Flow Process chart
Presented By:
Submitted To:
Dr. Awadesh Bhardwaj,
Mech. Engg. Deptt.,
MNIT,Jaipur
Dated: 11-sept-2013

•
•
•
•
•
•

Kapil jain
abhimanyu meena
Shubhender Singh
Mohit vats
Rajender kumar
Areesha Nafees

2013pie5199
2013pie5071
2013pie5244
2013pie5090
2013pie5122
2013pie5141

M.Tech (IE),Mech. Engg. Deptt.,
MNIT,Jaipur
What is the
purpose
of a flow chart?
• It is a picture of a process
• It is drawn with symbols

representing different types
of activities
• It defines the system
being studied.
• It documents changes to
the process.
Why are flow
charts useful?
• They provide a visual for

students to see steps in a process.
• They can be used as an
assessment to check for
student understanding.
• They can help organize classrooms
and minimize transition times.
Flow Diagram
Definition
 A flow diagram is a graphical means of presenting,

describing, or analyzing a process & movement of
material, men etc.
 This is done with the help of all five symbols which
represent steps in a chain of steps.
 These all symbols are connected to other one by lines and
arrows which represent sequence and dependency
relationships (i.e., X must be done before Y can be done).
Objectives Of Flow Diagram
 The flow charts indicates the sequence of events they do

not show the movement of men, material etc but the
path of movement can be better visualized by a flow
diagram.
 Flow diagram is drawn to scale.
 It shows the relative position of machines, jigs, fixture,
gangway etc and mark the paths followed by men and
material.
 Distances between two location is indicated in flow
diagram.
Steps in drawing a Flow Diagram
 Draw to scale the plan of the work area.
 Mark the relative position of machine tools, benches,

store, racks, inspection tables etc.
 From the different observations, draw the actual
movement of the material or worker on the diagram.
 Indicate the direction of movement.
 Mark the distances between consequence two locations.
CHARTS AND DIAGRAMS
USED IN METHOD STUDY
Following chart are used in method study :(1) OPC - Outline process chart
(2) FPC - Flow process chart
Man type
Material type
Equipment type
(3) Two handed process chart
(4) Multiple activity chart like man and machine chart
(5) SIMO chart
The following diagram are also used in method study.
(1) Flow diagram
(2) String diagram
(3) Cycle graph
(4) Cronocycle diagram
(5) Travel diagram
FLOW PROCESS CHART
FLOW PROCESS CHART
 When the overall idea of the process has been established it is

possible to go into greater details. Flow process chart can be
defined as a graphical presentation of all operations,
inspections, delays and storages occurring during a process or
procedure which includes information considered necessary
for analysis like time required, quantity and distance moved
etc.
TYPES OF FLOW PROCESS
CHART


Man type

-



Material type
material.

- It records what happens to the



Equipment type

- It records how the equipment is used.

It records what the worker does.
Flow Process Charts
A flow process chart is a chart of all the activities

involved in a process.
It is similar to an operations process chart, except that
more detail is shown by including transportations and
delays as well as operations, inspections, and storages.
Not usually used for entire assemblies, it is used for
just one component (or operator)
Add in information on:
 Operation duration (time to complete)
 Distance traveled (for transport operations)

Good for showing savings of a new method.
Flow Process Charts (Cont.)
Process charts summarizes the whole process
They are used to compare the existing and the
proposed methods
Process is observed, who, what, where, when, and

how questions are asked
Every detail is understood and the chart of the
existing situation is drawn
1.Operation

Process Chart Symbols

Indicates the main steps in a process, method or procedure.
Usually the part, material or product concerned is modified or
changed during the operation.

2.Inspection
Indicates an inspection for quality and / or check for quantity

3.Transport
Indicates the movement of workers, materials or equipment from place
to place
4.Temporary Storage or Delay
Indicates a delay in the sequence of events : for example, work waiting
between consecutive operations, or any object laid aside temporarily without
record until required.

5.Permanent Storage
Indicates a controlled storage in which material is received into or issued
from a store under some form of authorization; or an item is retained for
reference purposes.

6.Combined Activities
Indicates a controlled storage in which material is received into or issued
from a store under some form of authorization; or an item is retained for
reference purposes.
Record- Symbols
Operation (Make ready, Do, Put away)
Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Symbols
Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Symbols
Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Symbols
Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Symbols
Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
EXAMPLES
OF
FLOW PROCESS CHART
Before and After Comparison Flow Chart
Example
Typist has to take dictation from the author’s office. He
has to type the letter, copy the letter and get letters
attested by the author. He has to prepare the envelope
and put these letters in the envelope. Finally place the
letter and copy aside the tray. Author’s office is 20 feet
away from typist office.
Example
Author’s office

20 ft.
You

November 18, 2013

Lab # 6: Method Study

25
Record- Example
Flow Chart

Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Example
Flow Chart

Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Example
Flow Chart

Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Record- Example
Flow Chart

Select
Record
Examine
Develop
Evaluate
Define
Install
Maintain
Flow process chart
Information shown in a flow process chart :(1) Type of the flow process chart.
(2) Information of the person producing the part
(3) Information , place ,time & name of operator for
whom the product or process is prepared.
(4) Different stages and their involved in the process.
(5) Transport activity , its various stages and distance
travelled in it
(6) Different stages of delay ,storage and inspection
(7) Summary information of activities
References
 K.Narasimhan, “Handbook of Industrial Engineering: Technology and






Operations Management 3rd edition” Volume: 14 Issue: 6 2002.
RALPH M. BARNES , “MOTION AND TIME STUDY DESIGN AND
MEASUREMENT OF WORK” (7th EDITION)
Mahajan M.S., “Industrial management” 3rd Edition, 2008, Dhanpat Rai & Co.
(p) Ltd.
Khanna O.P., “Work Study (Time & motion Study),Reprint : 2003, Dhanpat Rai
& Co. (p) Ltd.
http://www.sil.org/lingualinks/literacy/ReferenceMaterials/glossaryofliteracyt
erms/WhatIsAFlowDiagram.htm
Flow process chart

More Related Content

What's hot

8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)sundar sivam
 
Recording techniques in method study
Recording techniques in method studyRecording techniques in method study
Recording techniques in method studyChandresh Suthar
 
Process flow and process chart
Process flow and process chartProcess flow and process chart
Process flow and process chartParvesh Mittal
 
Functions of production planning and control
Functions of production planning and controlFunctions of production planning and control
Functions of production planning and controlVignesh Jayakumar
 
travel chart for plant layout
travel chart for plant layouttravel chart for plant layout
travel chart for plant layoutYash Patel
 
Method Study
Method StudyMethod Study
Method Studyajithsrc
 
CYCLE AND CHRONOCYCLE GRAPH
CYCLE AND CHRONOCYCLE GRAPHCYCLE AND CHRONOCYCLE GRAPH
CYCLE AND CHRONOCYCLE GRAPHParth K dhanak
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurementEr. Vaibhav Agarwal
 
Production planning control ppt
Production planning control pptProduction planning control ppt
Production planning control pptsudhir pawar
 
Chronocycle graph
Chronocycle graphChronocycle graph
Chronocycle graphBinoy Benny
 
Work Study
Work StudyWork Study
Work Studyvishakeb
 
method study- micromotion vs memo motion
method study- micromotion vs memo motionmethod study- micromotion vs memo motion
method study- micromotion vs memo motionpranav teli
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancingRohit Goutam
 

What's hot (20)

8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
 
Recording techniques in method study
Recording techniques in method studyRecording techniques in method study
Recording techniques in method study
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
 
Line balancing
Line balancingLine balancing
Line balancing
 
Process flow and process chart
Process flow and process chartProcess flow and process chart
Process flow and process chart
 
Method study
Method studyMethod study
Method study
 
Functions of production planning and control
Functions of production planning and controlFunctions of production planning and control
Functions of production planning and control
 
travel chart for plant layout
travel chart for plant layouttravel chart for plant layout
travel chart for plant layout
 
Line balancing
Line balancingLine balancing
Line balancing
 
Work study
Work studyWork study
Work study
 
Method Study
Method StudyMethod Study
Method Study
 
CYCLE AND CHRONOCYCLE GRAPH
CYCLE AND CHRONOCYCLE GRAPHCYCLE AND CHRONOCYCLE GRAPH
CYCLE AND CHRONOCYCLE GRAPH
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurement
 
Assembly Line Production Introduction
Assembly Line Production   IntroductionAssembly Line Production   Introduction
Assembly Line Production Introduction
 
Production planning control ppt
Production planning control pptProduction planning control ppt
Production planning control ppt
 
Chronocycle graph
Chronocycle graphChronocycle graph
Chronocycle graph
 
Work Study
Work StudyWork Study
Work Study
 
method study- micromotion vs memo motion
method study- micromotion vs memo motionmethod study- micromotion vs memo motion
method study- micromotion vs memo motion
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 

Similar to Flow process chart

Similar to Flow process chart (20)

02 Method Study part_2.pdf
02 Method Study part_2.pdf02 Method Study part_2.pdf
02 Method Study part_2.pdf
 
Mareeswaran
MareeswaranMareeswaran
Mareeswaran
 
PRODUCTION PLANNING AND CONTROL-WORK STUDY
PRODUCTION  PLANNING AND CONTROL-WORK STUDYPRODUCTION  PLANNING AND CONTROL-WORK STUDY
PRODUCTION PLANNING AND CONTROL-WORK STUDY
 
Ppt on flow process chart...abhi
Ppt on flow process chart...abhiPpt on flow process chart...abhi
Ppt on flow process chart...abhi
 
Work study
Work studyWork study
Work study
 
Work study
Work studyWork study
Work study
 
Work study IEM unit v for MEs2
Work study   IEM unit v  for MEs2Work study   IEM unit v  for MEs2
Work study IEM unit v for MEs2
 
Flowchart
FlowchartFlowchart
Flowchart
 
presentation on opc and fpc
presentation on opc and fpcpresentation on opc and fpc
presentation on opc and fpc
 
Problem solving tools 112411
Problem solving tools 112411Problem solving tools 112411
Problem solving tools 112411
 
Work methods
Work methodsWork methods
Work methods
 
method Study.pptx
method Study.pptxmethod Study.pptx
method Study.pptx
 
Method study(abhishekkumar)
Method study(abhishekkumar)Method study(abhishekkumar)
Method study(abhishekkumar)
 
UNIT-II.ppt
UNIT-II.pptUNIT-II.ppt
UNIT-II.ppt
 
PPC-Unit II- WORK STUDY
PPC-Unit II- WORK STUDYPPC-Unit II- WORK STUDY
PPC-Unit II- WORK STUDY
 
Work study-150303084338-conversion-gate01
Work study-150303084338-conversion-gate01Work study-150303084338-conversion-gate01
Work study-150303084338-conversion-gate01
 
Unit 2 PPC
Unit 2 PPCUnit 2 PPC
Unit 2 PPC
 
Unit 2-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 2-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 2-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 2-IE6605 & PRODUCTION PLANNING AND CONTROL
 
Unit 2
Unit 2Unit 2
Unit 2
 
Unit 2
Unit 2Unit 2
Unit 2
 

Recently uploaded

ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Millenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxMillenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxJanEmmanBrigoli
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsRommel Regala
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 

Recently uploaded (20)

ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Millenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxMillenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptx
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World Politics
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Paradigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTAParadigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTA
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 

Flow process chart

  • 1. Flow Process chart Presented By: Submitted To: Dr. Awadesh Bhardwaj, Mech. Engg. Deptt., MNIT,Jaipur Dated: 11-sept-2013 • • • • • • Kapil jain abhimanyu meena Shubhender Singh Mohit vats Rajender kumar Areesha Nafees 2013pie5199 2013pie5071 2013pie5244 2013pie5090 2013pie5122 2013pie5141 M.Tech (IE),Mech. Engg. Deptt., MNIT,Jaipur
  • 2. What is the purpose of a flow chart? • It is a picture of a process • It is drawn with symbols representing different types of activities • It defines the system being studied. • It documents changes to the process.
  • 3. Why are flow charts useful? • They provide a visual for students to see steps in a process. • They can be used as an assessment to check for student understanding. • They can help organize classrooms and minimize transition times.
  • 4. Flow Diagram Definition  A flow diagram is a graphical means of presenting, describing, or analyzing a process & movement of material, men etc.  This is done with the help of all five symbols which represent steps in a chain of steps.  These all symbols are connected to other one by lines and arrows which represent sequence and dependency relationships (i.e., X must be done before Y can be done).
  • 5. Objectives Of Flow Diagram  The flow charts indicates the sequence of events they do not show the movement of men, material etc but the path of movement can be better visualized by a flow diagram.  Flow diagram is drawn to scale.  It shows the relative position of machines, jigs, fixture, gangway etc and mark the paths followed by men and material.  Distances between two location is indicated in flow diagram.
  • 6. Steps in drawing a Flow Diagram  Draw to scale the plan of the work area.  Mark the relative position of machine tools, benches, store, racks, inspection tables etc.  From the different observations, draw the actual movement of the material or worker on the diagram.  Indicate the direction of movement.  Mark the distances between consequence two locations.
  • 7. CHARTS AND DIAGRAMS USED IN METHOD STUDY Following chart are used in method study :(1) OPC - Outline process chart (2) FPC - Flow process chart Man type Material type Equipment type (3) Two handed process chart (4) Multiple activity chart like man and machine chart (5) SIMO chart
  • 8. The following diagram are also used in method study. (1) Flow diagram (2) String diagram (3) Cycle graph (4) Cronocycle diagram (5) Travel diagram
  • 10. FLOW PROCESS CHART  When the overall idea of the process has been established it is possible to go into greater details. Flow process chart can be defined as a graphical presentation of all operations, inspections, delays and storages occurring during a process or procedure which includes information considered necessary for analysis like time required, quantity and distance moved etc.
  • 11. TYPES OF FLOW PROCESS CHART  Man type -  Material type material. - It records what happens to the  Equipment type - It records how the equipment is used. It records what the worker does.
  • 12. Flow Process Charts A flow process chart is a chart of all the activities involved in a process. It is similar to an operations process chart, except that more detail is shown by including transportations and delays as well as operations, inspections, and storages. Not usually used for entire assemblies, it is used for just one component (or operator) Add in information on:  Operation duration (time to complete)  Distance traveled (for transport operations) Good for showing savings of a new method.
  • 13. Flow Process Charts (Cont.) Process charts summarizes the whole process They are used to compare the existing and the proposed methods Process is observed, who, what, where, when, and how questions are asked Every detail is understood and the chart of the existing situation is drawn
  • 14. 1.Operation Process Chart Symbols Indicates the main steps in a process, method or procedure. Usually the part, material or product concerned is modified or changed during the operation. 2.Inspection Indicates an inspection for quality and / or check for quantity 3.Transport Indicates the movement of workers, materials or equipment from place to place
  • 15. 4.Temporary Storage or Delay Indicates a delay in the sequence of events : for example, work waiting between consecutive operations, or any object laid aside temporarily without record until required. 5.Permanent Storage Indicates a controlled storage in which material is received into or issued from a store under some form of authorization; or an item is retained for reference purposes. 6.Combined Activities Indicates a controlled storage in which material is received into or issued from a store under some form of authorization; or an item is retained for reference purposes.
  • 16. Record- Symbols Operation (Make ready, Do, Put away) Select Record Examine Develop Evaluate Define Install Maintain
  • 22.
  • 23. Before and After Comparison Flow Chart
  • 24. Example Typist has to take dictation from the author’s office. He has to type the letter, copy the letter and get letters attested by the author. He has to prepare the envelope and put these letters in the envelope. Finally place the letter and copy aside the tray. Author’s office is 20 feet away from typist office.
  • 25. Example Author’s office 20 ft. You November 18, 2013 Lab # 6: Method Study 25
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 40. Information shown in a flow process chart :(1) Type of the flow process chart. (2) Information of the person producing the part (3) Information , place ,time & name of operator for whom the product or process is prepared. (4) Different stages and their involved in the process. (5) Transport activity , its various stages and distance travelled in it (6) Different stages of delay ,storage and inspection (7) Summary information of activities
  • 41. References  K.Narasimhan, “Handbook of Industrial Engineering: Technology and     Operations Management 3rd edition” Volume: 14 Issue: 6 2002. RALPH M. BARNES , “MOTION AND TIME STUDY DESIGN AND MEASUREMENT OF WORK” (7th EDITION) Mahajan M.S., “Industrial management” 3rd Edition, 2008, Dhanpat Rai & Co. (p) Ltd. Khanna O.P., “Work Study (Time & motion Study),Reprint : 2003, Dhanpat Rai & Co. (p) Ltd. http://www.sil.org/lingualinks/literacy/ReferenceMaterials/glossaryofliteracyt erms/WhatIsAFlowDiagram.htm