SlideShare ist ein Scribd-Unternehmen logo
1 von 116
Downloaden Sie, um offline zu lesen
VOLUME - I


TENDER AND CONTRACT CONDITIONS




        OCTOBER 2008
VOLUME I

                  TENDER AND CONTRACT CONDITIONS



                                                         PAGE NOS.


PART A     -   FORM OF TENDER                              A/1 - A/3


PART B     -   INSTRUCTIONS TO TENDERERS                  B/1 - B/11


PART C     -   FORM OF AGREEMENT                           C/1 - C/2


PART D     -   CONDITIONS OF CONTRACT

               GENERAL CONDITIONS                      CC/1 – CC/37

               CONDITIONS OF PARTICULAR APPLICATIONS     D/1 – D/38

PART E     -   DRAWINGS                                    E/1 - E/3

ANNEXURE   -   LETTER OF ACCEPTANCE

               MIZIN AUTHORITY REQUIREMENTS FOR
               DESIGN ERECTION OF HOARDING WALLS
PART A

FORM OF TENDER
FORM OF TENDER

                                           (The Appendix forms part of the Tender)



To:     ……………………………..
        P.O. Box ……………...…..
        ………………………….….
        ………………………….….


Dear Sir,




1.      Having examined the Instructions to Tenderers, Conditions of Contract, Drawings, Form of
        Agreement, Specifications and Bills of Quantities for the proposed Works, and having visited
        and examined the Site of the Works or caused it to be visited on our behalf by a competent and
        reliable person and having acquired all requisite information relating thereto as affecting this
        Tender, we the undersigned, hereby offer to construct, complete and maintain the whole of the
        said Works in conformity with the said Instructions to Tenderers, Conditions of Contract,
        Drawings, Form of Agreement, Specifications and Bills of Quantities for the Contract Price of




        or such other sums as may be ascertained in accordance with the said conditions.


2.      We acknowledge that the Appendix forms part of our Tender.

3.      We have priced the Bills of Quantities in detail and return them with this tender together with all
        the information requested in the Instructions to Tenderers and other Contract Documents.

4.      We confirm that we have fully taken into account the Tender Circulars and Bulletins listed below,
        copies of which are returned with our Tender.

        .......…………...........................................................................................................................

        ....................…………..............................................................................................................

        ....................…………..............................................................................................................

5.      We undertake if our Tender is accepted to commence the Works including erecting all site
        facilities required and to complete and deliver the whole of the Works comprised in the Contract
        within the time stated in the Appendix hereto. These periods include all Fridays, Public
        Holidays, etc., and other non-working days caused by inclement weather, etc., and shortened
        working hours during the Holy Month of Ramadan.
6.        If our Tender is accepted we will, when required, obtain the guarantee of a Bank (to be
          approved by you and the Employer’s Representative) to be jointly and severally bound with us in
          a sum equal to the percentage of the Contract value as defined in Clause C.10 of the Conditions
          of Contract for the due performance of the Contract. We further agree to provide this bond upon
          receipt of the Employer’s Representative order to commence the Works.

7.        In consideration of the trouble and expense incurred by you in preparing the contract and in
          examining and considering this Tender, we agree to abide by this tender for a period of 90 days
          from the date fixed for receiving the same and it shall remain binding upon us and may be
          accepted at any time before the expiration of that period.

8.        We undertake in the event of this Tender being accepted to enter into an Agreement with you in
          the form annexed hereto which may be altered and added to in such manner as you may
          require for the purpose of adapting it to the circumstances of this Tender.

9.        We understand that you are not bound to accept the lowest or any tender you may receive.

10.       We herewith provide a Tender Bond Guarantee in the sum of five percent (5%) of the Tender
          Amount.



Dated this.…........... day of .……..................................... Two Thousand and Eight



Name ……………………………………                                            (Signature.)....……...............…...............................



Acting in the capacity of ....……..........……………………………………………...................................

Duly authorized to sign Tenders for and on behalf of


Full Name of Company                  ...............................................................……………………………

Address                               .......................................................................................………….

                                      ............................................................................................……….

                                      ..................................................................................………………


Witness                               .........................................................................................…………


Address                               ............................................................................………………….


Occupation                            ............................…................................................………………..
Appendix to the Form of Tender

                                              Clause


Amount of Performance Security        10.1             5% of the Accepted Contract Amount


Minimum Amount of Third               23.2             Dhs. 5,000,000.00
Party Insurance                                        for any one occurrence, number of
                                                       Occurrences unlimited


Commencement of Works                 41.1             Date of receipt of Letter of Acceptance and
                                                       Date of the building permit


Time for Completion                   43.1             16 months with final hand over of the project
including final testing and                            including Mobilization
commissioning


Liquidated Damages for Delay          47.1             Dhs. 50,000.00 per day
                                                       limited to a total of 10% of the Contract price


Period of Maintenance                 49.1             365 days


Percentage for adjustment of
Provisional Sums                      59.4 (c)         ……… percentage to be inserted by the
                                                       Contractor


Percentage of Invoice value
of listed materials                   60.1 (c)         75%


Percentage of Retention               60.2             10%


Limit of Retention Money              60.2             10% of the Contract Price


Time within which payment to          60.10            30 days
be made after Certificate


Advance Payment                       60.11            5% of the Contract Price against Bank
                                                       Guarantee
PART B

INSTRUCTIONS TO TENDERERS
INSTRUCTIONS TO TENDERERS



One set of the following tender document is issued for tendering:

        Letter of Invitation
        Volume 1     -    Tender and Contract Conditions
        Volume 2      -   Bills of Quantities
        Volume 3      -   Civil General Specifications
        Volume 4      -   MEP Specifications
        Volume 5      -    Drawings
        Volume 6      -    Soil Investigation Reports

The following instructions should be carefully noted by intending tenderers as failure to comply with them
may lead to invalidation of the tender.


B.1              Scope of Works

B.1.1            The Works forming part of this Tender comprises the construction, completion and

                 drawings, specifications and bills of quantities contained in these tender documents.

B.1.2            The Contractor shall allow for coordinating his work with the Enabling Works Contractor
                 and any other separately employed contractors on site.



B.2              Location of Site

B.2.1            The site is located at Liwan, Dubai, U.A.E. as shown on the site plan.



B.3              Title of the Works

B.3.1            The title of the Works is: -


                    “CONSTRUCTION OF BUILDING AT LIWAN, DUBAI, U.A.E.”
B.4               Submission of Tenders

B.4.1             The tenderer shall submit three (3) copies of tender documents, the copies to be
                  marked quot;Originalquot;, 1st Copyquot; and quot;2nd Copyquot;, and one copy of tender drawings. The
                  Form of Tender shall be signed by a duly authorised representative of the Company
                  tendering and shall be stamped with the Company's stamp.

B.4.2             Each page of the tender document and tender drawings is to be stamped with the
                  Company's stamp and initialed by the duly authorised representative of the Company.

B.4.3             Tenders shall be sealed in an envelope marked only:



                  addressed and submitted at the office at the location specified in the invitation not later
                  than the time and date specified in the Letter of Invitation.


B.4.4             No alterations (other than filling the blanks intended to be filled in) shall be made in the
                  Form of Tender and other sections of the tender Document. The tender Document
                  shall be submitted intact with items in the Bills of Quantities fully priced and totaled, and
                  in United Arab Emirates Dirhams, having a unit rate or price (as applicable) affixed to
                  every item therein.

B.4.5             If any alteration is made, except as aforesaid, and if these Instructions to Tenderers are
                  not otherwise fully complied with, the tender will not be considered.

B.4.6             There shall be no overwriting and any mistakes which are corrected shall be initialed by
                  the duly authorized representative.

B.4.7             The following supporting documents must be submitted in triplicate with the tender
                  Documents.

                  (a)       A statement, signed by the Authorized Representative, stating that the tenderer
                            has visited the site and that he has no queries on any matter concerning the
                            contract.

                  (b)       A tender Bond in accordance with Clause B 18 of these Instructions to
                            Tenderers (the original plus two photocopies).


B.4.8             The tenderer shall submit with his tender proof of the Authorized Representatives
                  authority, which shall be duly certified by an authorized officer of the Government of
                  Dubai, United Arab Emirates.




NEB – Tender and Contract Conditions                     B/2                                  October 2008
B.5      Opening of Tenders

B.5.1    The tenders will be opened in private at the convenience of the Employer.

B.5.2    The Employer reserves the exclusive rights to accept or reject all or any part of the
         tender without stating any reasons. The Employer will not be responsible or pay far
         expenses or losses which may be incurred by any Tenderer for the preparation of the
         Tender.

B.6      Visiting Site

B.6.1    The Tenderer will be deemed to have visited the Site or caused it to be visited on his
         behalf by a competent and reliable person to obtain for himself on his own responsibility
         all information that may be necessary for the purpose of preparing a tender and
         entering into a contract. All costs and charges in connection with the above mentioned
         visits shall be borne by the Tenderer.

B.7      Buildings, Work yards, etc.

B.7.1    The Tenderer must examine and consider the Site and its surroundings, he must satisfy
         himself as to the nature of the existing works and buildings in the vicinity of the
         proposed Works, the nature of the existing roads or other means of communication, the
         access to and egress from the Site and Works, the available accommodation as
         regards land for temporary purposes (inside or outside the Site), the buildings that may
         be required for temporary purposes, and must make his own enquiries as to work yard
         sites and such other additional areas as he may require for temporary occupation all for
         the construction, completion and maintenance of the Works described in the Contract
         Documents.

B.8      Physical Conditions

B.8.1    The Tenderer must make local and independent examination and enquiries as to the
         physical conditions prevailing at the Site and obtain his own information on all matters
         and things that may in any way influence him in making a tender. He must also satisfy
         himself as to the risks, obligations and responsibilities to be undertaken in the Contract
         to be entered into by him should his tender be accepted.

B.9      Materials, Labour, etc.

B.9.1    The Tenderer must enquire and satisfy himself as to the source of supply, the
         sufficiency and the means of obtaining and transporting all materials, labour, fuel, water,
         electrical current for light and power and other things required for or in connection with
         the Works and he must consider all other matters and possible contingencies affecting
         the construction, completion and maintenance of the Works.


B.10     Neglect to Obtain Reliable Information

B.10.1   Any neglect or failure on the part of the Tenderer to obtain reliable information on the
         spot or elsewhere upon the foregoing or any other matters affecting the construction,
         completion and maintenance of the Works and the Contract shall not relieve the
         accepted Tenderer from any risks or liabilities or from the responsibility completing and
         handing over the Works all as defined in the Contract.
B.11     Interpretation

B.11.1   The Tenderer may request clarification or interpretation from the Employer’s
         Representative / Engineer of any aspect of the Tender Documents by facsimile or letter.
          The Employer’s Representative / Engineer's response will be made by facsimile or
         letter addressed to all Tenderers. Where such clarification or interpretation requires a
         change in the Tender Documents, the Employer’s Representative / Engineer will
         prepare and issue an addendum to the Tender Documents.

B.11.2   The Employer’s Representative / Engineer will not be bound by, and the Tenderer shall
         not rely upon, any oral interpretation or clarification of the Tender Documents.

B.11.3   Any request for clarification or interpretation should be received by the Employer’s
         Representative / Engineer not later than five days before the tender submission date.

B.11.4   If the Tenderer requires clarification or interpretation in the final five days before tender
         submission date then he shall when submitting his tender set out in a covering letter the
         interpretation on which his tender has been based.


B.12     Information Supplied Not Binding

B.12.1   Neither the Employer nor the Employer’s Representative / Engineer nor any of their
         employees has any authority to make any representation or to give any explanation to
         Tenderers as to the meaning of the tender documents, or as to anything to be done or
         not to be done by the Contractor whose tender is accepted, or as to these Instructions,
         or as to any other matter or thing so as to bind the Employer or bind and fetter the
         judgment or discretion of the Employer’s Representative / Engineer in the exercise of
         their powers and duties under the contract, except in so far as the Employer’s
         Representative / Engineer may issue a formal Circular letter to all Tenderers, amending
         or explaining the tender documents, to be incorporated in to the Formal Agreement
         when the Contract is signed.

B.12.2   No claim for an increase in any of the rates or prices shown in the Bills of Quantities or
         in any other rate or price to be determined in accordance with the Conditions of
         Contract shall be entertained nor shall the Contractor whose tender is accepted be
         entitled to pursue any claim on the grounds of any representation or on the grounds that
         they were supplied with information or given any promise or guarantee by the Employer
         or to the Employer’s Representative / Engineer or their employees or by any other
         person.
B.13     No Alteration to Documents

B.13.1   No unauthorized addition, omission or alteration is to be made by the Tenderer to the
         Tender Documents. If any such alteration is made or if these instructions are not fully
         complied with or if any incomplete tender is submitted, the tender may be rejected.
         Unpriced items shall be deemed to be included in the final tender price.

B.13.2   It is a condition of tender that an offer must be submitted solely on the basis of the
         tender documents issued to Tenderers and must be free of all qualifications. Should
         Tenderers wish to submit an alternative offer to the Employer for consideration, such
         offer must be additional to and completely separate from the unqualified tender.

B.13.3   Alternative designs will be considered if the Contractor can guarantee an earlier or more
         timely completion than that stated in the Contract. Fully detailed calculations shall be
         submitted in a covering letter with the tender to substantiate the alternative in a covering
         letter with the Tender.

B.13.4   The tenderer should state on which of the alternative designs he has based his tender.
         He should insert quantities accordingly.


B.14     Currency and Prices

B.14.1   All prices quoted must be in U.A.E. Dirhams. Fractions of Dirhams shall be in Fils.

B.14.2   The quoted tender price shall be valid during the whole period of the execution of the
         works. No compensation shall be made due to currency fluctuations.


B.15     Acceptance or Rejection of Tenders

B.15.1   The Employer does not bind himself to accept the lowest or any tender and will not
         assign any reason for the rejection of any tender. The Employer will not be responsible
         for or pay for any expenses or losses which may be incurred by any Tenderer in the
         preparation of his tender.


B.16     Tender Prices

B.16.1   Each and every page of the priced tender document is to be stamped and initialled by
         the Tenderer. All tender prices to be extended in ink.

B.16.2   Any genuine arithmetical errors made by the Tenderer in extensions or totals in the Bills
         of Quantities and carried through to the Form of Tender will be corrected. The Tenderer
         must stand by his corrected Tender Price.

B.16.3   In cases where unit rates included in the priced Bills of Quantities are found to be
         unacceptable to the Employer’s Representative / Engineer, the Tenderer shall amend
         his rate by such amount as agreed with the Employer’s Representative / Engineer. The
         price difference in the extended total for the item of work shall be carried through to the
         General Summary page and clearly described and referenced, and added to or
         deducted from the tender amount.
B.16     Tender Prices [cont’d]

B.16.4   The Tenderer will be required to provide the Employer’s Representative / Engineer with
         a full and detailed Tender Breakdown within 24 hours of being so requested. The
         breakdown will be required amongst other things to detail the calculations and build up
         of all rates into labour, material and plant with detailed quantity take-offs, on-costs,
         overheads and any other additions together with the calculation of preliminaries.

B.16.5   The Contractor may be required, at his own expense, to visit the Employer's offices
         after submission of his tender in order to answer any queries raised by the Employer’s
         Representative / Engineer upon his tender.


B.17     Tender Bond

B.17.1   Tenderers shall provide an unconditional Tender Bond in favour of the party referred to
         as the Employer in these Tender and Contract Documents in an amount equal to 5%
         (five percent) of the Tender Amount stated in the Form of Tender. Such bond shall
         provide a surety or sureties satisfactory to the Employer to be jointly and severally
         bound with the Tenderer in a form approved by the Employer and the Employer’s
         Representative / Engineer.

B.17.2   A bond in respect of another Tender is not acceptable as the Bond in respect of this
         Tender and a declaration to this effect, signed by the Tenderer and the bond surety or
         sureties shall be submitted with the Tender Documents.

B.17.3   The security provided by unsuccessful Tenderers will be discharged three calendar
         months after the date fixed for delivery of Tenders to the Employer, or until such earlier
         date as a Tender shall have been accepted by the Employer and a Performance Bond
         shall have been duly provided by the Tenderer whose Tender is accepted.

B.17.4   Notwithstanding the above mentioned period of three calendar months, the security
         provided by the Tenderer whose Tender is accepted shall be discharged only upon the
         receipt by the Employer of the Performance Bond referred to and defined elsewhere in
         these Contract Documents.

B.17.5   If the Tenderer whose tender is accepted fails to provide the above mentioned
         Performance Bond at the time of receipt of the Employer’s Representative / Engineer's
         order to commence the full amount of the Tender Bond shall become payable to the
         Employer as compensation for such default.


B.18     Validity of Tender

B.18.1   Tenders shall remain valid and binding upon the Tenderers for a period of 90 days, with
         a provision for extension upon mutual agreement, commencing from the date fixed for
         delivery of tenders to the Employer and it may be accepted at any time before the
         expiry of this period.
B.19     Tender Evaluation

B.19.1   The Tenderer must be prepared to visit the Employer’s Representative / Engineer's
         offices in the period of tender evaluation to clarify and/or amplify any part of his tender
         in order to satisfy the Employer’s Representative / Engineer that he has carefully
         considered all matters affecting the execution of the work.

B.19.2   All costs in relation to these visits shall be borne by the Tenderer.


B.20     Tendering to be Confidential

B.20.1   All Tenderers shall consider and treat all details in these Tender and Contract
         Documents as private and confidential.


B.21     Language

B.21.1   All correspondence in connection with this contract shall be in English.


B.22     References

B.22.1   The Tenderer shall submit with his tender, references of all key personnel to be
         involved with the contract.


B.23     Manpower

B.23.1   The Tenderer shall submit with the tender a schedule of proposed manpower for the
         entire duration of the project.


B.24     Equipment and Plant

B.24.1   The Tenderer shall submit with the tender a schedule of proposed equipment and
         construction plant for the entire duration of the project.


B.25     Type of Contract

B.25.1   This is a lump sum fixed price contract. Unless specifically described as being
         provisional or estimated, the quantities will not be re-measured. Notwithstanding the
         lump sum nature of the contract, the contract price upon completion of the works will be
         amended to include only the approved expenditure of provisional sums and dayworks.
         This is in addition to the other amendments that are necessary to be carried out as
         provided for in the conditions of contract.

B.25.2   The Bills of Quantities have been prepared as estimated quantities and the Tenderer is
         responsible for the accuracy of the Quantities. No adjustments will be made in the event
         of any error in the Quantities being discovered after acceptance of the tender. The Bills
         of Quantities will be used to prepare interim Valuations and to value any Variations
         which may occur.
B.25     Type of Contract [cont’d]

B.25.3   The descriptions contained in the Bills of Quantities for each item are not necessarily
         complete. The Contractor is referred to the Conditions of Contract and other
         documents, Specifications and Drawings as well as relevant Standards and Codes of
         Practices for further information as no claim or variation will be considered on account
         of the Contractor's failure so to do.

B.25.4   The Contractor is to execute the Works in accordance with the intent and meaning of
         the Drawings and Specifications and is to supply all items/accessories necessary for
         the proper execution of the Work and is to execute all Work which may be inferred
         whether or not specifically shown or described.


B.26     Conditions of Contract

B.26.1   The General Conditions of Contract comprise the “General Conditions”, which form part
         of the “Conditions of Contract for Works of Civil Engineering Construction” Fourth
         Edition 1987, with 1992 amendments published by the Federation Internationale des
         Ingenieurs-Conseils (FIDIC), and the following Part II “Conditions of Particular
         Application”, which include amendments and additions to such General Conditions.


B.27     Time of the Essence

B.27.1   The tenderers shall note that the completion period of the project is most important.

B.27.2   To this end, the Employer will be very receptive to proposals for shortening the contract
         period by whatever possible means.


B.28     Local Agent

B.28.1   No tender will be accepted unless accompanied by a copy of a current and valid Trade
         License issued by Dubai Municipality in the name of the tenderer. In the event that the
         firm has not established an office in the Emirate of Dubai, then it must submit a letter
         stating the name and address of their local agent, countersigned by him and
         authenticated by the court concerned.


B.29     Project Programme

B.29.1   The Tenderer shall submit a proposed overall construction programme. The time
         scales shall be indicative of the periods in which the works have been planned to be
         carried out.

B.29.2   The Employer reserves the right to impose a financial penalty, pro-rata to the
         percentage of the value of each package in relation to the Contract Price and Liquidated
         damages. In the event the Contractor achieves the final completion date or the next
         agreed milestone, financial penalties incurred would be reimbursed. Any penalties
         imposed shall be limited to 10% of the package value.
B.30     Completion in accordance with Programme

B.30.1   The Tenderer is to allow for all necessary overtime or additional shifts in his tender to
         ensure compliance with the programme for the Works. Under no circumstances shall
         any claims for additional costs due to overtime or additional shift working required to
         complete the Works on time be entertained.

B.31     Bona Fide Tender

B.31.1   The Tenderer must not discuss this tender or any aspect of it with any third party. Any
         evidence of collusion or collaboration will result in rejection of the Tender.


B.32     Manufacturers / Suppliers of Materials

B.32.1   The tenderer shall consider using locally available materials provided those materials
         comply with the specification.


B.33     Particulars to be submitted with Tender

B.33.1   Tenderers shall submit with their tenders the following particulars:-

         (a)     a copy of each Circular Letter to Tenderers issued by the Employer’s
                 Representative / Engineer, if any, which must be endorsed by the Tenderer.

         (b)     a Method Statement giving in outline and detail their general scheme and
                 programme of the execution of each section of the Works in the form of a bar
                 chart; the programme shall be separated into sections to show how the various
                 elements of the works are to be integrated and shall incorporate in detail the
                 work of all sub-contractors ;

         (c)     particulars of their proposed site organization including CVs of senior staff and
                 the labour force they propose to use, giving details of the number of workmen
                 to be employed during the contract;

         (d)     particulars of the plant they propose to use ;

         (e)     a list of the Sub-Contractors, including local firms they propose to use with
                 particulars of the extent of the work which will be undertaken by them :

         (f)     the sources from which they propose to obtain their local materials and
                 aggregates ; and details of all other sources and types of materials where
                 these vary from the specification,

         (g)     their forecast of certificate payments in the form of a cash flow chart.

         (h)     a proposed Site layout which should clearly show the position of all temporary
                 works, offices, stores, sheds, work areas, etc. in relation to the permanent
                 works, access to the Site, temporary roads within the Site, etc.

         (i)     particulars of their proposed piling method as required by the Specification.

         (j)     A Site Access Plan including estimated traffic movements for the duration of the
                 Contract.
         All approved proposals will be binding on the Contractor and can only be altered at the
Employer's or Employer’s Representative / Engineer’s discretion.


B.34     Alternative Tenders:

B.34.1   In the event that the Tenderer wishes to submit and alternative tender based on
         specifications other than those in the Tender Documents, this alternative will only be
         considered provided that a Tender fully complying with the conditions laid in the
         Tender Documents is also submitted. The Tenderer shall give full details of such
         alternative specifications together with the effect, if any, on the Tender Sum. The
         Employer shall be free to accept whichever Tender he may choose. Alternative
         Tender must be submitted along with the main Tender and shall be endorsed
         “Alternative No. 1”


B.35     Value Engineering

B.35.1   In the event the proposed Contract Price is over and above the Employers Budget,
         the Contractor may be requested to participate in Value Engineering exercise. The
         Employer also reserves the right to transfer the any parts of work to Provisional Sums
         and nominating a Specialist Subcontractor.
SPECIMEN FORM OF TENDER BOND


To :
             ……………………
             P.O. Box …………
             Dubai
             U.A.E.

We have the honour to inform you that we guarantee

Messrs ...................................................................……..................…...............................................

for the amount of ..................................................................………...….............................................

...............................................................................................(Dhs……..............................................)

as guarantee for their good intention in the presentation of their Tender for construction, completion,
maintenance and delivering up of the above-named works mentioned in conformity with the provision of
the Contract Documents.

This guarantee shall remain valid and irrevocable for a period of ninety (90) days starting at twelve (12)
o'clock on the date indicated in your letter of invitation to tender.

In the event of Messrs ..................................................................................………..........................

..................................................................................................................................………................

................................................................. withdrawing their tender before the expiration of the period of
validity of this letter of guarantee we definitely undertake to deposit with you upon demand and not
withstanding any objection on the part of the

said Messrs .....................................................................................................................……….........

.....................................................................................................................................................……

the aforesaid sum of ........................................................................................................................…

.......................................................................................................................................…. in cash.


Yours faithfully


Signature
PART C

FORM OF AGREEMENT
FORM OF AGREEMENT

THIS       AGREEMENT               made        the       ..................   day    of     .................................   2008     BETWEEN




WHEREAS the Employer is desirous that certain Works should be executed, namely construction,
completion and remedying of any defects of Residential Building at Liwan, Dubai, U.A.E. and has
accepted a tender by the Contractor for undertaking such works.

NOW THIS AGREEMENT WITNESSES as follows:-

1.         The             Employer               will            pay           to           the            Contractor               the           sum
           of…………………………………………………....
...................................................................................................................... (hereinafter referred to as the
quot;Contract Pricequot;) or such other sum as shall become payable under the Contract.

2.         In this Agreement words and expressions shall have the same meanings as are respectively
           assigned to them in the Conditions of Contract hereinafter referred to.

3.         The following documents shall be deemed to form and be read and construed as part of this
           Agreement, viz:-

           (a)         The Conditions of Contract
           (b)         The Drawings
           (c)         The General Specification
           (d)         The Priced Bills of Quantities
           (e)         The Form of Tender
           (f)         Appendices
           (g)         The Letter of Acceptance
           (h)         The Instructions to Tenderers
           (j)         Any other documents mutually agreed to be signed and dated at this time and listed
                       hereunder:
                       ..…......……….............................................................................................................

                       ..…......……….............................................................................................................

4.         In consideration of the payments to be made by the Employer to the Contractor as herein
           mentioned the Contractor hereby covenants with the Employer to undertake the Works in
           conformity in all respects with the provisions of this Agreement.

5.         The Employer hereby covenants to pay the Contractor in consideration of the completion of the
           Works the Contract Price within 30 days of acceptance of the Contractor’s final report.
Form of Agreement



IN WITNESS whereof the authorized representative of the parties have hereunto set their respective
hands the day and year first above written.



SIGNED BY................................…………....................


SIGNED BY...................................................………….

for and on behalf of THE EMPLOYER


In the presence of :-


Signature.....................................................


Address.......................................................

Occupation..................................................




SIGNED BY................................................……………

for and on behalf of THE CONTRACTOR


In the presence of :-


Signature.....................................................


Address.......................................................

Occupation..................................................
PART D

CONDITIONS OF CONTRACT
GENERAL CONDITIONS
CONDITIONS OF PARTICULAR APPLICATIONS
Part D

_____________________________________________________________


PART 1

GENERAL CONDITIONS


The General Conditions of Contract shall be the Conditions of Contract for Works of Civil
Engineering Construction, (Fourth Edition 1987 – reprinted 1988 with editorial amendments and
reprinted 1992 with further amendments) published by the Federation Internationale des Ingenieurs –
Conseils (FIDIC) and shall be amended and added to in accordance with the following Part II entitled
“Conditions of Particular Application”.

Tenderers are deemed to be in possession of their own copy of this document.

The Clauses in Part II Conditions of Particular Application shall take precedence over the Clauses of
the General Conditions of Contract.
Part D

_____________________________________________________________
PART II

CONDITIONS OF PARTICULAR APPLICATION


Note:     Clause reference numbers refer to Clause numbers in the General Conditions of Contract
          where applicable.


Definitions




                                  Dubai, U.A.E




                            (x) The quot;Quantity Surveyorquot; is


                                  Dubai, U.A.E




Engineer’s Duties
and Authority            2.1(b)   Before exercising his authority under the following Clauses of the
                                  Contract, the Engineer is required to obtain the specific approval of
                                  the Employer.

                                  Clause 2.3      Authority to Delegate
                                  Clause 2.4      Appointment of Assistants
                                  Clause 4.1      Subcontracting
                                  Clause 14.1     Programme
                                  Clause 15.1     Contractor's Superintendence
                                  Clause 44.1     Extension of Time
                                  Clause 48       Taking-Over Certificate
                                  Clause 51.1     Variations
                                  Clause 52.1     Valuation of Variations
                                  Clause 52.2     Power to Fix Rates
                                  Clause 58.2     Use of Provisional Sums
                                  Clause 60.8     Final Certificate
                                  Clause 62.1     Defects Liability Certificate
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Language            5.1(a)    The Contract Documents shall be drawn up in the English
and Law                       language.

                       (b)    The Contract shall be governed by and construed according to the
                              Laws in force in Dubai, U.A.E.

                          (c) The Contractor shall conduct all correspondence with the Employer
                              and the Engineer in English language.


Priority of        5.2        Add the following:
Contract Documents
                              If any discrepancies occur between the contracts documents, the
                              Engineer has the right to choose any of the specified materials
                              and the Contractor to price the items considering such errors or
                              mistakes.


Supplementary       7.1       Add the following:
Drawings
and Instructions              The Contractor shall give the Engineer reasonable notice of any
                              additional design drawings, specifications or instructions required
                              to define the Works in greater detail or to permit the proper
                              progress of the Works. Failure to give notice under sub-clauses
                              6.3 and 7.1 will remove the Contractor’s right to claim for
                              extensions of time under sub-clause 6.4. The Contractor shall
                              not be entitled to additional payment if such drawings do not incur
                              the contractor in additional work.


Contractor’s        8.4       The contractor shall perform all his obligations under the Contract
Obligations                   strictly in accordance with the standards of skill, care and
                              diligence adhered to by experienced and competent contractors
                              specialising in work of the particular type, nature and magnitude,
                              and shall not unreasonably object to any measures adopted by
                              the Engineer in the general interest of works and quality control.



                    Delete Sub-clause 11.1 of the General Conditions and insert the following:

Inspection          11.1      The Contract shall be deemed to be based on
of Site                       the understanding that the Contractor is completely familiar with
                              the physical conditions prevailing at the Site. No additional
                              payment in respect of the above will be considered.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

                    Sub-clause 14.1 and 14.2 of the General Conditions are deleted and the
                    following substituted:

Programme to        14.1     The Contractor shall submit to the Engineer/ the Employer, within
be Submitted                 28 days after the date of Letter of Acceptance, for their consent, a
                             programme (three paper copies and one electronic copy in
                             Primavera Version) in a form prescribed hereunder, for the
                             execution of the Works. The Contractor’s first monthly payment
                             will be dependent upon the consent, by the Engineer, of the said
                             programme.

                           The Contractor shall also submit:
                             a) a general description of the arrangements and methods which
                                the Contractor proposes to adopt for the execution of the
                                Works.
                             b) a schedule of submission of shop drawings indicating the
                                approved required-by date.
                             c) fabrication schedules.
                             d) material procurement schedules.
                             e) a cash flow forecast by loading each activity in the Base Line
                                by the equivalent Budgeted cost.
                             f)    a subcontractors’ procurement schedule.
                             g) a list of key project indicators e.g. concrete, formwork,
                                blockwork etc.
                             h) the Contractor shall coordinate with the Engineer/ the
                                Employer for the required dates for appointment of all PC &
                                PS items taking into consideration that none of the PC & PS
                                items shall commence prior to 5 months of project
                                commencement dates. Items (a), (b), ( c), (d), (e), (f) and (g)
                                are to be in line with the programme.

                             The programme shall include the following:

                             1.    A critical path analysis.
                             2.    Total and free floats.
                             3.    Duration of each activity.
                             4.    Early start, early finish, latest start and latest finish of each
                                   activity.
                             5.    Critical activities.
                             6.    Predecessors and successors.
                             7.    The programme shall be resourced and the manpower and
                                   plant requirements and cost of each items are to be indicated
                                   time unit wise.
                             8.    The footer shall include a revision box, programme number
                                   and the issue date.
                             9.    The header shall include the project title and programme title.
                             10.   The package numbers together with the subcontractors’
                                   names.
                             11.   The activities shall also show relationship between
                                   procurement, construction and installation.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]


Recovery            14.2   If at any time it should appear to the Engineer that the
Programme                  actual progress of the Works does not conform to the approved
                           programme referred to in Sub Clause 14.1, the Contractor shall
                           produce within 7 days of being so requested by the Engineer a
                           recovery programme showing the modifications to the approved
                           programme necessary to ensure completion of the Works within
                           the time for completion as defined in Clause 43 of the Conditions
                           of Contract.

Cash Flow           14.3   Submit the cash flow estimate within 28 days after the date of the
Estimate                   Letter of Acceptance.

Contractor not      14.4   The submission to and consent by the Engineer of such
Relieved of                programmes or the provision of such general descriptions or cash
Duties or                  flow estimates shall not relieve the Contractor of any of his duties
Responsibilities           or responsibilities under the Contract.

Contractor          14.5   The Contractor is requested to submit daily, weekly and
Reports                    monthly reports in accordance with the common standards and
                           practice. All the above reports format to be in compliance with the
                           Engineer / the Employer’s planning and scheduling requirements.

Contractor's        15.2   The Contractor's authorised representative shall be fluent
Superintendence            in English.

Setting Out         17.1   In line 10 after quot;Employerquot;, the following sentence is to be added.

                           quot;Provided that the expense of rectifying any errors shall be borne
                           by the Contractor if such error results from incorrect data on the
                           Drawings or in the Specifications which were used for Tender
                           purposes which Drawings and Specifications are deemed to have
                           been carefully studied by the Contractor and accepted by him as
                           being correct unless he has notified the Engineer in writing of such
                           errors at the time of tenderingquot;.


Employer's          20.4   Delete sub-clause 20.4(h).
Risks

Accident or         24.1   After each reference to Employer, insert 'and Engineer'.
Injury to Workmen

Transport of        30.2   This clause is deleted and the following substituted:
Contractor’s
Equipment or
Temporary Works                    “Should it be found necessary for the Contractor to move
                           One or more loads of constructional plant, machinery or pre-
                           constructed units or parts of units of work over part of a highway
                           or bridge, the moving whereof is likely to damage any highway or
                           bridge unless special protection or strengthening is carried out,
                           the Contractor shall before moving the load on to such highway or
                           bridge, give notice to the concerned owner or Government
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]


                            Department. All costs, expenses, delays and the like arising
                            therefrom shall be the entire responsibility of the Contractor. No
                            claim will be allowed by the Engineer for any such costs,
                            expenses, delays and the like.

                            After Sub-clause 34.1 insert the following:

Accident            34.2    The Contractor shall have on his staff at the Site an officer
Prevention                  dealing only with questions regarding the safety and protection
Officer,                    against accidents of all staff and labour. This officer shall be
Accidents                   qualified for this work and shall have the authority to issue
                            instructions and shall take protective measures to prevent
                            accidents.

Health and          34.3    Due precautions shall be taken by the Contractor, and at his own
Safety                      cost, to ensure the safety of his staff and labour and, in
                            collaboration with and to the requirements of the local health
                            authorities, to ensure that medical staff, first aid equipment and
                            stores, sick bay and suitable ambulance service are available at
                            the camps, housing and on the Site at all times throughout the
                            period of the Contract and that suitable arrangements are made
                            for the prevention of epidemics and for all necessary welfare and
                            hygiene requirement.

Supply of           34.4    The Contractor shall, so far as is reasonably practicable, having
Water                       regard to local conditions, provide on the Site an adequate supply
                            of drinking and other water for the use of his staff and labour.

Alcoholic           34.5 The Contractor shall not, otherwise than in accordance with the
Liquor or                Statutes, Ordinances and Government Regulations or Orders for
Drugs                      the time being in force, import, sell, give, barter or otherwise
                           dispose of any alcoholic liquor or drugs, or permit or suffer any
                           such importation, sale, gift, barter, or disposal by his sub-
                           contractors, agents, staff or labour.

Arms and            34.6 The Contractor shall not give, barter or otherwise dispose of to
Ammunition                 any person or persons, any arms or ammunition of any kind or
                           permit or suffer the same as aforesaid.

Festival            34.7 The Contractor shall in all dealings with his staff and labour have
and Religious            due regard to all recognised festivals, days of rest and religious or
Customs                  other customs.

Disorderly          34.8 The Contractor shall at all times take all reasonable precautions
Conduct                    to prevent any unlawful, riotous or disorderly conduct by or
                           amongst his staff and labour and for the preservation of peace
                           and protection of persons and property in the neighborhood of the
                           Works against the same.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

                    After Sub-clause 35.1 insert the following:

Reporting           35.2 The Contractor shall report to the Engineer details of any
to Accidents               accidents as soon as possible after its occurrence. In the case of
                           any fatality or serious accident, the Contractor shall, in addition,
                           notify the Engineer immediately by the quickest available means.


Cost of test not    36.4    Sub – clause 36.4 is deleted entirely & Substitute: -
provided for
                    36.4.1 The Contractor shall allow in his pricing for all tests as necessary
                           to be carried out on the materials due for incorporation into the
                           works. The Contractor shall note that it may be required that the
                           Engineer will have to visit the factories of various manufacturers
                           in order to establish and monitor testing procedures and the
                           Contractor’s price is deemed to have included for providing such
                           provisions.

                    36.4.2 The Contractor is to submit samples of all materials and / or
                           catalogues requested by the Engineer, and the cost for the same
                           is deemed to be included in the Contract.          Samples of
                           workmanship requested by the Engineer shall be provided by the
                           Contractor and the cost for the same is deemed to be included in
                           the Contract.

                    36.4.3 The Contractor is to carry out tests of materials as required by the
                           Engineer and the cost for the same is deemed to be included in
                           the contract.


Time for Completion 43      Delete quot;calculated from the last day of the period named in the
                            appendix to the Tender as that within which the Works which are
                            to be commencedquot; and Substitute quot;calculated from the date of the
                            Engineer's written order to commence the Works on Site”.


Cost of Overtime    45.2    After Sub-clause 45.1 insert the following:

                            The rates wherever applicable to be used for calculating overtime
                            for the Engineer and the Design Consultant will be as follows:


                                                                          Overtime Dhs/hr
                             Resident Engineer / Project Manager                350
                             Structural Engineer / Architect                        250
                             MEP Engineer                                           250
                             Site Engineer                                          200
                             Quantity Surveyor                                      250
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Penalty for Delays   47.1   After Sub-clause 47.1 insert the following:
                            If the amount of penalty for delays payable to the employer should
                            reach 10%, The Employer has the right to take over the project
                            and complete it and charge any extra cost over the contract
                            amount to the contractor. This is in addition to the 10% penalty
                            and excluding consultant supervision fees for additional time of
                            construction.

Reduction of penalty 47.2   This clause has been entirely deleted.
for delay.

Concurrent Delays    48.5   Add the following:

                            In the event of concurrent delays, client will not pay any
                            prolongation costs and Contractor to consider that this clause will
                            supersedes any clauses that may contradict with the content of this
                            clause.”

Quantities           55.1   The Contractor shall be deemed to have satisfied himself as to the
                            accuracy of the quantities (except for any provisional items and/or
                            provisional quantities) and to have included in the Contract Price for
                            all variances in measurements and inserting appropriate prices in
                            the Bills of Quantities where provision is made for the Contractor to
                            price such variances.

                            Any error in the description in or any omission from the Bill of
                            Quantities shall not vitiate the Contract nor release the Contractor
                            from the execution of the whole or any part of the works according
                            the drawings and specifications or from any of his obligations or
                            liabilities under the contract.

Quantities not to    55.2   The quantities shall not be subject to re measurement. Any errors
Be remeasured               shall not be adjusted in accordance with Clause 51 here in.

Works to be          56.1   This clause has been deleted and substitute:
remeasured
                            “This is a Lump Sum Contract and therefore the works shall not be
                            subject to re-measurement except where specifically ascertain and
                            determine by reference to the Contract Price. The value of the
                            works in accordance with the Contract and the Contractor shall be
                            paid that value in accordance with clause 60. The Engineer shall,
                            when he requires any variations or provisional items to be
                            measured, give reasonable notice to the Contractor’s authorised
                            agent, who shall:

                        a) forthwith attend or send a qualified representative to assist the
                           Engineer in making such measurements and

                        b) supply all particulars required by the Engineer.
_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Definition of       59.1    Add the following:
“Nominated
Subcontractors”     The contractor has to prove within 28 days from the receipt of the
                    nomination letter from the Engineer that he entered in a Sub contractor
                    agreement with the nominated Subcontractor.




Nominated           59.2    Insert after sub clause 59.2(b) the following:
Sub-Contractors
Objection to
Nomination             c)   that the sub-contract works shall be completed within the period or
                            (where they are to be completed in sections) periods therein
                            specified. The Contractor shall not without the written consent of
                            the Engineer grant any extensions of time for completion of the
                            sub-contract works or any sections thereof, and the Contractor shall
                            inform the Engineer of any representations made by the nominated
                            sub-contractor as to the cause of any delay in the progress or
                            completion of the sub-contract works or any section thereof.

                       d)   that if the nominated sub-contractor shall fail to complete the
                            sub-contract works or (where the sub-contract works are to be
                            completed in sections) any section thereof within the period
                            therein specified or within any extended time granted by the
                            Contractor with the written consent of the Engineer and the
                            Engineer certifies in writing to the Contractor that the same ought
                            reasonably so to have been completed, the nominated
                            sub-contractor shall pay or allow to the Contractor either a sum
                            calculated at the rate therein agreed as liquidated and ascertained
                            damages for the period during which the said Works or any section
                            thereof, as the case may be, shall so remain or have remained
                            incomplete or (where no such rate is therein agreed) a sum
                            equivalent to any loss or damage suffered or incurred by the
                            Contractor and caused by the failure of the nominated
                            sub-contractor as aforesaid.

                       f)   that the Contractor shall retain from the sum directed by the
                            Engineer as having been included in any certificate issued a
                            percentage (which percentage shall be equal to the percentage
                            currently being retained by the Employer) or such value; and that if
                            and when such sums or any part thereof are released to the
                            nominated sub-contractor they shall be paid in full within three (3)
                            days of receipt by the Contractor of payment from the Employer.

                       g)   that the Engineer shall have the right of access to the
                            workshops and other places of the nominated sub-contractor.

                       h)   that the employment of the nominated sub-contractor under the
                            sub-contract shall determine immediately upon the determination
                            (for any reason) of the Contractor's employment under this
                            Contract unless at the time of such determination the Employer
                            requires the Contractor to assign to him the benefit of the
                            sub-contract.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]


                        j)   that in the event of the last paragraph of Clause 59.5 hereof being
                             operated by the Engineer the nominated sub-contractor shall
                             indemnify the Contractor against any claim which the Employer
                             might make in respect of latent defects in the Sub-contract Works.

                       k)    that the Contractor shall obtain the approval of the Engineer
                             of all forms of Sub-Contract Agreement he proposes to enter
                             into with each nominated Sub-Contractor.

                       m)    the time for the contractor to raise reasonable objection against
                             the nomination to be defined as seven (7) days. Therefore the
                             contractor has to proof within seven (7) days from the receipt of
                             the nomination letter from the engineer that he entered in a sub
                             contractor agreement with the nominated sub contractor unless
                             otherwise reasonable objection raised.


Payments to          59.4    Add the following:
Nominated
Subcontractors:              The contractor before raising the next payment certificate to
                             enclose a proof that all the nominated Subcontractors payments
                             have been released, paid and received by the nominated
                             Subcontractor within three (3) days after receipt by the Contractor,
                             without proofing the same the Engineer may suspend the
                             Contractors payments waiting for him to pay the payments due to
                             the nominated Subcontractors or to recover the same payments
                             from the contractor payment and pay it to the nominated
                             Subcontractors.

                             Penalty clause to be generated on the delay of the As built and
                             guarantee delay.


Monthly Statements   60.1    Add the following at the end of Clause 60.1 (c):

                             Materials on site shall only be paid at the percentage stated in the
                             Appendix to tender only when the Engineer and Employer
                             Representative is satisfied that the materials have been delivered
                             to site for timely incorporation into the works. (i.e. not prematurely).


Advance payment      60.11   An Advance payment in percentage as stated in the Appendix to
                             the Tender shall, following the presentation by the Contractor to the
                             Employer of an approved performance security in accordance with
                             Sub-Clause 10.1, insurances required to be effected by the
                             Contractor and a guarantee in terms approved by the Employer, for
                             the full advance payment, be certified by the Engineer for payment
                             to the Contractor. The Advance payment security shall be in the
                             form as annexed to these Conditions of Contract. Such guarantee
                             shall be progressively reduced by the amount recovered by the
                             Contractor as indicated in interim certificates of the Engineer issued
                             in accordance with this Clause.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Advance payment     60.11   The advance payment shall not be subject to retention. The
         [cont,d]           advance payment shall be recovered by way of reduction in interim
                            certificates commencing with the first certificate. The amount of
                            reduction in each interim certificate shall be at the same % as
                            stated in the Appendix to the Tender, for the purpose of this
                            Clause, of the gross certified value in such interim certificates until
                            the advance payment has been recovered in full, subject to the
                            provision that the full value of the advance payment shall be
                            recovered within a period of 30 days prior of completion date.
                            Upon the happening of any of the events specified in Sub-Clause
                            63.1 or termination under Clause 65, 66, or 69, the whole of the
                            balance then outstanding shall immediately become due and
                            payable by the Contractor to the Employer.


Arbitration         67.3    Following paragraph (b), delete the words quot;shall be finally settled
                            unless otherwise specified in the contract, under the Rules of
                            Conciliation and Arbitration of the International Chamber of
                            Commercequot; and substitute quot;shall be finally settled under the Rules
                            of Arbitration and Conciliation of the Dubai Chamber Commerce
                            and Industryquot;.

Notice to           68.2    All notices to be given to the Employer or to the Employer’s
Employer or                 Representative / Engineer under the terms of Contract shall be
Employer’s                  served by delivering the same to:-
Representative
                            Employer           -


                                                    Dubai U.A.E




                            Employer’s         -




Increase or         70.1    No adjustments to the Contract Price shall be made in
Decrease of Cost            respect of rise or fall in the costs of labour and/or plant and/or
                            materials or any other matters affecting the costs of the execution
                            of the Works except as provided elsewhere in the Contract.

Subsequent          70.2    Delete quot;after the date 28 days priorquot; and replace with
Legislation                 quot;subsequentquot;.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]


Currency            71.1   Delete Sub-clause 71.1 and replace with:
Restrictions
                           The Contractor shall allow in his contract price for all effects of
                           currency restrictions and/or transfer of currency restrictions which
                           may be imposed by the Government or authorised agency of the
                           Government of the country in which the Works are being or are to
                           be executed before or during the period of the Contract. The
                           Employer shall not have any liability or responsibility to reimburse
                           the Contractor for any loss or damage to the Contractor arising
                           from such restriction.


Rates of            72.1   Sub-clause 72.1 is deleted.
Exchange

Currency            72.2   Sub-clause 72.2 is deleted.
Proportions

Currencies          72.3   Sub-clause 72.3 is deleted.
of Payment for
Provisional Sums

Law to Apply        73.    The Contract shall in all respects be construed in accordance with
                           the Law of Dubai and U.A.E. and any difference that may arise
                           between the Employer and the Contractor in regard thereof shall be
                           settled in accordance therewith.


Compliance with     74.    The Contractor's operations and proceedings in connection
Local Laws and             the Works shall at all times during the continuance of the contract
Regulations                be conducted in accordance with Local Laws and Regulations for
                           the time being in force in Dubai. The Contractor shall also comply
                           with the bye-laws and regulations of all authorities (if any) having
                           jurisdiction over or in connection with the Works on Site or other
                           operations such as those carried out by the Contractor and shall
                           give all notices required by such bye-laws and regulations.
                           Hospital and medical regulations in force for the time being shall
                           also be complied with by the Contractor, his sub-contractors,
                           employees and workmen.

Taxation            75.    The Contractor shall pay all Government and Municipal taxes
                           including road taxes and vehicle registration fees, building permit
                           and inspection charges and any taxes which may in the future be
                           levied on the Contractor or his expatriate employees whilst
                           employed on this project.


Details             76.    The Contractor shall treat the Contract and everything
Confidential               contained therein as private and confidential. In particular, the
                           Contractor shall not publish any information, drawing or
                           photographs concerning the Works and shall not use the site for the
                           purpose of advertising except with the written consent of the
                           Employer and subject to such conditions as he may prescribe.
1
                                                                                              Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Bribery                77.    Any commission, advantage, gift, gratuity, reward or bribe given,
                              promised or offered by or on behalf of the Contractor or his agent or
                              servant or any other person on his or their behalf to any officer,
                              servant, representative or agent of the Employer or the Engineer or
                              to any person on their behalf or on behalf or on of any of them in
                              relation to the obtaining or to the execution of this or of any other
                              contract with the Employer shall, in addition, to any criminal liability
                              which may be thereby incurred, subject the Contractor to the
                              cancellation of this and of all other contracts with the Employer and
                              also the payment of any loss or damage resulting from such
                              cancellations.


Service Authorities    78.    The Contractor shall comply in all respects with the regulations of
                              all Service Authorities whether for temporary or permanent work in
                              connection with those Authorities in carrying out his obligations
                              under the Contract.


Work on Adjoining      79.1   The Contractor shall neither be entitled to claim indemnity or
Site                          extension of time for the works nor to be excused from any of the
                              obligations of the Contract by reason of or to submit any claim in
                              respect of disturbances or delay due to the simultaneous
                              execution of work adjoining the Site.


Indemnity to the       80.1   The Contractor shall indemnify the Employer and the
Employer’s Officials          Employer's Representative and every member, officer and
and Engineer                  employee thereof and the Engineer and the Engineer's
                              Representative and every member of their staff from any claim or
                              demand for accident, injury, damage, loss and/or compensation of
                              any kind whatsoever arising out of or in connection with all claims
                              and demands which may be made against the Employer for or in
                              respect of or arising out of any failure by the Contractor in the
                              performance of his obligations under any of the provisions of the
                              Contract.

                       80.2   If the Employer has to pay any money in respect of any claims or
                              demands as aforesaid, the amount so paid and the cost incurred by
                              the Employer shall be charged to and paid by the Contractor,
                              provided always that the Employer, shall, if circumstances permit,
                              give to the Contractor reasonable opportunity of examining such
                              claims or demands before payment. In the event of the Contractor
                              disputing the amount of any payment (except payments made in
                              accordance with legal obligations or after approval by the
                              Contractor) then the Contractor shall have the right to dispute the
                              matter, and refer it to Arbitration in accordance with the provisions
                              herein contained.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Decennial           81.1   The Contractor shall be liable for the consequence or errors,
Liability                  omissions or negligence on his part and in particular he shall be
                           liable for any defects in the construction of any part of the Works
                           where such defects are due to any error, omission or negligence
                           of the Contractor or his staff provided that such defects become
                           apparent during the period of ten years from the issue of the
                           Taking-Over Certificate for the part of the Works in question. The
                           liability of the Contractor shall in any event be limited to the cost of
                           rectification of the Works. The approval of the Engineer shall not
                           in any way absolve or relieve the Contractor from any such
                           obligations, responsibility or liability.


Contractor          82.1   The Contractor shall be responsible for the collection of the
to collect                 permit documentation from Dubai Municipality and pay all
Permit                     necessary fees for this collection within two working days from
                           receiving written instructions from the Engineer.


Contractor          82.2   The Contractor shall be responsible for completing the Works in
to obtain                  accordance with the Building Permit and to the satisfaction of the
Municipality               Dubai Municipality. He shall be responsible for arranging
Completion                 inspection by the Municipality and for obtaining the Municipality’s
Certificate                Certificate of Completion and other approvals necessary for the
                           connection of services, in order to ensure completion of the
                           Contract.


Contractor          82.3   On receipt of the Municipality building permit the Contractor shall
to Advise of               examine all the documentation handed over by Dubai
Dubai                      Municipality as part of the building permit and advise the
Municipality’s             Engineer in writing within 14 days from the date of receipt of any
Comments                   comment or special requirement stated by Dubai Municipality on
                           any of the documents which make up the Municipality building
                           permit. Failure of the Contractor to submit such advice within the
                           prescribed period of 14 days shall be deemed to be confirmation
                           to the Engineer and the Employer that the Works required in this
                           Contract have received the mandatory Municipality building
                           permit, relieving the Employer thereafter from any responsibility to
                           liaise with Dubai Municipality for obtaining any permit in
                           connection with the Works required in the Contract and from
                           considering any claim by the Contractor for any extension of time
                           or additional payments due to extra work resulting from comments
                           made in writing by the Municipality on any of the documents of the
                           Municipality building permit.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Inspection                 83.1   Upon the written request of the Contractor to the Engineer,
for                               the Engineer will issue a letter stating that the Works are
Municipality                      complete to allow the inspection of the Municipality for the
Certificate                       Municipality Completion Certificate to take place, provided always
of Completion                     that the Engineer shall be satisfied that the Works are complete to
                                  this extent. If the Works are not complete to the satisfaction of the
                                  Engineer, the Contractor will be required to complete the
                                  necessary works and issue further request. The issuance of the
                                  letter referred to in this Clause by the Engineer shall not constitute
                                  completion within the meaning of Clause 48 or shall have any
                                  meaning other than that the Works are complete for the purpose
                                  of initiating the inspection for the Municipality Completion
                                  Certificate.

Contractor          83.2          In addition to the requirements of Clause 48, the Contractor is
solely                            required to complete the Works necessary for obtaining the
responsible                       Municipality Certificate of Completion defined in Clause 85 and
for obtaining                     86 by the Milestone Date shown in the programme referred to in
Municipality                      Clause 14. The Contractor’s failure to obtain this certificate for
Certificate of                    any reason other than reasons which entitle the Contractor within
Completion                        the provision of the Contract to an Extension of Time, shall be the
                                  sole responsibility of the Contractor and shall not constitute any
                                  ground for an Extension of Time or additional costs

Permanent           84.1          The Contractor shall be responsible under this Contract to liaise
Electricity,                      with all Statutory Authorities to ensure that the work is carried out
Water,                            to their latest regulations and rules regardless of the fact that the
Telephone and                     Engineer has already liaised with such Authorities prior to the
Drainage                          award of this Contract.

Contractor          84.2          Notwithstanding his responsibility under sub-clause 87.1, the
to Advise of                      Contractor shall within 28 days of the notice to commence the
Statutory                         Works contact all Statutory Authorities and discuss in detail with
Authorities’                      them the requirements of the Works. He shall be responsible to
Changes                           ensure that no rules, regulations or requirements of the Statutory
                                  Authorities have changed, or that the Authorities require any details
                                  for the Works which are different from those included or inferred in the
                                  Contract, which may cause a variation to the Contract. If any changes
                                  are required by the Statutory Authorities, the Contractor shall inform
                                  the Engineer within a further 14 days (i.e. within 42 days of the notice
                                  to commence) giving full details of the consequence of these changes
                                  including details of costs and programme. If no notification has been
                                  received by the Engineer within the time stipulated, it will be deemed
                                  that no variation will be necessary and the Contractor will forfeit his
                                  rights to any additional time or costs due to any subsequent Statutory
                                  Authorities requirements.

Contractor to     84.3            The Contractor shall liaise with all Statutory Authorities
Obtain full                       throughout the Contract and shall be responsible for obtaining full
Approval of                       approval of the Authorities and connections as required by the
Statutory Authorities             Contract.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]

Employer            84.4   The Employer shall be responsible to pay directly to the relevant
Responsible to             authority all charges and fees which are necessary for the
Pay Fees                   completion of the Works. The Contractor shall be responsible for
                           giving the Employer two (2) weeks notice that the payment is due.

Delay to            84.5   In the event that the supplies of permanent services to the site are
Permanent                  delayed for reasons for which the Contractor is not responsible
Services and               under the contract, the final commissioning of the building may be
Commissioning              delayed but the Contractor shall complete all testing required
                           under the Contract using temporary supplies for which he shall be
                           responsible. In this event the Contractor shall be awarded an
                           extension of time in accordance with Clause 44.2 for the
                           commissioning only. The commissioning shall be completed within
                           4 weeks from the connection of the permanent services, or such
                           other time as may be specified by the Engineer. If the
                           commissioning is not completed within this period, the Contractor
                           shall pay liquidated damages as defined in Clause 47.1 and 47.2.
                           If an extension of time is given for this reason the Contractor shall
                           be entitled to any expense which he demonstrates that he has
                           incurred as a result of the delay provided such claims are
                           submitted in accordance with Clause 52.2.

Contractor’s        85.1   All Contractor design items are to be carried out by an Engineer
Design Items               who is approved by the Employers Engineer for each particular
                           discipline. The Contractor shall maintain a design indemnity
                           insurance policy covering for a period of ten (10) years all designs
                           carried out by the Contractor and incorporated in the Works.

Separate to       86.0     The Employer reserves the right to omit any part of the works or
Contracts with             let separate contracts in connection with the undertaking of the
other Contractors          works and may form part of the works in order to substantially
                           complete the works. The Contractor shall carryout properly and
                           coordinates his work with that of the other Contractors. If any part
                           of the Contractors work depends for its proper execution or results
                           upon the work of any other Contractor, the Contractor shall in
                           writing report promptly to the Engineer any defects in the work of
                           such other Contractors as may interfere with the proper execution
                           of the Contractors works.

                           The Employer can, with 7 calendar days written notice of intention
                           to do so, adjust the Contractors scope of works by removing
                           sections of works and having them completed by other
                           Contractors appointed by him. The cost of the works will be
                           deducted at their contracted cost plus overhead, profit and
                           preliminaries, this deduction is not related to and is in addition to
                           any Liquidated Damages costs recovered under the contract.
                           Where preliminaries items have to be completed by others these
                           will be deducted from the Contractors account at full cost
                           including supervision. The Contractors duties will remain in line
                           with his contractual obligations to Employers direct contractors.
                           Should it be necessary to transfer the Building Permit to another
                           Contractors name the Contractor shall do so within 7 calendar
                           days of a written request by the Employer.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]



Engineer’s and 87.0       The Contractor shall provide Engineer’s and Contractor’s site
Contractor’s Site         offices, facilities, site management team, parking, etc all as
Requirements              specified and herewith.

                          a)     SITE MANAGEMENT
                                 The Contractor shall allow for all site management. He shall
                                 maintain adequate site organization under the control of
                                 qualified and experienced staff that is capable of assuming
                                 complete responsibility for a contract of this nature:
                                 1.       Project Manager – 1 No ( Full time )
                                 2.       Project Engineer – 1 No ( Full Time )
                                 3.       Quantity Surveyor – 1 No ( Full Time )
                                 4.       Planning Engineer – 1 No ( Full Time )
                                 5.       Supervision Team
                                          5.1    Civil Engineers – Minimum 2 Nos.
                                          5.2    Materials Engineer – 1 No – as and when
                                                 required.
                                          5.3    Services Engineers for Elec., -2 No–
                                                 Mechanical Engineer 2 Nos.
                                          5.4    MEP Coordinator – 1 No.
                                          5.5    Land Surveyor – 1 No.
                                 6.       QA/QC Team for
                                          6.1    Site Quality Control – 1 No
                                          6.2    Material & Shop Drawing schedule
                                 7.       Safety Officer – 1 No
                                 8.       Shop drawing preparation Team consisting of:
                                          8.1    Engineers - Min 1 No
                                          8.6    Draftsman along with necessary computer
                                                 equipment/plotters at site. – 2 Nos
                                 And other necessary staff required for satisfactory
                                 completion of the project – to be assessed by the
                                 Contractor.
                                 The Contractor to submit the CV(s) of the above mentioned
                                 personnel to the Project Manager for approval. All the above
                                 personnel should have minimum seven years experience in
                                 similar size project in the U.A.E.
                                 The Contractor shall be responsible for his own setting out
                                 levels and lines to the satisfaction of the Engineer.
Part D

_____________________________________________________________
PART II [cont’d.]

CONDITIONS OF PARTICULAR APPLICATION [cont’d.]


Engineer’s and 87.0       The Contractor shall provide Engineer’s and Contractor’s site
Contractor’s Site         offices, facilities, site management team, parking, etc all as
Requirements              specified and herewith. [cont’d]


                              b)    OFFICE REQUIREMENTS - GENERAL
                                    1.01   DESCRIPTION OF WORK
                                    The Contractor is required to make necessary provision
                                    for temporary utilities (electricity, lighting, heating,
                                    ventilation, telephone service, water and sanitary),
                                    temporary controls (barriers, fencing, protection of
                                    work, security, and traffic), and construction facilities
                                    (25 parking slots and staging areas, progress cleaning,
                                    and offices) to fulfill the requirements of the Contract,
                                    support the Contractor’s work force and support the
                                    Owner’s representatives. All facilities and equipment
                                    will become the property of the Owner. The Contractor
                                    shall bear the responsibility to maintain and pay for all
                                    services and bills until the final handover to the main
                                    contractor.

                                    1.02   TEMPORARY POWER
                                    A.     Contractor shall provide necessary power
                                           service.
                                    B.     Contractor shall arrange with the electrical utility,
                                           as needed, for additional power requirements,
                                           including power takeoff points, voltage and
                                           phasing, transformers, and metering, and shall
                                           pay resulting costs and fees.

                                    1.03   TELEPHONE SERVICE
                                    Contractor shall provide telephone service at the
                                    Engineer’s site office for the PMs own use. Additional
                                    requirements are defined in section 1.13.

                                    1.04   TEMPORARY WATER SERVICE
                                    Contractor shall provide necessary water service and
                                    any necessary special connections to a water supply,
                                    as well as chilled bottled drinking water for the
                                    Engineer’s site office.

                                    1.05   TEMPORARY SANITARY FACILITIES
                                    Contractor shall provide on-site toilet and wash-up
                                    facilities for its work force that comply with applicable
                                    laws, ordinances, and regulations pertaining to the
                                    public health and sanitation of dwellings and camps.
                                    Additional requirements for the Engineer’s Site Office
                                    are contained in Section 1.13
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract
Conditions Of Contract

Weitere ähnliche Inhalte

Was ist angesagt?

Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentationnipuna_bopage
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.Abhishek kumar maurya
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 

Was ist angesagt? (20)

Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Contracts
ContractsContracts
Contracts
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Construction process
Construction processConstruction process
Construction process
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Tendering
TenderingTendering
Tendering
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Item rate contract
Item rate contractItem rate contract
Item rate contract
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 

Ähnlich wie Conditions Of Contract

Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practiceAditya Sanyal
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tenderneharajpl
 
5. international standard contract for construction
5. international standard contract for construction5. international standard contract for construction
5. international standard contract for constructionHyoyoung Kim
 
Mantenimiento y refaccion casa de justicia de riberalta (cubierta) beni
Mantenimiento y refaccion casa de justicia de riberalta (cubierta)   beniMantenimiento y refaccion casa de justicia de riberalta (cubierta)   beni
Mantenimiento y refaccion casa de justicia de riberalta (cubierta) benialbertoescobar52
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...
Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...
Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...GLC
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxMeneerGultom
 
Contrato de Servicios en Inglés – Service Provider Contract
Contrato de Servicios en Inglés – Service Provider ContractContrato de Servicios en Inglés – Service Provider Contract
Contrato de Servicios en Inglés – Service Provider ContractGlobal Negotiator
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
(Interior const) instruction to bidders
(Interior const) instruction to bidders(Interior const) instruction to bidders
(Interior const) instruction to bidderspiyush1266
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 
International construction contract
International construction contractInternational construction contract
International construction contractGlobal Negotiator
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 

Ähnlich wie Conditions Of Contract (20)

Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
5. international standard contract for construction
5. international standard contract for construction5. international standard contract for construction
5. international standard contract for construction
 
Tender
TenderTender
Tender
 
Mantenimiento y refaccion casa de justicia de riberalta (cubierta) beni
Mantenimiento y refaccion casa de justicia de riberalta (cubierta)   beniMantenimiento y refaccion casa de justicia de riberalta (cubierta)   beni
Mantenimiento y refaccion casa de justicia de riberalta (cubierta) beni
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Oht tender
Oht tenderOht tender
Oht tender
 
Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...
Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...
Contract Agreement for The Erection Work for Wood Chip Mill Equipment (Purcha...
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
 
Notes unit 2A.ppt
Notes unit 2A.pptNotes unit 2A.ppt
Notes unit 2A.ppt
 
Contrato de Servicios en Inglés – Service Provider Contract
Contrato de Servicios en Inglés – Service Provider ContractContrato de Servicios en Inglés – Service Provider Contract
Contrato de Servicios en Inglés – Service Provider Contract
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
(Interior const) instruction to bidders
(Interior const) instruction to bidders(Interior const) instruction to bidders
(Interior const) instruction to bidders
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
tendering
 tendering tendering
tendering
 
International construction contract
International construction contractInternational construction contract
International construction contract
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Contract management sys
Contract management sysContract management sys
Contract management sys
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 

Conditions Of Contract

  • 1. VOLUME - I TENDER AND CONTRACT CONDITIONS OCTOBER 2008
  • 2. VOLUME I TENDER AND CONTRACT CONDITIONS PAGE NOS. PART A - FORM OF TENDER A/1 - A/3 PART B - INSTRUCTIONS TO TENDERERS B/1 - B/11 PART C - FORM OF AGREEMENT C/1 - C/2 PART D - CONDITIONS OF CONTRACT GENERAL CONDITIONS CC/1 – CC/37 CONDITIONS OF PARTICULAR APPLICATIONS D/1 – D/38 PART E - DRAWINGS E/1 - E/3 ANNEXURE - LETTER OF ACCEPTANCE MIZIN AUTHORITY REQUIREMENTS FOR DESIGN ERECTION OF HOARDING WALLS
  • 3. PART A FORM OF TENDER
  • 4. FORM OF TENDER (The Appendix forms part of the Tender) To: …………………………….. P.O. Box ……………...….. ………………………….…. ………………………….…. Dear Sir, 1. Having examined the Instructions to Tenderers, Conditions of Contract, Drawings, Form of Agreement, Specifications and Bills of Quantities for the proposed Works, and having visited and examined the Site of the Works or caused it to be visited on our behalf by a competent and reliable person and having acquired all requisite information relating thereto as affecting this Tender, we the undersigned, hereby offer to construct, complete and maintain the whole of the said Works in conformity with the said Instructions to Tenderers, Conditions of Contract, Drawings, Form of Agreement, Specifications and Bills of Quantities for the Contract Price of or such other sums as may be ascertained in accordance with the said conditions. 2. We acknowledge that the Appendix forms part of our Tender. 3. We have priced the Bills of Quantities in detail and return them with this tender together with all the information requested in the Instructions to Tenderers and other Contract Documents. 4. We confirm that we have fully taken into account the Tender Circulars and Bulletins listed below, copies of which are returned with our Tender. .......…………........................................................................................................................... ....................………….............................................................................................................. ....................………….............................................................................................................. 5. We undertake if our Tender is accepted to commence the Works including erecting all site facilities required and to complete and deliver the whole of the Works comprised in the Contract within the time stated in the Appendix hereto. These periods include all Fridays, Public Holidays, etc., and other non-working days caused by inclement weather, etc., and shortened working hours during the Holy Month of Ramadan.
  • 5. 6. If our Tender is accepted we will, when required, obtain the guarantee of a Bank (to be approved by you and the Employer’s Representative) to be jointly and severally bound with us in a sum equal to the percentage of the Contract value as defined in Clause C.10 of the Conditions of Contract for the due performance of the Contract. We further agree to provide this bond upon receipt of the Employer’s Representative order to commence the Works. 7. In consideration of the trouble and expense incurred by you in preparing the contract and in examining and considering this Tender, we agree to abide by this tender for a period of 90 days from the date fixed for receiving the same and it shall remain binding upon us and may be accepted at any time before the expiration of that period. 8. We undertake in the event of this Tender being accepted to enter into an Agreement with you in the form annexed hereto which may be altered and added to in such manner as you may require for the purpose of adapting it to the circumstances of this Tender. 9. We understand that you are not bound to accept the lowest or any tender you may receive. 10. We herewith provide a Tender Bond Guarantee in the sum of five percent (5%) of the Tender Amount. Dated this.…........... day of .……..................................... Two Thousand and Eight Name …………………………………… (Signature.)....……...............…............................... Acting in the capacity of ....……..........……………………………………………................................... Duly authorized to sign Tenders for and on behalf of Full Name of Company ...............................................................…………………………… Address .......................................................................................…………. ............................................................................................………. ..................................................................................……………… Witness .........................................................................................………… Address ............................................................................…………………. Occupation ............................…................................................………………..
  • 6. Appendix to the Form of Tender Clause Amount of Performance Security 10.1 5% of the Accepted Contract Amount Minimum Amount of Third 23.2 Dhs. 5,000,000.00 Party Insurance for any one occurrence, number of Occurrences unlimited Commencement of Works 41.1 Date of receipt of Letter of Acceptance and Date of the building permit Time for Completion 43.1 16 months with final hand over of the project including final testing and including Mobilization commissioning Liquidated Damages for Delay 47.1 Dhs. 50,000.00 per day limited to a total of 10% of the Contract price Period of Maintenance 49.1 365 days Percentage for adjustment of Provisional Sums 59.4 (c) ……… percentage to be inserted by the Contractor Percentage of Invoice value of listed materials 60.1 (c) 75% Percentage of Retention 60.2 10% Limit of Retention Money 60.2 10% of the Contract Price Time within which payment to 60.10 30 days be made after Certificate Advance Payment 60.11 5% of the Contract Price against Bank Guarantee
  • 8. INSTRUCTIONS TO TENDERERS One set of the following tender document is issued for tendering: Letter of Invitation Volume 1 - Tender and Contract Conditions Volume 2 - Bills of Quantities Volume 3 - Civil General Specifications Volume 4 - MEP Specifications Volume 5 - Drawings Volume 6 - Soil Investigation Reports The following instructions should be carefully noted by intending tenderers as failure to comply with them may lead to invalidation of the tender. B.1 Scope of Works B.1.1 The Works forming part of this Tender comprises the construction, completion and drawings, specifications and bills of quantities contained in these tender documents. B.1.2 The Contractor shall allow for coordinating his work with the Enabling Works Contractor and any other separately employed contractors on site. B.2 Location of Site B.2.1 The site is located at Liwan, Dubai, U.A.E. as shown on the site plan. B.3 Title of the Works B.3.1 The title of the Works is: - “CONSTRUCTION OF BUILDING AT LIWAN, DUBAI, U.A.E.”
  • 9. B.4 Submission of Tenders B.4.1 The tenderer shall submit three (3) copies of tender documents, the copies to be marked quot;Originalquot;, 1st Copyquot; and quot;2nd Copyquot;, and one copy of tender drawings. The Form of Tender shall be signed by a duly authorised representative of the Company tendering and shall be stamped with the Company's stamp. B.4.2 Each page of the tender document and tender drawings is to be stamped with the Company's stamp and initialed by the duly authorised representative of the Company. B.4.3 Tenders shall be sealed in an envelope marked only: addressed and submitted at the office at the location specified in the invitation not later than the time and date specified in the Letter of Invitation. B.4.4 No alterations (other than filling the blanks intended to be filled in) shall be made in the Form of Tender and other sections of the tender Document. The tender Document shall be submitted intact with items in the Bills of Quantities fully priced and totaled, and in United Arab Emirates Dirhams, having a unit rate or price (as applicable) affixed to every item therein. B.4.5 If any alteration is made, except as aforesaid, and if these Instructions to Tenderers are not otherwise fully complied with, the tender will not be considered. B.4.6 There shall be no overwriting and any mistakes which are corrected shall be initialed by the duly authorized representative. B.4.7 The following supporting documents must be submitted in triplicate with the tender Documents. (a) A statement, signed by the Authorized Representative, stating that the tenderer has visited the site and that he has no queries on any matter concerning the contract. (b) A tender Bond in accordance with Clause B 18 of these Instructions to Tenderers (the original plus two photocopies). B.4.8 The tenderer shall submit with his tender proof of the Authorized Representatives authority, which shall be duly certified by an authorized officer of the Government of Dubai, United Arab Emirates. NEB – Tender and Contract Conditions B/2 October 2008
  • 10. B.5 Opening of Tenders B.5.1 The tenders will be opened in private at the convenience of the Employer. B.5.2 The Employer reserves the exclusive rights to accept or reject all or any part of the tender without stating any reasons. The Employer will not be responsible or pay far expenses or losses which may be incurred by any Tenderer for the preparation of the Tender. B.6 Visiting Site B.6.1 The Tenderer will be deemed to have visited the Site or caused it to be visited on his behalf by a competent and reliable person to obtain for himself on his own responsibility all information that may be necessary for the purpose of preparing a tender and entering into a contract. All costs and charges in connection with the above mentioned visits shall be borne by the Tenderer. B.7 Buildings, Work yards, etc. B.7.1 The Tenderer must examine and consider the Site and its surroundings, he must satisfy himself as to the nature of the existing works and buildings in the vicinity of the proposed Works, the nature of the existing roads or other means of communication, the access to and egress from the Site and Works, the available accommodation as regards land for temporary purposes (inside or outside the Site), the buildings that may be required for temporary purposes, and must make his own enquiries as to work yard sites and such other additional areas as he may require for temporary occupation all for the construction, completion and maintenance of the Works described in the Contract Documents. B.8 Physical Conditions B.8.1 The Tenderer must make local and independent examination and enquiries as to the physical conditions prevailing at the Site and obtain his own information on all matters and things that may in any way influence him in making a tender. He must also satisfy himself as to the risks, obligations and responsibilities to be undertaken in the Contract to be entered into by him should his tender be accepted. B.9 Materials, Labour, etc. B.9.1 The Tenderer must enquire and satisfy himself as to the source of supply, the sufficiency and the means of obtaining and transporting all materials, labour, fuel, water, electrical current for light and power and other things required for or in connection with the Works and he must consider all other matters and possible contingencies affecting the construction, completion and maintenance of the Works. B.10 Neglect to Obtain Reliable Information B.10.1 Any neglect or failure on the part of the Tenderer to obtain reliable information on the spot or elsewhere upon the foregoing or any other matters affecting the construction, completion and maintenance of the Works and the Contract shall not relieve the accepted Tenderer from any risks or liabilities or from the responsibility completing and handing over the Works all as defined in the Contract.
  • 11. B.11 Interpretation B.11.1 The Tenderer may request clarification or interpretation from the Employer’s Representative / Engineer of any aspect of the Tender Documents by facsimile or letter. The Employer’s Representative / Engineer's response will be made by facsimile or letter addressed to all Tenderers. Where such clarification or interpretation requires a change in the Tender Documents, the Employer’s Representative / Engineer will prepare and issue an addendum to the Tender Documents. B.11.2 The Employer’s Representative / Engineer will not be bound by, and the Tenderer shall not rely upon, any oral interpretation or clarification of the Tender Documents. B.11.3 Any request for clarification or interpretation should be received by the Employer’s Representative / Engineer not later than five days before the tender submission date. B.11.4 If the Tenderer requires clarification or interpretation in the final five days before tender submission date then he shall when submitting his tender set out in a covering letter the interpretation on which his tender has been based. B.12 Information Supplied Not Binding B.12.1 Neither the Employer nor the Employer’s Representative / Engineer nor any of their employees has any authority to make any representation or to give any explanation to Tenderers as to the meaning of the tender documents, or as to anything to be done or not to be done by the Contractor whose tender is accepted, or as to these Instructions, or as to any other matter or thing so as to bind the Employer or bind and fetter the judgment or discretion of the Employer’s Representative / Engineer in the exercise of their powers and duties under the contract, except in so far as the Employer’s Representative / Engineer may issue a formal Circular letter to all Tenderers, amending or explaining the tender documents, to be incorporated in to the Formal Agreement when the Contract is signed. B.12.2 No claim for an increase in any of the rates or prices shown in the Bills of Quantities or in any other rate or price to be determined in accordance with the Conditions of Contract shall be entertained nor shall the Contractor whose tender is accepted be entitled to pursue any claim on the grounds of any representation or on the grounds that they were supplied with information or given any promise or guarantee by the Employer or to the Employer’s Representative / Engineer or their employees or by any other person.
  • 12. B.13 No Alteration to Documents B.13.1 No unauthorized addition, omission or alteration is to be made by the Tenderer to the Tender Documents. If any such alteration is made or if these instructions are not fully complied with or if any incomplete tender is submitted, the tender may be rejected. Unpriced items shall be deemed to be included in the final tender price. B.13.2 It is a condition of tender that an offer must be submitted solely on the basis of the tender documents issued to Tenderers and must be free of all qualifications. Should Tenderers wish to submit an alternative offer to the Employer for consideration, such offer must be additional to and completely separate from the unqualified tender. B.13.3 Alternative designs will be considered if the Contractor can guarantee an earlier or more timely completion than that stated in the Contract. Fully detailed calculations shall be submitted in a covering letter with the tender to substantiate the alternative in a covering letter with the Tender. B.13.4 The tenderer should state on which of the alternative designs he has based his tender. He should insert quantities accordingly. B.14 Currency and Prices B.14.1 All prices quoted must be in U.A.E. Dirhams. Fractions of Dirhams shall be in Fils. B.14.2 The quoted tender price shall be valid during the whole period of the execution of the works. No compensation shall be made due to currency fluctuations. B.15 Acceptance or Rejection of Tenders B.15.1 The Employer does not bind himself to accept the lowest or any tender and will not assign any reason for the rejection of any tender. The Employer will not be responsible for or pay for any expenses or losses which may be incurred by any Tenderer in the preparation of his tender. B.16 Tender Prices B.16.1 Each and every page of the priced tender document is to be stamped and initialled by the Tenderer. All tender prices to be extended in ink. B.16.2 Any genuine arithmetical errors made by the Tenderer in extensions or totals in the Bills of Quantities and carried through to the Form of Tender will be corrected. The Tenderer must stand by his corrected Tender Price. B.16.3 In cases where unit rates included in the priced Bills of Quantities are found to be unacceptable to the Employer’s Representative / Engineer, the Tenderer shall amend his rate by such amount as agreed with the Employer’s Representative / Engineer. The price difference in the extended total for the item of work shall be carried through to the General Summary page and clearly described and referenced, and added to or deducted from the tender amount.
  • 13. B.16 Tender Prices [cont’d] B.16.4 The Tenderer will be required to provide the Employer’s Representative / Engineer with a full and detailed Tender Breakdown within 24 hours of being so requested. The breakdown will be required amongst other things to detail the calculations and build up of all rates into labour, material and plant with detailed quantity take-offs, on-costs, overheads and any other additions together with the calculation of preliminaries. B.16.5 The Contractor may be required, at his own expense, to visit the Employer's offices after submission of his tender in order to answer any queries raised by the Employer’s Representative / Engineer upon his tender. B.17 Tender Bond B.17.1 Tenderers shall provide an unconditional Tender Bond in favour of the party referred to as the Employer in these Tender and Contract Documents in an amount equal to 5% (five percent) of the Tender Amount stated in the Form of Tender. Such bond shall provide a surety or sureties satisfactory to the Employer to be jointly and severally bound with the Tenderer in a form approved by the Employer and the Employer’s Representative / Engineer. B.17.2 A bond in respect of another Tender is not acceptable as the Bond in respect of this Tender and a declaration to this effect, signed by the Tenderer and the bond surety or sureties shall be submitted with the Tender Documents. B.17.3 The security provided by unsuccessful Tenderers will be discharged three calendar months after the date fixed for delivery of Tenders to the Employer, or until such earlier date as a Tender shall have been accepted by the Employer and a Performance Bond shall have been duly provided by the Tenderer whose Tender is accepted. B.17.4 Notwithstanding the above mentioned period of three calendar months, the security provided by the Tenderer whose Tender is accepted shall be discharged only upon the receipt by the Employer of the Performance Bond referred to and defined elsewhere in these Contract Documents. B.17.5 If the Tenderer whose tender is accepted fails to provide the above mentioned Performance Bond at the time of receipt of the Employer’s Representative / Engineer's order to commence the full amount of the Tender Bond shall become payable to the Employer as compensation for such default. B.18 Validity of Tender B.18.1 Tenders shall remain valid and binding upon the Tenderers for a period of 90 days, with a provision for extension upon mutual agreement, commencing from the date fixed for delivery of tenders to the Employer and it may be accepted at any time before the expiry of this period.
  • 14. B.19 Tender Evaluation B.19.1 The Tenderer must be prepared to visit the Employer’s Representative / Engineer's offices in the period of tender evaluation to clarify and/or amplify any part of his tender in order to satisfy the Employer’s Representative / Engineer that he has carefully considered all matters affecting the execution of the work. B.19.2 All costs in relation to these visits shall be borne by the Tenderer. B.20 Tendering to be Confidential B.20.1 All Tenderers shall consider and treat all details in these Tender and Contract Documents as private and confidential. B.21 Language B.21.1 All correspondence in connection with this contract shall be in English. B.22 References B.22.1 The Tenderer shall submit with his tender, references of all key personnel to be involved with the contract. B.23 Manpower B.23.1 The Tenderer shall submit with the tender a schedule of proposed manpower for the entire duration of the project. B.24 Equipment and Plant B.24.1 The Tenderer shall submit with the tender a schedule of proposed equipment and construction plant for the entire duration of the project. B.25 Type of Contract B.25.1 This is a lump sum fixed price contract. Unless specifically described as being provisional or estimated, the quantities will not be re-measured. Notwithstanding the lump sum nature of the contract, the contract price upon completion of the works will be amended to include only the approved expenditure of provisional sums and dayworks. This is in addition to the other amendments that are necessary to be carried out as provided for in the conditions of contract. B.25.2 The Bills of Quantities have been prepared as estimated quantities and the Tenderer is responsible for the accuracy of the Quantities. No adjustments will be made in the event of any error in the Quantities being discovered after acceptance of the tender. The Bills of Quantities will be used to prepare interim Valuations and to value any Variations which may occur.
  • 15. B.25 Type of Contract [cont’d] B.25.3 The descriptions contained in the Bills of Quantities for each item are not necessarily complete. The Contractor is referred to the Conditions of Contract and other documents, Specifications and Drawings as well as relevant Standards and Codes of Practices for further information as no claim or variation will be considered on account of the Contractor's failure so to do. B.25.4 The Contractor is to execute the Works in accordance with the intent and meaning of the Drawings and Specifications and is to supply all items/accessories necessary for the proper execution of the Work and is to execute all Work which may be inferred whether or not specifically shown or described. B.26 Conditions of Contract B.26.1 The General Conditions of Contract comprise the “General Conditions”, which form part of the “Conditions of Contract for Works of Civil Engineering Construction” Fourth Edition 1987, with 1992 amendments published by the Federation Internationale des Ingenieurs-Conseils (FIDIC), and the following Part II “Conditions of Particular Application”, which include amendments and additions to such General Conditions. B.27 Time of the Essence B.27.1 The tenderers shall note that the completion period of the project is most important. B.27.2 To this end, the Employer will be very receptive to proposals for shortening the contract period by whatever possible means. B.28 Local Agent B.28.1 No tender will be accepted unless accompanied by a copy of a current and valid Trade License issued by Dubai Municipality in the name of the tenderer. In the event that the firm has not established an office in the Emirate of Dubai, then it must submit a letter stating the name and address of their local agent, countersigned by him and authenticated by the court concerned. B.29 Project Programme B.29.1 The Tenderer shall submit a proposed overall construction programme. The time scales shall be indicative of the periods in which the works have been planned to be carried out. B.29.2 The Employer reserves the right to impose a financial penalty, pro-rata to the percentage of the value of each package in relation to the Contract Price and Liquidated damages. In the event the Contractor achieves the final completion date or the next agreed milestone, financial penalties incurred would be reimbursed. Any penalties imposed shall be limited to 10% of the package value.
  • 16. B.30 Completion in accordance with Programme B.30.1 The Tenderer is to allow for all necessary overtime or additional shifts in his tender to ensure compliance with the programme for the Works. Under no circumstances shall any claims for additional costs due to overtime or additional shift working required to complete the Works on time be entertained. B.31 Bona Fide Tender B.31.1 The Tenderer must not discuss this tender or any aspect of it with any third party. Any evidence of collusion or collaboration will result in rejection of the Tender. B.32 Manufacturers / Suppliers of Materials B.32.1 The tenderer shall consider using locally available materials provided those materials comply with the specification. B.33 Particulars to be submitted with Tender B.33.1 Tenderers shall submit with their tenders the following particulars:- (a) a copy of each Circular Letter to Tenderers issued by the Employer’s Representative / Engineer, if any, which must be endorsed by the Tenderer. (b) a Method Statement giving in outline and detail their general scheme and programme of the execution of each section of the Works in the form of a bar chart; the programme shall be separated into sections to show how the various elements of the works are to be integrated and shall incorporate in detail the work of all sub-contractors ; (c) particulars of their proposed site organization including CVs of senior staff and the labour force they propose to use, giving details of the number of workmen to be employed during the contract; (d) particulars of the plant they propose to use ; (e) a list of the Sub-Contractors, including local firms they propose to use with particulars of the extent of the work which will be undertaken by them : (f) the sources from which they propose to obtain their local materials and aggregates ; and details of all other sources and types of materials where these vary from the specification, (g) their forecast of certificate payments in the form of a cash flow chart. (h) a proposed Site layout which should clearly show the position of all temporary works, offices, stores, sheds, work areas, etc. in relation to the permanent works, access to the Site, temporary roads within the Site, etc. (i) particulars of their proposed piling method as required by the Specification. (j) A Site Access Plan including estimated traffic movements for the duration of the Contract. All approved proposals will be binding on the Contractor and can only be altered at the
  • 17. Employer's or Employer’s Representative / Engineer’s discretion. B.34 Alternative Tenders: B.34.1 In the event that the Tenderer wishes to submit and alternative tender based on specifications other than those in the Tender Documents, this alternative will only be considered provided that a Tender fully complying with the conditions laid in the Tender Documents is also submitted. The Tenderer shall give full details of such alternative specifications together with the effect, if any, on the Tender Sum. The Employer shall be free to accept whichever Tender he may choose. Alternative Tender must be submitted along with the main Tender and shall be endorsed “Alternative No. 1” B.35 Value Engineering B.35.1 In the event the proposed Contract Price is over and above the Employers Budget, the Contractor may be requested to participate in Value Engineering exercise. The Employer also reserves the right to transfer the any parts of work to Provisional Sums and nominating a Specialist Subcontractor.
  • 18. SPECIMEN FORM OF TENDER BOND To : …………………… P.O. Box ………… Dubai U.A.E. We have the honour to inform you that we guarantee Messrs ...................................................................……..................…............................................... for the amount of ..................................................................………...…............................................. ...............................................................................................(Dhs……..............................................) as guarantee for their good intention in the presentation of their Tender for construction, completion, maintenance and delivering up of the above-named works mentioned in conformity with the provision of the Contract Documents. This guarantee shall remain valid and irrevocable for a period of ninety (90) days starting at twelve (12) o'clock on the date indicated in your letter of invitation to tender. In the event of Messrs ..................................................................................……….......................... ..................................................................................................................................………................ ................................................................. withdrawing their tender before the expiration of the period of validity of this letter of guarantee we definitely undertake to deposit with you upon demand and not withstanding any objection on the part of the said Messrs .....................................................................................................................………......... .....................................................................................................................................................…… the aforesaid sum of ........................................................................................................................… .......................................................................................................................................…. in cash. Yours faithfully Signature
  • 19. PART C FORM OF AGREEMENT
  • 20. FORM OF AGREEMENT THIS AGREEMENT made the .................. day of ................................. 2008 BETWEEN WHEREAS the Employer is desirous that certain Works should be executed, namely construction, completion and remedying of any defects of Residential Building at Liwan, Dubai, U.A.E. and has accepted a tender by the Contractor for undertaking such works. NOW THIS AGREEMENT WITNESSES as follows:- 1. The Employer will pay to the Contractor the sum of………………………………………………….... ...................................................................................................................... (hereinafter referred to as the quot;Contract Pricequot;) or such other sum as shall become payable under the Contract. 2. In this Agreement words and expressions shall have the same meanings as are respectively assigned to them in the Conditions of Contract hereinafter referred to. 3. The following documents shall be deemed to form and be read and construed as part of this Agreement, viz:- (a) The Conditions of Contract (b) The Drawings (c) The General Specification (d) The Priced Bills of Quantities (e) The Form of Tender (f) Appendices (g) The Letter of Acceptance (h) The Instructions to Tenderers (j) Any other documents mutually agreed to be signed and dated at this time and listed hereunder: ..…......………............................................................................................................. ..…......………............................................................................................................. 4. In consideration of the payments to be made by the Employer to the Contractor as herein mentioned the Contractor hereby covenants with the Employer to undertake the Works in conformity in all respects with the provisions of this Agreement. 5. The Employer hereby covenants to pay the Contractor in consideration of the completion of the Works the Contract Price within 30 days of acceptance of the Contractor’s final report.
  • 21. Form of Agreement IN WITNESS whereof the authorized representative of the parties have hereunto set their respective hands the day and year first above written. SIGNED BY................................………….................... SIGNED BY...................................................…………. for and on behalf of THE EMPLOYER In the presence of :- Signature..................................................... Address....................................................... Occupation.................................................. SIGNED BY................................................…………… for and on behalf of THE CONTRACTOR In the presence of :- Signature..................................................... Address....................................................... Occupation..................................................
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57.
  • 58.
  • 59.
  • 60.
  • 61.
  • 62. CONDITIONS OF PARTICULAR APPLICATIONS
  • 63. Part D _____________________________________________________________ PART 1 GENERAL CONDITIONS The General Conditions of Contract shall be the Conditions of Contract for Works of Civil Engineering Construction, (Fourth Edition 1987 – reprinted 1988 with editorial amendments and reprinted 1992 with further amendments) published by the Federation Internationale des Ingenieurs – Conseils (FIDIC) and shall be amended and added to in accordance with the following Part II entitled “Conditions of Particular Application”. Tenderers are deemed to be in possession of their own copy of this document. The Clauses in Part II Conditions of Particular Application shall take precedence over the Clauses of the General Conditions of Contract.
  • 64. Part D _____________________________________________________________ PART II CONDITIONS OF PARTICULAR APPLICATION Note: Clause reference numbers refer to Clause numbers in the General Conditions of Contract where applicable. Definitions Dubai, U.A.E (x) The quot;Quantity Surveyorquot; is Dubai, U.A.E Engineer’s Duties and Authority 2.1(b) Before exercising his authority under the following Clauses of the Contract, the Engineer is required to obtain the specific approval of the Employer. Clause 2.3 Authority to Delegate Clause 2.4 Appointment of Assistants Clause 4.1 Subcontracting Clause 14.1 Programme Clause 15.1 Contractor's Superintendence Clause 44.1 Extension of Time Clause 48 Taking-Over Certificate Clause 51.1 Variations Clause 52.1 Valuation of Variations Clause 52.2 Power to Fix Rates Clause 58.2 Use of Provisional Sums Clause 60.8 Final Certificate Clause 62.1 Defects Liability Certificate
  • 65. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Language 5.1(a) The Contract Documents shall be drawn up in the English and Law language. (b) The Contract shall be governed by and construed according to the Laws in force in Dubai, U.A.E. (c) The Contractor shall conduct all correspondence with the Employer and the Engineer in English language. Priority of 5.2 Add the following: Contract Documents If any discrepancies occur between the contracts documents, the Engineer has the right to choose any of the specified materials and the Contractor to price the items considering such errors or mistakes. Supplementary 7.1 Add the following: Drawings and Instructions The Contractor shall give the Engineer reasonable notice of any additional design drawings, specifications or instructions required to define the Works in greater detail or to permit the proper progress of the Works. Failure to give notice under sub-clauses 6.3 and 7.1 will remove the Contractor’s right to claim for extensions of time under sub-clause 6.4. The Contractor shall not be entitled to additional payment if such drawings do not incur the contractor in additional work. Contractor’s 8.4 The contractor shall perform all his obligations under the Contract Obligations strictly in accordance with the standards of skill, care and diligence adhered to by experienced and competent contractors specialising in work of the particular type, nature and magnitude, and shall not unreasonably object to any measures adopted by the Engineer in the general interest of works and quality control. Delete Sub-clause 11.1 of the General Conditions and insert the following: Inspection 11.1 The Contract shall be deemed to be based on of Site the understanding that the Contractor is completely familiar with the physical conditions prevailing at the Site. No additional payment in respect of the above will be considered.
  • 66. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Sub-clause 14.1 and 14.2 of the General Conditions are deleted and the following substituted: Programme to 14.1 The Contractor shall submit to the Engineer/ the Employer, within be Submitted 28 days after the date of Letter of Acceptance, for their consent, a programme (three paper copies and one electronic copy in Primavera Version) in a form prescribed hereunder, for the execution of the Works. The Contractor’s first monthly payment will be dependent upon the consent, by the Engineer, of the said programme. The Contractor shall also submit: a) a general description of the arrangements and methods which the Contractor proposes to adopt for the execution of the Works. b) a schedule of submission of shop drawings indicating the approved required-by date. c) fabrication schedules. d) material procurement schedules. e) a cash flow forecast by loading each activity in the Base Line by the equivalent Budgeted cost. f) a subcontractors’ procurement schedule. g) a list of key project indicators e.g. concrete, formwork, blockwork etc. h) the Contractor shall coordinate with the Engineer/ the Employer for the required dates for appointment of all PC & PS items taking into consideration that none of the PC & PS items shall commence prior to 5 months of project commencement dates. Items (a), (b), ( c), (d), (e), (f) and (g) are to be in line with the programme. The programme shall include the following: 1. A critical path analysis. 2. Total and free floats. 3. Duration of each activity. 4. Early start, early finish, latest start and latest finish of each activity. 5. Critical activities. 6. Predecessors and successors. 7. The programme shall be resourced and the manpower and plant requirements and cost of each items are to be indicated time unit wise. 8. The footer shall include a revision box, programme number and the issue date. 9. The header shall include the project title and programme title. 10. The package numbers together with the subcontractors’ names. 11. The activities shall also show relationship between procurement, construction and installation.
  • 67. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Recovery 14.2 If at any time it should appear to the Engineer that the Programme actual progress of the Works does not conform to the approved programme referred to in Sub Clause 14.1, the Contractor shall produce within 7 days of being so requested by the Engineer a recovery programme showing the modifications to the approved programme necessary to ensure completion of the Works within the time for completion as defined in Clause 43 of the Conditions of Contract. Cash Flow 14.3 Submit the cash flow estimate within 28 days after the date of the Estimate Letter of Acceptance. Contractor not 14.4 The submission to and consent by the Engineer of such Relieved of programmes or the provision of such general descriptions or cash Duties or flow estimates shall not relieve the Contractor of any of his duties Responsibilities or responsibilities under the Contract. Contractor 14.5 The Contractor is requested to submit daily, weekly and Reports monthly reports in accordance with the common standards and practice. All the above reports format to be in compliance with the Engineer / the Employer’s planning and scheduling requirements. Contractor's 15.2 The Contractor's authorised representative shall be fluent Superintendence in English. Setting Out 17.1 In line 10 after quot;Employerquot;, the following sentence is to be added. quot;Provided that the expense of rectifying any errors shall be borne by the Contractor if such error results from incorrect data on the Drawings or in the Specifications which were used for Tender purposes which Drawings and Specifications are deemed to have been carefully studied by the Contractor and accepted by him as being correct unless he has notified the Engineer in writing of such errors at the time of tenderingquot;. Employer's 20.4 Delete sub-clause 20.4(h). Risks Accident or 24.1 After each reference to Employer, insert 'and Engineer'. Injury to Workmen Transport of 30.2 This clause is deleted and the following substituted: Contractor’s Equipment or Temporary Works “Should it be found necessary for the Contractor to move One or more loads of constructional plant, machinery or pre- constructed units or parts of units of work over part of a highway or bridge, the moving whereof is likely to damage any highway or bridge unless special protection or strengthening is carried out, the Contractor shall before moving the load on to such highway or bridge, give notice to the concerned owner or Government
  • 68. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Department. All costs, expenses, delays and the like arising therefrom shall be the entire responsibility of the Contractor. No claim will be allowed by the Engineer for any such costs, expenses, delays and the like. After Sub-clause 34.1 insert the following: Accident 34.2 The Contractor shall have on his staff at the Site an officer Prevention dealing only with questions regarding the safety and protection Officer, against accidents of all staff and labour. This officer shall be Accidents qualified for this work and shall have the authority to issue instructions and shall take protective measures to prevent accidents. Health and 34.3 Due precautions shall be taken by the Contractor, and at his own Safety cost, to ensure the safety of his staff and labour and, in collaboration with and to the requirements of the local health authorities, to ensure that medical staff, first aid equipment and stores, sick bay and suitable ambulance service are available at the camps, housing and on the Site at all times throughout the period of the Contract and that suitable arrangements are made for the prevention of epidemics and for all necessary welfare and hygiene requirement. Supply of 34.4 The Contractor shall, so far as is reasonably practicable, having Water regard to local conditions, provide on the Site an adequate supply of drinking and other water for the use of his staff and labour. Alcoholic 34.5 The Contractor shall not, otherwise than in accordance with the Liquor or Statutes, Ordinances and Government Regulations or Orders for Drugs the time being in force, import, sell, give, barter or otherwise dispose of any alcoholic liquor or drugs, or permit or suffer any such importation, sale, gift, barter, or disposal by his sub- contractors, agents, staff or labour. Arms and 34.6 The Contractor shall not give, barter or otherwise dispose of to Ammunition any person or persons, any arms or ammunition of any kind or permit or suffer the same as aforesaid. Festival 34.7 The Contractor shall in all dealings with his staff and labour have and Religious due regard to all recognised festivals, days of rest and religious or Customs other customs. Disorderly 34.8 The Contractor shall at all times take all reasonable precautions Conduct to prevent any unlawful, riotous or disorderly conduct by or amongst his staff and labour and for the preservation of peace and protection of persons and property in the neighborhood of the Works against the same.
  • 69. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] After Sub-clause 35.1 insert the following: Reporting 35.2 The Contractor shall report to the Engineer details of any to Accidents accidents as soon as possible after its occurrence. In the case of any fatality or serious accident, the Contractor shall, in addition, notify the Engineer immediately by the quickest available means. Cost of test not 36.4 Sub – clause 36.4 is deleted entirely & Substitute: - provided for 36.4.1 The Contractor shall allow in his pricing for all tests as necessary to be carried out on the materials due for incorporation into the works. The Contractor shall note that it may be required that the Engineer will have to visit the factories of various manufacturers in order to establish and monitor testing procedures and the Contractor’s price is deemed to have included for providing such provisions. 36.4.2 The Contractor is to submit samples of all materials and / or catalogues requested by the Engineer, and the cost for the same is deemed to be included in the Contract. Samples of workmanship requested by the Engineer shall be provided by the Contractor and the cost for the same is deemed to be included in the Contract. 36.4.3 The Contractor is to carry out tests of materials as required by the Engineer and the cost for the same is deemed to be included in the contract. Time for Completion 43 Delete quot;calculated from the last day of the period named in the appendix to the Tender as that within which the Works which are to be commencedquot; and Substitute quot;calculated from the date of the Engineer's written order to commence the Works on Site”. Cost of Overtime 45.2 After Sub-clause 45.1 insert the following: The rates wherever applicable to be used for calculating overtime for the Engineer and the Design Consultant will be as follows: Overtime Dhs/hr Resident Engineer / Project Manager 350 Structural Engineer / Architect 250 MEP Engineer 250 Site Engineer 200 Quantity Surveyor 250
  • 70. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Penalty for Delays 47.1 After Sub-clause 47.1 insert the following: If the amount of penalty for delays payable to the employer should reach 10%, The Employer has the right to take over the project and complete it and charge any extra cost over the contract amount to the contractor. This is in addition to the 10% penalty and excluding consultant supervision fees for additional time of construction. Reduction of penalty 47.2 This clause has been entirely deleted. for delay. Concurrent Delays 48.5 Add the following: In the event of concurrent delays, client will not pay any prolongation costs and Contractor to consider that this clause will supersedes any clauses that may contradict with the content of this clause.” Quantities 55.1 The Contractor shall be deemed to have satisfied himself as to the accuracy of the quantities (except for any provisional items and/or provisional quantities) and to have included in the Contract Price for all variances in measurements and inserting appropriate prices in the Bills of Quantities where provision is made for the Contractor to price such variances. Any error in the description in or any omission from the Bill of Quantities shall not vitiate the Contract nor release the Contractor from the execution of the whole or any part of the works according the drawings and specifications or from any of his obligations or liabilities under the contract. Quantities not to 55.2 The quantities shall not be subject to re measurement. Any errors Be remeasured shall not be adjusted in accordance with Clause 51 here in. Works to be 56.1 This clause has been deleted and substitute: remeasured “This is a Lump Sum Contract and therefore the works shall not be subject to re-measurement except where specifically ascertain and determine by reference to the Contract Price. The value of the works in accordance with the Contract and the Contractor shall be paid that value in accordance with clause 60. The Engineer shall, when he requires any variations or provisional items to be measured, give reasonable notice to the Contractor’s authorised agent, who shall: a) forthwith attend or send a qualified representative to assist the Engineer in making such measurements and b) supply all particulars required by the Engineer.
  • 71. _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Definition of 59.1 Add the following: “Nominated Subcontractors” The contractor has to prove within 28 days from the receipt of the nomination letter from the Engineer that he entered in a Sub contractor agreement with the nominated Subcontractor. Nominated 59.2 Insert after sub clause 59.2(b) the following: Sub-Contractors Objection to Nomination c) that the sub-contract works shall be completed within the period or (where they are to be completed in sections) periods therein specified. The Contractor shall not without the written consent of the Engineer grant any extensions of time for completion of the sub-contract works or any sections thereof, and the Contractor shall inform the Engineer of any representations made by the nominated sub-contractor as to the cause of any delay in the progress or completion of the sub-contract works or any section thereof. d) that if the nominated sub-contractor shall fail to complete the sub-contract works or (where the sub-contract works are to be completed in sections) any section thereof within the period therein specified or within any extended time granted by the Contractor with the written consent of the Engineer and the Engineer certifies in writing to the Contractor that the same ought reasonably so to have been completed, the nominated sub-contractor shall pay or allow to the Contractor either a sum calculated at the rate therein agreed as liquidated and ascertained damages for the period during which the said Works or any section thereof, as the case may be, shall so remain or have remained incomplete or (where no such rate is therein agreed) a sum equivalent to any loss or damage suffered or incurred by the Contractor and caused by the failure of the nominated sub-contractor as aforesaid. f) that the Contractor shall retain from the sum directed by the Engineer as having been included in any certificate issued a percentage (which percentage shall be equal to the percentage currently being retained by the Employer) or such value; and that if and when such sums or any part thereof are released to the nominated sub-contractor they shall be paid in full within three (3) days of receipt by the Contractor of payment from the Employer. g) that the Engineer shall have the right of access to the workshops and other places of the nominated sub-contractor. h) that the employment of the nominated sub-contractor under the sub-contract shall determine immediately upon the determination (for any reason) of the Contractor's employment under this Contract unless at the time of such determination the Employer requires the Contractor to assign to him the benefit of the sub-contract.
  • 72. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] j) that in the event of the last paragraph of Clause 59.5 hereof being operated by the Engineer the nominated sub-contractor shall indemnify the Contractor against any claim which the Employer might make in respect of latent defects in the Sub-contract Works. k) that the Contractor shall obtain the approval of the Engineer of all forms of Sub-Contract Agreement he proposes to enter into with each nominated Sub-Contractor. m) the time for the contractor to raise reasonable objection against the nomination to be defined as seven (7) days. Therefore the contractor has to proof within seven (7) days from the receipt of the nomination letter from the engineer that he entered in a sub contractor agreement with the nominated sub contractor unless otherwise reasonable objection raised. Payments to 59.4 Add the following: Nominated Subcontractors: The contractor before raising the next payment certificate to enclose a proof that all the nominated Subcontractors payments have been released, paid and received by the nominated Subcontractor within three (3) days after receipt by the Contractor, without proofing the same the Engineer may suspend the Contractors payments waiting for him to pay the payments due to the nominated Subcontractors or to recover the same payments from the contractor payment and pay it to the nominated Subcontractors. Penalty clause to be generated on the delay of the As built and guarantee delay. Monthly Statements 60.1 Add the following at the end of Clause 60.1 (c): Materials on site shall only be paid at the percentage stated in the Appendix to tender only when the Engineer and Employer Representative is satisfied that the materials have been delivered to site for timely incorporation into the works. (i.e. not prematurely). Advance payment 60.11 An Advance payment in percentage as stated in the Appendix to the Tender shall, following the presentation by the Contractor to the Employer of an approved performance security in accordance with Sub-Clause 10.1, insurances required to be effected by the Contractor and a guarantee in terms approved by the Employer, for the full advance payment, be certified by the Engineer for payment to the Contractor. The Advance payment security shall be in the form as annexed to these Conditions of Contract. Such guarantee shall be progressively reduced by the amount recovered by the Contractor as indicated in interim certificates of the Engineer issued in accordance with this Clause.
  • 73. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Advance payment 60.11 The advance payment shall not be subject to retention. The [cont,d] advance payment shall be recovered by way of reduction in interim certificates commencing with the first certificate. The amount of reduction in each interim certificate shall be at the same % as stated in the Appendix to the Tender, for the purpose of this Clause, of the gross certified value in such interim certificates until the advance payment has been recovered in full, subject to the provision that the full value of the advance payment shall be recovered within a period of 30 days prior of completion date. Upon the happening of any of the events specified in Sub-Clause 63.1 or termination under Clause 65, 66, or 69, the whole of the balance then outstanding shall immediately become due and payable by the Contractor to the Employer. Arbitration 67.3 Following paragraph (b), delete the words quot;shall be finally settled unless otherwise specified in the contract, under the Rules of Conciliation and Arbitration of the International Chamber of Commercequot; and substitute quot;shall be finally settled under the Rules of Arbitration and Conciliation of the Dubai Chamber Commerce and Industryquot;. Notice to 68.2 All notices to be given to the Employer or to the Employer’s Employer or Representative / Engineer under the terms of Contract shall be Employer’s served by delivering the same to:- Representative Employer - Dubai U.A.E Employer’s - Increase or 70.1 No adjustments to the Contract Price shall be made in Decrease of Cost respect of rise or fall in the costs of labour and/or plant and/or materials or any other matters affecting the costs of the execution of the Works except as provided elsewhere in the Contract. Subsequent 70.2 Delete quot;after the date 28 days priorquot; and replace with Legislation quot;subsequentquot;.
  • 74. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Currency 71.1 Delete Sub-clause 71.1 and replace with: Restrictions The Contractor shall allow in his contract price for all effects of currency restrictions and/or transfer of currency restrictions which may be imposed by the Government or authorised agency of the Government of the country in which the Works are being or are to be executed before or during the period of the Contract. The Employer shall not have any liability or responsibility to reimburse the Contractor for any loss or damage to the Contractor arising from such restriction. Rates of 72.1 Sub-clause 72.1 is deleted. Exchange Currency 72.2 Sub-clause 72.2 is deleted. Proportions Currencies 72.3 Sub-clause 72.3 is deleted. of Payment for Provisional Sums Law to Apply 73. The Contract shall in all respects be construed in accordance with the Law of Dubai and U.A.E. and any difference that may arise between the Employer and the Contractor in regard thereof shall be settled in accordance therewith. Compliance with 74. The Contractor's operations and proceedings in connection Local Laws and the Works shall at all times during the continuance of the contract Regulations be conducted in accordance with Local Laws and Regulations for the time being in force in Dubai. The Contractor shall also comply with the bye-laws and regulations of all authorities (if any) having jurisdiction over or in connection with the Works on Site or other operations such as those carried out by the Contractor and shall give all notices required by such bye-laws and regulations. Hospital and medical regulations in force for the time being shall also be complied with by the Contractor, his sub-contractors, employees and workmen. Taxation 75. The Contractor shall pay all Government and Municipal taxes including road taxes and vehicle registration fees, building permit and inspection charges and any taxes which may in the future be levied on the Contractor or his expatriate employees whilst employed on this project. Details 76. The Contractor shall treat the Contract and everything Confidential contained therein as private and confidential. In particular, the Contractor shall not publish any information, drawing or photographs concerning the Works and shall not use the site for the purpose of advertising except with the written consent of the Employer and subject to such conditions as he may prescribe.
  • 75. 1 Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Bribery 77. Any commission, advantage, gift, gratuity, reward or bribe given, promised or offered by or on behalf of the Contractor or his agent or servant or any other person on his or their behalf to any officer, servant, representative or agent of the Employer or the Engineer or to any person on their behalf or on behalf or on of any of them in relation to the obtaining or to the execution of this or of any other contract with the Employer shall, in addition, to any criminal liability which may be thereby incurred, subject the Contractor to the cancellation of this and of all other contracts with the Employer and also the payment of any loss or damage resulting from such cancellations. Service Authorities 78. The Contractor shall comply in all respects with the regulations of all Service Authorities whether for temporary or permanent work in connection with those Authorities in carrying out his obligations under the Contract. Work on Adjoining 79.1 The Contractor shall neither be entitled to claim indemnity or Site extension of time for the works nor to be excused from any of the obligations of the Contract by reason of or to submit any claim in respect of disturbances or delay due to the simultaneous execution of work adjoining the Site. Indemnity to the 80.1 The Contractor shall indemnify the Employer and the Employer’s Officials Employer's Representative and every member, officer and and Engineer employee thereof and the Engineer and the Engineer's Representative and every member of their staff from any claim or demand for accident, injury, damage, loss and/or compensation of any kind whatsoever arising out of or in connection with all claims and demands which may be made against the Employer for or in respect of or arising out of any failure by the Contractor in the performance of his obligations under any of the provisions of the Contract. 80.2 If the Employer has to pay any money in respect of any claims or demands as aforesaid, the amount so paid and the cost incurred by the Employer shall be charged to and paid by the Contractor, provided always that the Employer, shall, if circumstances permit, give to the Contractor reasonable opportunity of examining such claims or demands before payment. In the event of the Contractor disputing the amount of any payment (except payments made in accordance with legal obligations or after approval by the Contractor) then the Contractor shall have the right to dispute the matter, and refer it to Arbitration in accordance with the provisions herein contained.
  • 76. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Decennial 81.1 The Contractor shall be liable for the consequence or errors, Liability omissions or negligence on his part and in particular he shall be liable for any defects in the construction of any part of the Works where such defects are due to any error, omission or negligence of the Contractor or his staff provided that such defects become apparent during the period of ten years from the issue of the Taking-Over Certificate for the part of the Works in question. The liability of the Contractor shall in any event be limited to the cost of rectification of the Works. The approval of the Engineer shall not in any way absolve or relieve the Contractor from any such obligations, responsibility or liability. Contractor 82.1 The Contractor shall be responsible for the collection of the to collect permit documentation from Dubai Municipality and pay all Permit necessary fees for this collection within two working days from receiving written instructions from the Engineer. Contractor 82.2 The Contractor shall be responsible for completing the Works in to obtain accordance with the Building Permit and to the satisfaction of the Municipality Dubai Municipality. He shall be responsible for arranging Completion inspection by the Municipality and for obtaining the Municipality’s Certificate Certificate of Completion and other approvals necessary for the connection of services, in order to ensure completion of the Contract. Contractor 82.3 On receipt of the Municipality building permit the Contractor shall to Advise of examine all the documentation handed over by Dubai Dubai Municipality as part of the building permit and advise the Municipality’s Engineer in writing within 14 days from the date of receipt of any Comments comment or special requirement stated by Dubai Municipality on any of the documents which make up the Municipality building permit. Failure of the Contractor to submit such advice within the prescribed period of 14 days shall be deemed to be confirmation to the Engineer and the Employer that the Works required in this Contract have received the mandatory Municipality building permit, relieving the Employer thereafter from any responsibility to liaise with Dubai Municipality for obtaining any permit in connection with the Works required in the Contract and from considering any claim by the Contractor for any extension of time or additional payments due to extra work resulting from comments made in writing by the Municipality on any of the documents of the Municipality building permit.
  • 77. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Inspection 83.1 Upon the written request of the Contractor to the Engineer, for the Engineer will issue a letter stating that the Works are Municipality complete to allow the inspection of the Municipality for the Certificate Municipality Completion Certificate to take place, provided always of Completion that the Engineer shall be satisfied that the Works are complete to this extent. If the Works are not complete to the satisfaction of the Engineer, the Contractor will be required to complete the necessary works and issue further request. The issuance of the letter referred to in this Clause by the Engineer shall not constitute completion within the meaning of Clause 48 or shall have any meaning other than that the Works are complete for the purpose of initiating the inspection for the Municipality Completion Certificate. Contractor 83.2 In addition to the requirements of Clause 48, the Contractor is solely required to complete the Works necessary for obtaining the responsible Municipality Certificate of Completion defined in Clause 85 and for obtaining 86 by the Milestone Date shown in the programme referred to in Municipality Clause 14. The Contractor’s failure to obtain this certificate for Certificate of any reason other than reasons which entitle the Contractor within Completion the provision of the Contract to an Extension of Time, shall be the sole responsibility of the Contractor and shall not constitute any ground for an Extension of Time or additional costs Permanent 84.1 The Contractor shall be responsible under this Contract to liaise Electricity, with all Statutory Authorities to ensure that the work is carried out Water, to their latest regulations and rules regardless of the fact that the Telephone and Engineer has already liaised with such Authorities prior to the Drainage award of this Contract. Contractor 84.2 Notwithstanding his responsibility under sub-clause 87.1, the to Advise of Contractor shall within 28 days of the notice to commence the Statutory Works contact all Statutory Authorities and discuss in detail with Authorities’ them the requirements of the Works. He shall be responsible to Changes ensure that no rules, regulations or requirements of the Statutory Authorities have changed, or that the Authorities require any details for the Works which are different from those included or inferred in the Contract, which may cause a variation to the Contract. If any changes are required by the Statutory Authorities, the Contractor shall inform the Engineer within a further 14 days (i.e. within 42 days of the notice to commence) giving full details of the consequence of these changes including details of costs and programme. If no notification has been received by the Engineer within the time stipulated, it will be deemed that no variation will be necessary and the Contractor will forfeit his rights to any additional time or costs due to any subsequent Statutory Authorities requirements. Contractor to 84.3 The Contractor shall liaise with all Statutory Authorities Obtain full throughout the Contract and shall be responsible for obtaining full Approval of approval of the Authorities and connections as required by the Statutory Authorities Contract.
  • 78. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Employer 84.4 The Employer shall be responsible to pay directly to the relevant Responsible to authority all charges and fees which are necessary for the Pay Fees completion of the Works. The Contractor shall be responsible for giving the Employer two (2) weeks notice that the payment is due. Delay to 84.5 In the event that the supplies of permanent services to the site are Permanent delayed for reasons for which the Contractor is not responsible Services and under the contract, the final commissioning of the building may be Commissioning delayed but the Contractor shall complete all testing required under the Contract using temporary supplies for which he shall be responsible. In this event the Contractor shall be awarded an extension of time in accordance with Clause 44.2 for the commissioning only. The commissioning shall be completed within 4 weeks from the connection of the permanent services, or such other time as may be specified by the Engineer. If the commissioning is not completed within this period, the Contractor shall pay liquidated damages as defined in Clause 47.1 and 47.2. If an extension of time is given for this reason the Contractor shall be entitled to any expense which he demonstrates that he has incurred as a result of the delay provided such claims are submitted in accordance with Clause 52.2. Contractor’s 85.1 All Contractor design items are to be carried out by an Engineer Design Items who is approved by the Employers Engineer for each particular discipline. The Contractor shall maintain a design indemnity insurance policy covering for a period of ten (10) years all designs carried out by the Contractor and incorporated in the Works. Separate to 86.0 The Employer reserves the right to omit any part of the works or Contracts with let separate contracts in connection with the undertaking of the other Contractors works and may form part of the works in order to substantially complete the works. The Contractor shall carryout properly and coordinates his work with that of the other Contractors. If any part of the Contractors work depends for its proper execution or results upon the work of any other Contractor, the Contractor shall in writing report promptly to the Engineer any defects in the work of such other Contractors as may interfere with the proper execution of the Contractors works. The Employer can, with 7 calendar days written notice of intention to do so, adjust the Contractors scope of works by removing sections of works and having them completed by other Contractors appointed by him. The cost of the works will be deducted at their contracted cost plus overhead, profit and preliminaries, this deduction is not related to and is in addition to any Liquidated Damages costs recovered under the contract. Where preliminaries items have to be completed by others these will be deducted from the Contractors account at full cost including supervision. The Contractors duties will remain in line with his contractual obligations to Employers direct contractors. Should it be necessary to transfer the Building Permit to another Contractors name the Contractor shall do so within 7 calendar days of a written request by the Employer.
  • 79. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Engineer’s and 87.0 The Contractor shall provide Engineer’s and Contractor’s site Contractor’s Site offices, facilities, site management team, parking, etc all as Requirements specified and herewith. a) SITE MANAGEMENT The Contractor shall allow for all site management. He shall maintain adequate site organization under the control of qualified and experienced staff that is capable of assuming complete responsibility for a contract of this nature: 1. Project Manager – 1 No ( Full time ) 2. Project Engineer – 1 No ( Full Time ) 3. Quantity Surveyor – 1 No ( Full Time ) 4. Planning Engineer – 1 No ( Full Time ) 5. Supervision Team 5.1 Civil Engineers – Minimum 2 Nos. 5.2 Materials Engineer – 1 No – as and when required. 5.3 Services Engineers for Elec., -2 No– Mechanical Engineer 2 Nos. 5.4 MEP Coordinator – 1 No. 5.5 Land Surveyor – 1 No. 6. QA/QC Team for 6.1 Site Quality Control – 1 No 6.2 Material & Shop Drawing schedule 7. Safety Officer – 1 No 8. Shop drawing preparation Team consisting of: 8.1 Engineers - Min 1 No 8.6 Draftsman along with necessary computer equipment/plotters at site. – 2 Nos And other necessary staff required for satisfactory completion of the project – to be assessed by the Contractor. The Contractor to submit the CV(s) of the above mentioned personnel to the Project Manager for approval. All the above personnel should have minimum seven years experience in similar size project in the U.A.E. The Contractor shall be responsible for his own setting out levels and lines to the satisfaction of the Engineer.
  • 80. Part D _____________________________________________________________ PART II [cont’d.] CONDITIONS OF PARTICULAR APPLICATION [cont’d.] Engineer’s and 87.0 The Contractor shall provide Engineer’s and Contractor’s site Contractor’s Site offices, facilities, site management team, parking, etc all as Requirements specified and herewith. [cont’d] b) OFFICE REQUIREMENTS - GENERAL 1.01 DESCRIPTION OF WORK The Contractor is required to make necessary provision for temporary utilities (electricity, lighting, heating, ventilation, telephone service, water and sanitary), temporary controls (barriers, fencing, protection of work, security, and traffic), and construction facilities (25 parking slots and staging areas, progress cleaning, and offices) to fulfill the requirements of the Contract, support the Contractor’s work force and support the Owner’s representatives. All facilities and equipment will become the property of the Owner. The Contractor shall bear the responsibility to maintain and pay for all services and bills until the final handover to the main contractor. 1.02 TEMPORARY POWER A. Contractor shall provide necessary power service. B. Contractor shall arrange with the electrical utility, as needed, for additional power requirements, including power takeoff points, voltage and phasing, transformers, and metering, and shall pay resulting costs and fees. 1.03 TELEPHONE SERVICE Contractor shall provide telephone service at the Engineer’s site office for the PMs own use. Additional requirements are defined in section 1.13. 1.04 TEMPORARY WATER SERVICE Contractor shall provide necessary water service and any necessary special connections to a water supply, as well as chilled bottled drinking water for the Engineer’s site office. 1.05 TEMPORARY SANITARY FACILITIES Contractor shall provide on-site toilet and wash-up facilities for its work force that comply with applicable laws, ordinances, and regulations pertaining to the public health and sanitation of dwellings and camps. Additional requirements for the Engineer’s Site Office are contained in Section 1.13