This document provides guidelines for an expedited permit process for small-scale photovoltaic (PV) systems. It begins with the required information for a permit, including a site plan, electrical diagram, and component specification sheets. It then outlines a two-step review process. Step 1 involves reviewing the structural mounting system, providing information on the roof and mounting hardware. Step 2 is an electrical review to ensure the system meets simple criteria like being under 15 kW, using 4 series strings or less, and connecting to the load side of the main service panel. Various appendices provide additional details on structural calculations, electrical diagrams, costs, and temperature tables to aid the permitting and installation process. The goal is to streamline permitting for