3. Diaphragm Wall
• Diaphragm Walls Are A Method Of Creating A Cast In-situ
Reinforced Concrete Retaining Wall Using The Slurry
Supported Trench Method. As Such, They Are Often
Known As Slurry Walls. However, The Term “Diaphragm
Walls”
• Standard Width Are 100-200 Mm For Cut Off Wall And
450-1200 Mm For Structural Member.
• Diaphragm Walls Provide A Water Tight Barrier And Are
Constructed With A Minimum Back Slope Subsidence.
• They Are Formed From Reinforced Concrete And Are
Constructed As Normal Cast-in-place Walls With Support,
Which Become Part Of The Main Structure.
4. APPLICATIONS
As permanent and temporary foundation walls for deep basements.
In earth retention schemes for highway and tunnel projects.
As permanent walls for deep shafts for tunnel access.
As permanent cut-off walls through the core of earth dams.
In congested areas for retention systems and permanent foundation walls.
Deep ground water barriers through and under dams.
8. DEFINITION
Cofferdams are temporary enclosures to keep out water and soil so
as to permit dewatering and construction of the permanent facility
(structure) in the dry.
Its temporary structure which is built in a river, lake etc. to
remove water from an area and make it possible to carry on the
construction work under reasonably dry conditions.
Meaning of Coffer Dam : Coffer = Box
Cofferdams are usually required for projects such as dams, docks
and construction of bridge piers and abutments etc.
8
9. 9
watertight.
Materials – earth , timber , steel & concrete.
Constructed at site of work.
Depend- depth , soil condition , difference in water level,
availability of materials.
total cost of construction, maintenance and pumping is
minimum.
Stable against bursting, overturning and sliding, under the floods
and waves.
How it is?
10. When it is?
To facilitate pile driving operations.
To place grillage & raft foundations.
To construct foundations of piers & abutments of bridges, dams, docks
etc.
To provide a working platform for foundations when water is meet with it.
To retain Soil & Water.
Can be used as either Temporary or Permanent.
Main purpose is to provide dry working area for workers.
10
11. Civil Engineering: Underground Car Parking, Foundation,
Basement Construction
Transport Engineering: Bridge Pier, Support Walls, Ramps,
Ground Water Retention, Tunnel Work etc.
Water Engineering: Weirs, Culverts, Flood Protection Walls, Scour
Protection Walls, Securing Embankment etc.
Port Construction: Dock Works, Jetty Works etc.
11
12. TYPES OF COFFER DAM
1.Earth fill cofferdams - mainly for low level water
2.Rock fill cofferdams
3.Timber Crib or rock filled crib cofferdams - Construction on
land and than floated into place, which is also known as Gravity Dam
4.Braced / Sheet Pile Coffer Dam- Consisting of Sheet Piles,
mainly used in shallow water depth
(i). Single wall coffer dams
(ii). Double wall coffer dams
(iii). Cellular cofferdams
12
13. It is constructed in places where the depth of water is not much, say
1.3 to 1.8 m.
The earth bank is carried about one meter above the water level.
The top width of the bank should not be less than 1 mtr. and the side
slopes in a vary from 1 : 1 to 1 : 2.
The earth embankment should be built from a mixture of clay and
sand or clay and gravel.
In order to prevent the embankment from scouring due to the action
of water, side slopes of the bank on water side should be pitched with
rubble boulders.
EARTH FILL COFFERDAMS
19. If the depth of water to be retained by the embankment
of cofferdam is of order of 3 m .
Stone or rubble is used for the embankment.
This construction is adopted only if the stone is easily
available in the nearby areas.
The stones are assembled in the required shape of the
embankment and the voids are partially filled with earth
and stone-chips.
On the waterside, the rock fill is to be provided with an
impervious layer of earth.
19
27. 1. SINGLE WALLED COFFER DAM
27
Area to be enclosed is small and the depth of water is
more 4.5 to 6 m.
Timber piles known as guide piles are first driven deep
into the firm ground below the river bed.
spacing of the piles may vary between 1.8 to 4.5 m.
Longitudinal runners called Wales are then bolted to the
guide.
4. SHEET PILE COFFERDAM
28. 28
Steel or wooden sheet piles are then driven into the river
bed along the Wales and are secured to the Wales by bolts.
The sheets on the two faces are braced by trussed
arrangement of struts. This helps in increasing the stability
of walls against the water pressure.
Half-filled bags of sand stacked on the inside and the
outside faces of the sheets help in increasing the stability of
cofferdam.
After the cofferdam is constructed, the water in the enclosed
area is pumped out and the construction work is taken up.
33. DOUBLE WALLED COFFERDAMS
Double-walled cofferdam is provided to enclose a larger area.
Its construction is essentially the same as that of a single-walled
cofferdam except that in place of one wall, a pair of walls with a
gap in between is used all along the boundary of the space to be
enclosed.
This type of cofferdam can be used in depth of water up to 12 m.
- The double wall cofferdams are of two types:
(I) Ohio – river type cofferdams
(ii) Timber or steel sheeting cofferdams
37. Timber Sheet Pile
Timber sheet pile were extensively
used for cofferdam when depth of
water is about 6 to 10 m.
It can be gradually replaced with
steel pile.
It can only be used for small
depth since no deep piling in
37
42. TIMBER CRIB OR ROCK FILLED CRIB
COFFERDAMS
Constructed on land and floated into place
It consists of a unit or a cell open at the bottom and
having the framework of horizontal timber members.
Hollow space formed are then filled with rock or
gravel
Depth of water – 10 to 20 m
Used for wide excavation and rocky river bottoms
42
44. 44
OHIO RIVER TYPE COFFERDAM
Ohio river in USA.
Used in hard & soft bed (no erosion).
Unsuitable in deep water & swift flow.
Construction
Wales fixed at 1.50m vertically.
Wale joints, double vertical planks are provided.
Tie rods threaded & cross braces fixed.
Fixes sheet piles.
Beams (inside & outside)
Removing safely.
54. CELLULAR COFFERDAMS
- The cellular cofferdams are mostly used for dewatering
large areas , where the depth of water may be 19 to 21 m.
- Mostly used the construction of marine structures like
Dams, Locks etc.
- The two common shapes of the cellular cofferdam are:
(i) Circular type
(ii) Diaphragm type
54
55. Circular type cellular cofferdam:
The circular type of cellular cofferdam has the advantage that each
cell may be filled completely to the top before starting the
construction of the next cell without causing any distortion to the
shell of the cofferdam.
Thus, when one cell is completely filled up with crushed stone,
broken bricks, gravel and sand. It can be used for placing crane or
other equipment required for the construction of other cells.
56. 56
In addition, each cell acts as a self-supporting independent unit
and in case one of the cells collapses due to scour or interlock
damage or some other reason, it does not produce any adverse
effect on the neighboring cells. It is found that the interlock
stresses reach their maximum permissible value when the
diameter of cell is about 21 meter.
Hence in case, from design consideration it is necessary to have
effective width of the cofferdam more than 21 meter,
diaphragm type of cofferdam must be used.
64. Diaphragm type cellular cofferdam:
• This Consists of a series of arcs of steel sheet piles connected as
shown in the image.
• The straight diaphragm wails are connected to each other by steel
piles arranged in the form of arches on either sides.
• The radius of the connecting arcs is generally made equal to the
distance between the straight diaphragm walls.
64
65. 65
• After the cells are driven to the required depth, they are filled with earth,
sand, gravel or other filling material. In this type of cofferdam, as the
diaphragm which separates the two cells is a straight wall, it is
necessary to fill adjacent cells at approximately the same rate.
• If this is not done, the unbalanced pressure from the fill will distort the
diaphragm (cross-walls) which may result in the failure of the
interlocks.
• In this respect, the circular type cofferdam has the advantage over the
diaphragm type cofferdam because in the former, it is not necessary to fill
the adjacent cells at the same time.
68. 68
These are actually small concrete dams and they have been used
economically on many jobs.
The framework usually consist of pre cast R.C.C piles and sheets.
The pre cast R.C.C sheet piles are provided with suitable edges
and they are driven in a similar manner to steel sheet piles.
The main disadvantage of this cofferdam is that it is costly. But
when it is to be incorporated as a part of permanent structure it
proves to be economical.
CONCRETE COFFERDAM
70. MOVABLE OR SUSPENDED
COFFERDAMS
Where there are numbers of repetition work in
under water foundations ,such as in the piers
of multi span river bridges , it is economical to
design the cofferdams to be moved as a single
unit from one foundation to another.
70
72. 72
Water may leak through the underground flow of water or through the
piling sheet of the cofferdam. The following measures can be adopted
to prevent leakages in cofferdam.
1.Water entering the dewatered area through fissures or cracks in the
rocks can be stopped by grouting the fissures by cement grout.
2. Clay or mixture of clay and sand can be dumped in form of beams
both on inside and outside faces of the cofferdam.
3. Cracks or fine joints or nail holes in the sheet piles should be closed
using bitumen or cement mortar.
LEAKAGE PREVENTION IN COFFERDAMS
73. 73
4. If a lot of leakages is taking place and no measures stated above
have been to control it, the water face of the cofferdam may be
completely covered with canvass coated with tar or tarpaulin.
5. In case of double-walled cofferdams leakage is generally because of
insufficient compaction of the filling material. In this case, measures to
control seepage through filling material should be adopted.
6. Sufficient grease applied at interlocks of sheet piles also helps check
leakage of water.
74. DESIGN FEATURES OF COFFERDAMS
The design of a cofferdam depends on various factors such as.
(i) Hydrostatic head of Water
(ii) Dimensions of the area to be covered by the cofferdams
(iii) Subsoil conditions
(iv) Fluctuations of outside water level
(v) Possibility of erosion
(vi) Presence of ice
74
75. A purely theoretically designed cofferdam may fail for
factors unaccounted in its design.
Therefore ,become necessary to combine practical
knowledge or experience with the theoretical aspects in the
design of a cofferdam.
For width and Depth of cofferdam :
for H < 3 m, W = H
H > 3 m, W = 3 + 1/3*(H - 3)
Where, W = Width of cofferdam in metres
H = Height of water above river bed in metres
75
76. Economic Height of Coffer Dam
1.Depth of Water
Low depth => Earthen Dam
High Depth => Sheet Pile Coffer Dam
2.Current and nature of flowering of Sheet Pile
High Current => Sheet Pile Coffer Dam (Higher Seepage Control
Capacity)
Low Current => Earthen or any other Dam (Less Seepage Control
Capacity)
76
The maximum height of cofferdam for which its total cost is minimums
known as the most economic height of cofferdam.
77. 3.Type and Period of Work
Short Duration Work => Timber Dam
Long Duration work => Sheet Pile Coffer Dam
4.High and Low Tide Level of Reservoir
Sheet Pile must have top level slightly higher than that of the HTL.
So that even in extreme case water can not over top the coffer dam, to
achieve the dry working through out the season.
77
86. Background
Dubai, UAE
The first 7 stars hotel in theworld
The start of Dubai’s new vision of attracting new
investments in areas outside the oilindustry.
If you want to book a night there it will cost you
around $2000
321 meters height from thesea.
8
6
88. Building theisland
Temporary tube piles driven into sea bed
Temporary sheet piles and tierods driven
into sea bed to support boundary rocks
Sheet pilewall
8
8
Tubularpile
89. Rock armor
8
9
Permanentboundary rock bunds (rock armor) depositedon both sides of the sheet piles
No solid ground under the building just weak sand (up to 180 meters deep with no solid
ground). So it was decidedto go withfriction piles.
Sand fill
Building theisland
90. PermanentSHED units placed around the island to dissipate the action of waves and
protectit.
2M (6.5ft) diameter 43M (141ft) deep piles weredriven throughthe
island and seabed
Main buildingpiles 6
SHED units
94. Excavationsbegan in theislandto removethehydraulicfill
Acoffer dam was being built while excavating
2M (6.5 ft) thick concreteplug slab laid on the base of the island to prevent
the base from popping out because of the seapressure
Reinforced concreteretaining wallbuilt
Theconstruction of thebasement started
94
Concreteslab