bharat Heavy Electricals Limited                                          T1-08-0801G
Rev 00, 7-98                                                               Page No. 33
Check contact between spherical Torus piece of bearing and
     spherical/cylindrical seat. In case of any variation in contact no
     scraping/cutting to be carried out at site and this may be referred to
     manufacturing unit. Also refer T1-08-0808G. Check centering of individual
     bearing w.r.t. pedestal seal bores by fixing pianowire on individual
     pedestal.

Ensure cleanliness of all pedestal oil lines. Close opening of oil lines of
     pedestal to avoid any foreign material entering in these pipe lines during
     erection at site.

Weld MOP suction and discharge pipe lines in HP front pedestal as per the
     drawing before placement.

Assemble protection sheet in the foundation bolt holes of pedestals.

Assemble anchor bolts along with anchor plate of the pedestals. Ensure that
     there is good contact available to the backing plate with the
     foundation. If required colour matching/grinding may be carried out to
     achieve the contact.

Assemble protection sheet in the anchor bolt hole from bottom side of HP rear
     pedestal foundation to avoid entry of grout metal.

Ensure level of both anchor plate of H.P. rear pedestal with 70-90 mm gap for
     filling of grouting concrete.

Adjust height of the Anchor Bolts as specified in the drawing.

PLACEMENT OF LP BASE PLATE, OVER THE FOUNDATION :
Clean all the four base plates.

Mark/punch center line on the base plate as per drawing.

Ensure proper cleaning of base plate on bottom side.

Put identification marks on each base plate to avoid any mistake in positioning of
      the same.

Do colour matching of all the eight nos. carrier plate on both the faces.

Match LP base plate with the individual carrier plate.

Place all the four base plates in position along with their leveling screws and
      foundation bolts.

Provisionally align and level all the four base plates.

Assemble protection sheet in the foundation bolt holes.




Bharat Heavy Electricals Limited                                      T1-08-0801G
Rev 00, 7-98                                                           Page No. 34
ALIGNMENT OF PEDESTALS AND LP BASE PLATES
Provisionally align and level all the four pedestals including LP base plates with
      reference to the earlier marked longitudinal and transverse axis. The
      elevation reference is to be taken from the already positioned plate for
      this purpose.

Align and level LP rear pedestal and set the elevation as per machine center line.

Use piano wire arrangement with micrometer for centering of pedestal bore and
      use water level jar for setting of elevation. Use measuring tape to
      maintain pitching of the bearing from one pedestal to another. Pedestals
      are to be set in level condition on both longitudinal and transverse
      direction. Align and level HP front, HP rear and LP front pedestals.
      Elevation of the pedestals are to be set as per catenary of the machine
      considering the half bore error of the pedestal if any.

Align and level, LP base plates. Elevation of LP base plate is to be kept higher
      than the rear pair of LP base plate in line with catenary of rotor.

After alignment of LP rear pedestal weld the locating rings as mentioned in the
       drawing.

During welding of locating ring, ensure that there is no movement in the
      pedestal in any of the direction.




Bharat Heavy Electricals Limited                                      T1-08-0801G
Rev 00, 7-98                                                           Page No. 35
GROUTING OF PEDESTALS AND LP BASE PLATES
Fill 3 to 8 mm washed Pea-gravel in all the anchor bolts sleeves. These gravel
       are necessary to give damping effect to the anchor bolts during operation
       of the machine.

Seal anchor bolts holes after filling of gravel to avoid any entry of grout metal.
      Medical tape may be used for sealing of these anchor bolt holes.

Clean foundation with compressed air.

Make shuttering of all the pedestal and LP base plates. Use thick polythene
     sheet inside the shuttering to give better finish and avoid moisture
     absorption by shuttering.

Shuttering should be made with maximum care to avoid any leakage of grout
      concrete. All sides of the shuttering are to be sealed either with some
      sealing compound or with thick mixture of grout material to avoid leakage
      of grout material.

Foundation are to be kept wet for about 6 hrs. before grouting.

Non shrinkage cement duly approved by BHEL is to be used for grouting of the
     pedestals and base plate.

Use fresh stock of the grouting material only and check the strength of the
      material before use.

During grouting, the mixture has to be poured from one end only and it has to
      flow to opposite end to avoid any blockage of air pocket.

Water curing is to be carried out for about 10 days duration.

All anchor bolts are to be stretched minimum after 21 days of grouting.

HP, IP & LP module placement work can be taken up after 24 hours of grouting
      of the pedestal and base plates.

For individual pedestal and base plate, grout mixture should be poured in one lot
      only.

PLACEMENT OF HP MODULE IN POSITION
Ensure matching of all the four palms of the module where it is resting on the
     pedestals.

Ensure matching and parallelity of front and rear key block of the HP casing.

Assemble all four jacking screw of HPC and ensure their free movement.

Clean journals and coupling of the HP rotor.

Record journal dia, coupling hole sizes and spigot dia of HP rotor.



Bharat Heavy Electricals Limited                                        T1-08-0801G
Rev 00, 7-98                                                             Page No. 36
Lift module in level condition and place it in position by keeping it 3 to 5 mm
      toward front pedestal side.

During placement of module use temporary packers similar to permanent and
      additionally support it by four jacking screws.

Ensure load on all four packers with the help of some additional shims if
     required.

Install temporary radial and axial keys of the casing.

Prepare HP rotor for alignment (Ref. section 20 before placing the IP module.

PLACEMENT OF IP MODULE IN POSITION
Ensure matching of all the four palms of the module where it is resting on the
     pedestals.

Ensure matching and parallelity of front and rear key block of IP casing.

Assemble all four jacking screws of IP casing and ensure their free
     movement. If these jacking screw holes are provided with the bolts
     from factory then same are to be removed before placement of module.

Clean IP rotor on both sides including coupling and journal.

Record spigot /recess, journal dia, and coupling hole sizes.

Lift the module in level condition and place the module in position by moving
       about 7 to 8 mm towards generator end. Use temporary packers for
       placement of module in position and additionally support the module with
       jacking screws.

Ensure load on all four packers with the help of some additional shims if
     required.

Provisionally align the casing on front and rear pedestal bore. Install temporary
      radial and axial keys of the casing with some shims.

Prepare IP rotor for alignment (Ref. section 20).
      NOTE: In case IP module is sent to site in disassembled condition, refer
              Instruction T1-08-0606G.


ASSEMBLY OF LP MODULE
      This assembly can be divided in following sub assemblies:




Bharat Heavy Electricals Limited                                      T1-08-0801G
Rev 00, 7-98                                                           Page No. 37
Assembly of girder and end walls.

Assembly of LP inner inner and LP inner outer casing lower half.

Assembly / welding of LP outer casing.

            Before starting assembly of LP casing in position, following works are
            also to be completed :

            - Positioning and welding of LP casing centering pin of front and rear
              side.

            - Positioning of key block of LP casing axial keys.

            - Positioning of all internal of condenser.


POSITIONING AND WELDING OF LP CASING CENTERING
   PIN

      Two nos. centering pins are to be located below LP front and LP rear pedestal.
      Necessary pipe along with two sq. end plates are already provided in the
      foundation to take the radial load of the LP casing:
Plumb the center line from LP front and LP rear pedestal bore on both side
     over the square plate of the foundation.

Establish accurate position of the pin and put a punch mark at a required height
      and mark a circle and a controlling circle over all the four sq. Plates.




Bharat Heavy Electricals Limited                                         T1-08-0801G
Rev 00, 7-98                                                              Page No. 38
Dia of the circle must be equal to pin dia. A template equivalent to pin dia has
      to be made for this purpose with about 20 mm thick plate and a welded
      pipe for using as an handle. The template dia must be very accurate and
      same may be made on machine.

Make precise hole with gas cutting/grinding to match template on all four
     embedded plate. Ensure that the template is fitted with minimum
     clearance and hole center are perfect as per marking.

Drill hole of about 10 mm dia on one of square plate of LP front and on one
       plate of LP rear for air venting to avoid cracks during welding.

Insert both the pins and carry out the welding as per laid down procedure.
      Before welding set correct axial position of the pins.

Insert key block on both the pins and weld their locking ring also. Ensure
      proper clearances in key block before welding of its locking ring.

Preheating of 200 degree Celsius or more to be achieved before any welding.
     Dye penetrate test on root run and after final welding is to be carried out.




Bharat Heavy Electricals Limited                                     T1-08-0801G
Rev 00, 7-98                                                          Page No. 39
ASSEMBLY OF GIRDER AND END WALL
Colour match side matching flange of girder with the surface plate.

Colour match seating flange of girder where it rests over the LP base plate.

Match and ensure parallality of axial key ways of girder.

Colour match side flanges of end wall.

Match and ensure parallality of key block of end wall.

Place left and right girder with carrier plate, spacer and lubrite packer on LP
      base plate.

Provisionally align and level the girders. Set height of the girder equivalent to
      machine center line maintaining catenary of the machine with the help of
      water level jar arrangement.

Assemble locking plate of the front and rear end wall to facilitate its assembly
     with the girders.

Assemble front and rear end wall with the girders and ensure perfect parting
     plane level during tightening.

Align, level LP outer casing and ensure contact of packers by colour
      matching/machining of spacer height.

Install LP casing radial and axial keys.

Assemble inner outer casing axial key blocks on left and right side of girder
     and dowel them.

Lock with tack welding all the vertical joint bolts.

Put a seal weld run between girder and end wall joint all around except on top
      face.

Weld girder and end wall parting plane joint with argon welding. Before
     welding make a V groove with the help of a chisel and allow the projection
     of material on surface. Do not make the groove by grinding.

Do colour matching with a surface plate on all four corner where argon welding
     have been carried out.


ASSEMBLY OF LP INNER INNER AND LP INNER OUTER
   CASING LOWER HALF
      The LP inner inner casing lower half is received from factory in assembled
      condition with LP inner outer casing lower half.




Bharat Heavy Electricals Limited                                       T1-08-0801G
Rev 00, 7-98                                                            Page No. 40
Clean the casing and check all the threaded holes.

Do colour matching on all four corners of the casing where it rest over the
     girder.

Colour match all eight carrier plates of inner casing on both side.

Assemble all carrier plates on girder and do the colour matching with
     individual carrier plate.

Prepare Gusset plate of front and rear side with temporary radial keys for fitting
      in LP inner casing.


Level and lift LP inner outer casing and assemble/weld both the gusset plates
      with the help of some temporary support.

Lower the casing in position over the carrier plates fitted with spacer and lubrite
     packer.

Provisionally align the casing radially and axially.


Support the gusset plate with the help of screw jack (about 10-15 tons) on front
     and rear side by taking support from condenser stiffeners. Screw jack is to
     be unscrewed after box-up.




Bharat Heavy Electricals Limited                                       T1-08-0801G
Rev 00, 7-98                                                            Page No. 41
Adjust the height of the LP inner outer casing as per center line of the machine
      and then level it with the help of water level jar arrangement.

Ensure that all the eight packers have good contact. Loading of each packer is
     to be ensured.

Lower the casing by about 2 mm on all the eight packers with the help of shims
     for placement of LP rotor to avoid any fauling during placement of rotor.

Fit and weld all gusset plate stiffener pipes except pipe between LP inner outer
      casing and condenser. Do not make any weld connection between
      condenser and any of these stiffeners till neck welding of the condenser
      is over.



PLACEMENT OF LP ROTOR
Measure journal dia, spigot dia and coupling hole sizes.

Ensure centering of temporary bearing support in the LP front pedestal for
     placement of LP rotor.

Place LP rear bearing in position.

Prepare shaft seal compensator along with gaskets (Gasket to be installed in
      fully ring shape only ) and position them on LP rotor with the help of
      supplied supports of compensator.

Lift LP rotor with the supplied lifting beam in perfectly level condition and place
      it in position. During lowering of rotor ensure radial clearance with the
      help of long feeler gauges in the LP casing.

WELDING OF LP OUTER CASING
     The welding of LP outer cover is to be carried out before placement of LP
     Rotor in position to avoid damage to the rotor.




Bharat Heavy Electricals Limited                                      T1-08-0801G
Rev 00, 7-98                                                           Page No. 42
Colour match and remove all high spots of the matching flange of the LP
     outer casing.

Ensure good contact between parted diffuser of LP front and LP rear cover.

Colour match and remove all the high spots of the parted diffuser/vertical face
     to ensure good contact with the compensator at a later stage.

Colour match and remove all burrs and high spots from parting plane of LP outer
     casing.

Side flange of LP front and rear cover are to be ensured in right angle to
       achieve good contact with their matching flanges.

Place LP front LP rear cover along with parted diffuser and ensure feeler tight
      joint after tightening the parting plane bolts. The joint must be feeler
      tight just after normal tightening of bolts. Do not over tighten parting
      plane bolts.

Ensure matching of parted diffuser face on both side of LP casing. If necessary
     colour matching may be carried out to achieve a feeler tight joint.

Drill/ream all the parting plane holes as per drawings and install all dowel pins.

After fixing of LP front and rear cover measure the dimension for
      positioning of both the center flanges. The dimension are to be recorded
      in such a way that there is no clearance after fitting of center flanges in
      position on both side with the LP front and rear cover. The center
      flanges are supplied in extra length on both sides from the factory and
      final length are to be maintained at site only.

Drill/ream dowel pin holes in center flanges and install all dowel pins in position.
        Ensure drilling and reaming of all dowel pin holes to equal depth.

Fit both the center pieces of the cover in position.

Achieve the fitting clearances for welding as per laid down procedure.

Weld/lock LP upper half flange with respect to lower half casing with the help
      of metal cleats to minimise the distortion during welding of LP cover.
      The cleats may be welded at an interval of about one meter distance.

Carry out the welding as per the following welding procedure.

WELDING PROCEDURE
Tack weld the crowned seam joint. permanently welding approx. 100 mm at the
      generator end of the joint.

Opposite tack welded radial joint 2, permanently weld approx. 100 mm of the
     crowned seam joint, pos. 1, staggering the two weld ends to ensure a
     perfect transition when the crowned seam joint is finish welded.



Bharat Heavy Electricals Limited                                        T1-08-0801G
Rev 00, 7-98                                                             Page No. 43
Tack weld the crowned seam joint at regular intervals with a tack of 5T and pitch
      of 25T.

When welding radial joint 2, shell plates 1 & 2, tacked together, rest on but are
    not tacked to the retaining strip in the region of joint 1, so that any
    shrinkage occurring during welding of seam 2 is not obstructed.

The tacking & welding sequence applies for all shells courses.

Weld radial seam at TE according to welding sequence plan.

Align, adjust and tack weld radial seam at GE.

Weld radial seam at GE according to welding sequence plan.

Weld crowned seam joint.

Align shell courses on joint strips and tack weld,

Weld on joint strips from center & ends of shell plate.

Insert pins in top half casing, release top half casing and lift to insert and tack
       filler piece between joint strips.

Unbolt top half casing and lift in order to weld and finish - machine filler pieces in
     the region of the joint surface.

Check welds according to specifications.


ALIGNMENT AND COUPLING OF LP-IP & HP ROTOR
     LP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to be
     centralised in such a way that enough clearances are available to LP rotor,
     during alignment. Now this alignment activity of all the three rotor can be
     divided as below :




Bharat Heavy Electricals Limited                                          T1-08-0801G
Rev 00, 7-98                                                               Page No. 44
Preparation of HP rotor for alignment.

Preparation of IP rotor for alignment.

Preparation of LP rotor for alignment.

Alignment of LP-IP & HP rotors.

Reaming, honing of the coupling holes.

Balancing of coupling bolts weight.

PREPARATION OF HP ROTOR FOR ALIGNMENT
Align HP rotor with reference to front and rear pedestal seal bore reading. If
      required move complete HP module along with the rotor.

Fix temporary radial and axial key of the casing on both front and rear side of
      the casing. Remove HP front upper half transportation device.

Lift module by 0.20 mm on front side by putting additional shims in front
      packers.

Insert HP front bearing in position.

Reduce 0.20 mm shims gradually and ensure about 0.10 mm load on the rotor. If
     required further lower the front side of the module to achieve the loading
     on bearing by about 0.10 mm.




Bharat Heavy Electricals Limited                                    T1-08-0801G
Rev 00, 7-98                                                         Page No. 45
Remove HP front lower half transport device gradually and ensure no
    movement between HP casing and rotor. If necessary adjust shims of
    HP casing front packers.

During loading of bearing always ensure that the rotor is not fouling inside the
      casing with the shaft seals. This may be ensured by checking with feeler
      gauge also.

Check axial position of HP rotor in front side on left; right and top position
     from the rotor reference point to the HPC as given in the shop protocol.

Insert and load the bearing in HP rear end in similar way as carried out in
      case of HP front end and record axial position of rotor as per shop
      protocol.

Lock axially HP rotor with some fixture along with the arrangement of
     jacking screw for movement of rotor. This fixture may be mounted on rear
     pedestal. Before locking of rotor ensure axial position of the shaft.

Center HP shaft with reference to HP casing front and rear spigot. If necessary,
      move the casing readily to achieve the centering. A fixture can be
      fabricated at site for mounting the dial gauge on both the end of the rotor
      to check the centering of the shaft.

Use thick oil during rotation of shaft on the bearing.

Protect bearing from any of the dust particles. It is recommended to place
      upper half of bearing in position to avoid dust and any other damage to
      the shaft journal.

Realign the rotor shaft with respect to pedestal seal bore and if necessary
      adjust the shims below spherical support of the bearing.

Care should be taken during alignment that radial and axial clearances
      between rotor and casings does not get bridged.

Check HP rotor radial run out on journal and coupling.

Check axial run out on thrust collar and both the coupling faces of HP rotor.

Check axial float of the rotor. Compare values with shop protocol values. (Ref. T1-
     08-0802G). Deviations to be reported to Manufacturing Unit.


PREPARATION OF IP ROTOR FOR ALIGNMENT
      The IP module is also to be prepared in line with the HP module. However
      as IP rotor is provided with one side bearing and opposite side is coupled
      with the HP rotor without a bearing, extra care is necessary during
      alignment of rotor in IP casing. The additional point which are to be taken care
      are explained below :


Bharat Heavy Electricals Limited                                        T1-08-0801G
Rev 00, 7-98                                                             Page No. 46
Place IP rotor rear end on bearing similar to the HP rotor and remove
      transportation device.

Provisionally align HP/IP rotors and couple on temporary bolts by moving both
      the modules. During coupling of the rotors, the transportation device of IP
      front end is also to be taken out.

Check axial position of rotor w.r.t. IP casing and adjust as per shop protocol.

Check centering of IP rotor front and rear end w.r.t. IP casing (similar to the HP
     rotor centering check).

Check float of the IP rotor. Compare values with the shop protocol values. (Ref.
     T1-08-0802G). During checking of float ensure HP casing is not fouling
     with HP rotor. If required HP casing may be moved axially for this purpose.

Check facial runout on IP rear coupling face and radial runout on journals and
     couplings.

PREPARATION OF LP ROTOR FOR ALIGNMENT
Provisionally align LP rotor in pedestal seal bore placing the front end of shaft
      on auxiliary bearing and rear end on bearing.

Align LP inner outer casing radially with the help of long feeler gauges and
      install temporary radial keys in the gusset plate.




Bharat Heavy Electricals Limited                                      T1-08-0801G
Rev 00, 7-98                                                           Page No. 47
Record all the radial and axial clearances of the LP casing without coupling
     the LP-IP rotor. Variation if any in radial or axial clearances are to be
     corrected/approved at this stage.

Remove shims from the front end of auxiliary bearing and keep rotor on lifting
    tackle.

Record radial run out of LP rotor coupling and journal and axial run out of the
     coupling faces of the both end.

Record float of the LP rotor by moving the LP inner outer casing lower half.

After ensuring the radial and axial run out of the LP rotor the LP inner outer
       casing can be boxed up. Parting plane bolts of LP inner-inner casing are to
       be heat tightened.

ALIGNMENT OF HP, IP AND LP ROTORS
Ensure radial and axial runout of all the three rotors are individually in order. If
     necessary individual rotor module can be taken out for correction of
     coupling face runout. Any variation on radial runout of rotor is to be
     referred to the factory.

Match coupling faces of two rotor as per the axial face reading of the rotor.
     Ensure that the higher point of the rotor coupling face and lower point of
     another rotor coupling face are matched together. This is to be compared
     with shop protocol also.

Preliminary align radially and axially all the three rotors and shift them in spigot
      along with the casing to avoid fouling of rotor inside the casing.

During alignment achieve left and right movement of the rotor with the help of
      shims in spherical / torus piece of the bearing. The up and down
      movement of the rotor is to be achieved with the help of shims in the
      cylindrical/spherical support of the bearing . The adjustment of shims in
      the bearing should be within the permissible limits only.

Ensure during alignment that the catenary of the shaft is maintained.

Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving them
     in spigot.

Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IP
       coupling. Hand tighten the coupling bolts by keeping a gap of > 1.00 mm
       in coupling faces for alignment.

Rotate the rotor system and record the coupling gap at 90 Deg. interval on
      left, right and top position. Ensure that the coupling, bolts and pins
      remain free while recording the gap of the coupling for the alignment
      purposes.




Bharat Heavy Electricals Limited                                        T1-08-0801G
Rev 00, 7-98                                                             Page No. 48
Check swing check value of the HP rotor with alternate bolts in position. The
     above value must be within the prescribed limit only otherwise a
     correction must be carried out at site in consultation with designer.

Ensure free movement of rotor on their bearing. Do not rotate the              rotor if it
     is tight during its rotation.

Ensue that the coupling holes are properly aligned to avoid unnecessary
     enlargement of holes.

Ensure HP-IP-LP rotor radial run out after tightening with alternate clearance
     bolts. Release the couplings for reaming / honing of couplings.

      In case of spring loaded TG decks, refer alignment procedure                 T1-08-
             0909G

REAMING / HONING OF COUPLING
Ensure that there is no disturbance on coupling during reaming/honing
     operation.

First ream/hone two opposite holes of the coupling and install two pins/bolts
       with sliding fit and then take up all other holes.

Enlarge coupling holes to the minimum possible diameter and try to make all the
      holes to same dia.

Ensure that the finished holes are straight and there is no banana shape. This
     can be ensured by checking hole with a straight ground finish pin having
     0.02/0.03 mm clearance.

The length of the pin should be equal to the bolt length. In case, few holes have
      gone considerably over size during reaming/honing at site/works, do not
      enlarge all the holes. As a special case in such cases these few holes
      may be left as oversize.

Ensure that the holes during reaming/honing are perfectly finished as ground
     bore and size obtained should be within 0.005 mm. Ensure all the coupling
     bolts are fitted within 0.02/0.03 mm clearance with sliding fit and bolts are
     to be ground within an accuracy of 0.005 mm.

Coupling bolts are not to be hammered in the holes and these are to be fitted with
      thumb pressure only.

Do not decouple the coupling in any case without ensuring the fitting of all the
     coupling bolts.


BALANCING OF COUPLING BOLTS
      After fitting the coupling bolts in all the holes these are to be balanced within 5
      gms accuracy and an accurate balance which can take a load of about 20 kg.


Bharat Heavy Electricals Limited                                             T1-08-0801G
Rev 00, 7-98                                                                  Page No. 49
may be used. During balancing of coupling bolts following points are to be taken
      care.
Final balancing of the coupling bolts are to be done along with the coupling
      nut of individual bolt.

If all the coupling bolt hole sizes are same before/after reaming and honing
        then all the bolts can be kept of equal weight.

If necessary adjust the weight of the bolts by machining the metal from the bolt
       head.

When the holes of the coupling are of different sizes then it must be seen that
    whether excess enlargement have been done at site or works. In such
    cases if excess cutting have been done at site in a particular hole then
    coupling bolt with excess weight are to be used. The amount of excess
    weight must be equivalent to the excess enlargement of hole at site. If a
    particular hole of excess dia. is noticed from factory then it is assured that
    the particular rotor is balanced with excess dia hole and there is no
    need of providing excess weight bolt at site.

COLOUR MATCHING OF THRUST BEARING
      After completion of reaming/honing and preliminary tightening of the coupling
      bolts, the colour matching of the thrust bearing pad have to be carried out with
      respect to the thrust collar of the HP Rotor. During colour matching a good
      contact on all the pads of front and rear side are to be ensured with respect to
      rotor collar by moving the rotor in +/- direction during its hand rotation. Following
      points are to be taken care during colour matching.




Bharat Heavy Electricals Limited                                            T1-08-0801G
Rev 00, 7-98                                                                 Page No. 50
Thrust bearing must be axially locked with the help of axial keys during the
      colour matching of the pads. Axial keys to be fitted while finalising the
      alignment of thrust bearing with rotor collar without pads.

Few drops of oil is to be put on journal portion of the thrust bearing during
     rotation of rotor to ensure that the oil is not entering in pad portion of the
     bearing.

Colour is to be applied on the thrust collar of the rotor.

If necessary move the spherical support of the bearing pedestal to ensure the
       equal thickness of the pads before fittment of axial keys of the bearing.

During moving of the spherical support in front or rear direction ensure that
      there is no left - right movement to the support otherwise that may
      cause misalignment of the bearing.

After colour matching of the thrust pad the axial zero position of the rotor is
      achieved and this can be taken for all other future reference for setting of
      axial position of HP, IP & LP casing.

HP, IP and LP lower casing are to be set axially after fixing the axial position
      of the rotor and their final axial keys can be installed at this stage.




Bharat Heavy Electricals Limited                                       T1-08-0801G
Rev 00, 7-98                                                            Page No. 51
ALIGNMENT OF HP, IP & LP CASING
      After completion of colour matching of the thrust bearing pads the casing
      alignment work can be taken up. The following points are to be taken care
      while aligning HP, IP and LP casing.
The roll check have to be carried out in HP, IP and LP casing to ensure the
     correct radial clearances of the casing.

TG deck springs are to be kept in floating condition while recording the roll
     check of LP casing. However the roll check of HP/IP casing may be carried
     out before floating of TG deck for fitting of their radial keys but up and
     down roll check of HP/IP casings are to be done with TG deck in floating
     condition as per the procedure TS/ST/ 01/0008/00/96.

Ensure that there is no obstruction in the movement of LP inner casing due to
     welding of any of extraction piping. The one of the joint of extraction
     piping may be left free till completion of roll check of the casing.

The welding of steam inlet pipes between LP inner casing and LP girders are to
     be taken up after completion of roll check of the casing.

HP, IP and LP casing are to be fitted with final packers and axial key immediately
      after the roll check. During fitting of casing axial keys and palm packers
      ensure proper contact on lubrite coating of the keys/packers to avoid any
      damage of these coating during operation of the machine,

After completion of fitting of final keys and packers only the casing are to be
      cleared for further works of welding of various pipe lines.

The gland steam, balancing leak of lines, steam inlet and exhaust pipes are to
     be welded with HP casing after fitting of final axial keys and packers of the
     casing.

Center HP rotor w.r.t. casing front and rear spigots. Compare the readings with
      shop protocol and record the readings.

Offset center line of the HP, IP & LP casing w.r.t. respective rotor center line as
      per recommended logsheet.




Bharat Heavy Electricals Limited                                         T1-08-0801G
Rev 00, 7-98                                                              Page No. 52
Check/record LP diffusers centering readings after roll check of the casing.

Before roll check of LP casing all the stiffener pipe welding work must be
      completed. Refer T1-08-0909G.


FINAL TIGHTENING OF COUPLINGS
     In case of spring loaded foundation after completing all other works the HP / IP ,
      IP/LP , LP/GEN , GEN/EXCITER couplings are to be reopened and realigned
      after completing the reaming /honing . The rotors alignment are to be checked
      with TG deck in floating condition       as per the laid down procedure. After
      checking of alignment /catenary the final couplings are to be tightened including
      their coupled run out and swing check of rotors on HP front and Exciter end of
      the shaft.

BOXING UP OF LP INNER INNER AND LP INNER OUTER
   CASING
     The boxing up of LP inner inner and LP inner outer casing can be taken up
     before starting the alignment of HP-IP & LP rotor for coupling work. The
     following points are to be taken care before/during boxing up of these two
     casings.

Ensure matching of all the parting plane holes, fitting of cap nuts and
     accessibility of spanner .

Ensure feeler tightness of the parting plane joint of both the casing.

Check/record all the radial and axial clearances of the casing.

Ensure proper cleanliness of the LP inner inner and LP inner outer casing.

Ensure adequate clearance between LP inner inner casing and LP inner outer
     casing to avoid any obstruction during expansion of the LP inner casing
     inside the LP inner outer casing during operation of machines.



BOXING UP OF LP OUTER CASING
      During the boxing up of the LP outer casing following points are to be taken care.




Bharat Heavy Electricals Limited                                          T1-08-0801G
Rev 00, 7-98                                                               Page No. 53
Roll check of LP inner casing including the fitting of key, packers etc. must be
      finished.

All the works must be finished inside the LP casing before boxing up of LP
      casing including LP extraction pipe line works.

Ensure matching of all parting plane holes and feeler tightness of the joint
     before boxing up of the casing.

Ensure feeler tightness of bursting diaphragm flange joint before boxing up of
     the casing.

Ensure proper assembly of parting plane rubber cord.

FINAL HORN DROP CHECK
            After completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaust
            and other piping of HP/IP casing the final horn drop readings are recorded
            as per the laid down procedure mentioned in the manual for horn drop
            check. However the IP casing horn drop is also to be recorded with IP
            inlet upper half pipe welded with casing alone.




Bharat Heavy Electricals Limited                                        T1-08-0801G
Rev 00, 7-98                                                             Page No. 54
Grouting of turbine base plates, bearing pedestals, foundation frame with shrink-free
grouting compound is intended to ensure uniform transmission of the force and vibration
of the TG unit to the foundation.


Caution:
Preparations for grouting, and grouting must be carried out with great care as it is no
longer possible to check and rectify the parts once they have been grouted.


CONBEXTRA GP-II or equivalent should be used as grouting compound.               Further
details on the grouting depths, mixing time, quantity of water to be mixed, should be
refereed from the manufacturers brochures.



PROCEDURE

The foundation should be thoroughly cleaned. All foundation bolt holes should be filled
with pea-gravels and covered at the top to avoid entry and sticking of grouting materials
with the bolts.



NOTE:- Remove all rust preventive paints, grease etc. from surfaces by wire brushes
to ensure proper adhesion of the grouting compound.



SETTING UP OF SHUTTERING
Set up shuttering from suitable material in box like manner around the foundation plates
and secure it firmly.



NOTE:- Shuttering must be sealed well to prevent the liquid grouting compound from
running out. This can be done by using paste of grout materials and allowing it sets.
As the grouting compound remains workable for a limited time, to prevent air bubbles, it
must be poured from one side only. For this, a large size filling heaped should be used.



 Bharat Heavy Electricals Limited                                          T1-08-0801G
 Rev 00, 7-98                                                               Page No. 55
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel
Ere ction manual bhel

More Related Content

What's hot

example hydrogen seal oil presentation
example hydrogen seal oil presentationexample hydrogen seal oil presentation
example hydrogen seal oil presentationSteve Ford
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing systemAshvani Shukla
 
Thermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on MalfunctionsThermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on MalfunctionsManohar Tatwawadi
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINESAI SHARATH GAMPA
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingTahoor Alam Khan
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineManohar Tatwawadi
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergenciesManohar Tatwawadi
 
AUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMAUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMkumarswamy927
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsVijay Raj
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing SystemSalil Vaidya
 
condensate system
condensate systemcondensate system
condensate systemvikrantdesh
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerVaibhav Paydelwar
 
Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownAshvani Shukla
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 

What's hot (20)

example hydrogen seal oil presentation
example hydrogen seal oil presentationexample hydrogen seal oil presentation
example hydrogen seal oil presentation
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Thermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on MalfunctionsThermal Power Plant Simulator Hands-on Malfunctions
Thermal Power Plant Simulator Hands-on Malfunctions
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & Working
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
AUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEMAUTOMATIC TURBINE RUNUP SYSTEM
AUTOMATIC TURBINE RUNUP SYSTEM
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
Erection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressurepartsErection guidelinesfor500mw boilerpressureparts
Erection guidelinesfor500mw boilerpressureparts
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
condensate system
condensate systemcondensate system
condensate system
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
Cmc philosophy
Cmc philosophyCmc philosophy
Cmc philosophy
 
Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdown
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 

Similar to Ere ction manual bhel

Erectn n commisioning
Erectn n commisioningErectn n commisioning
Erectn n commisioningnileshgiri
 
IRJET- Solar Powered Water Pumping System
IRJET- Solar Powered Water Pumping SystemIRJET- Solar Powered Water Pumping System
IRJET- Solar Powered Water Pumping SystemIRJET Journal
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler okBunk Bonk
 
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptxCASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptxanand735393
 
Memoria técnica del proyecto de instalación Calidad de Energía eléctrica
Memoria técnica del proyecto de instalación Calidad de Energía eléctrica  Memoria técnica del proyecto de instalación Calidad de Energía eléctrica
Memoria técnica del proyecto de instalación Calidad de Energía eléctrica JOe Torres Palomino
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction reportSumit Singh
 
BHEL-Generator BHEL-Generator BHEL-Generator.ppt
BHEL-Generator BHEL-Generator BHEL-Generator.pptBHEL-Generator BHEL-Generator BHEL-Generator.ppt
BHEL-Generator BHEL-Generator BHEL-Generator.pptBhaiyaKamalendu1
 
A seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaA seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaASHOK KHOJA
 
Fabrication of Advanced Hybrid Savonius Wind Turbine
Fabrication of Advanced Hybrid Savonius Wind TurbineFabrication of Advanced Hybrid Savonius Wind Turbine
Fabrication of Advanced Hybrid Savonius Wind TurbineDigvijay Gabhane
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main pageRanjan kumar
 
Kota tharmal plant new.pdf
Kota tharmal plant new.pdfKota tharmal plant new.pdf
Kota tharmal plant new.pdfRahulLodha11
 
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...IRJET Journal
 
Ntpc(btps) report
Ntpc(btps) reportNtpc(btps) report
Ntpc(btps) reportAlok Tiwari
 
Nitrogen plant Genset Report
Nitrogen plant Genset ReportNitrogen plant Genset Report
Nitrogen plant Genset ReportOsvaldo Zumba
 
toaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdf
toaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdftoaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdf
toaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdfJayshreeDutta4
 

Similar to Ere ction manual bhel (20)

Ere
EreEre
Ere
 
Erectn n commisioning
Erectn n commisioningErectn n commisioning
Erectn n commisioning
 
IRJET- Solar Powered Water Pumping System
IRJET- Solar Powered Water Pumping SystemIRJET- Solar Powered Water Pumping System
IRJET- Solar Powered Water Pumping System
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
 
Bhel report block 4
Bhel report block 4Bhel report block 4
Bhel report block 4
 
MAPS TG
MAPS TGMAPS TG
MAPS TG
 
Company profile MAPS TG
Company profile MAPS TGCompany profile MAPS TG
Company profile MAPS TG
 
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptxCASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
CASE STUDY ON GENERATOR SUSTAINABLE OPERATION.pptx
 
Memoria técnica del proyecto de instalación Calidad de Energía eléctrica
Memoria técnica del proyecto de instalación Calidad de Energía eléctrica  Memoria técnica del proyecto de instalación Calidad de Energía eléctrica
Memoria técnica del proyecto de instalación Calidad de Energía eléctrica
 
500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
 
BHEL-Generator BHEL-Generator BHEL-Generator.ppt
BHEL-Generator BHEL-Generator BHEL-Generator.pptBHEL-Generator BHEL-Generator BHEL-Generator.ppt
BHEL-Generator BHEL-Generator BHEL-Generator.ppt
 
LAWSON RESUME
LAWSON RESUMELAWSON RESUME
LAWSON RESUME
 
A seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaA seminar report on stps by ashok khoja
A seminar report on stps by ashok khoja
 
Fabrication of Advanced Hybrid Savonius Wind Turbine
Fabrication of Advanced Hybrid Savonius Wind TurbineFabrication of Advanced Hybrid Savonius Wind Turbine
Fabrication of Advanced Hybrid Savonius Wind Turbine
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main page
 
Kota tharmal plant new.pdf
Kota tharmal plant new.pdfKota tharmal plant new.pdf
Kota tharmal plant new.pdf
 
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
Retro-fitting of Pre-Stressed Concrete Poles Using Carbon Fibre Reinforced Po...
 
Ntpc(btps) report
Ntpc(btps) reportNtpc(btps) report
Ntpc(btps) report
 
Nitrogen plant Genset Report
Nitrogen plant Genset ReportNitrogen plant Genset Report
Nitrogen plant Genset Report
 
toaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdf
toaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdftoaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdf
toaz.info-pwd-electrical-csr18-19pdf-pr_0b568bd5a34db1e29ae436dce34430a6.pdf
 

Ere ction manual bhel

  • 1. ERECTION MANUAL STEAM TURBINE 500 MW (KWU DESIGN) DOCUMENT NO. TS-T1-08 Bharat Heavy Electricals Limited POWER SECTOR TECHNICAL SERVICES (HQ) NOIDA Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 1
  • 2. FOREWORD I am glad that Power Sector - Technical Services ( Head Quarters), Noida has brought out this erection manual of 500 MW steam turbine (KWU design) being produced by BHEL. This manual lays emphasis on site optimisation techniques which aims at uniform erection practices, improvement in quality, reduction in time cycle and saving in cost. I am sure, this manual will form the basis for site erection activities so that the organisation can derive full benefit out of this. It is needless to emphasize that upgrading of technology is a continuous process and we have to review our methods of working and make suitable changes, wherever required. (K P Mathur) New Delhi Executive Director (PEM & TS) Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 2
  • 3. PREFACE The Erection Manual for 500 MW Steam Turbine (KWU design) manufactured by BHEL for Thermal Power Stations has been prepared by a team of BHEL engineers having long experience in Erection & Commissioning, Design, Quality control of steam turbines. This dedicated team has been drawn from regional erection group, designed department of manufacturing units, PS-Q & TS-HQ, Noida. The manual carries general description of steam turbine, erection procedure, special instruction, general instructions, and various other technical instructions with an intention to establish an uniform approach for erection of steam turbine. The Erection Manual provides broad based guide line for erection of steam turbine. Product standard, technical circulars & BHEL drawings for the specific project will precede the instructions and guidelines furnished in this manual. Project specific document will be generated by region concerned. This document is generated as a standard Erection Manual for 500 MW fixed pedestal type steam turbine with spring loaded foundation. The work done by TASK FORCE is commendable. Feed-back and suggestions are welcome for the improvement of this Erection Manual to bringing down the cycle time with quality. BHEL reserves the right to suggest alternative procedure if necessity arises at site due to local site conditions . (BABOO RAM) NOIDA GENERAL MANAGER(TS&Q) SNO DESCRIPTION INSTRUCTION NO Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 3
  • 4. 1 TECHNICAL DATA T 1- 08-0101G 2 INSTRUCTION FOR HANDLING AND T 1-08-0202G STORAGE OF TURBINE 3 ERECTION SEQUENCE T 1-08-0303G 4 ERECTION PROCEDURE T 1-08-0404G 5 GROUTING PROCEDURE T 1- 08-0505G 6 ASSEMBLY OF IP MODULE AT SITE T 1-08-0606G 7 SEALING AND ANTISEIZING COMPOUNDS T 1-08-0707G 8 CRITICAL ACTIVITIES T 1-08-0808G 9 SPRING LOADED FOUNDATION T 1- 08-0909G 10 ERECTION OF PIPING T 1-08-1010G 11 SPECIFICATION FOR GAS HEATING DEVICE T 1-08-1111G 12 SPECIFICATION FOR BREECH NUT HEATING T 1-08-1212G DEVICE 13 SPECIFICATION FOR THERMAL INSULATION T1-08-1313 G Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 4
  • 5. The following codification system is used for numbering of instructions and the codification of Log Sheets is as per FQA document. XX X - XX XX XX X Alpha Numeric Numeric Numeric Numeric Alpha Type of Instruction System Instruction No System Designation Rating of Main Equipment Type of Manual Product Code 1.1 PRODUCT CODE B Boiler BA Boiler Aux. T Turbine TA Turbine Aux. G Generator GA Generator Aux P Power Plant Piping CI C&I 1.2 TYPE OF MANUAL 1 Erection 2 Commissioning 3 Service Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 5
  • 6. 1.3 RATING OF MAIN EQUIPMENT 01 200/210 MW 02 120 MW 03 110 MW 04 60 MW 05 30 MW 06 100 MW 07 235 MW 08 500 MW KWU Design 09 210 MW KWU Design 10 120 MW KWU Design 11 60 MW KWU Design 12 70 MW KWU Design 13 Industrial Units 14 210 MW Tower Type Concrete Pylem 15 210 MW Tower Type Steel Structure 16 500 MW Tower Type Once through 17 250 MW 18 CCP Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 6
  • 7. 1.4 SYSTEM DESIGNATION SNO DESCRIPTION 1. TECHNICAL DATA 2. INSTRUCTION FOR HANDLING AND STORAGE OF TURBINE 3. ERECTION SEQUENCE 4. ERECTION PROCEDURE 5. GROUTING PROCEDURE 6. ASSEMBLY OF IP MODULE AT SITE 7. SEALING AND ANTISEIZING COMPOUNDS 8. CRITICAL ACTIVITIES 9. SPRING LOADED FOUNDATION 10. ERECTION OF PIPING 11. SPECIFICATION FOR GAS HEATING DEVICE 12. SPECIFICATION FOR BREECH NUT HEATING DEVICE 13. SPECIFICATION FOR THERMAL INSULATION 1.5 TYPE OF INSTRUCTION G General T Technical L Log Sheet C Check List Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 7
  • 8. LOAD RATED 500 MW MAX. UNDER VALVE WIDE OPEN (VWO) CONDITION 524.2 CONSTRUCTION THREE CYLINDER REHEAT CONDENSING TURBINE 500 MW SINGLE FLOW HP TURBINE WITH 17 REACTION STAGES TYPE H30-100-2 DOUBLE FLOW IP TURBINE WITH 12 REACTION STAGES PER TYPE M30-63 FLOW DOUBLE FLOW LP TURBINE WITH 6 REACTION STAGES PER TYPE N30-2X10 FLOW 2 MAIN STOP AND CONTROL VALVES TYPE EV320-1 2 REHEAT STOP AND CONTROL VALVES TYPE IV560 1 SWING CHECK VALVE IN COLD REHEAT LINE DN-800 MAKE BHEL,TIRUCHY 2 BYPASS STOP AND CONTROL VALVES DN-320 EXTRACTION SWING CHECK VALVES : EXTRACTION-1 : NO VALVE - EXTRACTION-2 : 1 SWING CHECK VALVE WITH ACTUATOR DN-800 MAKE BHEL,TIRUCHY EXTRACTION-3 : 1 SWING CHECK VALVE WITH ACTUATOR DN-500 & MAKE BHEL,TIRUCHY 1 SWING CHECK VALVE WITHOUT ACTUATOR EXTRACTION-4.1 : 2 SWING CHECK VALVE WITH ACTUATOR DN-500 MAKE BHEL,TIRUCHY EXTRACTION-4.2 : 2 SWING CHECK VALVE WITH ACTUATOR DN-500 MAKE BHEL,TIRUCHY EXTRACTION-5 : 1 SWING CHECK VALVE WITH ACTUATOR DN-400 & MAKE BHEL,TIRUCHY 1 SWING CHECK VALVE WITHOUT ACTUATOR EXTRACTION-6 : NO VALVE SPEED RATED SPEED 50.0 /S Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 8
  • 9. SPEED LIMITATION IN LOAD & STATION AUX. LOAD 524.2 OPERATION : 51.5 /S MAX. SPEED, NO TIME LIMITATION : 47.5 /S MIN. SPEED, NO TIME LIMITATION PERMISSIBLE FOR A MAXIMUM OF 2 HRS. DURING THE LIFE OF : 47.5 /S LP BLADING SPEED : 51.5 TO 60 /S BELOW SPEED ABOVE SPEED EXECUTION RANGE AT OPERATION WITHOUT LOAD* : 6.7 TO 47.5 /S STANDARD OVER SPEED TRIP SETTING : MAX. 55.5 /s * THIS SPEED RANGE SHOULD BE PASSED THROUGH IN ONE SMOOTH OPERATION TO AVOID ENDANGERING THE BLADES DUE TO RESONANCE STEAM PRESSURES RATED* LONG TIME SHORT TIME OPERATION OPERATION INITIAL STEAM 166.7 166.7 20.7 BAR BEFORE 1st HP DRUM STAGE 154.4 163.4 169.9 BAR HP CYLINDER EXHAUST 44.9 52.0 57.4** BAR IP CYLINDER STOP VALVE INLET 40.3 46.7 55.2** BAR EXTRACTION 6 44.9 52.0 57.4 BAR EXTRACTION 5 17.5 22.2 22.2 BAR EXTRACTION 4 7.2 8.7 8.7 BAR EXTRACTION 3 2.58 3.2 3.2 BAR EXTRACTION 2 1.329 1.66 1.66 BAR EXTRACTION 1 0.257 0.41 0.41 BAR LP CYLINDER EXHAUST 0.1013 0.3 0.3 BAR * THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACK PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS. ** THE SAFETY VALVES MUST BE SET SO THAT THESE SHORT TIME VALUES ARE NOT EXCEEDED. LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT. SHORT TIME OPERATION : PERMISSIBLE MOMENTARY VALUE. THE AGGREGATE DURATION OF SUCH SWINGS MUST NOT EXCEED 12 HOURS IN ANY ONE YEAR. ALL PRESSURES ARE ABSOLUTE PRESSURES Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 9
  • 10. LOW VACUUM TRIP, STANDARD SETTING HYDRAULIC LOW VACUUM TRIP : 0.3 BAR ELECTRICAL LOW VACUUM TRIP : 0.3 BAR HYDRAULIC LOW VACUUM TRIP BYPASS OPERATION : 0.6 BAR SEAL STEAM SUPPLY SYSTEM PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC) : 35 MBAR AXIAL SHIFT ALARM TRIP * 0.5 mm * 1 mm * DIRECTION OF ROTATION ANTI CLOCK WISE WHEN VIEWED FROM FRONT PEDESTAL TOWARDS THE GENERATOR Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 10
  • 11. STEAM TEMPERATURES RATED LONG TIME 400 h 80 h PER VAL. VALUE PER ANNUM ANNUAL (WITHIN ANNUM MAX. 15 MEAN ANNUAL MIN IN VALUE MEAN INDIVIDUA VAL.) L CASE O INITIAL STEAM 536.0 546.O 552.O 566.0 C O IP CYLINDER STOP VALVE INLET 536.0 546.3 552.0 566.0 C RATED LONG 80 h PER IN VALVE * TIME ANNUM SPECIAL OPERATI MAX. 15 CASES ON MIN IN AT NO INDIVIDU LOAD AL CASE O HP CYLINDER EXHAUST 340.0 360.0 440.0 500.0** C O EXTRACTION 6 340.0 360.0 440.0 500.0** C O EXTRACTION 5 413.9 421.9 459.9 C O EXTRACTION 4 292.1 304.1 346.4 C O EXTRACTION 3 187.3 195.3 242.3 C O EXTRACTION 2 128.3 139.3 184.3 C O EXTRACTION 1 66.5 86.5 136.5 C O LP CYLINDER EXHAUST 46.1 70.0 70.0 C LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT. * THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACK PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS. ** ONLY VALID FOR THE NO LOAD PERIOD WITH HIGH REHEAT PRESSURE AFTER TRIP-OUT FROM FULL LOAD OPERATION. FOR INDIVIDUAL CASE APPROX. 15 MINUTES THE TURBINE IS IMMEDIATELY RE-LOADED OR THE BOILER IMMEDIATELY REDUCED TO MINIMUM LOAD IF NO LOAD OPERATION IS MAINTAINED. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 11
  • 12. CASING TEMPERATURES WALL TEMPERATURES ALARM MACHINE MUST BE AT SHUT DOWN AT O HP TURBINE CASING EXHAUST 480 500 C O OUTER CASING OF LP CYLINDER 90 110 C PERMISSIBLE DIFFERENTIAL TEMP. BETWEEN PARALLEL STEAM SUPPLY LINES : O • NO TIME LIMITATION : 17 C O • SHORT TIME PERIOD (15 MIN.) : 28 C IN THE HOTTEST LINE THE LIMITATIONS INDICATED FOR INITIAL STEAM & REHEAT TEMP. MUST NOT BE EXCEEDED. O SPRAY WATER TO LP TURBINE MUST BE SWITCHED ON AT 90 C. TEMPERATURES DIFFERENCE ALARM MACHINE MUST BE AT SHUT DOWN AT O DIFFERENCE BETWEEN UPPER & LOWER * 90 * 100 C CASING HALVES HP TURBINE. MIDDLE O LP TURBINE. FRONT * 30 * 45 C O LP TURBINE. REAR * 30 * 45 C FEEDWATER HEATER OUT OF SERVICE OPERATION WITH FEEDWATER HEATER OUT OF SERVICE MAIN STEAM LOAD FLOW Kg/s MW EXTRACTION A6 = 0 395 500 EXTRACTION A5 = 0 421 500 EXTRACTION A3 = 0 423 500 EXTRACTION A2 = 0 425 500 EXTRACTION A1 = 0 423 500 EXTRACTION A6, A5 = 0 400 525 OUTPUT LIMIT DURING TESTING WITH AUTOMATIC TURBINE TESTER TESTING OF MAIN STEAM STOP & CONTROL VALVE 400 MW TESTING OF HRH STEAM STOP & CONTROL VALVE 200 - 500 MW MOTORING : MOTORING IS THE CONDITION IN WHICH THE TURBINE IS DRIVEN BY THE GENERATOR AT RATED SPEED WITH THE STOP & CONTROL VALVES CLOSED. IN THIS OPERATING MODE, CERTAIN TURBINE COMPONENTS ARE HEATED UP BY WINDAGE POWER IN THE BLADING. TO PREVENT HEAT-UP BEYOND PERMISSIBLE TEMPERATURES, MOTORING MUST NOT BE ALLOWED TO CONTINUE FOR LONGER THAN ONE MINUTE. IF THE CONDENSER LOW VACUUM LIMIT OF 0.3 BAR IS EXCEEDED, MOTORING MUST NOT BE ALLOWED TO CONTINUE FOR MORE THAN 4 SECONDS. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 12
  • 13. BEARING TEMPERATURES ALARM MACHINE MUST BE AT SHUT DOWN AT O OPERATION TEMPERATURE BELOW 75 OC 90 120 C O OPERATION TEMPERATURE 75 TO 85 OC 100 120 C O OPERATION TEMPERATURE 85 TO 90OC 110 120 C O OPERATION TEMPERATURE ABOVE 90OC 115 120 C VIBRATION ABSOLUTE BEARING ABSOLUTE SHAFT HOUSING VIBRATION VIBRATION STANDARD ALARM SETTING 30 µ m ABOVE µm NORMAL LEVEL* MAXIMUM ALARM SETTING 35 120 µm LIMIT VALUE FOR TRIPPING 45 200 µm * THE NORMAL LEVEL IS REPRODUCIBLE VIBRATIONAL BEHAVIOUR TYPICAL FOR THE MACHINE AND DEPENDENT ON THE OPERATING CONDITIONS, VIBRATION READINGS INDICATED IN CONTROL ROOM ARE HALF PEAK. THE ABOVE VALUES ARE ALSO GIVEN IN HALF PEAK. WEIGHTS HP TURBINE, COMPLETELY ASSEMBLED : 94.6 T IP TURBINE. TOP HALF OUTER CASING : 25.7 T IP TURBINE, TOP HALF INNER CASING, COMPLETE WITH BLADING : 15.5 T LP TURBINE. TOP HALF OUTER CASING COMPLETE : 42.6 T LP CYLINDER, TOP HALF OUTER SHELL OF INNER CASING, COMPLETE : 38.5 T WITH BLADING, STATIONARY BLADE CARRIERS & DIFFUSER HP TURBINE ROTOR, COMPLETE WITH BLADING : 16.3 T IP TURBINE ROTOR, COMPLETE WITH BLADING : 23.1 T LP TURBINE ROTOR, COMPLETE WITH BLADING : 85.8 T MAIN STOP & CONTROL VALVE, COMPLETE WITH SERVO MOTORS, : 20.9 T WITHOUT BEND & PIPE SECTION REHEAT STOP & CONTROL VALVE, COMPLETE WITH SERVO : 32.2 T MOTORS, WITHOUT BEND & PIPE SECTION ALL WEIGHTS HAVE BEEN CALCULATED WITH SAFETY ALLOWANCES. SLINGS CHOSEN MUST PROVIDE SUFFICIENT SECURITY. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 13
  • 14. OIL SUPPLY MAIN OIL TANK, RATED CAPACITY : 25/40 Cu . M Ist OIL FILLING (ESTIMATED) : 47.5 Cu . M FLUSHING OIL QUANTITY (ESTIMATED) : 28.5 Cu . M OIL COOLER FOR OPERATION, NUMBER : 1 NO. OIL COOLER FOR RESERVE, NUMBER : I NO. OIL TEMP. AT COOLER OUTLET, UNIT IN OPERATION MIN. : 38 O NORMAL : 45 C MAX. : 47 OIL TEMP. AT COOLER OUTLET, UNIT SHUT DOWN O MAX. : 75 C TEMP. RISE OF OIL IN BEARINGS O NORMAL : 20 C MAX. : 25 ESTIMATED OIL REQUIREMENTS OF BEARINGS : BEARING 1(HP TURBINE, FRONT PEDESTAL) : 0.8 dm3/S BEARING 2 : 15.4 dm3/S BEARING 3 : 4.1 dm3/S BEARING 4 : 8.6 dm3/S GENERATOR FRONT BEARING : 7.92 dm3/S GENERATOR REAR BEARING : 7.92 dm3/S EXCITER BEARING : 0.70 dm3/S 1 DUPLEX OIL FILTER FOR BEARING OIL (FULL FLOW) : 200 mm DUPLEX OIL FILTER . TYPE - 2.62.9. SIZE 355/750. MAKE : BOLL & KIRCH FILTRATION PARTICLE SIZE OF DUPLEX FILTER ELEMENT : 37 µm FILTRATION PARTICLE SIZE OF MAIN OIL TANK FILTER : 250 µm ELEMENT SAFETY VALVE IN JACKING OIL SYSTEM, SETTING : 200 BAR MAX. PRESSURE LIMITING VALVE IN JACKING OIL SYSTEM, : 100 BAR SETTING 1 DUPLEX OIL FILTER FOR JACKING OIL : 25 mm FILTRATION PARTICLE SIZE OF JACKING OIL FILTER : 37 µm Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 14
  • 15. OIL PUMPS MAIN OIL AUXILIARY DC JACKING PUMP OIL PUMP EMERGENCY OIL PUMP OIL PUMP QUANTITY 1 2 1 AC : 2 DC : 1 MAKER BHEL KSB KSB TUSHAKO TYPE 97.22 dm3/S ETA-150- ETA-100- SDF80 50VVL 33VVL CAPACITY 75 89.25 30 1.53 dm3/s (RATED) DISCHARGE 8.6 6.2 2.3 178 BAR PRESSURE (GAUGE) SPEED 50 24.75 24.3 49.42 /s DRIVE TURBINE AC MOTOR DC MOTOR AC DC MOTOR MOTOR Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 15
  • 16. CONTROL FLUID SUPPLY CONTROL FLUID TANK, RATED CAPACITY : 10/16 Cu . M Ist FLUID FILLING (ESTIMATED) : 15 Cu . M FLUSHING FLUID QUANTITY (ESTIMATED) : 10 Cu . M CONTROL FLUID COOLER FOR OPERATION, NUMBER : 1 NO. CONTROL FLUID COOLER FOR RESERVE, NUMBER : I NO. CONTROL FLUID MAINTENANCE EQUIPMENT : GEAR PUMP MANUFACTURER : STEIMEL TYPE : BGK 2-24R FLUID FLOW : 0.28 dm3/S GAUGE PRESSURE : 3.06 at SPEED : 25 S-1 MOTOR POWER : 0.75 KW 2 EARTH FILTERS MANUFACTURER : ROTRING TYPE : PYG5-350 EARTH FILLING MESH : 140 Kg 1 FINE MESH FILTER MANUFACTURER : ROTRING TYPE : S-1800-14-TUY FILTRATION PARTICLE SIZE : 3-5 µm FILTER MATERIAL : COTTON CONTROL FLUID SUPPLY SYSTEM A FIRE RESISTANT FLUID IS USED FOR THE CONTROL SYSTEM SCOPE The document covers all steam turbine components and provides the handling, inspection and storage instructions for large steam turbine components at site. A strict adherence to these instructions is necessary to avoid damages during handling and storage at site. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 16
  • 17. HANDLING OF EQUIPMENT : In any kind of rigging work it is necessary to strictly observe the safety precautions, since even the slightest negligence and non observance of the rules may result in accidents, which may cause damage to equipment or injury to men. The site for the rigging work involving lifting and conveying of loads should be well lighted. The loads must not be lifted unless the crane operator can see clearly the signals given by the rigger. The positions where the slings are to be put, are marked on the packages and on the drawings. While lifting/handling these packages/equipment, the slings should only be put at the proper places. The slings of the proper sizes and lengths should only be used for handling the equipment/packages. The angle between the two arms of the sling at the crane hook should be small (depending upon the dia of the sling) so as to have proper loading of the sling. The turbine rotors and cylinder covers (in assembled condition are lifted by the use of special lifting devices supplied by BHEL. The use of these lifting devices facilitates correct slinging and maintain horizontal position of the components. These devices, after use, should be properly stored and conserved so as to ensure that they do not get damaged during storage. Before using them, they should be thoroughly inspected. The work related to handling of the loads (packages or equipment) by crane or by other hoisting mechanism should be entrusted to trained riggers only. If the rigger/operator is not sure of the weight of the item/package (load) to be handled, he must ask for the required information before handling the equipment. The rigger and the crane operator should see that the hook and the ropes of the crane occupy vertical position, before hoisting the load. Dragging of the load by slanting ropes is not allowed. The center of gravity of the load should be aligned with the vertical axis of the crane hook. The eye bolts, 'D' shackles, turn buckles, and wire ropes of suitable sizes should only be used for handling of the equipment. Before using, they should be thoroughly inspected to their full threads, so as to avoid any chance of slipping then the load comes on them. Before giving a signal to lift the load, the rigger must check and ensure that there are no loose parts or tools on the load, which might fall during lifting. Then the load must be lifted 100 or 200 mm high for checking the uniformity of sling tensioning and reliability of lashing. If it is necessary to rearrange the sling lengths, the load must be lowered and then the slings rearranged. Before horizontal conveyance of the load the rigger must see that the load has been lifted to a height at least 0.5 M above the tallest object, on the path of the load. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 17
  • 18. While the load is being conveyed, the rigger must accompany it and see that it is not moved above any person. Prior to lowering the load the rigger should examine the ground on which the load will be, lowered and make sure that these is no risk of falling or slipping of the load. If any one of the personnel present during lifting or lowering of the load detects some defect of the crane or sling of notices some conditions jeopardizing the lifting or lowering operation, he must give a signal for emergency grounding of the package or components. Smooth lifting and transportation of equipment must be ensured. Shocks and jerks should be avoided. All lifting devices, slings must be properly conserved after use and periodically inspected and tested. In the turbines having diaphragms, it is prohibited to handle diaphragms by putting slings in between the blades. For handling the welded diaphragms, special lifting devices is supplied by BHEL and the cast diaphragms are handled by putting the eye bolts, for which the provision of threads holes have been made in the diaphragms. While handling the bearings, it is prohibited to put the sling across the rabbit surface of the bearings. Threaded holes have been provided; in which the eye bolts have to be put for handling of the bearings. While handling the cylinders, it must be ensured that the slings or any other material does not get rubbed at their horizontal and vertical parting planes or at any other machined surface. The handling of the long components such as longitudinal girder, endwall etc. should be done with extra care. When they are placed on the floor, in addition to the end supports, few extra supports at the intermediate positions must be provided. While handling LP rotor with free standing blades, care must be taken to ensure that no force is exerted on the free standing blades to avoid collapsing of clamping pieces under blade root. MARKINGS ON PACKING CASES Various symbols are marked on the packing cases as per 0456.001 to facilitate storage and handling of the crates and protection of equipment inside. INSPECTION Before storing the equipment it should be opened for visual examination or the internal packing, protective coating and condition of the equipment. Any damage to packing and conservation should be immediately rectified. It is necessary to carryout first inspection within three weeks of arrival of the consignment. Thereafter, all the equipment should be inspected once in every three months to insure that the conservation is intact. During rainy season, the inspection should be done once in a month. At any time, if any original Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 18
  • 19. conservation is found damaged, it should be reconserved as per relevant conservation instructions No. ST 33004. While inspecting the packages containing rotors, special care should be taken to check the journals. In case of slightest sign of pitting on the journals and thrust collar, immediate steps for rectification should be taken and equipment reconserved as per relevant conservation instructions. STORAGE All steam turbine equipment should be accommodated in the designated place of storage immediately after arrival at destination. This is very essential particularly during the rainy season. Store houses fall into the following categories TYPE OF CONDITIONS STORE TEMP. RELATIVE ARRANGEMENT HOUSE HUMIDITY 'P' +50 C < 70 % Totally enclosed, rain proof, ventilated to and dry with cemented floor. 500 C 'Q' upto - Roofed area with walls (of brick / 500 C asbestos/ GI sheet ) around and cemented / pucca hard floor. 'R' - - Raised platform with shed of asbestos / GI sheet / water proof tarapaulin. 'S' - - Raised Platform. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 19
  • 20. The platforms and store-houses should be built up in conformity with the fire prevention rules and standards. Complete storage area especially the ‘R’ & ‘S’ catagory must be adequately fenced & protected against theft & pilferage. These store houses and areas around them should have proper drainage facility for the sub-soil, surface and rain water. The water should not be allowed to stand or get accumulated in these areas, especially where the material has been stored. Store house should be provided with proper ventilation facilities. Level should be maintained for all the packages and equipment and should be uniformly supported to avoid distortion. The long packages should be supported at intermediate places also, so as to avoid sagging during storage. Store houses should preferably be equipped with proper lifting devices to ensure normal handling of equipment. Small and medium size parts can be kept on shelves with proper identification tags. Packages upto 5 tones can be placed on upon the other upto 2.5m in height using required number of wooden spacers 50 mm thick. In doing so, lighter packages would be laid upon heavier once to avoid any damage to lower packages. Articles weighing more than 5 tones should be laid in a single tier. For heavier components under ‘Q’, the roof/walls may be constructed/fabricated after placement of the component on cemented/pucca hard floor. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 20
  • 21. STORAGE OF STEAM TURBINE COMPONENTS SNO. DESCRIPTION OF THE COMPONENT TYPE OF STORAGE 1. FOUNDATION BOLT Q 2. EMBEDDED PARTS (ADDITIONAL) R 3. COMPONENTS OF BASE PLATE ASSLY. Q 4. BASE PLATE LP CASING R 5. LP OUTER CASIONG R 6. LONGITUDINAL GIRDER (LEFT & RIGHT) R 7. LP FRONT WALL (TS&GS) R 8. LP SHAFT SEALING (FRONT & REAR) Q 9. AUXILIARIES OF TURBINE Q 10. HP/IP BEARING PEDESTAL Q 11. HP/IP BEARING PEDESTAL ASSEMBLY PARTS Q 12. IP/LP PEDESTAL ASSEMBLY Q 13. LP/GEN. PEDESTAL Q 14. BEARING PEDESTAL PARTS Q 15. FRONT BEARING PEDESTAL Q 16. LIFTING BEAM R 17. LP CASING EXTRACTION A1 R 18. LP EXTRACTION A2 R 19. LP EXTRACTION A3 R 20. LP EXTRACTION PIPE SHEATHING R 21. INNER GUIDE PLATE DIFFUSER R 22. DIFFUSER (UPPER & LOWER HALVES) R 23. LP INNER-OUTER CASING (VH) Q 24. LP INNER CASING ASSEMBLY (LH & VH) Q 25. HEATING DEVICE Q 26. LP CASING ASSEMBLY Q 27. LP INNER CASING ASSEMBLY (FASTENER) Q 28. INNER GUIDE PLATE DIFFUSER (GS) R 29. LP ROTOR Q 30. IP TURBINE Q Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 21
  • 22. 31. IP TURBINE PARTS Q 32. IP INLET PIPES Q 33. HP TURBINE Q 34. HP INLET ASSEMBLY Q 35. HP EXHAUST ELBOW Q 36. HPT RELATED PARTS Q 37. FRAME FOR SUSPENSION (ESV) R 38. SUSPENSION OF VALVE (ESV) Q 39. ESV & CV CASING WITH VALVE Q 40. ESV SERVOMOTORS WITH LIMIT SWITCH Q 41. HP CONTROL VALVE SERVOMOTORS Q 42. SUSPENSION OF VALVE (IV) Q 43. IV & CV CASING WITH VALVE Q 44. IV SERVOMOTORS WITH LIMIT SWITCH Q 45. IP CONTROL VALVE SERVOMOTORS Q 46. FRAME FOR SUSPENSION (IV) R 47. IV SERVOMOTORS WITH LIMIT SWITCH Q 48. STEAM BLOWING & HYD. TEST DEVICE Q 49. TOOLS FOR GOVERNING SYSTEM Q 50. SUSPENSION OF LPB VALVE Q 51. WATER INJECTION VALVES Q 52. CHEST LPB WITH STOP & CONTROL VALVE q 53. LPB STOP VALVE SERVOMOTOR Q 54. LPB CONTROL VALVES SERVOMOTORS Q 55. INJR. FOR SUCTION PIPE NB 350 R 56. INJR. FOR SUCTION PIPE NB 300 R 57. MAIN OIL TANK R 58. MAIN OIL TANK & NOZZLE ASSEMBLY R 59. OIL STRAINER Q 60. LEVEL MONITOR INSTALLATION Q 61. INSTRUMENTS Q 62. LEAKAGE / DIRTY FLUID TANK R 63. VARIABLE ORIFICES & THROTTLE Q Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 22
  • 23. 64. CONTROL FLUID TANK R 65. CONTROL FLUID TANK NOZZLE ARRANGEMENT R 66. EXPANSION TANK R 67. FILTER & PR. DAMPING DEVICES Q 68. CROSS AROUND PIPE R 69. SUPPORT FOR CAP R 70. CHANGE OVER VALVE R 71. RATING & MONOGRAM PLATES Q 72. OIL STRIPER R 73. HOUSING FOR HRH STEAM STRAINER R 74. HOUSING FOR MAIN STEAM STRAINER R 75. MS & HRH STR.HSG GASKET Q 76. STEAM STRAINER MS Q 77. STEAM STRAINER HRH Q 78. COMPENSATOR Q 79. TURBINE CONTROL LPB / SUPPLY RACK Q 80. TEMPERATURE & PRESSURE CONNECTIONS Q 81. PR. TRANSMITTERS BAR. PROBES THERMOCOUPLES Q 82. TRANSMITTERS & JUNCTION BOXES Q Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 23
  • 24. STORAGE & PRESERVATION OF COMPONENTS OF TURBOGENERATOR, EXCITER AND SYSTEMS SNO. DESCRIPTION OF THE COMPONENT TYPE OF STORAGE 1. EMBEDDED PARTS R 2. FOUNDATION PARTS R 3. WOUND STATOR WITH GAS COOLERS Q 4. TURNION FOOT PLATES Q 5. ROTOR Q 6. ASSEMBLY OF PIPE CONTROL FOR GAS COOLERS R 7. END SHIELDS Q 8. FAN SHIELD, GEN VVIEW HEADER ASSEMBLY R 9. TERMINAL BUSHING AND HEADER ASSEMBLY Q 10. BEARING WITH BRUSH GEAR Q 11. SEAL BODY Q 12. TEMP. CONNECTION Q 13. CASING FOR TURNIONS R 14. ERECTION MATERIALS Q 15. ERECTION DEVICES R 16. SHAFT SEALS Q 17. SEAL RINGS Q 18. ADOPTING RING Q 19. AUXILIARY BEARING Q 20. CENTRIFUGAL FAN Q 21. CARBON DIOXIDE VAPOURISER Q 22. FILTER O.C.P. Q 23. EXPANSION TANK R 24. OIL SEPARATOR R 25. PRE CHAMBER R 26. S.O.S.T. R 27. SEAL OIL UNIT Q 28. HYDROGEN DISTRIBUTION R 29. CARBON DIOXIDE DISTRIBUTION R 30. VALVES FOR AUXILIARY SYSTEMS P 31. GAS UNITS Q 32. FLEXIBLE LEADS Q STORAGE & PRESERVATION OF COMPONENTS OF HEAT EXCHANGERS SNO. DESCRIPTION OF THE COMPONENT TYPE OF STORAGE PRODUCT : CONDENSER Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 24
  • 25. 1. BOTTOM PLATE S 2. LOWER DOM WALL S 3. SIDE WALL S 4. WATER CHAMBER Q 5. UPPER DOM WALL S 6. STIFFENING PIPES S 7. STIFFENING RODS S 8. TUBE SUPPORT PLATE R 9. WATER BOX R 10. AIR EXTRACTION PIPING R 11. HOTWELL S 12. SPRING ELEMENTS R 13. LOOSE ITEMS Q 14. INSTRUMENTS Q 15. CONDENSER TUBES (STAINLESS STEEL) R 16. CONDENSER TUBES (NON-FERROUS) Q 17. VACUUM PUMP Q 18. EJECTOR R 19. AIR MEASURING DEVICE Q PRODUCT : HEATER 1. GLAND STEAM CONDENSER R 2. STAND PIPE Q 3. INSTRUMENTS Q 4. DRAIN COOLER R 5. L.P.HEATERS R PRODUCT : COOLER 1. OIL COOLER R 2. CONTROL FLUID COOLER R 3. STATOR WATER COOLER R 4. HYDROGEN COOLER Q 5. EXCITER AIR COOLER Q 6. INSTRUMENTS / LOOSE ITEM Q Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 25
  • 26. MAXIMUM PERMISSIBLE LOADING FOR WIRE ROPES IN KG. NOMINAL SINGLE DOUBLE CORD WITH INCLUDED ANGLE OF DIA (d) OF CORD ROPES mm 0o 45o 90o 120o 9 522 1044 965 738 522 12 1170 2340 2070 1580 1170 18 2150 4300 4000 3060 2150 24 3850 7700 2100 5400 3850 30 6200 12400 11500 8800 6200 36 9000 18000 16600 12700 9000 42 12200 24400 22600 17300 12200 48 16000 32000 29500 22600 16000 54 20200 40400 37300 28500 20200 60 24900 49800 46000 35200 24900 66 30100 60200 55700 42600 30100 72 35800 71600 66200 50700 35800 78 42100 84200 77700 59500 42100 84 48800 97600 90200 69000 48800 90 56000 112000 103500 79200 56000 96 63700 127400 117700 90000 63700 102 71900 143800 132900 101700 71900 108 81000 162000 149700 114500 81000 114 89900 179800 166100 127100 89900 120 99700 199400 184300 141100 99700 Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 26
  • 27. ERECTION SEQUENCE (For 500 MW Fixed pedestal type Turbine with spring loaded foundation) 1. Cleaning and checking of Turbine and Generator foundations as per the transverse and longitudinal axis including their elevation. 2. Prepare and install LP base plates, HP front pedestal, HP rear pedestal, LP front pedestal, LP rear pedestal along with their anchor bolts and anchor plates. 3. Provisionally align and level all the pedestal and LP base plates as per the transverse and longitudinal axis including their elevation. 4. Matching of anchor plates of pedestal and LP base plates to ensure their perfect seating. 5. Finally align and level HP front, HP rear, LP front and LP rear pedestals along with LP base plates as per the transverse and longitudinal axis including their elevation and catenary as per the design. 6. Prepare and install steel bars for LP casing centralising keys in foundation slab as per the required center line . 7. Weld locating ring of LP front pedestal and steel bars of LP front and LP rear centralising keys. 8. Prepare shuttering and grouting of the pedestals and LP base plates including anchor plates of HP rear pedestal. 9. Prepare, install, align/ level both the LP girder along with their carrier plates. 10. Prepare , install and assemble LP front and rear end walls with the LP girders. 11. Level / align LP outer casing lower half as per the transverse and longitudinal axis of the machine. 12. Install permanent packers of LP outer casing including their radial and axial keys. 13. Prepare and install LP inner outer casing along with gusset plates in position Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 27
  • 28. 14. Align LP inner outer casing lower half and level it. Install LP casing parting plane platform . 15. Prepare and install LP front and LP rear lower half shaft seals housing and align it provisionally. 16. Prepare and install LP rotor along with their bellows in position. 17. Align LP rotor radially and axially in position and record free run out of rotor. 18. Record/ Ensure radial and axial clearances of the LP casing including rotor float including fitting of final axial keys of the LP inner casing . 19. Box up LP inner inner casing and heat tighten the parting plane bolts. 20. Box up LP inner outer casing . 21. Prepare and place HP module in position on temporary packers. 22. Transfer the load of HP rotor on bearings from the transport device and align it radially and axially. 23. Check free run out of HP rotor on journal and coupling face including its float. 24. Prepare and place IP module in position on temporary packers. (In case IP module is sent to site in disassembled condition, refer Instruction T1-08-0606G. 25. Loading of IP rear end of the shaft on bearing and removal of transport device. 26. Provisionally align HP , IP and LP rotor . 27. Couple HP / IP rotor on temporary Bolts and align rotor / casing radially and axially. 28. Record/ Ensure IP rotor float by shifting HP casing axially. 29. Conduct Horn drop test of HP casing without any radial and axial keys and pipe lines. 30. Conduct Horn drop test of IP casing without IP inlet upper half pipe lines. 31. Assembly of breech nut of HP casing and Main Steam Stop & Control valve assembly. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 28
  • 29. 32. Erection of Reheat Stop & Control valve assembly. 33. Weld IP inlet upper half pipe and record Horn drop values without radial-axial keys. 34. Alignment of HP/IP/LP rotors and their coupling on temporary bolts including its couple runout. 35. Swing check of HP rotor on its front end with temporary alternate bolt tightened on HP/IP coupling . 36. MOP alignment and its doweling. 37. Reaming/honing of HP/IP and LP/IP coupling including fitting of final coupling bolts. 38. Fixing of axial position of shaft and assembly of thrust bearing including its colour matching. 39. Roll check of HP/IP casing and fixing of radial and axial keys of the casing (Casing final packers need not to be put at this stage). 40. Assembly of bearings and checking of all clearances including fittings of side pads of bearing, yoke keys etc. 41. Turbovisory works in all the pedestal i.e. assembly and calibration of thrust bearing axial shift, LP rotor expansions pick up, Hall generator and thermocouples of bearing . 42. Preparations of the bearing for oil flushing. 43. Oil flushing of the machine and normalizing the bearing after oil flushing. 44. Preparation and floating of TG deck as per Instruction No. T1-08-0909G. 45. Decoupling of HP / IP, LP/IP, LP/Gen., Gen./Exciter coupling and rechecking of alignment/catenary after floating of TG deck spring. 46. Final tightening of HP/IP, IP/LP , LP/Generator and Generator / Exciter coupling after correcting the alignment including their couple run out and swing check of rotor on HP Front and exciter rotor. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 29
  • 30. 47. Checking /Correction of LP shaft seal clearance after floating of TG deck with CW pump in operation and water in the hot well of condenser upto operating level. 48. Roll check of HP, IP casing in up and down direction only with TG deck in floating condition and CW pump in operation including water in hot well upto normal level. 49. Assembly of final packers of the HP, IP casing after completing the roll check in up and down direction. 50. Recording of final Horn drop of HP and IP casing after completing the welding of HP inlet, HP exhaust , IP inlet and Cross around piping. 51. Preparation and boxing up of LP casing after competing the full Roll check of LP casing and fitting of final casing packers and radial keys. 52. Barring gear. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 30
  • 31. CHECKING OF FOUNDATION BEFORE CASTING Customer to provide, center line and elevation point. Check positioning of all the inserts and fixed points with respect to center line in transverse and longitudinal direction as per BHEL Hardwar drawings. Check elevation of all points. Check verticality of all the pipe sleeves with the help of plumb. Ensure proper locking of all the insert and fixed points before grouting. Ensure leveling on the fixed points of LP girder and LP rear pedestal. Preserve machined surfaces of all the fixed points against any damages due to Improper handling. Ensure proper flatness of the bottom seating plate of all the inserts. Ensure proper stiffeners in all the vertical and horizontal embedment provided for various purposes like hangers and supports etc. Ensure proper cleaning of the area before casting. Remove all unwanted material. NOTE: In case of spring loaded TG deck refer Installation Instruction No. T1-08-0909G prior to positioning of inserts etc. CHECKS DURING CASTING/POURING OF CONCRETE Casting of foundationTG deck should be carried out immediately after inspection of the foundationTG deck i.e. within 3-4 days after final inspection to avoid any disturbance to the inserts and fixed point. Ensure no disturbance to the insert etc. during pouring of concrete while vibrators are used. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 31
  • 32. About 15-20 mm extra concrete may be left on top on all the pedestals and LP base plate area for chipping/cleaning purpose at a later date. Close all the pipe sleeve from top to avoid entry of concrete inside. Alternately the pipe sleeve should be filled with sand. CHECKING OF FOUNDATION AFTER CASTING Clean complete foundation and remove all shuttering etc. Ensure there is no loose concrete layer in the region where the pedestal and base plates are to be laid. No repair should be done in this region without consulting the turbine erection engineer. Cover all the opening before checking any dimensional measurement to avoid any accident. Establish a suitable longitudinal axis considering the fixed point of the LP rear pedestal and various pipe sleeves / inserts. Establish a transverse axis as 90 degree with the help of the odolite. Measure pitching/elevation of all the inserts and fixed points. Measure elevation of all foundation on different pedestal and LP base plate area. Check level of LP rear pedestal fixed points and if required correction may be carried out. PREPARATION OF FOUNDATION FOR PLACEMENT OF PEDESTALS AND BASE PLATES: Foundation are to be cleaned and loose concrete are to be chipped off. Maintain elevation of foundation to ensure correct thickness of non-shrink grout. A reference point for elevation in respect of machine center line (equivalent to LP rear pedestal) is to be maintained at a proper place. This point is to be preserved with proper protection. For making reference point a one side ground plate of about 200 x300 x20 mm may be used. This may be welded on a I-beam near Generator. The ground position of the plate is to be kept on top side and all elevation are to be transferred from this point with the help of water level jar. A correct elevation reading is to be punched on this plate. This reference point is to be used only during the turbine erection period. Clean and deburr piping sleeves of the foundation on ID/OD of the pipe. Ensure all corners of the foundation remains perfect during chipping of extra concrete of foundation. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 32
  • 33. PLACEMENT OF PEDESTALS Open and clean the pedestal. Ensure there is no paint/oil on bottom face of the pedestal sole plate. Ensure there is no paint on inside surface or the pedestal and if required sand blasting may be carried out at site. Ensure correct fitting/clearance of locating rings of LP rear pedestal. The half bore error of pedestals is punched by manufacturing unit however in case it is not there, measure and punch half bore error of pedestal in left/right side of the pedestal. If the error is nil then this may be punched as zero-zero. Ensure that the pedestal parting plane is feeler tight after tightening all the parting plane bolts. If required, colour matching may be carried out but scraping/cutting is to be done on upper half cover only. Check proper colour contact of spherical/cylindrical supports of the bearing with the pedestal. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 33
  • 34. Check contact between spherical Torus piece of bearing and spherical/cylindrical seat. In case of any variation in contact no scraping/cutting to be carried out at site and this may be referred to manufacturing unit. Also refer T1-08-0808G. Check centering of individual bearing w.r.t. pedestal seal bores by fixing pianowire on individual pedestal. Ensure cleanliness of all pedestal oil lines. Close opening of oil lines of pedestal to avoid any foreign material entering in these pipe lines during erection at site. Weld MOP suction and discharge pipe lines in HP front pedestal as per the drawing before placement. Assemble protection sheet in the foundation bolt holes of pedestals. Assemble anchor bolts along with anchor plate of the pedestals. Ensure that there is good contact available to the backing plate with the foundation. If required colour matching/grinding may be carried out to achieve the contact. Assemble protection sheet in the anchor bolt hole from bottom side of HP rear pedestal foundation to avoid entry of grout metal. Ensure level of both anchor plate of H.P. rear pedestal with 70-90 mm gap for filling of grouting concrete. Adjust height of the Anchor Bolts as specified in the drawing. PLACEMENT OF LP BASE PLATE, OVER THE FOUNDATION : Clean all the four base plates. Mark/punch center line on the base plate as per drawing. Ensure proper cleaning of base plate on bottom side. Put identification marks on each base plate to avoid any mistake in positioning of the same. Do colour matching of all the eight nos. carrier plate on both the faces. Match LP base plate with the individual carrier plate. Place all the four base plates in position along with their leveling screws and foundation bolts. Provisionally align and level all the four base plates. Assemble protection sheet in the foundation bolt holes. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 34
  • 35. ALIGNMENT OF PEDESTALS AND LP BASE PLATES Provisionally align and level all the four pedestals including LP base plates with reference to the earlier marked longitudinal and transverse axis. The elevation reference is to be taken from the already positioned plate for this purpose. Align and level LP rear pedestal and set the elevation as per machine center line. Use piano wire arrangement with micrometer for centering of pedestal bore and use water level jar for setting of elevation. Use measuring tape to maintain pitching of the bearing from one pedestal to another. Pedestals are to be set in level condition on both longitudinal and transverse direction. Align and level HP front, HP rear and LP front pedestals. Elevation of the pedestals are to be set as per catenary of the machine considering the half bore error of the pedestal if any. Align and level, LP base plates. Elevation of LP base plate is to be kept higher than the rear pair of LP base plate in line with catenary of rotor. After alignment of LP rear pedestal weld the locating rings as mentioned in the drawing. During welding of locating ring, ensure that there is no movement in the pedestal in any of the direction. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 35
  • 36. GROUTING OF PEDESTALS AND LP BASE PLATES Fill 3 to 8 mm washed Pea-gravel in all the anchor bolts sleeves. These gravel are necessary to give damping effect to the anchor bolts during operation of the machine. Seal anchor bolts holes after filling of gravel to avoid any entry of grout metal. Medical tape may be used for sealing of these anchor bolt holes. Clean foundation with compressed air. Make shuttering of all the pedestal and LP base plates. Use thick polythene sheet inside the shuttering to give better finish and avoid moisture absorption by shuttering. Shuttering should be made with maximum care to avoid any leakage of grout concrete. All sides of the shuttering are to be sealed either with some sealing compound or with thick mixture of grout material to avoid leakage of grout material. Foundation are to be kept wet for about 6 hrs. before grouting. Non shrinkage cement duly approved by BHEL is to be used for grouting of the pedestals and base plate. Use fresh stock of the grouting material only and check the strength of the material before use. During grouting, the mixture has to be poured from one end only and it has to flow to opposite end to avoid any blockage of air pocket. Water curing is to be carried out for about 10 days duration. All anchor bolts are to be stretched minimum after 21 days of grouting. HP, IP & LP module placement work can be taken up after 24 hours of grouting of the pedestal and base plates. For individual pedestal and base plate, grout mixture should be poured in one lot only. PLACEMENT OF HP MODULE IN POSITION Ensure matching of all the four palms of the module where it is resting on the pedestals. Ensure matching and parallelity of front and rear key block of the HP casing. Assemble all four jacking screw of HPC and ensure their free movement. Clean journals and coupling of the HP rotor. Record journal dia, coupling hole sizes and spigot dia of HP rotor. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 36
  • 37. Lift module in level condition and place it in position by keeping it 3 to 5 mm toward front pedestal side. During placement of module use temporary packers similar to permanent and additionally support it by four jacking screws. Ensure load on all four packers with the help of some additional shims if required. Install temporary radial and axial keys of the casing. Prepare HP rotor for alignment (Ref. section 20 before placing the IP module. PLACEMENT OF IP MODULE IN POSITION Ensure matching of all the four palms of the module where it is resting on the pedestals. Ensure matching and parallelity of front and rear key block of IP casing. Assemble all four jacking screws of IP casing and ensure their free movement. If these jacking screw holes are provided with the bolts from factory then same are to be removed before placement of module. Clean IP rotor on both sides including coupling and journal. Record spigot /recess, journal dia, and coupling hole sizes. Lift the module in level condition and place the module in position by moving about 7 to 8 mm towards generator end. Use temporary packers for placement of module in position and additionally support the module with jacking screws. Ensure load on all four packers with the help of some additional shims if required. Provisionally align the casing on front and rear pedestal bore. Install temporary radial and axial keys of the casing with some shims. Prepare IP rotor for alignment (Ref. section 20). NOTE: In case IP module is sent to site in disassembled condition, refer Instruction T1-08-0606G. ASSEMBLY OF LP MODULE This assembly can be divided in following sub assemblies: Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 37
  • 38. Assembly of girder and end walls. Assembly of LP inner inner and LP inner outer casing lower half. Assembly / welding of LP outer casing. Before starting assembly of LP casing in position, following works are also to be completed : - Positioning and welding of LP casing centering pin of front and rear side. - Positioning of key block of LP casing axial keys. - Positioning of all internal of condenser. POSITIONING AND WELDING OF LP CASING CENTERING PIN Two nos. centering pins are to be located below LP front and LP rear pedestal. Necessary pipe along with two sq. end plates are already provided in the foundation to take the radial load of the LP casing: Plumb the center line from LP front and LP rear pedestal bore on both side over the square plate of the foundation. Establish accurate position of the pin and put a punch mark at a required height and mark a circle and a controlling circle over all the four sq. Plates. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 38
  • 39. Dia of the circle must be equal to pin dia. A template equivalent to pin dia has to be made for this purpose with about 20 mm thick plate and a welded pipe for using as an handle. The template dia must be very accurate and same may be made on machine. Make precise hole with gas cutting/grinding to match template on all four embedded plate. Ensure that the template is fitted with minimum clearance and hole center are perfect as per marking. Drill hole of about 10 mm dia on one of square plate of LP front and on one plate of LP rear for air venting to avoid cracks during welding. Insert both the pins and carry out the welding as per laid down procedure. Before welding set correct axial position of the pins. Insert key block on both the pins and weld their locking ring also. Ensure proper clearances in key block before welding of its locking ring. Preheating of 200 degree Celsius or more to be achieved before any welding. Dye penetrate test on root run and after final welding is to be carried out. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 39
  • 40. ASSEMBLY OF GIRDER AND END WALL Colour match side matching flange of girder with the surface plate. Colour match seating flange of girder where it rests over the LP base plate. Match and ensure parallality of axial key ways of girder. Colour match side flanges of end wall. Match and ensure parallality of key block of end wall. Place left and right girder with carrier plate, spacer and lubrite packer on LP base plate. Provisionally align and level the girders. Set height of the girder equivalent to machine center line maintaining catenary of the machine with the help of water level jar arrangement. Assemble locking plate of the front and rear end wall to facilitate its assembly with the girders. Assemble front and rear end wall with the girders and ensure perfect parting plane level during tightening. Align, level LP outer casing and ensure contact of packers by colour matching/machining of spacer height. Install LP casing radial and axial keys. Assemble inner outer casing axial key blocks on left and right side of girder and dowel them. Lock with tack welding all the vertical joint bolts. Put a seal weld run between girder and end wall joint all around except on top face. Weld girder and end wall parting plane joint with argon welding. Before welding make a V groove with the help of a chisel and allow the projection of material on surface. Do not make the groove by grinding. Do colour matching with a surface plate on all four corner where argon welding have been carried out. ASSEMBLY OF LP INNER INNER AND LP INNER OUTER CASING LOWER HALF The LP inner inner casing lower half is received from factory in assembled condition with LP inner outer casing lower half. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 40
  • 41. Clean the casing and check all the threaded holes. Do colour matching on all four corners of the casing where it rest over the girder. Colour match all eight carrier plates of inner casing on both side. Assemble all carrier plates on girder and do the colour matching with individual carrier plate. Prepare Gusset plate of front and rear side with temporary radial keys for fitting in LP inner casing. Level and lift LP inner outer casing and assemble/weld both the gusset plates with the help of some temporary support. Lower the casing in position over the carrier plates fitted with spacer and lubrite packer. Provisionally align the casing radially and axially. Support the gusset plate with the help of screw jack (about 10-15 tons) on front and rear side by taking support from condenser stiffeners. Screw jack is to be unscrewed after box-up. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 41
  • 42. Adjust the height of the LP inner outer casing as per center line of the machine and then level it with the help of water level jar arrangement. Ensure that all the eight packers have good contact. Loading of each packer is to be ensured. Lower the casing by about 2 mm on all the eight packers with the help of shims for placement of LP rotor to avoid any fauling during placement of rotor. Fit and weld all gusset plate stiffener pipes except pipe between LP inner outer casing and condenser. Do not make any weld connection between condenser and any of these stiffeners till neck welding of the condenser is over. PLACEMENT OF LP ROTOR Measure journal dia, spigot dia and coupling hole sizes. Ensure centering of temporary bearing support in the LP front pedestal for placement of LP rotor. Place LP rear bearing in position. Prepare shaft seal compensator along with gaskets (Gasket to be installed in fully ring shape only ) and position them on LP rotor with the help of supplied supports of compensator. Lift LP rotor with the supplied lifting beam in perfectly level condition and place it in position. During lowering of rotor ensure radial clearance with the help of long feeler gauges in the LP casing. WELDING OF LP OUTER CASING The welding of LP outer cover is to be carried out before placement of LP Rotor in position to avoid damage to the rotor. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 42
  • 43. Colour match and remove all high spots of the matching flange of the LP outer casing. Ensure good contact between parted diffuser of LP front and LP rear cover. Colour match and remove all the high spots of the parted diffuser/vertical face to ensure good contact with the compensator at a later stage. Colour match and remove all burrs and high spots from parting plane of LP outer casing. Side flange of LP front and rear cover are to be ensured in right angle to achieve good contact with their matching flanges. Place LP front LP rear cover along with parted diffuser and ensure feeler tight joint after tightening the parting plane bolts. The joint must be feeler tight just after normal tightening of bolts. Do not over tighten parting plane bolts. Ensure matching of parted diffuser face on both side of LP casing. If necessary colour matching may be carried out to achieve a feeler tight joint. Drill/ream all the parting plane holes as per drawings and install all dowel pins. After fixing of LP front and rear cover measure the dimension for positioning of both the center flanges. The dimension are to be recorded in such a way that there is no clearance after fitting of center flanges in position on both side with the LP front and rear cover. The center flanges are supplied in extra length on both sides from the factory and final length are to be maintained at site only. Drill/ream dowel pin holes in center flanges and install all dowel pins in position. Ensure drilling and reaming of all dowel pin holes to equal depth. Fit both the center pieces of the cover in position. Achieve the fitting clearances for welding as per laid down procedure. Weld/lock LP upper half flange with respect to lower half casing with the help of metal cleats to minimise the distortion during welding of LP cover. The cleats may be welded at an interval of about one meter distance. Carry out the welding as per the following welding procedure. WELDING PROCEDURE Tack weld the crowned seam joint. permanently welding approx. 100 mm at the generator end of the joint. Opposite tack welded radial joint 2, permanently weld approx. 100 mm of the crowned seam joint, pos. 1, staggering the two weld ends to ensure a perfect transition when the crowned seam joint is finish welded. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 43
  • 44. Tack weld the crowned seam joint at regular intervals with a tack of 5T and pitch of 25T. When welding radial joint 2, shell plates 1 & 2, tacked together, rest on but are not tacked to the retaining strip in the region of joint 1, so that any shrinkage occurring during welding of seam 2 is not obstructed. The tacking & welding sequence applies for all shells courses. Weld radial seam at TE according to welding sequence plan. Align, adjust and tack weld radial seam at GE. Weld radial seam at GE according to welding sequence plan. Weld crowned seam joint. Align shell courses on joint strips and tack weld, Weld on joint strips from center & ends of shell plate. Insert pins in top half casing, release top half casing and lift to insert and tack filler piece between joint strips. Unbolt top half casing and lift in order to weld and finish - machine filler pieces in the region of the joint surface. Check welds according to specifications. ALIGNMENT AND COUPLING OF LP-IP & HP ROTOR LP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to be centralised in such a way that enough clearances are available to LP rotor, during alignment. Now this alignment activity of all the three rotor can be divided as below : Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 44
  • 45. Preparation of HP rotor for alignment. Preparation of IP rotor for alignment. Preparation of LP rotor for alignment. Alignment of LP-IP & HP rotors. Reaming, honing of the coupling holes. Balancing of coupling bolts weight. PREPARATION OF HP ROTOR FOR ALIGNMENT Align HP rotor with reference to front and rear pedestal seal bore reading. If required move complete HP module along with the rotor. Fix temporary radial and axial key of the casing on both front and rear side of the casing. Remove HP front upper half transportation device. Lift module by 0.20 mm on front side by putting additional shims in front packers. Insert HP front bearing in position. Reduce 0.20 mm shims gradually and ensure about 0.10 mm load on the rotor. If required further lower the front side of the module to achieve the loading on bearing by about 0.10 mm. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 45
  • 46. Remove HP front lower half transport device gradually and ensure no movement between HP casing and rotor. If necessary adjust shims of HP casing front packers. During loading of bearing always ensure that the rotor is not fouling inside the casing with the shaft seals. This may be ensured by checking with feeler gauge also. Check axial position of HP rotor in front side on left; right and top position from the rotor reference point to the HPC as given in the shop protocol. Insert and load the bearing in HP rear end in similar way as carried out in case of HP front end and record axial position of rotor as per shop protocol. Lock axially HP rotor with some fixture along with the arrangement of jacking screw for movement of rotor. This fixture may be mounted on rear pedestal. Before locking of rotor ensure axial position of the shaft. Center HP shaft with reference to HP casing front and rear spigot. If necessary, move the casing readily to achieve the centering. A fixture can be fabricated at site for mounting the dial gauge on both the end of the rotor to check the centering of the shaft. Use thick oil during rotation of shaft on the bearing. Protect bearing from any of the dust particles. It is recommended to place upper half of bearing in position to avoid dust and any other damage to the shaft journal. Realign the rotor shaft with respect to pedestal seal bore and if necessary adjust the shims below spherical support of the bearing. Care should be taken during alignment that radial and axial clearances between rotor and casings does not get bridged. Check HP rotor radial run out on journal and coupling. Check axial run out on thrust collar and both the coupling faces of HP rotor. Check axial float of the rotor. Compare values with shop protocol values. (Ref. T1- 08-0802G). Deviations to be reported to Manufacturing Unit. PREPARATION OF IP ROTOR FOR ALIGNMENT The IP module is also to be prepared in line with the HP module. However as IP rotor is provided with one side bearing and opposite side is coupled with the HP rotor without a bearing, extra care is necessary during alignment of rotor in IP casing. The additional point which are to be taken care are explained below : Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 46
  • 47. Place IP rotor rear end on bearing similar to the HP rotor and remove transportation device. Provisionally align HP/IP rotors and couple on temporary bolts by moving both the modules. During coupling of the rotors, the transportation device of IP front end is also to be taken out. Check axial position of rotor w.r.t. IP casing and adjust as per shop protocol. Check centering of IP rotor front and rear end w.r.t. IP casing (similar to the HP rotor centering check). Check float of the IP rotor. Compare values with the shop protocol values. (Ref. T1-08-0802G). During checking of float ensure HP casing is not fouling with HP rotor. If required HP casing may be moved axially for this purpose. Check facial runout on IP rear coupling face and radial runout on journals and couplings. PREPARATION OF LP ROTOR FOR ALIGNMENT Provisionally align LP rotor in pedestal seal bore placing the front end of shaft on auxiliary bearing and rear end on bearing. Align LP inner outer casing radially with the help of long feeler gauges and install temporary radial keys in the gusset plate. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 47
  • 48. Record all the radial and axial clearances of the LP casing without coupling the LP-IP rotor. Variation if any in radial or axial clearances are to be corrected/approved at this stage. Remove shims from the front end of auxiliary bearing and keep rotor on lifting tackle. Record radial run out of LP rotor coupling and journal and axial run out of the coupling faces of the both end. Record float of the LP rotor by moving the LP inner outer casing lower half. After ensuring the radial and axial run out of the LP rotor the LP inner outer casing can be boxed up. Parting plane bolts of LP inner-inner casing are to be heat tightened. ALIGNMENT OF HP, IP AND LP ROTORS Ensure radial and axial runout of all the three rotors are individually in order. If necessary individual rotor module can be taken out for correction of coupling face runout. Any variation on radial runout of rotor is to be referred to the factory. Match coupling faces of two rotor as per the axial face reading of the rotor. Ensure that the higher point of the rotor coupling face and lower point of another rotor coupling face are matched together. This is to be compared with shop protocol also. Preliminary align radially and axially all the three rotors and shift them in spigot along with the casing to avoid fouling of rotor inside the casing. During alignment achieve left and right movement of the rotor with the help of shims in spherical / torus piece of the bearing. The up and down movement of the rotor is to be achieved with the help of shims in the cylindrical/spherical support of the bearing . The adjustment of shims in the bearing should be within the permissible limits only. Ensure during alignment that the catenary of the shaft is maintained. Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving them in spigot. Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IP coupling. Hand tighten the coupling bolts by keeping a gap of > 1.00 mm in coupling faces for alignment. Rotate the rotor system and record the coupling gap at 90 Deg. interval on left, right and top position. Ensure that the coupling, bolts and pins remain free while recording the gap of the coupling for the alignment purposes. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 48
  • 49. Check swing check value of the HP rotor with alternate bolts in position. The above value must be within the prescribed limit only otherwise a correction must be carried out at site in consultation with designer. Ensure free movement of rotor on their bearing. Do not rotate the rotor if it is tight during its rotation. Ensue that the coupling holes are properly aligned to avoid unnecessary enlargement of holes. Ensure HP-IP-LP rotor radial run out after tightening with alternate clearance bolts. Release the couplings for reaming / honing of couplings. In case of spring loaded TG decks, refer alignment procedure T1-08- 0909G REAMING / HONING OF COUPLING Ensure that there is no disturbance on coupling during reaming/honing operation. First ream/hone two opposite holes of the coupling and install two pins/bolts with sliding fit and then take up all other holes. Enlarge coupling holes to the minimum possible diameter and try to make all the holes to same dia. Ensure that the finished holes are straight and there is no banana shape. This can be ensured by checking hole with a straight ground finish pin having 0.02/0.03 mm clearance. The length of the pin should be equal to the bolt length. In case, few holes have gone considerably over size during reaming/honing at site/works, do not enlarge all the holes. As a special case in such cases these few holes may be left as oversize. Ensure that the holes during reaming/honing are perfectly finished as ground bore and size obtained should be within 0.005 mm. Ensure all the coupling bolts are fitted within 0.02/0.03 mm clearance with sliding fit and bolts are to be ground within an accuracy of 0.005 mm. Coupling bolts are not to be hammered in the holes and these are to be fitted with thumb pressure only. Do not decouple the coupling in any case without ensuring the fitting of all the coupling bolts. BALANCING OF COUPLING BOLTS After fitting the coupling bolts in all the holes these are to be balanced within 5 gms accuracy and an accurate balance which can take a load of about 20 kg. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 49
  • 50. may be used. During balancing of coupling bolts following points are to be taken care. Final balancing of the coupling bolts are to be done along with the coupling nut of individual bolt. If all the coupling bolt hole sizes are same before/after reaming and honing then all the bolts can be kept of equal weight. If necessary adjust the weight of the bolts by machining the metal from the bolt head. When the holes of the coupling are of different sizes then it must be seen that whether excess enlargement have been done at site or works. In such cases if excess cutting have been done at site in a particular hole then coupling bolt with excess weight are to be used. The amount of excess weight must be equivalent to the excess enlargement of hole at site. If a particular hole of excess dia. is noticed from factory then it is assured that the particular rotor is balanced with excess dia hole and there is no need of providing excess weight bolt at site. COLOUR MATCHING OF THRUST BEARING After completion of reaming/honing and preliminary tightening of the coupling bolts, the colour matching of the thrust bearing pad have to be carried out with respect to the thrust collar of the HP Rotor. During colour matching a good contact on all the pads of front and rear side are to be ensured with respect to rotor collar by moving the rotor in +/- direction during its hand rotation. Following points are to be taken care during colour matching. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 50
  • 51. Thrust bearing must be axially locked with the help of axial keys during the colour matching of the pads. Axial keys to be fitted while finalising the alignment of thrust bearing with rotor collar without pads. Few drops of oil is to be put on journal portion of the thrust bearing during rotation of rotor to ensure that the oil is not entering in pad portion of the bearing. Colour is to be applied on the thrust collar of the rotor. If necessary move the spherical support of the bearing pedestal to ensure the equal thickness of the pads before fittment of axial keys of the bearing. During moving of the spherical support in front or rear direction ensure that there is no left - right movement to the support otherwise that may cause misalignment of the bearing. After colour matching of the thrust pad the axial zero position of the rotor is achieved and this can be taken for all other future reference for setting of axial position of HP, IP & LP casing. HP, IP and LP lower casing are to be set axially after fixing the axial position of the rotor and their final axial keys can be installed at this stage. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 51
  • 52. ALIGNMENT OF HP, IP & LP CASING After completion of colour matching of the thrust bearing pads the casing alignment work can be taken up. The following points are to be taken care while aligning HP, IP and LP casing. The roll check have to be carried out in HP, IP and LP casing to ensure the correct radial clearances of the casing. TG deck springs are to be kept in floating condition while recording the roll check of LP casing. However the roll check of HP/IP casing may be carried out before floating of TG deck for fitting of their radial keys but up and down roll check of HP/IP casings are to be done with TG deck in floating condition as per the procedure TS/ST/ 01/0008/00/96. Ensure that there is no obstruction in the movement of LP inner casing due to welding of any of extraction piping. The one of the joint of extraction piping may be left free till completion of roll check of the casing. The welding of steam inlet pipes between LP inner casing and LP girders are to be taken up after completion of roll check of the casing. HP, IP and LP casing are to be fitted with final packers and axial key immediately after the roll check. During fitting of casing axial keys and palm packers ensure proper contact on lubrite coating of the keys/packers to avoid any damage of these coating during operation of the machine, After completion of fitting of final keys and packers only the casing are to be cleared for further works of welding of various pipe lines. The gland steam, balancing leak of lines, steam inlet and exhaust pipes are to be welded with HP casing after fitting of final axial keys and packers of the casing. Center HP rotor w.r.t. casing front and rear spigots. Compare the readings with shop protocol and record the readings. Offset center line of the HP, IP & LP casing w.r.t. respective rotor center line as per recommended logsheet. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 52
  • 53. Check/record LP diffusers centering readings after roll check of the casing. Before roll check of LP casing all the stiffener pipe welding work must be completed. Refer T1-08-0909G. FINAL TIGHTENING OF COUPLINGS In case of spring loaded foundation after completing all other works the HP / IP , IP/LP , LP/GEN , GEN/EXCITER couplings are to be reopened and realigned after completing the reaming /honing . The rotors alignment are to be checked with TG deck in floating condition as per the laid down procedure. After checking of alignment /catenary the final couplings are to be tightened including their coupled run out and swing check of rotors on HP front and Exciter end of the shaft. BOXING UP OF LP INNER INNER AND LP INNER OUTER CASING The boxing up of LP inner inner and LP inner outer casing can be taken up before starting the alignment of HP-IP & LP rotor for coupling work. The following points are to be taken care before/during boxing up of these two casings. Ensure matching of all the parting plane holes, fitting of cap nuts and accessibility of spanner . Ensure feeler tightness of the parting plane joint of both the casing. Check/record all the radial and axial clearances of the casing. Ensure proper cleanliness of the LP inner inner and LP inner outer casing. Ensure adequate clearance between LP inner inner casing and LP inner outer casing to avoid any obstruction during expansion of the LP inner casing inside the LP inner outer casing during operation of machines. BOXING UP OF LP OUTER CASING During the boxing up of the LP outer casing following points are to be taken care. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 53
  • 54. Roll check of LP inner casing including the fitting of key, packers etc. must be finished. All the works must be finished inside the LP casing before boxing up of LP casing including LP extraction pipe line works. Ensure matching of all parting plane holes and feeler tightness of the joint before boxing up of the casing. Ensure feeler tightness of bursting diaphragm flange joint before boxing up of the casing. Ensure proper assembly of parting plane rubber cord. FINAL HORN DROP CHECK After completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaust and other piping of HP/IP casing the final horn drop readings are recorded as per the laid down procedure mentioned in the manual for horn drop check. However the IP casing horn drop is also to be recorded with IP inlet upper half pipe welded with casing alone. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 54
  • 55. Grouting of turbine base plates, bearing pedestals, foundation frame with shrink-free grouting compound is intended to ensure uniform transmission of the force and vibration of the TG unit to the foundation. Caution: Preparations for grouting, and grouting must be carried out with great care as it is no longer possible to check and rectify the parts once they have been grouted. CONBEXTRA GP-II or equivalent should be used as grouting compound. Further details on the grouting depths, mixing time, quantity of water to be mixed, should be refereed from the manufacturers brochures. PROCEDURE The foundation should be thoroughly cleaned. All foundation bolt holes should be filled with pea-gravels and covered at the top to avoid entry and sticking of grouting materials with the bolts. NOTE:- Remove all rust preventive paints, grease etc. from surfaces by wire brushes to ensure proper adhesion of the grouting compound. SETTING UP OF SHUTTERING Set up shuttering from suitable material in box like manner around the foundation plates and secure it firmly. NOTE:- Shuttering must be sealed well to prevent the liquid grouting compound from running out. This can be done by using paste of grout materials and allowing it sets. As the grouting compound remains workable for a limited time, to prevent air bubbles, it must be poured from one side only. For this, a large size filling heaped should be used. Bharat Heavy Electricals Limited T1-08-0801G Rev 00, 7-98 Page No. 55