3.0 PROJECT DESIGN ANALYSIS
3.1 SWOT Analysis
STRENGTH
The site was located in the heart of the city and faing the main axis of Putrajaya, The Boule-
vard. It was a location where most of the activities happening here. Hence, it also consist the
highest vehicular and pedestrian circulation among the Putrajaya. The site was located
beside the Palace of Justice, one of the well known landmarks. Therefore, it will bringing
constant visitor for site seeing.
OPPORTUNITY
WEAKNESS
The strongest weakness of the site is lack of shading which will make the visitors quickly pass
through the site. Besides, the site was surround by the bulky and enclosed commercial and
govermental building which lack of activities happen. The tall court house beside the site
might block the vision of visitor to notice the site.
THREAT
Due to the site facing the main road, the smoke of vehicles will lead to air pollution to site.
The site was exposed to sun since the building beside just covered partial of site.
3.2 Pestle Analysis
Political Factor
Economical Factor
Sociological Factor
Technological Factor
Legal Factor
Environmental Factor
By following the buiding requirement implemented by Perbadanan Putra-
jaya, the requirement such as 3 meter of green perimeter for free standing
building, 6 meter setback from the sides , vertical control, LRT reserve,green
building design, OKU needs and etc, are imposed into the building design.
The flat and open site allows the proposed building to maximize its exposure
to sun and wind coverage. The boulevard infront of the site contain green
landscape which have little coverage to the site. To ensure the commercial
entertainment activities do not create noise problem and the waste water
Putrajaya now planned as a garden and intelligent city, they are trying to
promote paper-less system among different department and company.Hence,
putrajaya located along the Multimedia super corridor path where it acco-
modate underground fibre cable to achieve high internet connection speed.
Putrajaya now accommodates most of the ministries and the government ser-
vants.It was Malaysia's biggest project with estimated final cost of US 8.1
billion dollars. The host of activities in Putrajaya as an administrative capi-
tal includes governing the nation, hosting international conferences and
events. Other major activities for the public include agro bazaars, religious
activities, hosting festivals and special sporting events. The various parks are
meant for recreational, research and educational activities. The events gave
many job oppotunities to locals expand their business to visitors.
`
As a city planned and built virtually overnight of just over 20 years, Putrajaya is replicated
based on a northern city model, and arguably not appropriated to the local environmental
and cultural conditions. Putrajaya had strong islamic identity due to government are trying
to promote malaysia has strong islamic background to international. Precinct 3 planned as
a civic and cultural precinct,it has to create commercial area that contributes to a liely and
safe environment.Hence, the area is surround by the massive government building and was
monitored by the Perbandaran Putrajaya..
As of 2015, the population of putrajaya were recorded be roughly 88300
people where malayu took 97% of the population. Through different events
from different organisation,such as Hot Air Balloon Events dy, Lampu and
etc. This brought many opportunities for people to socialize with others
Many facilities nearby the site which provide opportunity for the location to become a cen-
tral node. The location also has a great potential to become a public community space since
there is no public space around the site in the range of 5 km. Hence, the future railway system
will bring in the crowd to our site.
2.0 PROGRAMME VIABILITY
2.1 Proposed Programme
2.2 Project Objectives
2.3 Target User & Programme Relevance
2.4 Client & Stakeholders
CENTRE OF DEMOCRACY
When political theorist discuss public space, they generally refer the print
and digital media as the representative for democracy, this is contrast to the
olden civilization where public spaces such as the forum and debating cham-
ber played a significant role in determine the idea of democracy, the shift
from physical to virtual has taken place for a number of reasons. This is due
to scale and complexity of our society, as our civilization evolves and grew
larger, it is impossible for everyone to gather and argue in a physical forum,
furthermore with the invention of print media and the beginning of digital
age, physical forum has taken a backseat and sadly it remained architectur-
ally stagnant in term of design.
The centre accommodate a sequence of varied, liberal spaces interconnect-
ing larger institutional and domestic spaces. Suspended above the settle-
ment is a protective tensile membrane which respond to varying environ-
mental conditions as well as social ones.The centre was constructed around
various practical, environmental, political, and symbolic constituents,
mainly model the site into an democracy hub that sustains the act of protest
through institutional and domestic facilities.
Public Community
Bersih Commitee Member
Political Parties:Authorities:Organisation:
Bersih Steering Commitee
Aliran Kesedaran Negara
Bar Council
Tenaga Nasional(TNB)
Syarikat Bekalan Air
Selangor Sdn.Bhd
Perbandaran Putrajaya
People’s Justice Party
Pan-Malaysian Islamic Party
Democratic Action Party
The target user group are the Bersih movement
supporter and the commitee members.The centre will
provide the legal advice and support for the supporter.
Hence, the centre will also conduct workshop and
classroom to promote the awareness of democracy.
The community from public and the nearby building
are one of the target user for the building. In the
centre, it provides the public space for people to
engage and communicate. Beside, the programme will
promote the freedom of expression and speech.
There are few project objectives to focused in order to achieve client’s goal.
The main criteria where this project have to be completed in time, so the
construction schedule must be well planned and ensure every stage were not
delayed .Then, the second goal for the project is managed according to the
project constrained : time,quality, scope and Budget. This project is a com-
munity project, the budget is crucial for the project. Successful negotiation
with supplier and contractor can help client to keeping budget according to
their affordability. Another criteria is the flexibility,the project is being flexi-
ble to facing any difficuties and accidents.Back up plan must be ready from
any aspect. Last but not least, to ensure the project to be success,thesupport
and cooperation from every different field is essential. So, the project can be
complete effectively and to be perfect.
4.0 DESIGN SUITABILITY
4.1 Design Process 4.2 Spatial Planning
SPACE REQUIREMENT
Basement Floor:
1. Underground Subway
Ground FLoor:
1.Drop-off Area
2.Foyer
3.Registration
4.Merchandise shop
5.Press Conference Area
6.Justice Exhibition
7.Cafeteria
8.Citizen Living
9.Selling Stall
10.Services
1st Floor:
1. Debating Chamber
2. Bersih Office
3. Legal Aids
4. First Aids
5. Interactive Classroom
6. Freedom Platform
7. Services
2nd FLoor:
1. Library
2. Accommondation
3. Viewing Deck
Plot Area: 5,140 sqm
Plot GFA: 25,789.60 sqm
Plot Ratio: 5.02
PersiaranPerdana
NORTH
Palace of Justice
Menara Prisma
Jabatan Alam Sekitar
Jalan Kemerdekaan
Private
Semi Private
Public
Spatial Hierarchy
The ground level of the centre house a cafe, Public Conference Area where people can
access freely without authorisation and constraints. The first level, where Bersih office
and Legal aids area where users can access with request and some authorisation
approved. Then, the second level is the floor where the library and accommondation
locared. These spaces require quiet and privacy.
A
A
B
B
UP
DN
UP
UP
Context Relation
The site of the centre is
located on the parking lot
facing the Boulevard anf
adjacent to Palace of
Justice. The space in the
centre is design according
to people, community and
democracy. Hence, its
allow public to access
seamless inside the build-
ing to achieve the idealogy
od democracy.
Axonometric
Public
Community
Democracy
Programme Relation
It is no secret that the Malaysian mainstream
media fails to practice proportionate, fair
and objective reporting for political parties
of all divide. It calls on the EC to press for
all media agencies, especially state-funded
media agencies such as Radio and Televi-
sion Malaysia (RTM) and Bernama to allo-
cate proportionate and objective coverage
for all potlical parties.This centre provides a
lot of platform for people to giving out their
idea and thought.Based on the local context
which promote a paperless city. This
approach can attract the crowd to gather to
learn in the process of recycling stuff and
how to wisely turn their recycle material into
an installation art and profit rather than
useless thing.
5.0 MAINTENANCE STRATEGY 6.0 SUCCESS CRITERIA
Maintanance Strategy ( Programme)
Element Frequency Maintenance Factor
Maintanance Strategy (Building & Site)
Element Frequency Maintenance Factor
Debating chamber daily
Library
Bersih Office
Accommondation
Workshops
Classroom
Children activity
weekly
weekly
weekly
Daily
Daily
Daily
Cleanliness of the stage flooring and audience seating needs to kept
clean to avoid accidents for the next use.
Arrangement of books and cleanliness of the bookshelves should be
managed due to the constant flow of users.
Vacuuming and cleaning of the office is needed to avoid bad building condition.
Bedrooms to be maintained and cleaned for new users everyday
Area need to be clean to ensure the well hygiene of the space to avoid children get sick.
To ensure sufficient furnitures are provided for users and maintain furniture if needed.
To ensure the cleanliness of space and sufficient equipments.
Elevators Monthly
Cafeteria
Flooring
Tensile Fabric
landscaping
Daily
Monthly
Daily
Elevators used for carrying the loads and OKU to go up and down stairs.Hence,it should
be checked and serviced once a month to ensure safety.
Cafeteria is one of the main income of the center so it should give the visitors a sense of
well maintain and in good condition.
Daily cleaning of floor to prevent any dirty components from sticking to the ground and
maintained to ensure user’s health.
Trimming and cutting of overgrown tree or grass to preserve the cleanliness of the
landscape.
To ensure the fabric structure maintains its fresh and vibrant appeal, increasing the
structures operational lifespan.
Yearly
TIME
1) To hold Client-Consultant Meeting(CCM) weekly to ensure the
ongoing of project with minimal disruption.
2) Internal meetings between consultants to solve construction issues
until the end of project.
3)Use of Gannt Chart throughout the construction to ensure tasks to
be completed on time.
4)Determine the critical path and the float of tasks using the pert
chart to calculate the shortest time needed for project completion.
5)The project should be completed within a period of 12 months while
ensuring the good quality of works.
COST
QUALITY
1) Proper building construction in conjunction with the materials
used.
2) Proper safety equipment installed during the construction of the
building.
3)Building to have spatial quality for occupants to have a good user
experience.
1) Completed within budget.
2) Minimal change of materials to reduce materials wastage.
3)Costs of materials to be calculated accurately by Quantity Survey-
ors.
4)The cost of project should benefit the client in long term investment.
Time
CostScope
Quality
7.0 RISK ANALYSIS
DESIGN STAGE RISK AND MITIGATION
RISK LIKELIHOOD SEVERITY COST IMPACT STRATEGY CONTINGENCY
Design not up to satisfaction.
Misunderstanding with client
and consultants.
Building plans not approved
by authority.
Medium
Low
Medium
Medium
High
High
Low
High
High
Project delayed
from innitiation
Delay in project
Design process
procrastinated
Negotiate with
consultants for
better design
Fullfill authority
and building
guidelines.
Hold client-consul-
tant meeting weekly.
Compromise with consultants to prevent further
delay.
Redesign under the guidelines and submit for
approval.
Ensure an agreement was done before ending the
meeting and record meeting detail in meeting
minutes.
CONSTRUCTION STAGE RISK AND MITIGATION
RISK LIKELIHOOD SEVERITY COST IMPACT STRATEGY CONTINGENCY
Suppliers quoting over
budget.
Change in consultant due to
misunderstanding and poor
working efficiency.
On site accidents due to
faulty or improper safety
Medium
High
Low Medium
High
High
Low
High
High
Construction
materials needed
to be replaced.
Construction
facing legal
Construction
process delayed.
Negotiate with
suppliers to sign a
contract with a fixed
Rececive claims from
insurance company
and compensate the
Prevent having
conflicts during
meetings.
prepare enough budget pool to move on with
construction.
Replace all safety equipments and increase the
equioment checking numbers.
Come in good terms with all consultants.
MAINTENANCE AND OPERATION STAGE RISK AND MITIGRATION
RISK LIKELIHOOD SEVERITY COST IMPACT STRATEGY CONTINGENCY
Lack of visitor
theft and robbery case.
Fire incidents.
Low
Low
Low
Medium Medium
High
High High
High
programme failed
to sustain itself.
Damage and
destruction of
property
Tools and exhibi-
tion desplays
Use of promotion
and advertising to
draw in visitors.
Equip building with fire
safety requirement and fire
rated precaution equipments.
Install security
measures and hire
security guards.
Promote the benefits of the programme to
the community.
Claim loss from fire insurance.
Claim insurance to cover
1.2 Site Introduction
The site is located at Presint 3 in Putrajaya, Selangor. Putrajaya are now accommodates most of the
ministries and the government servants. Planned as a garden and intelligent city, 38% of the area is
reserved for green spaces. As indicated in the figure ground diagram, the buildings are quite spread
out with large swathes of green and water bodies in between.The site was facing toward the boulevard
and located beside the Palace of Justice which is house two courts: The federal court , the highest
court of Malaysia and Court of appeal. A monorail reserve cuts through the site into two portions,
which it’s now absorbed as part of the site.The current site was treated as a carpark area where the
goverment servant and workers from nearby building can park their transport.
NORTH
Palace of Justice
Menara Prisma
PersiaranPerdana
Jabatan Alam Sekitar
Jalan Kemerdekaan
1.0 INTRODUCTION
1.1 Introduction of Project
In this project, the proposed programme is to increase the public awareness and par-
ticipation in the movement of democracy.The proposed site is located beside the
Palace of justice.The centre for democracy was a constructed space for exploring
and expressing democracy ideologies via legitimate and progressive means, and
developing strategies to counteract modes of suppression by law enforcement and
government.Conceived with direct help from ‘BERSIH’ organisation, the project
developed from the growing numbers of people and organisations who fight for the
right to protest against undemocratic ideals.
1.3 Client and Client Brief
The BERSIH 2.0 Steering Committee
The original Committee comprises members from the political parties, as well as repre-
sentatives from thefollowing NGOs: Suara Rakyat Malaysia (Suaram), Women’s Devel-
opment Collective (WDC) and Writers Alliance for Media Independence (WAMI).The
Coalition for Clean and Fair Elections (better known by its Bahasa Malaysia name
“BERSIH”) issued its first joint communiqué on 23 November 2006.
At its formation, BERSIH comprised civil society organisations and political parties with
the objective of campaigning for clean and fair elections in Malaysia. BERSIH’s journey
thus far has been both monumental and memorable. Almost 3 ½ years later, the aims of
BERSIH remain relevant. The time came for BERSIH to continue its crusade for clean
and fair elections independent of any political party. BERSIH was thus re-launched as
BERSIH 2.0, a coalition of like-minded civil society organisations unaffiliated to any
political party. Our aim is to effectively monitor both sides of the political divide.
The Organization Chart of BERSIH 2.0 Steering Comitee
CONTENT
1.0 Introduction
1.1 Introduction of Project
1.2 Site introduction
1.2 Client & Client Brief
2.0 Programme viability
2.1 Proposed Programme
2.2 Project Objectives
2.3 Client & Skateholder
2.4 Target User & Programme Relevances
3.0 Project Design Analysis
3.1 SWOT Analysis
3.2 Pestel Analysis
4.0 Design Sutainability
4.1 Space Planning
4.2 Key Features
5.0 Maintenance Strategy
5.1 Maintenance Strategy Table
6.0 Success Criteria
7.0 Risk Analysis
8.0 Work Breakdown Structure
9.0 Construction Schedule
8.0 WORK BREAKDOWN STRUCTURE(WBS)
Center for Democracy
Note:
The diagram above is known as a Work Breakdown Structure which is a toll used for breaking
down a project into smaller and easily manageable components. A decomposition of a project
into smaller components that can effectively estimated and supervised during on-site construc-
tion phase.
1.General Condition
2.Site Grading
3.Foundation
4.Framing
5.Wall & Opening
6.Services
7.Finishes
8.Exterior Works
9.Final Works
-Apply Permit
-Clear & Grub Lot
-Install Electrical
& Underground
Utilities
-Soil Investigation &
Analysis
-Excavate for Foundation
-Formwork of Foundation
-Rebars Placement &
Concrete Pouring
-Backfill Foundation &
Compact Earth
-Ground Floor Slab & Structure
-First Floor Slab & Structure
-Second Floor Slab & Structure
-Roof
-Ground Floor
-First Floor
-Second Floor
-Elelctrical & Lighting
-Passenger & Service Lift
-Plumbing & Sanitary
-Mechanical Ventilation
-Fire Fighting System
-Plastering
-Flooring Works
-Painting
-Piping & Drain
-Road & Pavement
-Landscaping
-Testing & Commissioning
-Site Cleaning
-Inspection & Hand Over
9.0 CONSTRUCTION SCHEDULE

Weitere ähnliche Inhalte

Andere mochten auch

UX, ethnography and possibilities: for Libraries, Museums and Archives
UX, ethnography and possibilities: for Libraries, Museums and ArchivesUX, ethnography and possibilities: for Libraries, Museums and Archives
UX, ethnography and possibilities: for Libraries, Museums and ArchivesNed Potter
 
Hype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerHype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerLuminary Labs
 
Designing Teams for Emerging Challenges
Designing Teams for Emerging ChallengesDesigning Teams for Emerging Challenges
Designing Teams for Emerging ChallengesAaron Irizarry
 
Bscience report
Bscience reportBscience report
Bscience reportkerneng
 
Visual Design with Data
Visual Design with DataVisual Design with Data
Visual Design with DataSeth Familian
 
3 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 20173 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 2017Drift
 
Merged document
Merged documentMerged document
Merged documentkerneng
 
Final site analysis board
Final site analysis boardFinal site analysis board
Final site analysis boardkerneng
 
B Science Report Project 2
B Science Report Project 2B Science Report Project 2
B Science Report Project 2J-Sern Phua
 
How to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your NicheHow to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your NicheLeslie Samuel
 
Edchewgroup
EdchewgroupEdchewgroup
EdchewgroupWm Chia
 
PUTRAJAYA SITE ANALSYS - TEAM CY
PUTRAJAYA SITE ANALSYS - TEAM CYPUTRAJAYA SITE ANALSYS - TEAM CY
PUTRAJAYA SITE ANALSYS - TEAM CYPreston Liew
 
Bscience board
Bscience boardBscience board
Bscience boardkerneng
 
Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya Hilmi Awaludin
 
Menara PjH Handout
Menara PjH HandoutMenara PjH Handout
Menara PjH Handoutaadzla
 
Lot 2C2 Building Science Report
Lot 2C2 Building Science ReportLot 2C2 Building Science Report
Lot 2C2 Building Science ReportXingYue0907
 
Theorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreTheorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreDexter Ng
 

Andere mochten auch (18)

UX, ethnography and possibilities: for Libraries, Museums and Archives
UX, ethnography and possibilities: for Libraries, Museums and ArchivesUX, ethnography and possibilities: for Libraries, Museums and Archives
UX, ethnography and possibilities: for Libraries, Museums and Archives
 
Hype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerHype vs. Reality: The AI Explainer
Hype vs. Reality: The AI Explainer
 
Designing Teams for Emerging Challenges
Designing Teams for Emerging ChallengesDesigning Teams for Emerging Challenges
Designing Teams for Emerging Challenges
 
Bscience report
Bscience reportBscience report
Bscience report
 
btech 2
btech 2btech 2
btech 2
 
Visual Design with Data
Visual Design with DataVisual Design with Data
Visual Design with Data
 
3 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 20173 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 2017
 
Merged document
Merged documentMerged document
Merged document
 
Final site analysis board
Final site analysis boardFinal site analysis board
Final site analysis board
 
B Science Report Project 2
B Science Report Project 2B Science Report Project 2
B Science Report Project 2
 
How to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your NicheHow to Become a Thought Leader in Your Niche
How to Become a Thought Leader in Your Niche
 
Edchewgroup
EdchewgroupEdchewgroup
Edchewgroup
 
PUTRAJAYA SITE ANALSYS - TEAM CY
PUTRAJAYA SITE ANALSYS - TEAM CYPUTRAJAYA SITE ANALSYS - TEAM CY
PUTRAJAYA SITE ANALSYS - TEAM CY
 
Bscience board
Bscience boardBscience board
Bscience board
 
Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya
 
Menara PjH Handout
Menara PjH HandoutMenara PjH Handout
Menara PjH Handout
 
Lot 2C2 Building Science Report
Lot 2C2 Building Science ReportLot 2C2 Building Science Report
Lot 2C2 Building Science Report
 
Theorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreTheorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention Centre
 

Ähnlich wie Centre for Democracy Hub

PROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORTPROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORTAdibah Awang
 
Project management (3)
Project management (3)Project management (3)
Project management (3)Benjamin Tan
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Reportzerospaces_
 
Project Management Documentation: Medium-Sized Project
Project Management Documentation: Medium-Sized ProjectProject Management Documentation: Medium-Sized Project
Project Management Documentation: Medium-Sized ProjectJoe Onn Lim
 
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT jolynnTJL
 
Project management final - KSHV SZ
Project management final - KSHV SZProject management final - KSHV SZ
Project management final - KSHV SZKeshav Seewraz
 
Architectural Comprehensive Design Report
Architectural Comprehensive Design ReportArchitectural Comprehensive Design Report
Architectural Comprehensive Design ReportLimSiewNi
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management ReportCarmen Chan
 
Project management
Project management Project management
Project management Jing Fan Koh
 
Tul_Srisompun_resume and portfolio_
Tul_Srisompun_resume and portfolio_Tul_Srisompun_resume and portfolio_
Tul_Srisompun_resume and portfolio_Tul Srisompun
 

Ähnlich wie Centre for Democracy Hub (20)

PROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORTPROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORT
 
Project management (3)
Project management (3)Project management (3)
Project management (3)
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Report
 
Project Management Documentation: Medium-Sized Project
Project Management Documentation: Medium-Sized ProjectProject Management Documentation: Medium-Sized Project
Project Management Documentation: Medium-Sized Project
 
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
BSC (H) IN ARCHITECTURE DEGREE SEM 6 PROJECT MANAGEMENT FINAL REPORT
 
10 rules for smart city success
10 rules for smart city success10 rules for smart city success
10 rules for smart city success
 
Project management final - KSHV SZ
Project management final - KSHV SZProject management final - KSHV SZ
Project management final - KSHV SZ
 
Architectural Comprehensive Design Report
Architectural Comprehensive Design ReportArchitectural Comprehensive Design Report
Architectural Comprehensive Design Report
 
Final Project Management Report
Final Project Management ReportFinal Project Management Report
Final Project Management Report
 
Project management
Project management Project management
Project management
 
Input soliciting v2
Input soliciting v2Input soliciting v2
Input soliciting v2
 
Tul_Srisompun_resume and portfolio_
Tul_Srisompun_resume and portfolio_Tul_Srisompun_resume and portfolio_
Tul_Srisompun_resume and portfolio_
 
M
MM
M
 
Smart school
Smart schoolSmart school
Smart school
 
Smart school
Smart schoolSmart school
Smart school
 
M
MM
M
 
Smart school
Smart schoolSmart school
Smart school
 
Smart school
Smart schoolSmart school
Smart school
 
Smart school
Smart schoolSmart school
Smart school
 
Smart school
Smart schoolSmart school
Smart school
 

Mehr von kerneng

Project management networking
Project management networkingProject management networking
Project management networkingkerneng
 
Final bscience report compilation
Final bscience report compilationFinal bscience report compilation
Final bscience report compilationkerneng
 
C1 (3 files merged)
C1 (3 files merged)C1 (3 files merged)
C1 (3 files merged)kerneng
 
Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)kerneng
 
Plan 1 (6 files merged)
Plan 1 (6 files merged)Plan 1 (6 files merged)
Plan 1 (6 files merged)kerneng
 
E1 (3 files merged)
E1 (3 files merged)E1 (3 files merged)
E1 (3 files merged)kerneng
 
Ph 4 (9 files merged)
Ph 4 (9 files merged)Ph 4 (9 files merged)
Ph 4 (9 files merged)kerneng
 
I1 (4 files merged)
I1 (4 files merged)I1 (4 files merged)
I1 (4 files merged)kerneng
 
1 (4 files merged) (1)
1 (4 files merged) (1)1 (4 files merged) (1)
1 (4 files merged) (1)kerneng
 
Theory project-2-analytical-paper
Theory project-2-analytical-paperTheory project-2-analytical-paper
Theory project-2-analytical-paperkerneng
 
5 elements-kerneng
5 elements-kerneng5 elements-kerneng
5 elements-kernengkerneng
 
R1 (5 files merged)
R1 (5 files merged)R1 (5 files merged)
R1 (5 files merged)kerneng
 
2 (4 files merged)
2 (4 files merged)2 (4 files merged)
2 (4 files merged)kerneng
 
1 (5 files merged)
1 (5 files merged)1 (5 files merged)
1 (5 files merged)kerneng
 
Merged document
Merged documentMerged document
Merged documentkerneng
 

Mehr von kerneng (20)

Project management networking
Project management networkingProject management networking
Project management networking
 
Btech
BtechBtech
Btech
 
Images
ImagesImages
Images
 
Final bscience report compilation
Final bscience report compilationFinal bscience report compilation
Final bscience report compilation
 
C1 (3 files merged)
C1 (3 files merged)C1 (3 files merged)
C1 (3 files merged)
 
Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)
 
Plan 1 (6 files merged)
Plan 1 (6 files merged)Plan 1 (6 files merged)
Plan 1 (6 files merged)
 
E1 (3 files merged)
E1 (3 files merged)E1 (3 files merged)
E1 (3 files merged)
 
Ph 4 (9 files merged)
Ph 4 (9 files merged)Ph 4 (9 files merged)
Ph 4 (9 files merged)
 
I1 (4 files merged)
I1 (4 files merged)I1 (4 files merged)
I1 (4 files merged)
 
1 (4 files merged) (1)
1 (4 files merged) (1)1 (4 files merged) (1)
1 (4 files merged) (1)
 
Theory project-2-analytical-paper
Theory project-2-analytical-paperTheory project-2-analytical-paper
Theory project-2-analytical-paper
 
5 elements-kerneng
5 elements-kerneng5 elements-kerneng
5 elements-kerneng
 
R1 (5 files merged)
R1 (5 files merged)R1 (5 files merged)
R1 (5 files merged)
 
2 (4 files merged)
2 (4 files merged)2 (4 files merged)
2 (4 files merged)
 
1 (5 files merged)
1 (5 files merged)1 (5 files merged)
1 (5 files merged)
 
Merged document
Merged documentMerged document
Merged document
 
Window
WindowWindow
Window
 
Door
DoorDoor
Door
 
Uwip
UwipUwip
Uwip
 

Kürzlich hochgeladen

Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degreeyuu sss
 
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree ttt fff
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一Fi sss
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfAayushChavan5
 
How to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIHow to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIyuj
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,Aginakm1
 
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一A SSS
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degreeyuu sss
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfSumit Lathwal
 
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degreeyuu sss
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptMaryamAfzal41
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 

Kürzlich hochgeladen (20)

Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdf
 
How to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIHow to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AI
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
 
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdf
 
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
2024新版美国旧金山州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis ppt
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
 

Centre for Democracy Hub

  • 1. SCHOOL OF ARCHITECTURE,BUILDING & DESIGN PROJECT MANAGEMENT (ARC 3612/ARC3614) PROJECT 2 : PROJECT MANAGEMENT IN ARCHITECTURAL DESIGN PROJECT NAME : PEH KER NENG ID : 0314619 TUTOR : Ar SATEERAH MARKS FOR 3 COMPONENT: 1.___/10 2. ___/10 3.___/10 TOTAL : ___/30
  • 2. 3.0 PROJECT DESIGN ANALYSIS 3.1 SWOT Analysis STRENGTH The site was located in the heart of the city and faing the main axis of Putrajaya, The Boule- vard. It was a location where most of the activities happening here. Hence, it also consist the highest vehicular and pedestrian circulation among the Putrajaya. The site was located beside the Palace of Justice, one of the well known landmarks. Therefore, it will bringing constant visitor for site seeing. OPPORTUNITY WEAKNESS The strongest weakness of the site is lack of shading which will make the visitors quickly pass through the site. Besides, the site was surround by the bulky and enclosed commercial and govermental building which lack of activities happen. The tall court house beside the site might block the vision of visitor to notice the site. THREAT Due to the site facing the main road, the smoke of vehicles will lead to air pollution to site. The site was exposed to sun since the building beside just covered partial of site. 3.2 Pestle Analysis Political Factor Economical Factor Sociological Factor Technological Factor Legal Factor Environmental Factor By following the buiding requirement implemented by Perbadanan Putra- jaya, the requirement such as 3 meter of green perimeter for free standing building, 6 meter setback from the sides , vertical control, LRT reserve,green building design, OKU needs and etc, are imposed into the building design. The flat and open site allows the proposed building to maximize its exposure to sun and wind coverage. The boulevard infront of the site contain green landscape which have little coverage to the site. To ensure the commercial entertainment activities do not create noise problem and the waste water Putrajaya now planned as a garden and intelligent city, they are trying to promote paper-less system among different department and company.Hence, putrajaya located along the Multimedia super corridor path where it acco- modate underground fibre cable to achieve high internet connection speed. Putrajaya now accommodates most of the ministries and the government ser- vants.It was Malaysia's biggest project with estimated final cost of US 8.1 billion dollars. The host of activities in Putrajaya as an administrative capi- tal includes governing the nation, hosting international conferences and events. Other major activities for the public include agro bazaars, religious activities, hosting festivals and special sporting events. The various parks are meant for recreational, research and educational activities. The events gave many job oppotunities to locals expand their business to visitors. ` As a city planned and built virtually overnight of just over 20 years, Putrajaya is replicated based on a northern city model, and arguably not appropriated to the local environmental and cultural conditions. Putrajaya had strong islamic identity due to government are trying to promote malaysia has strong islamic background to international. Precinct 3 planned as a civic and cultural precinct,it has to create commercial area that contributes to a liely and safe environment.Hence, the area is surround by the massive government building and was monitored by the Perbandaran Putrajaya.. As of 2015, the population of putrajaya were recorded be roughly 88300 people where malayu took 97% of the population. Through different events from different organisation,such as Hot Air Balloon Events dy, Lampu and etc. This brought many opportunities for people to socialize with others Many facilities nearby the site which provide opportunity for the location to become a cen- tral node. The location also has a great potential to become a public community space since there is no public space around the site in the range of 5 km. Hence, the future railway system will bring in the crowd to our site.
  • 3. 2.0 PROGRAMME VIABILITY 2.1 Proposed Programme 2.2 Project Objectives 2.3 Target User & Programme Relevance 2.4 Client & Stakeholders CENTRE OF DEMOCRACY When political theorist discuss public space, they generally refer the print and digital media as the representative for democracy, this is contrast to the olden civilization where public spaces such as the forum and debating cham- ber played a significant role in determine the idea of democracy, the shift from physical to virtual has taken place for a number of reasons. This is due to scale and complexity of our society, as our civilization evolves and grew larger, it is impossible for everyone to gather and argue in a physical forum, furthermore with the invention of print media and the beginning of digital age, physical forum has taken a backseat and sadly it remained architectur- ally stagnant in term of design. The centre accommodate a sequence of varied, liberal spaces interconnect- ing larger institutional and domestic spaces. Suspended above the settle- ment is a protective tensile membrane which respond to varying environ- mental conditions as well as social ones.The centre was constructed around various practical, environmental, political, and symbolic constituents, mainly model the site into an democracy hub that sustains the act of protest through institutional and domestic facilities. Public Community Bersih Commitee Member Political Parties:Authorities:Organisation: Bersih Steering Commitee Aliran Kesedaran Negara Bar Council Tenaga Nasional(TNB) Syarikat Bekalan Air Selangor Sdn.Bhd Perbandaran Putrajaya People’s Justice Party Pan-Malaysian Islamic Party Democratic Action Party The target user group are the Bersih movement supporter and the commitee members.The centre will provide the legal advice and support for the supporter. Hence, the centre will also conduct workshop and classroom to promote the awareness of democracy. The community from public and the nearby building are one of the target user for the building. In the centre, it provides the public space for people to engage and communicate. Beside, the programme will promote the freedom of expression and speech. There are few project objectives to focused in order to achieve client’s goal. The main criteria where this project have to be completed in time, so the construction schedule must be well planned and ensure every stage were not delayed .Then, the second goal for the project is managed according to the project constrained : time,quality, scope and Budget. This project is a com- munity project, the budget is crucial for the project. Successful negotiation with supplier and contractor can help client to keeping budget according to their affordability. Another criteria is the flexibility,the project is being flexi- ble to facing any difficuties and accidents.Back up plan must be ready from any aspect. Last but not least, to ensure the project to be success,thesupport and cooperation from every different field is essential. So, the project can be complete effectively and to be perfect.
  • 4. 4.0 DESIGN SUITABILITY 4.1 Design Process 4.2 Spatial Planning SPACE REQUIREMENT Basement Floor: 1. Underground Subway Ground FLoor: 1.Drop-off Area 2.Foyer 3.Registration 4.Merchandise shop 5.Press Conference Area 6.Justice Exhibition 7.Cafeteria 8.Citizen Living 9.Selling Stall 10.Services 1st Floor: 1. Debating Chamber 2. Bersih Office 3. Legal Aids 4. First Aids 5. Interactive Classroom 6. Freedom Platform 7. Services 2nd FLoor: 1. Library 2. Accommondation 3. Viewing Deck Plot Area: 5,140 sqm Plot GFA: 25,789.60 sqm Plot Ratio: 5.02 PersiaranPerdana NORTH Palace of Justice Menara Prisma Jabatan Alam Sekitar Jalan Kemerdekaan Private Semi Private Public Spatial Hierarchy The ground level of the centre house a cafe, Public Conference Area where people can access freely without authorisation and constraints. The first level, where Bersih office and Legal aids area where users can access with request and some authorisation approved. Then, the second level is the floor where the library and accommondation locared. These spaces require quiet and privacy. A A B B UP DN UP UP Context Relation The site of the centre is located on the parking lot facing the Boulevard anf adjacent to Palace of Justice. The space in the centre is design according to people, community and democracy. Hence, its allow public to access seamless inside the build- ing to achieve the idealogy od democracy. Axonometric Public Community Democracy Programme Relation It is no secret that the Malaysian mainstream media fails to practice proportionate, fair and objective reporting for political parties of all divide. It calls on the EC to press for all media agencies, especially state-funded media agencies such as Radio and Televi- sion Malaysia (RTM) and Bernama to allo- cate proportionate and objective coverage for all potlical parties.This centre provides a lot of platform for people to giving out their idea and thought.Based on the local context which promote a paperless city. This approach can attract the crowd to gather to learn in the process of recycling stuff and how to wisely turn their recycle material into an installation art and profit rather than useless thing.
  • 5. 5.0 MAINTENANCE STRATEGY 6.0 SUCCESS CRITERIA Maintanance Strategy ( Programme) Element Frequency Maintenance Factor Maintanance Strategy (Building & Site) Element Frequency Maintenance Factor Debating chamber daily Library Bersih Office Accommondation Workshops Classroom Children activity weekly weekly weekly Daily Daily Daily Cleanliness of the stage flooring and audience seating needs to kept clean to avoid accidents for the next use. Arrangement of books and cleanliness of the bookshelves should be managed due to the constant flow of users. Vacuuming and cleaning of the office is needed to avoid bad building condition. Bedrooms to be maintained and cleaned for new users everyday Area need to be clean to ensure the well hygiene of the space to avoid children get sick. To ensure sufficient furnitures are provided for users and maintain furniture if needed. To ensure the cleanliness of space and sufficient equipments. Elevators Monthly Cafeteria Flooring Tensile Fabric landscaping Daily Monthly Daily Elevators used for carrying the loads and OKU to go up and down stairs.Hence,it should be checked and serviced once a month to ensure safety. Cafeteria is one of the main income of the center so it should give the visitors a sense of well maintain and in good condition. Daily cleaning of floor to prevent any dirty components from sticking to the ground and maintained to ensure user’s health. Trimming and cutting of overgrown tree or grass to preserve the cleanliness of the landscape. To ensure the fabric structure maintains its fresh and vibrant appeal, increasing the structures operational lifespan. Yearly TIME 1) To hold Client-Consultant Meeting(CCM) weekly to ensure the ongoing of project with minimal disruption. 2) Internal meetings between consultants to solve construction issues until the end of project. 3)Use of Gannt Chart throughout the construction to ensure tasks to be completed on time. 4)Determine the critical path and the float of tasks using the pert chart to calculate the shortest time needed for project completion. 5)The project should be completed within a period of 12 months while ensuring the good quality of works. COST QUALITY 1) Proper building construction in conjunction with the materials used. 2) Proper safety equipment installed during the construction of the building. 3)Building to have spatial quality for occupants to have a good user experience. 1) Completed within budget. 2) Minimal change of materials to reduce materials wastage. 3)Costs of materials to be calculated accurately by Quantity Survey- ors. 4)The cost of project should benefit the client in long term investment. Time CostScope Quality
  • 6. 7.0 RISK ANALYSIS DESIGN STAGE RISK AND MITIGATION RISK LIKELIHOOD SEVERITY COST IMPACT STRATEGY CONTINGENCY Design not up to satisfaction. Misunderstanding with client and consultants. Building plans not approved by authority. Medium Low Medium Medium High High Low High High Project delayed from innitiation Delay in project Design process procrastinated Negotiate with consultants for better design Fullfill authority and building guidelines. Hold client-consul- tant meeting weekly. Compromise with consultants to prevent further delay. Redesign under the guidelines and submit for approval. Ensure an agreement was done before ending the meeting and record meeting detail in meeting minutes. CONSTRUCTION STAGE RISK AND MITIGATION RISK LIKELIHOOD SEVERITY COST IMPACT STRATEGY CONTINGENCY Suppliers quoting over budget. Change in consultant due to misunderstanding and poor working efficiency. On site accidents due to faulty or improper safety Medium High Low Medium High High Low High High Construction materials needed to be replaced. Construction facing legal Construction process delayed. Negotiate with suppliers to sign a contract with a fixed Rececive claims from insurance company and compensate the Prevent having conflicts during meetings. prepare enough budget pool to move on with construction. Replace all safety equipments and increase the equioment checking numbers. Come in good terms with all consultants. MAINTENANCE AND OPERATION STAGE RISK AND MITIGRATION RISK LIKELIHOOD SEVERITY COST IMPACT STRATEGY CONTINGENCY Lack of visitor theft and robbery case. Fire incidents. Low Low Low Medium Medium High High High High programme failed to sustain itself. Damage and destruction of property Tools and exhibi- tion desplays Use of promotion and advertising to draw in visitors. Equip building with fire safety requirement and fire rated precaution equipments. Install security measures and hire security guards. Promote the benefits of the programme to the community. Claim loss from fire insurance. Claim insurance to cover
  • 7. 1.2 Site Introduction The site is located at Presint 3 in Putrajaya, Selangor. Putrajaya are now accommodates most of the ministries and the government servants. Planned as a garden and intelligent city, 38% of the area is reserved for green spaces. As indicated in the figure ground diagram, the buildings are quite spread out with large swathes of green and water bodies in between.The site was facing toward the boulevard and located beside the Palace of Justice which is house two courts: The federal court , the highest court of Malaysia and Court of appeal. A monorail reserve cuts through the site into two portions, which it’s now absorbed as part of the site.The current site was treated as a carpark area where the goverment servant and workers from nearby building can park their transport. NORTH Palace of Justice Menara Prisma PersiaranPerdana Jabatan Alam Sekitar Jalan Kemerdekaan 1.0 INTRODUCTION 1.1 Introduction of Project In this project, the proposed programme is to increase the public awareness and par- ticipation in the movement of democracy.The proposed site is located beside the Palace of justice.The centre for democracy was a constructed space for exploring and expressing democracy ideologies via legitimate and progressive means, and developing strategies to counteract modes of suppression by law enforcement and government.Conceived with direct help from ‘BERSIH’ organisation, the project developed from the growing numbers of people and organisations who fight for the right to protest against undemocratic ideals. 1.3 Client and Client Brief The BERSIH 2.0 Steering Committee The original Committee comprises members from the political parties, as well as repre- sentatives from thefollowing NGOs: Suara Rakyat Malaysia (Suaram), Women’s Devel- opment Collective (WDC) and Writers Alliance for Media Independence (WAMI).The Coalition for Clean and Fair Elections (better known by its Bahasa Malaysia name “BERSIH”) issued its first joint communiqué on 23 November 2006. At its formation, BERSIH comprised civil society organisations and political parties with the objective of campaigning for clean and fair elections in Malaysia. BERSIH’s journey thus far has been both monumental and memorable. Almost 3 ½ years later, the aims of BERSIH remain relevant. The time came for BERSIH to continue its crusade for clean and fair elections independent of any political party. BERSIH was thus re-launched as BERSIH 2.0, a coalition of like-minded civil society organisations unaffiliated to any political party. Our aim is to effectively monitor both sides of the political divide. The Organization Chart of BERSIH 2.0 Steering Comitee
  • 8. CONTENT 1.0 Introduction 1.1 Introduction of Project 1.2 Site introduction 1.2 Client & Client Brief 2.0 Programme viability 2.1 Proposed Programme 2.2 Project Objectives 2.3 Client & Skateholder 2.4 Target User & Programme Relevances 3.0 Project Design Analysis 3.1 SWOT Analysis 3.2 Pestel Analysis 4.0 Design Sutainability 4.1 Space Planning 4.2 Key Features 5.0 Maintenance Strategy 5.1 Maintenance Strategy Table 6.0 Success Criteria 7.0 Risk Analysis 8.0 Work Breakdown Structure 9.0 Construction Schedule
  • 9. 8.0 WORK BREAKDOWN STRUCTURE(WBS) Center for Democracy Note: The diagram above is known as a Work Breakdown Structure which is a toll used for breaking down a project into smaller and easily manageable components. A decomposition of a project into smaller components that can effectively estimated and supervised during on-site construc- tion phase. 1.General Condition 2.Site Grading 3.Foundation 4.Framing 5.Wall & Opening 6.Services 7.Finishes 8.Exterior Works 9.Final Works -Apply Permit -Clear & Grub Lot -Install Electrical & Underground Utilities -Soil Investigation & Analysis -Excavate for Foundation -Formwork of Foundation -Rebars Placement & Concrete Pouring -Backfill Foundation & Compact Earth -Ground Floor Slab & Structure -First Floor Slab & Structure -Second Floor Slab & Structure -Roof -Ground Floor -First Floor -Second Floor -Elelctrical & Lighting -Passenger & Service Lift -Plumbing & Sanitary -Mechanical Ventilation -Fire Fighting System -Plastering -Flooring Works -Painting -Piping & Drain -Road & Pavement -Landscaping -Testing & Commissioning -Site Cleaning -Inspection & Hand Over