SlideShare ist ein Scribd-Unternehmen logo
1 von 49
EIA OF NAVI MUMBAI INTERNATIONAL AIRPORT (NMIA) By : KetanWadodkar M. Tech. 1st Year Environment Engineering Enrollment No.: 10519013 4/27/2011 1
Content 4/27/2011 2 ,[object Object]
Analysis of Alternative Sites
Location and Geography
Description of Environment
Project Activities
Introduction
Mumbai
Navi Mumbai
Need of NMIA project?
General understanding about the project ,[object Object]
Positive impacts
Negative impacts
Mitigation measures
Disaster management plan
Conclusions,[object Object]
Navi Mumbai
Need Of NMIA Project?
General Understanding About The Project4/27/2011 3
Mumbai 4/27/2011 4 Mumbai developed by British and nurtured by Local Mumbaikars. Earlier comprised of 7 isle now a metro city Financial capital of the country Busiest and 1 of the rapidly growing city in world.
Navi Mumbai Navi Mumbai is being developed as a counter magnet to the main city to achieve the goal of de-congestion of Mumbai CIDCO developed a new town Navi Mumbai of area 344 sq. km. Its Asias largest planned and developed city for population 2 million and 0.8 million jobs. high-tech  Jawaharlal  Nehru  Port  (JNPT)  catering   to   International Container Cargo traffic at Nhava-Sheva is  located on  the southern side of the  city. 4/27/2011 5
Need of NMIA project? Mumbai contributes about 40% of total net domestic product of Maharashtra. The share of manufacturing sector employment is expected to decline from 35 % to 27% and share of tertiary sector employment is expected to increase from 64%  to 72%. City is shifting from traditional manufacturing activities to trading and service activities. There is a need of increasing the capacity of airport as the existing Sahar airport (domestic) and CSIA (international) are not sufficient. 4/27/2011 6 ,[object Object]
Mumbai airport at Santacruz is the busiest airport in the country and handles approx. 23% of total passengers,  31% of Cargo  traffic and 18% of aircraft movement in the country.
The airport can handle 40 MPPA which is expected  to reach  by 2012-13.
There is a need to develop the second  airport for Mumbai.,[object Object]
Project description ,[object Object]
Location and Geography
Environment
Project Activities4/27/2011 8
Analysis of alternative sites The  following sites were  considered and analysed : Mahapan in Sindhudurg District Rewas-Mandwa in Raigad District Navi Mumbai (Panvel) 4/27/2011 9
Mahapan in Sindhudurg District: The site is approximately 350 km. away from Mumbai and would take about 8-10 hours by road  to reach the site. It is not considered for site for international airport Rewas-Mandwa: Site is about 120 kms away from Mumbai airport. This will result a travel time of around 3hrs which exceeds the international norms or travel time to airport i.e. 1.5hrs. The site is abutting Dharamatar creek. 2 parallel runways are planned. The availability of various infrastructure reqd. for the development of airport are absent at the site. A trans-harbour link from Sewri-Nhava is proposed to be constructed on Dharamatar creek. 4/27/2011 10
4/27/2011 11 Fig: Rewas-Mandwa site
Navi Mumbai site Located near Panvel town about 45 kms from the CBD of Belapur. 2 runways are planned. Phase wise development is adopted to meet the air travel demand. The site is also proposed to be accessed from Mumbai by high-speed water transportation system abutting airport site. Considering a SWOT analysis this site was finalized for new airport. 4/27/2011 12
Fig: Navi Mumbai Site 4/27/2011 13
4/27/2011 14
4/27/2011 15
4/27/2011 16
Location and Geography Located at Panveltaluka, Raigad Dist. Maharashtra. Present site is majorly CIDCO owned and remaining is private which will be acquired for airport development. SH54, NH4B, AamraMarg (Running on the Boundary of Airport site). Panvel creek, Gadhi river, Taloja river and Ulwe river running along and through  the boundary of the airport. Ulwe hill – RL 82 Mts. within the site. Elephanta at a distance of 13 Kms. West  Seismic zone :Zone-III as per IS: 1893 (Part-I) 2002.  Study area falls in coastal region of Konkan area. Panvel  1.5 kms. on Central Rly./KonkanRly.  Khandeshwar – 1 km. suburban Rly.. 4/27/2011 17 The study area is about 10 kms in radius around the airport site.
Description Of Environment Study area covers the district of Thane and Panvel. Climate is hot and humid.  it is included in Deccan Trap where all the balastic compositions are surrounded by large no. Of dykes. Taloja river and Kasadi river in the North, Kalundri and  Gadhi river in the East and Ulwe river in the South. The physico-chemical parameters ranges value within the prescribed standard except the BOD and nutrients. A total of 58 species of birds, 46 animals, 23 aquatic animals and maximum of 198 plant were found in study area. There is no forest area in the project area.  4/27/2011 18
Description Of Environment 4/27/2011 19
Description Of Environment 50% of project area is open land, salt marshes cover another 25%, 10% under mangrove forest, rain fed agriculture occupies 7% area rest is man-made things in the project area. Open land:  hilly terrain extending NW and is towards the SW end of the proposed runway. Salt marshes: more common in the Eastern region of the site of proposed airport than in the west. Used for Prawn culture and are also man made. No life as anaerobic condition prevails. Mangroves:  Avicennia marina more dominant species found here. Agricultural Land: rain fed agriculture in mansoon else barren land. Brick making also observed. 4/27/2011 20
Description Of Environment 4/27/2011 21 Ulwe River: Head portion is narrow and shallow. Covered with mangroves. Sand dredging activities are common. Prawn farming also done. Gadhi River: It is similar to Ulwe river at head. But broad and deep in rest region. On southern bank transported soil is laid and road is constructed. Relatively denser mangroves observed. ,[object Object],[object Object]
4/27/2011 23
4/27/2011 24
Socio-economic Status Of  Study Area: Total population under the study area is about 5.68 lakhs based on 2001 census consisting of urban as 4.8 lakhs and rest rural. For urban area: Average built-up area  - 45 Sq.m. Ownership household – 74%. Rental accommodation –  22%. Employer’s accommodation – 4%. Occupation- Professional 40%, Business or Industry owners 18%, skilled workers 21%, unskilled workers 9% & Clerks & typist 12%. Working population - total 32%, Males-89%, Female-11%. Average monthly income is Rs.12,700/- Infrastructure facilities   -  82% of the population are satisfied with the physical and social infrastructure available in the urban area. 4/27/2011 25
For rural area: Occupation- Fishermen 2%, Farmers 5%, Broker/Real Esate Agent/Businessmen 18%, Supervisor/skilled workers 13%, unskilled workers 21% & others 41% Income – Average monthly income is Rs.5499/- All the villages, falling within the NMIA project area, have asphalted approach road. All 10 settlements have primary school and 2 settlements have secondary school. 4/27/2011 26
Description Of Environment Study area includes places of historical importance such as: The Elephanta Caves. Karnala Bird Sanctuary. Matheran Eco-sensitive Zone. 4/27/2011 27
Project Activites Project area s about 2054 Ha. Airport zone is about 1615 Ha. Consisting of 1200 Ha. For aeronautical activity and 415 Ha. For non- aeronautical activity. Remaining area is there for utility services. 4/27/2011 28
Project activities involves: Development of Airport in four phases Training of Gadhi river Diversion of Ulve river Shifting of EHT Lines Development of off-airport site (non-aeronautical  area) Approach roads, railways, interchanges, water  transport service to airport zone in the vicinity and far Re-settlement and Rehabilitation Development of various Utilities in the airport zone 4/27/2011 29

Weitere ähnliche Inhalte

Was ist angesagt?

ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .onkar solshe
 
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGIONREGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGIONYash Shah
 
Kathputli colony slum development
Kathputli colony slum developmentKathputli colony slum development
Kathputli colony slum developmentM.I.T.,AURANGABAD
 
Planning of industrial estate
Planning of industrial estatePlanning of industrial estate
Planning of industrial estateKU Leuven
 
Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...Himanshu Goyal
 
EIA report on jaitapur nuclear power plant
EIA report on jaitapur nuclear power plantEIA report on jaitapur nuclear power plant
EIA report on jaitapur nuclear power plantsumankumar507
 
Kochi city study(intro, history, demography, infrastructure, economy, tourism)
Kochi  city study(intro, history, demography, infrastructure, economy, tourism)Kochi  city study(intro, history, demography, infrastructure, economy, tourism)
Kochi city study(intro, history, demography, infrastructure, economy, tourism)Arun Chandra Babu
 
A case study on Rajkillpakkam Junction,Chennai
A case study on Rajkillpakkam Junction,ChennaiA case study on Rajkillpakkam Junction,Chennai
A case study on Rajkillpakkam Junction,ChennaiSukhdeep Jat
 
legal aspects of navi mumbai international airport
legal aspects  of navi mumbai international airportlegal aspects  of navi mumbai international airport
legal aspects of navi mumbai international airporttwinkle Chhadwa
 
Environmental impact assessment case study
Environmental impact assessment case studyEnvironmental impact assessment case study
Environmental impact assessment case studyKundan Sanap
 
Urban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla MubarakpurUrban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla MubarakpurJoel Michael
 
Road development projects.
Road development projects.Road development projects.
Road development projects.Abhishek Rajput
 
Development control regulations kochi report
Development control regulations kochi reportDevelopment control regulations kochi report
Development control regulations kochi reportGeeva Chandana
 
Review of Mumbai Metropolitan regional development plan
Review of Mumbai Metropolitan regional development planReview of Mumbai Metropolitan regional development plan
Review of Mumbai Metropolitan regional development planAnoushka Tyagi
 
Lavasa, india's first planned hill city
Lavasa, india's first planned hill cityLavasa, india's first planned hill city
Lavasa, india's first planned hill citySoumitra Smart
 

Was ist angesagt? (20)

ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .
 
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGIONREGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION
REGIONAL PLAN: A CASE OF MUMBAI METROPOLITAN REGION
 
Regional plan
Regional plan Regional plan
Regional plan
 
EIA OF DAM: DURGAWATI RESERVIOR
EIA OF DAM: DURGAWATI RESERVIOREIA OF DAM: DURGAWATI RESERVIOR
EIA OF DAM: DURGAWATI RESERVIOR
 
Kathputli colony slum development
Kathputli colony slum developmentKathputli colony slum development
Kathputli colony slum development
 
Planning of industrial estate
Planning of industrial estatePlanning of industrial estate
Planning of industrial estate
 
Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...Factor considered for Environment Impact assessment (EIA) in legal procedure ...
Factor considered for Environment Impact assessment (EIA) in legal procedure ...
 
EIA report on jaitapur nuclear power plant
EIA report on jaitapur nuclear power plantEIA report on jaitapur nuclear power plant
EIA report on jaitapur nuclear power plant
 
Kochi city study(intro, history, demography, infrastructure, economy, tourism)
Kochi  city study(intro, history, demography, infrastructure, economy, tourism)Kochi  city study(intro, history, demography, infrastructure, economy, tourism)
Kochi city study(intro, history, demography, infrastructure, economy, tourism)
 
Urban study of Adyar
Urban study of AdyarUrban study of Adyar
Urban study of Adyar
 
A case study on Rajkillpakkam Junction,Chennai
A case study on Rajkillpakkam Junction,ChennaiA case study on Rajkillpakkam Junction,Chennai
A case study on Rajkillpakkam Junction,Chennai
 
legal aspects of navi mumbai international airport
legal aspects  of navi mumbai international airportlegal aspects  of navi mumbai international airport
legal aspects of navi mumbai international airport
 
Environmental impact assessment case study
Environmental impact assessment case studyEnvironmental impact assessment case study
Environmental impact assessment case study
 
Urban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla MubarakpurUrban Villages of Delhi: Case study Kotla Mubarakpur
Urban Villages of Delhi: Case study Kotla Mubarakpur
 
Road development projects.
Road development projects.Road development projects.
Road development projects.
 
Development control regulations kochi report
Development control regulations kochi reportDevelopment control regulations kochi report
Development control regulations kochi report
 
Review of Mumbai Metropolitan regional development plan
Review of Mumbai Metropolitan regional development planReview of Mumbai Metropolitan regional development plan
Review of Mumbai Metropolitan regional development plan
 
Mumbai and the mmr (rajiv misra)
Mumbai and the mmr (rajiv misra)Mumbai and the mmr (rajiv misra)
Mumbai and the mmr (rajiv misra)
 
Lavasa, india's first planned hill city
Lavasa, india's first planned hill cityLavasa, india's first planned hill city
Lavasa, india's first planned hill city
 
Tcpo
TcpoTcpo
Tcpo
 

Andere mochten auch

Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Mitesh Gupta
 
Navi Mumbai Project management
Navi Mumbai Project management  Navi Mumbai Project management
Navi Mumbai Project management Prateek Nigam
 
EIA thermal power plant
EIA thermal power plantEIA thermal power plant
EIA thermal power plantvandana bharti
 
Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)Sarah Shuchi
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Designsrinivas2036
 
Collaboration with the Future: An infrastructure for Art+Technology at the Sa...
Collaboration with the Future: An infrastructure for Art+Technology at the Sa...Collaboration with the Future: An infrastructure for Art+Technology at the Sa...
Collaboration with the Future: An infrastructure for Art+Technology at the Sa...Matt Gorbet
 
Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Jayesh Kambli
 
Analysis of Mumbai - Jijamata Nagar
Analysis of Mumbai - Jijamata NagarAnalysis of Mumbai - Jijamata Nagar
Analysis of Mumbai - Jijamata NagarRuochen Yang
 
Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008Parti Djibouti
 
The Girlfriend Network Presentation Mayshree Bhim - Copy
The Girlfriend Network Presentation Mayshree Bhim - CopyThe Girlfriend Network Presentation Mayshree Bhim - Copy
The Girlfriend Network Presentation Mayshree Bhim - CopyMayshree Bhim
 
Otay cross border xpress slideshow
Otay cross border xpress slideshowOtay cross border xpress slideshow
Otay cross border xpress slideshowStantec
 

Andere mochten auch (20)

Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
Chhatrapati Shivaji International Airport, Mumbai - Terminal 2
 
Navi Mumbai Project management
Navi Mumbai Project management  Navi Mumbai Project management
Navi Mumbai Project management
 
EIA thermal power plant
EIA thermal power plantEIA thermal power plant
EIA thermal power plant
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
harish pawar
harish pawarharish pawar
harish pawar
 
Top investments destination in mumbai mmr jan-jun15
Top investments destination in mumbai mmr  jan-jun15Top investments destination in mumbai mmr  jan-jun15
Top investments destination in mumbai mmr jan-jun15
 
EIA repot for Airport
EIA repot for AirportEIA repot for Airport
EIA repot for Airport
 
Collaboration with the Future: An infrastructure for Art+Technology at the Sa...
Collaboration with the Future: An infrastructure for Art+Technology at the Sa...Collaboration with the Future: An infrastructure for Art+Technology at the Sa...
Collaboration with the Future: An infrastructure for Art+Technology at the Sa...
 
Floating airport
Floating airportFloating airport
Floating airport
 
Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)Mthl( Mumbai Transe Harbour link)
Mthl( Mumbai Transe Harbour link)
 
Analysis of Mumbai - Jijamata Nagar
Analysis of Mumbai - Jijamata NagarAnalysis of Mumbai - Jijamata Nagar
Analysis of Mumbai - Jijamata Nagar
 
Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008Djibouti lake assal salt_project_eia_report_nov 2008
Djibouti lake assal salt_project_eia_report_nov 2008
 
Ryan khargar, navi mumbai
Ryan khargar, navi mumbaiRyan khargar, navi mumbai
Ryan khargar, navi mumbai
 
EIA-Final-Report (1)
EIA-Final-Report (1)EIA-Final-Report (1)
EIA-Final-Report (1)
 
The Girlfriend Network Presentation Mayshree Bhim - Copy
The Girlfriend Network Presentation Mayshree Bhim - CopyThe Girlfriend Network Presentation Mayshree Bhim - Copy
The Girlfriend Network Presentation Mayshree Bhim - Copy
 
Otay cross border xpress slideshow
Otay cross border xpress slideshowOtay cross border xpress slideshow
Otay cross border xpress slideshow
 

Ähnlich wie Eia Of Navi Mumbai International Airport (Nmia

Navi Mumbai International Airport.pptx
Navi Mumbai International Airport.pptxNavi Mumbai International Airport.pptx
Navi Mumbai International Airport.pptxSaurabh Patil
 
EIA Tool for Evaluating Pre & Post Impacts of Development Projects
EIA Tool for Evaluating Pre & Post Impacts of Development ProjectsEIA Tool for Evaluating Pre & Post Impacts of Development Projects
EIA Tool for Evaluating Pre & Post Impacts of Development ProjectsOsada Vishvajith
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureKANTHARAJAN GANESAN
 
IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...
IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...
IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...IRJET Journal
 
Law presentation
Law presentationLaw presentation
Law presentationRachit Shiv
 
Enbe future town
Enbe future townEnbe future town
Enbe future towndhirazain
 
Presentation-on-Water-Transport-System
Presentation-on-Water-Transport-SystemPresentation-on-Water-Transport-System
Presentation-on-Water-Transport-SystemMahjabeen Rahman Mim
 
Kicc presentation development of port of lamu manda bay 3
Kicc presentation development of port of lamu manda bay 3Kicc presentation development of port of lamu manda bay 3
Kicc presentation development of port of lamu manda bay 3Parti Djibouti
 
Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...
Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...
Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...Shahadat Hossain Shakil
 
Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010zubeditufail
 
Incheon international airport
Incheon international airportIncheon international airport
Incheon international airportNatsuko Iwashita
 
Architectural Framework For The Development Of Boat Terminals
Architectural Framework For The Development Of Boat TerminalsArchitectural Framework For The Development Of Boat Terminals
Architectural Framework For The Development Of Boat TerminalsSara Perez
 
EIA Report on Ring road lahore
EIA Report on Ring road lahoreEIA Report on Ring road lahore
EIA Report on Ring road lahoreAyesha Akhtar
 
INFRASTRUCTURE IN FARIDABAD
INFRASTRUCTURE IN FARIDABADINFRASTRUCTURE IN FARIDABAD
INFRASTRUCTURE IN FARIDABADGagan Tanwar
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspectszubeditufail
 
River Edge Development: A case of West Zone, Surat City
River Edge Development: A case of West Zone, Surat CityRiver Edge Development: A case of West Zone, Surat City
River Edge Development: A case of West Zone, Surat CityIRJET Journal
 
Environmental Carrying Capacity Assessment of Industrial Growth Center Region
Environmental Carrying Capacity Assessment of Industrial Growth Center RegionEnvironmental Carrying Capacity Assessment of Industrial Growth Center Region
Environmental Carrying Capacity Assessment of Industrial Growth Center RegionDahlan Tampubolon
 
Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...
Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...
Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...MILLA MENGA
 

Ähnlich wie Eia Of Navi Mumbai International Airport (Nmia (20)

Navi Mumbai International Airport.pptx
Navi Mumbai International Airport.pptxNavi Mumbai International Airport.pptx
Navi Mumbai International Airport.pptx
 
EIA Tool for Evaluating Pre & Post Impacts of Development Projects
EIA Tool for Evaluating Pre & Post Impacts of Development ProjectsEIA Tool for Evaluating Pre & Post Impacts of Development Projects
EIA Tool for Evaluating Pre & Post Impacts of Development Projects
 
EIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & AquacultureEIA an introduction - Case study wrt Coastal development & Aquaculture
EIA an introduction - Case study wrt Coastal development & Aquaculture
 
IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...
IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...
IRJET- Environmental Impact Assessment on River Jhelum for Inland Water Trans...
 
Law presentation
Law presentationLaw presentation
Law presentation
 
Enbe future town
Enbe future townEnbe future town
Enbe future town
 
Presentation-on-Water-Transport-System
Presentation-on-Water-Transport-SystemPresentation-on-Water-Transport-System
Presentation-on-Water-Transport-System
 
Inland water transport kochi
Inland water transport kochiInland water transport kochi
Inland water transport kochi
 
Kicc presentation development of port of lamu manda bay 3
Kicc presentation development of port of lamu manda bay 3Kicc presentation development of port of lamu manda bay 3
Kicc presentation development of port of lamu manda bay 3
 
Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...
Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...
Sustainable City Design: Developing Conceptual Planning Proposal for Eastern ...
 
Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010Zorlu pakistan eia april 2010
Zorlu pakistan eia april 2010
 
report
reportreport
report
 
Incheon international airport
Incheon international airportIncheon international airport
Incheon international airport
 
Architectural Framework For The Development Of Boat Terminals
Architectural Framework For The Development Of Boat TerminalsArchitectural Framework For The Development Of Boat Terminals
Architectural Framework For The Development Of Boat Terminals
 
EIA Report on Ring road lahore
EIA Report on Ring road lahoreEIA Report on Ring road lahore
EIA Report on Ring road lahore
 
INFRASTRUCTURE IN FARIDABAD
INFRASTRUCTURE IN FARIDABADINFRASTRUCTURE IN FARIDABAD
INFRASTRUCTURE IN FARIDABAD
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspects
 
River Edge Development: A case of West Zone, Surat City
River Edge Development: A case of West Zone, Surat CityRiver Edge Development: A case of West Zone, Surat City
River Edge Development: A case of West Zone, Surat City
 
Environmental Carrying Capacity Assessment of Industrial Growth Center Region
Environmental Carrying Capacity Assessment of Industrial Growth Center RegionEnvironmental Carrying Capacity Assessment of Industrial Growth Center Region
Environmental Carrying Capacity Assessment of Industrial Growth Center Region
 
Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...
Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...
Ministry of transport 2nd transport and economic corridor-lapsset by p.s dr c...
 

Mehr von Ketan Wadodkar

Heavy Metal Precipitation In Uasb
Heavy Metal Precipitation In UasbHeavy Metal Precipitation In Uasb
Heavy Metal Precipitation In UasbKetan Wadodkar
 
Air Pollution Episodes And Disasters
Air Pollution Episodes And DisastersAir Pollution Episodes And Disasters
Air Pollution Episodes And DisastersKetan Wadodkar
 
Land Use And Regulation
Land Use And RegulationLand Use And Regulation
Land Use And RegulationKetan Wadodkar
 
E Waste And Management
E Waste And ManagementE Waste And Management
E Waste And ManagementKetan Wadodkar
 
Hydrothermal Treatment Of Solid Waste
Hydrothermal Treatment Of Solid WasteHydrothermal Treatment Of Solid Waste
Hydrothermal Treatment Of Solid WasteKetan Wadodkar
 
Airpollution Dispersion And Modelling Using Computers Ub Chitranshi
Airpollution Dispersion And Modelling Using Computers  Ub ChitranshiAirpollution Dispersion And Modelling Using Computers  Ub Chitranshi
Airpollution Dispersion And Modelling Using Computers Ub ChitranshiKetan Wadodkar
 

Mehr von Ketan Wadodkar (11)

E waste management
E waste managementE waste management
E waste management
 
Vedangi ppt
Vedangi pptVedangi ppt
Vedangi ppt
 
Ppt on fab mbbr
Ppt on fab mbbrPpt on fab mbbr
Ppt on fab mbbr
 
Ketan seminar ppt
Ketan seminar pptKetan seminar ppt
Ketan seminar ppt
 
Grbmp
GrbmpGrbmp
Grbmp
 
Heavy Metal Precipitation In Uasb
Heavy Metal Precipitation In UasbHeavy Metal Precipitation In Uasb
Heavy Metal Precipitation In Uasb
 
Air Pollution Episodes And Disasters
Air Pollution Episodes And DisastersAir Pollution Episodes And Disasters
Air Pollution Episodes And Disasters
 
Land Use And Regulation
Land Use And RegulationLand Use And Regulation
Land Use And Regulation
 
E Waste And Management
E Waste And ManagementE Waste And Management
E Waste And Management
 
Hydrothermal Treatment Of Solid Waste
Hydrothermal Treatment Of Solid WasteHydrothermal Treatment Of Solid Waste
Hydrothermal Treatment Of Solid Waste
 
Airpollution Dispersion And Modelling Using Computers Ub Chitranshi
Airpollution Dispersion And Modelling Using Computers  Ub ChitranshiAirpollution Dispersion And Modelling Using Computers  Ub Chitranshi
Airpollution Dispersion And Modelling Using Computers Ub Chitranshi
 

Eia Of Navi Mumbai International Airport (Nmia

  • 1. EIA OF NAVI MUMBAI INTERNATIONAL AIRPORT (NMIA) By : KetanWadodkar M. Tech. 1st Year Environment Engineering Enrollment No.: 10519013 4/27/2011 1
  • 2.
  • 10. Need of NMIA project?
  • 11.
  • 16.
  • 18. Need Of NMIA Project?
  • 19. General Understanding About The Project4/27/2011 3
  • 20. Mumbai 4/27/2011 4 Mumbai developed by British and nurtured by Local Mumbaikars. Earlier comprised of 7 isle now a metro city Financial capital of the country Busiest and 1 of the rapidly growing city in world.
  • 21. Navi Mumbai Navi Mumbai is being developed as a counter magnet to the main city to achieve the goal of de-congestion of Mumbai CIDCO developed a new town Navi Mumbai of area 344 sq. km. Its Asias largest planned and developed city for population 2 million and 0.8 million jobs. high-tech Jawaharlal Nehru Port (JNPT) catering to International Container Cargo traffic at Nhava-Sheva is located on the southern side of the city. 4/27/2011 5
  • 22.
  • 23. Mumbai airport at Santacruz is the busiest airport in the country and handles approx. 23% of total passengers, 31% of Cargo traffic and 18% of aircraft movement in the country.
  • 24. The airport can handle 40 MPPA which is expected to reach by 2012-13.
  • 25.
  • 26.
  • 30. Analysis of alternative sites The following sites were considered and analysed : Mahapan in Sindhudurg District Rewas-Mandwa in Raigad District Navi Mumbai (Panvel) 4/27/2011 9
  • 31. Mahapan in Sindhudurg District: The site is approximately 350 km. away from Mumbai and would take about 8-10 hours by road to reach the site. It is not considered for site for international airport Rewas-Mandwa: Site is about 120 kms away from Mumbai airport. This will result a travel time of around 3hrs which exceeds the international norms or travel time to airport i.e. 1.5hrs. The site is abutting Dharamatar creek. 2 parallel runways are planned. The availability of various infrastructure reqd. for the development of airport are absent at the site. A trans-harbour link from Sewri-Nhava is proposed to be constructed on Dharamatar creek. 4/27/2011 10
  • 32. 4/27/2011 11 Fig: Rewas-Mandwa site
  • 33. Navi Mumbai site Located near Panvel town about 45 kms from the CBD of Belapur. 2 runways are planned. Phase wise development is adopted to meet the air travel demand. The site is also proposed to be accessed from Mumbai by high-speed water transportation system abutting airport site. Considering a SWOT analysis this site was finalized for new airport. 4/27/2011 12
  • 34. Fig: Navi Mumbai Site 4/27/2011 13
  • 38. Location and Geography Located at Panveltaluka, Raigad Dist. Maharashtra. Present site is majorly CIDCO owned and remaining is private which will be acquired for airport development. SH54, NH4B, AamraMarg (Running on the Boundary of Airport site). Panvel creek, Gadhi river, Taloja river and Ulwe river running along and through the boundary of the airport. Ulwe hill – RL 82 Mts. within the site. Elephanta at a distance of 13 Kms. West Seismic zone :Zone-III as per IS: 1893 (Part-I) 2002. Study area falls in coastal region of Konkan area. Panvel 1.5 kms. on Central Rly./KonkanRly. Khandeshwar – 1 km. suburban Rly.. 4/27/2011 17 The study area is about 10 kms in radius around the airport site.
  • 39. Description Of Environment Study area covers the district of Thane and Panvel. Climate is hot and humid. it is included in Deccan Trap where all the balastic compositions are surrounded by large no. Of dykes. Taloja river and Kasadi river in the North, Kalundri and Gadhi river in the East and Ulwe river in the South. The physico-chemical parameters ranges value within the prescribed standard except the BOD and nutrients. A total of 58 species of birds, 46 animals, 23 aquatic animals and maximum of 198 plant were found in study area. There is no forest area in the project area. 4/27/2011 18
  • 41. Description Of Environment 50% of project area is open land, salt marshes cover another 25%, 10% under mangrove forest, rain fed agriculture occupies 7% area rest is man-made things in the project area. Open land: hilly terrain extending NW and is towards the SW end of the proposed runway. Salt marshes: more common in the Eastern region of the site of proposed airport than in the west. Used for Prawn culture and are also man made. No life as anaerobic condition prevails. Mangroves: Avicennia marina more dominant species found here. Agricultural Land: rain fed agriculture in mansoon else barren land. Brick making also observed. 4/27/2011 20
  • 42.
  • 45. Socio-economic Status Of Study Area: Total population under the study area is about 5.68 lakhs based on 2001 census consisting of urban as 4.8 lakhs and rest rural. For urban area: Average built-up area - 45 Sq.m. Ownership household – 74%. Rental accommodation – 22%. Employer’s accommodation – 4%. Occupation- Professional 40%, Business or Industry owners 18%, skilled workers 21%, unskilled workers 9% & Clerks & typist 12%. Working population - total 32%, Males-89%, Female-11%. Average monthly income is Rs.12,700/- Infrastructure facilities - 82% of the population are satisfied with the physical and social infrastructure available in the urban area. 4/27/2011 25
  • 46. For rural area: Occupation- Fishermen 2%, Farmers 5%, Broker/Real Esate Agent/Businessmen 18%, Supervisor/skilled workers 13%, unskilled workers 21% & others 41% Income – Average monthly income is Rs.5499/- All the villages, falling within the NMIA project area, have asphalted approach road. All 10 settlements have primary school and 2 settlements have secondary school. 4/27/2011 26
  • 47. Description Of Environment Study area includes places of historical importance such as: The Elephanta Caves. Karnala Bird Sanctuary. Matheran Eco-sensitive Zone. 4/27/2011 27
  • 48. Project Activites Project area s about 2054 Ha. Airport zone is about 1615 Ha. Consisting of 1200 Ha. For aeronautical activity and 415 Ha. For non- aeronautical activity. Remaining area is there for utility services. 4/27/2011 28
  • 49. Project activities involves: Development of Airport in four phases Training of Gadhi river Diversion of Ulve river Shifting of EHT Lines Development of off-airport site (non-aeronautical area) Approach roads, railways, interchanges, water transport service to airport zone in the vicinity and far Re-settlement and Rehabilitation Development of various Utilities in the airport zone 4/27/2011 29
  • 50.
  • 51. sewage treatment plant based on the SBR technology will treat aeronautical area will have 15 MLD capacity and non-aeronautical area 30 MLD installed capacity.
  • 52. The solid waste generated to the tune of 10 tones/day initially and finally 40 tones/day will be treated at plant at Chaal, Taloja.
  • 53.
  • 55. Positive Impacts Project will facilitate the fast movement of man and materials, thereby fostering trade and commerce. support employment generation, CM outlined that around 1lakh direct jobs and around 4lakh indirect jobs due to this project. Pressure on other airport at Santacruz will be eased. offer increased accessibility, which in turn fuels the tourism sector which causes more money flows into the local economy. raising the standard of living of the people in the region. provides a thrust to the GDP of the local region, having a positively impact on the national economy. it will handle 60 million passengers/year which is much smaller than the international standard of 100 million passengers/year so there is always possibilities of expansion. 4/27/2011 32
  • 56. Negative Impacts Impacts are identified considering 4 stages: NMIA location NMIA project design NMIA construction phase NMIA operation phase 4/27/2011 33
  • 57. Impacts due to NMIA Location Removal of Mangroves & Biodiversity: With the project intervention, A total of 161.50 ha of mangroves (though in degraded form) will be lost due to the project. Tree clearance: There is no forest in the project site area, though there are naturally growing trees/plants/vegetation in the area. This project will result in loss of all vegetation in the project site. Roads and infrastruture: two impacts namely the over concretizationand diversion of agricultural land leading to issues of land use change and food security. Though the surface soil is being stripped off for brick making. Water ways connectivity: stress on the surrounding marine ecosystem and fishing. Rehabilitation: Ten settlements approx 15000 people will be affected due to the project. 4/27/2011 34
  • 58. Impacts due to NMIA Project Design Training of Gadhi River: Channelization leads to altering of original dimensions of the rivers along with extreme physical disturbances, alterations in river bed morphology, change in flow characteristics and elimination of bank cover. The impacts of channelization on the aquatic community mainly arise due to channel excavation, dredging, clearing and removal of vegetation. Siltation affects aquatic vegetation by increasing the turbidity of water. loss and reduction in the number of organisms. Diversion of Ulwe River: he impacts of diversion is similar to that ‘ Training of Gadhi river” 4/27/2011 35
  • 60. Hill Cutting (Quarrying / Blasting): Generation of heavy quantity of dust which raises the SPM levels in the vicinity. noise levels also will increase occasionally. Reclamation of marshy lands: the rise in the water levels will be slightly over 1.5 m river training would take place on existing land cover. studies indicate marginal rise in the water levels in the Panvel creek reach along the proposed airport boundary. 4/27/2011 37
  • 61. Impact Due To Construction Phase Employment, Migration and Settlement: stress in the area surrounding the project in terms of water requirement, power, increased ecological footprint, increased requirement for health and educational facilities and changes in the land use pattern and local culture. Siting of construction camp for construction: stress on the local ecological resources Leveling of site: leveling process would lead to an intense / heavy quantity of dust which would raises the SPM levels in the vicinity. the noise levels would be high due to the machinery used for leveling. Safety of Workers Construction Activity 4/27/2011 38
  • 63. Impacts during Operation Phase of NMIA Operation of airport: two major impacts include that of air emissions and noise. Surface Traffic: air quality is affected Noise also is affected Employment, Migration & Settlement: 4/27/2011 40
  • 66. Air sector Appropriate dust suppression measures will be implemented within the project site. Use of asbestos will be prohibited. Background air quality of all transport corridors will be maintained by reducing idling time and control on emissions. Aerobridges would be used for passenger transportation 4/27/2011 43
  • 67. Biodiversity and Forests CIDCO has planned to take up approx 350 Ha. of plantation of mangroves against the 161.50 Ha. Loss. The channelization activities are designed to keep flow characteristics as close to the original natural flow. compensatory vegetation and plantation programme will be undertaken within the airport area contamination of estuarine body would occur mostly during the construction phase due to resuspension of sediments or dust from construction site, both of which are temporary. There was no wildlife, observed during the field survey. 4/27/2011 44
  • 68. Ecosystem and Land Impact of dredging and channelization can be reduced by proper routing of alignment to maintain a proper flow. The proposed project activity does not involve clearing of any forest areas The proposed site and the study area do not include any migratory route of animals. he excavated material/construction debris would be used for land development of marshy land in the project site area. The project area lies in Deccan trap composed of hard massive basalt rock and will not initiate any instability problems – landslide/subsidence etc The predicted water levels at different locations with and without the proposed airport are practically same. And as stated earlier STP and landfill sites are available in near by area to treat waste generated from the airport. 4/27/2011 45
  • 69. Disaster management plan Natural Disasters: earthquake flood storms/cyclone cloud burst/lightning/extreme weather conditions Fire Terror Attack, Plane Hijack, Sabotage A highly equiped airport is developed to counter all the calamities and disasters. Aircraft Accident Related Disasters: aircraft accident at airport aircraft accident off airport Hazardous material emergency, hydrocarbon spills (ATF) followed by vapour dispersion and pool fire fire 4/27/2011 46
  • 70. Conclusion The project is necessary and should be given a nod. Development is necessary, but development along with environment is acceptable. So adopt sustainable development. Human imagination is touching sky, sky is part of environment so better preserve for imagination hence future. Go green. 4/27/2011 47
  • 71. Refrence Google Wikipedia Maharashtra pollution control board CIDCO CESE, IIT Bombay LBG-INECO-RITES Consortium, USA Central Water and Power Research Station (CWPRS), Pune Ground water Survey & Development Agency (GSDA), Govt. of Maharashtra. 4/27/2011 48