1. Kanban team simulation.
Stages:
1. PO in progress
2. DEV waiting
3. DEV in progress
4. QA waiting
5. QA in progress
6. QA waiting RC
7. QA RC
8. DONE
2. WIP: 0 Done: 0
Lead times: (no data)
Now:
Limit:
0
7
Now:
Limit:
0
10
Day: 0
3. WIP: 3 Done: 0
Lead times: (no data)
Now:
Limit:
3
7
Now:
Limit:
0
10
Day: 1
4. WIP: 6 Done: 0
Lead times: (no data)
Now:
Limit:
6
7
Now:
Limit:
3
10
Day: 2
5. WIP: 7 Done: 0
Lead times: (no data)
Now:
Limit:
7
7
Now:
Limit:
4
10
Day: 3
6. WIP: 10 Done: 0
Lead times: (no data)
Now:
Limit:
7
7
Now:
Limit:
6
10
Day: 4
7. WIP: 11 Done: 0
Lead times: (no data)
Now:
Limit:
7
7
Now:
Limit:
7
10
Day: 5
8. WIP: 13 Done: 0
Lead times: (no data)
Now:
Limit:
7
7
Now:
Limit:
10
10
Day: 6
9. WIP: 14 Done: 0
Lead times: (no data)
Now:
Limit:
7
7
Now:
Limit:
10
10
Day: 7
23. Kanban team simulation.
Results after 20 days.
Work in Progress: 11 tasks
Done: 24 tasks
Work was released on: Day 8, Day 12, Day 16, Day 20
Lead times:
1st release: 3 x 6 days, 3 x 7 days
2nd release: 1 x 6 days, 1 x 7 days, 3 x 8 days, 1 x 9 days
3rd release: 1 x 6 days, 3 x 8 days, 1 x 9 days, 1 x 10 days
4th release: 1 x 7 days, 1 x 8 days, 2 x 9 days, 2 x 10 days