SlideShare ist ein Scribd-Unternehmen logo
1 von 33
Project Planning, Scheduling
and Resource allocation
Presented to:
Dr. Shakeel Iqbal

Presented by:
Jatin Mandhyan (06)
Kajal Kuki Patwari (07)
Krishna Mishra (08)
PM Process Summary
Define Project

State need, problem or opportunity
Define project objectives
Identify success criteria
List assumptions, risks and
obstacles
Define project scope and work
breakdown structure








We are here

Monitor & Control
Progress





Feedback




Establish progress reporting system
Set up change control process
Define problem escalation process
Monitor progress vs. plan
Revise project plan

Develop Detailed Plan






Identify project activities
Estimate activity duration
Determine resource requirements
Construct / analyze project network
Prepare project schedule

Close Out Project





Launch Plan






Recruit and organize project team
Establish team operating rules
Level project resources
Assign work




Obtain client acceptance
Install project deliverables
Complete project documentation
Complete post-implementation audit
Issue final project report

Adapted from Project Management, ©1987 Kepner-Tregoe, Inc.
and Effective Project Management by R.K. Wysocki, R. Beck Jr.
& D.B. Crane (Wiley, 1995)
2
3
4
“Failing to plan is planning to fail”
Planning:
 “what” is going to be done, “how”, “where”, by
“whom”, and “when”
 for effective monitoring and control of complex
projects

5
“Its about time”
Scheduling:
 “what” will be done, and “who” will be working
 relative timing of tasks & time frames
 a concise description of the plan

6
Three Basic Steps to a Project Schedule

7
Scheduling Techniques
Gantt or bar charts
Milestone charts
Line of balance
Networks
Program Evaluation and Review Technique (PERT)
Arrow Diagram Method (ADM) [Sometimes called the
Critical Path Method (CPM)]
Graphical Evaluation and Review Technique (GERT)
Precedence Diagram Method (PDM)

8
Types of Schedules
Gantt or Simple Bar Chart
• Graphical
representation
shows horizontal
bars against a
time scale
• At summary or
detailed levels

http://www.maxwideman.com/issacons/index.htm

9
Milestone Chart
• Graphical
representation
shows milestone
dates
• Identifies key
points in the
project's life span
• The bars are not
necessarily visible

http://www.maxwideman.com/issacons/index.htm

10
Progress Bar Chart
• Graphical
representation
shows progress
relative to plan
• In this case, behind
schedule
• No indication of
final completion

http://www.maxwideman.com/issacons/index.htm

11
Bar Chart Status Report
• Graphical
representation shows
original baseline
schedule (red bars)
and actual progress
relative to current
plan
• No indication of final
completion

http://www.maxwideman.com/issacons/index.htm

12
The Work Break Down Structure (WBS)
An organizational tool for complex projects
 A first step in creating a schedule
 Useful for defining the Scope of Work
 After decided how to do the work

Consists of:
 Goal statement for project
 Subdividing goal into smaller & smaller portions

13
Example WBS
W a re h o u s e W B S
T o c o n s t r u c t a 5 - u n it
w a r e h o u s e f o r lig h t in d u s t r y
C o m p le x

S it e P r e p a r a t io n

S urve y

S it e B o u n d a r ie s

E le v a t io n
D a t a P o in t s

S o ils A n a ly s is

B u ild in g
F o o t p r in t s

F o u n d a t io n

E x c a v a t e S o il

S tru c tu ra l

S y s te m s

F in is h in g

B a c k f ill & C o m p a c t

L o c a te
B u r ie d S e r v ic e s

Could be used to define scope of
work for surveyor sub-contract
14
15
Background
 Allahabad, about 600 km southeast of Delhi in Uttar
Pradesh (UP) State, is a major industrial city along National
Highway 2.
 The city is divided into the four districts of Allahabad, Naini,
Jhusi and Phaphamau.
 The adjacent Naini District across the River Yamuna is the
industrial center where communication, automobile,
fertilizer, textile and related industry companies are located.
The only traffic route connecting these two districts was the
existing bridge over the River Yamuna (Yamuna Bridge).
17
 The existing bridge (Yamuna Bridge) is a combined
highway-railway bridge constructed at the end of the 19th
century, and its narrow two lanes were straining to cope
with the increasing size and weight of the vehicles.
 Out of concern over the safety of the decaying bridge,
construction of a new substitute bridge was urgently
needed.

18
Objective
 Construct a four-lane bridge
 Replace the existing old two-lane bridge
 Alleviating chronic traffic congestion

19
Borrower/Executing Agency
 Borrower: The President of India
 Executing Agency: The Ministry of Surface
Transport (current Ministry of Shipping, Road
Transport and Highways)

20
Outline of Loan Agreement
Loan Amount / Loan Disbursed
Amount

10,037 million yen / 7,515 million yen

Exchange of Notes / Loan Agreement

December 1993 / January 1994

Terms and Conditions
-Interest Rate
-Repayment Period (Grace Period)
-Procurement

2.6%
30 years (10 years)
General untied

Final Disbursement Date

March 2005

Main Contractors

J/V of Hyundai Engineering Co. Ltd.
(Korea) and Hindustan Construction Co.
Ltd. (India)

Total Bridge Length:

1640 m

Width of superstructure

26 m

Main spans:

185 m – 260 m – 185 m
21
22
Output
The main scope of this
project include the
construction of a four-lane
cable-stayed bridge (Naini
Bridge; length, 1,640 m)
and approach roads (total
length: 3,806 m) was
implemented almost entirely
as planned.

23
In addition, based on recommendations suggested
in JBIC’s study the project scope was expanded
to include installation of toll booths and
monitoring equipment such as the weigh-in
motion system and the wind and structural health
monitoring system (WASHMS).

24
Project period
The project period was scheduled from January 1994 to July
2004 (ten years and seven months), which is four years and
four months longer than the planned period from January
1994 to March 2000 (six years three months) or 169% of the
planned period.
The main causes of delay:
(1)the delay in consultant tendering procedure
(2) the time required for the review and finalization of the
design of the first large-scale cable-stayed bridge in India.
(3)the delay in the tendering of contractors due to problems in
the course of the tendering procedure
(4)the change of the executing agency from the Ministry of
Surface Transport in 1997 in the midst of project
implementation
25
Project Cost
The project cost was 8,807 million yen 3,097 million
yen less than the planned 11,904 million yen or
74% of the planned project cost. In terms of
rupee, the actual cost was 3,145 million rupees
which is almost equal to the planned 3,217
rupees.
This difference is a resulted of the difference in the
rupee-yen exchange rate at time of planning and
ex-post evaluation.
26
Involvement of Maurer Söhne
Maurer Soehne manufactured 4 Swivel Joist
Expansion Joints with a length of 24,40 m each.
This cross-sectional width of the superstructure
considers 4 highway traffic lanes and two lateral
3m - tracks for “other” traffic and pedestrians.
Due to transport reasons, the joints were delivered
in two pieces to be connected on job site. The
joints can accommodate movements of 400 mm
(at both abutments) and 360 mm and 600 mm
respectively at the pylons.

27
Operation and maintenance status
On the Naini Bridge, weather observation devices,
which check conditions and measure the weight
and gradient of pylons, are set at seven positions
and are monitored 24 hours from the observation
equipment control room in the toll booth control
building.

28
Joint manufacture in the workshop

Joint installation

29
30
31
Effectiveness

Traffic volume

Time saving

Congestion length
decrease and time saving
32
bibliography
• Project planning, scheduling and control – James P. Lewis
• http://www.cowi.com/menu/service/BridgeTunnelandMarineStr
uctures/Bridges/Documents/BTM_Bridges_low.pdf
• http://www.cowi.dk/menu/service/Brotunnelogvandbygning/Do
cuments/021-1700-008e-07b_MajorBridges.pdf
• http://sine.ni.com/cs/app/doc/p/id/cs-12653
• http://en.wikipedia.org/wiki/File:New_Yamuna_Bridge_details.j
pg
• http://structurae.net/structures/data/index.cfm?id=s0011445

33

Weitere ähnliche Inhalte

Was ist angesagt?

Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Float in Projects
Float in ProjectsFloat in Projects
Float in ProjectsRd Pokhrel
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Financial & Economic Evaluation of projects
Financial & Economic Evaluation of projectsFinancial & Economic Evaluation of projects
Financial & Economic Evaluation of projectsamanideutsch
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 

Was ist angesagt? (20)

Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Float in Projects
Float in ProjectsFloat in Projects
Float in Projects
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Financial & Economic Evaluation of projects
Financial & Economic Evaluation of projectsFinancial & Economic Evaluation of projects
Financial & Economic Evaluation of projects
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Primavera software
Primavera softwarePrimavera software
Primavera software
 

Andere mochten auch

Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMOTURKI , PMP
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementBob Zoller
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisBPUG Congress
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsian jones
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation Riadh Mohammed Arif
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017Carol Smith
 

Andere mochten auch (15)

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMO
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_Management
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon Lewis
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Resource management
Resource managementResource management
Resource management
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tips
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
 

Ähnlich wie Planning, scheduling and resource allocation

3 planning and scheduling
3 planning and scheduling3 planning and scheduling
3 planning and schedulingDr.R. SELVAM
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaNarendra Vasudeva
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...IRJET Journal
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROIRJET Journal
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 
2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_dE'ville Eye
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear projectThanh Hoang Lam
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesaUtsav Tripathy
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...JumpingJaq
 
Expansion of state highway 1
Expansion of state highway 1Expansion of state highway 1
Expansion of state highway 1Sneha Kaira
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptxKumarAnand99
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET Journal
 
Feasibility study on expansion of state highway
Feasibility study on expansion of state highwayFeasibility study on expansion of state highway
Feasibility study on expansion of state highwaysnehakaira
 

Ähnlich wie Planning, scheduling and resource allocation (20)

3 planning and scheduling
3 planning and scheduling3 planning and scheduling
3 planning and scheduling
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
 
ToR
ToRToR
ToR
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d
 
MERAJ UL HUDA CV
MERAJ UL HUDA CVMERAJ UL HUDA CV
MERAJ UL HUDA CV
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear project
 
Training report on railway structure at tata aldesa
Training report on railway structure at tata aldesaTraining report on railway structure at tata aldesa
Training report on railway structure at tata aldesa
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...
 
Expansion of state highway 1
Expansion of state highway 1Expansion of state highway 1
Expansion of state highway 1
 
cv Updated M.Anwar
cv Updated M.Anwarcv Updated M.Anwar
cv Updated M.Anwar
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptx
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
 
Feasibility study on expansion of state highway
Feasibility study on expansion of state highwayFeasibility study on expansion of state highway
Feasibility study on expansion of state highway
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 
Experience Record
Experience RecordExperience Record
Experience Record
 
RDP Chapter 19
RDP Chapter 19RDP Chapter 19
RDP Chapter 19
 

Kürzlich hochgeladen

simpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdfsimpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdfLucyBonelli
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptJIT KUMAR GUPTA
 
Piece by Piece Magazine
Piece by Piece Magazine                      Piece by Piece Magazine
Piece by Piece Magazine CharlottePulte
 
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - MorgenboosterAI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster1508 A/S
 
General Simple Guide About AI in Design By: A.L. Samar Hossam ElDin
General Simple Guide About AI in Design By: A.L. Samar Hossam ElDinGeneral Simple Guide About AI in Design By: A.L. Samar Hossam ElDin
General Simple Guide About AI in Design By: A.L. Samar Hossam ElDinSamar Hossam ElDin Ahmed
 
Karim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 pppppppppppppppKarim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 pppppppppppppppNadaMohammed714321
 
guest bathroom white and blue ssssssssss
guest bathroom white and blue ssssssssssguest bathroom white and blue ssssssssss
guest bathroom white and blue ssssssssssNadaMohammed714321
 
NBA power point presentation final copy y
NBA power point presentation final copy yNBA power point presentation final copy y
NBA power point presentation final copy ysrajece
 
10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designers10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designersPixeldarts
 
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道yrolcks
 
Karim apartment ideas 02 ppppppppppppppp
Karim apartment ideas 02 pppppppppppppppKarim apartment ideas 02 ppppppppppppppp
Karim apartment ideas 02 pppppppppppppppNadaMohammed714321
 
world health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbbworld health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbbpreetirao780
 
FW25-26 Knit Cut & Sew Trend Book Peclers Paris
FW25-26 Knit Cut & Sew Trend Book Peclers ParisFW25-26 Knit Cut & Sew Trend Book Peclers Paris
FW25-26 Knit Cut & Sew Trend Book Peclers ParisPeclers Paris
 
10 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 202410 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 2024digital learning point
 
CAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdfCAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdfAlasAlthaher
 
guest bathroom white and bluesssssssssss
guest bathroom white and bluesssssssssssguest bathroom white and bluesssssssssss
guest bathroom white and bluesssssssssssNadaMohammed714321
 
Map of St. Louis Parks
Map of St. Louis Parks                              Map of St. Louis Parks
Map of St. Louis Parks CharlottePulte
 
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptxUnit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptxNitish292041
 
Niintendo Wii Presentation Template.pptx
Niintendo Wii Presentation Template.pptxNiintendo Wii Presentation Template.pptx
Niintendo Wii Presentation Template.pptxKevinYaelJimnezSanti
 
Sharif's 9-BOX Monitoring Model for Adaptive Programme Management
Sharif's 9-BOX Monitoring Model for Adaptive Programme ManagementSharif's 9-BOX Monitoring Model for Adaptive Programme Management
Sharif's 9-BOX Monitoring Model for Adaptive Programme ManagementMd. Shariful Hoque
 

Kürzlich hochgeladen (20)

simpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdfsimpson-lee_house_dt20ajshsjsjsjsjj15.pdf
simpson-lee_house_dt20ajshsjsjsjsjj15.pdf
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
 
Piece by Piece Magazine
Piece by Piece Magazine                      Piece by Piece Magazine
Piece by Piece Magazine
 
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - MorgenboosterAI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
AI and Design Vol. 2: Navigating the New Frontier - Morgenbooster
 
General Simple Guide About AI in Design By: A.L. Samar Hossam ElDin
General Simple Guide About AI in Design By: A.L. Samar Hossam ElDinGeneral Simple Guide About AI in Design By: A.L. Samar Hossam ElDin
General Simple Guide About AI in Design By: A.L. Samar Hossam ElDin
 
Karim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 pppppppppppppppKarim apartment ideas 01 ppppppppppppppp
Karim apartment ideas 01 ppppppppppppppp
 
guest bathroom white and blue ssssssssss
guest bathroom white and blue ssssssssssguest bathroom white and blue ssssssssss
guest bathroom white and blue ssssssssss
 
NBA power point presentation final copy y
NBA power point presentation final copy yNBA power point presentation final copy y
NBA power point presentation final copy y
 
10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designers10 must-have Chrome extensions for designers
10 must-have Chrome extensions for designers
 
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
怎么办理英国Newcastle毕业证纽卡斯尔大学学位证书一手渠道
 
Karim apartment ideas 02 ppppppppppppppp
Karim apartment ideas 02 pppppppppppppppKarim apartment ideas 02 ppppppppppppppp
Karim apartment ideas 02 ppppppppppppppp
 
world health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbbworld health day 2024.pptxgbbvggvbhjjjbbbb
world health day 2024.pptxgbbvggvbhjjjbbbb
 
FW25-26 Knit Cut & Sew Trend Book Peclers Paris
FW25-26 Knit Cut & Sew Trend Book Peclers ParisFW25-26 Knit Cut & Sew Trend Book Peclers Paris
FW25-26 Knit Cut & Sew Trend Book Peclers Paris
 
10 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 202410 Best WordPress Plugins to make the website effective in 2024
10 Best WordPress Plugins to make the website effective in 2024
 
CAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdfCAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdf
 
guest bathroom white and bluesssssssssss
guest bathroom white and bluesssssssssssguest bathroom white and bluesssssssssss
guest bathroom white and bluesssssssssss
 
Map of St. Louis Parks
Map of St. Louis Parks                              Map of St. Louis Parks
Map of St. Louis Parks
 
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptxUnit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
Unit1_Syllbwbnwnwneneneneneneentation_Sem2.pptx
 
Niintendo Wii Presentation Template.pptx
Niintendo Wii Presentation Template.pptxNiintendo Wii Presentation Template.pptx
Niintendo Wii Presentation Template.pptx
 
Sharif's 9-BOX Monitoring Model for Adaptive Programme Management
Sharif's 9-BOX Monitoring Model for Adaptive Programme ManagementSharif's 9-BOX Monitoring Model for Adaptive Programme Management
Sharif's 9-BOX Monitoring Model for Adaptive Programme Management
 

Planning, scheduling and resource allocation

  • 1. Project Planning, Scheduling and Resource allocation Presented to: Dr. Shakeel Iqbal Presented by: Jatin Mandhyan (06) Kajal Kuki Patwari (07) Krishna Mishra (08)
  • 2. PM Process Summary Define Project State need, problem or opportunity Define project objectives Identify success criteria List assumptions, risks and obstacles Define project scope and work breakdown structure      We are here Monitor & Control Progress    Feedback   Establish progress reporting system Set up change control process Define problem escalation process Monitor progress vs. plan Revise project plan Develop Detailed Plan      Identify project activities Estimate activity duration Determine resource requirements Construct / analyze project network Prepare project schedule Close Out Project    Launch Plan     Recruit and organize project team Establish team operating rules Level project resources Assign work   Obtain client acceptance Install project deliverables Complete project documentation Complete post-implementation audit Issue final project report Adapted from Project Management, ©1987 Kepner-Tregoe, Inc. and Effective Project Management by R.K. Wysocki, R. Beck Jr. & D.B. Crane (Wiley, 1995) 2
  • 3. 3
  • 4. 4
  • 5. “Failing to plan is planning to fail” Planning:  “what” is going to be done, “how”, “where”, by “whom”, and “when”  for effective monitoring and control of complex projects 5
  • 6. “Its about time” Scheduling:  “what” will be done, and “who” will be working  relative timing of tasks & time frames  a concise description of the plan 6
  • 7. Three Basic Steps to a Project Schedule 7
  • 8. Scheduling Techniques Gantt or bar charts Milestone charts Line of balance Networks Program Evaluation and Review Technique (PERT) Arrow Diagram Method (ADM) [Sometimes called the Critical Path Method (CPM)] Graphical Evaluation and Review Technique (GERT) Precedence Diagram Method (PDM) 8
  • 9. Types of Schedules Gantt or Simple Bar Chart • Graphical representation shows horizontal bars against a time scale • At summary or detailed levels http://www.maxwideman.com/issacons/index.htm 9
  • 10. Milestone Chart • Graphical representation shows milestone dates • Identifies key points in the project's life span • The bars are not necessarily visible http://www.maxwideman.com/issacons/index.htm 10
  • 11. Progress Bar Chart • Graphical representation shows progress relative to plan • In this case, behind schedule • No indication of final completion http://www.maxwideman.com/issacons/index.htm 11
  • 12. Bar Chart Status Report • Graphical representation shows original baseline schedule (red bars) and actual progress relative to current plan • No indication of final completion http://www.maxwideman.com/issacons/index.htm 12
  • 13. The Work Break Down Structure (WBS) An organizational tool for complex projects  A first step in creating a schedule  Useful for defining the Scope of Work  After decided how to do the work Consists of:  Goal statement for project  Subdividing goal into smaller & smaller portions 13
  • 14. Example WBS W a re h o u s e W B S T o c o n s t r u c t a 5 - u n it w a r e h o u s e f o r lig h t in d u s t r y C o m p le x S it e P r e p a r a t io n S urve y S it e B o u n d a r ie s E le v a t io n D a t a P o in t s S o ils A n a ly s is B u ild in g F o o t p r in t s F o u n d a t io n E x c a v a t e S o il S tru c tu ra l S y s te m s F in is h in g B a c k f ill & C o m p a c t L o c a te B u r ie d S e r v ic e s Could be used to define scope of work for surveyor sub-contract 14
  • 15. 15
  • 16.
  • 17. Background  Allahabad, about 600 km southeast of Delhi in Uttar Pradesh (UP) State, is a major industrial city along National Highway 2.  The city is divided into the four districts of Allahabad, Naini, Jhusi and Phaphamau.  The adjacent Naini District across the River Yamuna is the industrial center where communication, automobile, fertilizer, textile and related industry companies are located. The only traffic route connecting these two districts was the existing bridge over the River Yamuna (Yamuna Bridge). 17
  • 18.  The existing bridge (Yamuna Bridge) is a combined highway-railway bridge constructed at the end of the 19th century, and its narrow two lanes were straining to cope with the increasing size and weight of the vehicles.  Out of concern over the safety of the decaying bridge, construction of a new substitute bridge was urgently needed. 18
  • 19. Objective  Construct a four-lane bridge  Replace the existing old two-lane bridge  Alleviating chronic traffic congestion 19
  • 20. Borrower/Executing Agency  Borrower: The President of India  Executing Agency: The Ministry of Surface Transport (current Ministry of Shipping, Road Transport and Highways) 20
  • 21. Outline of Loan Agreement Loan Amount / Loan Disbursed Amount 10,037 million yen / 7,515 million yen Exchange of Notes / Loan Agreement December 1993 / January 1994 Terms and Conditions -Interest Rate -Repayment Period (Grace Period) -Procurement 2.6% 30 years (10 years) General untied Final Disbursement Date March 2005 Main Contractors J/V of Hyundai Engineering Co. Ltd. (Korea) and Hindustan Construction Co. Ltd. (India) Total Bridge Length: 1640 m Width of superstructure 26 m Main spans: 185 m – 260 m – 185 m 21
  • 22. 22
  • 23. Output The main scope of this project include the construction of a four-lane cable-stayed bridge (Naini Bridge; length, 1,640 m) and approach roads (total length: 3,806 m) was implemented almost entirely as planned. 23
  • 24. In addition, based on recommendations suggested in JBIC’s study the project scope was expanded to include installation of toll booths and monitoring equipment such as the weigh-in motion system and the wind and structural health monitoring system (WASHMS). 24
  • 25. Project period The project period was scheduled from January 1994 to July 2004 (ten years and seven months), which is four years and four months longer than the planned period from January 1994 to March 2000 (six years three months) or 169% of the planned period. The main causes of delay: (1)the delay in consultant tendering procedure (2) the time required for the review and finalization of the design of the first large-scale cable-stayed bridge in India. (3)the delay in the tendering of contractors due to problems in the course of the tendering procedure (4)the change of the executing agency from the Ministry of Surface Transport in 1997 in the midst of project implementation 25
  • 26. Project Cost The project cost was 8,807 million yen 3,097 million yen less than the planned 11,904 million yen or 74% of the planned project cost. In terms of rupee, the actual cost was 3,145 million rupees which is almost equal to the planned 3,217 rupees. This difference is a resulted of the difference in the rupee-yen exchange rate at time of planning and ex-post evaluation. 26
  • 27. Involvement of Maurer Söhne Maurer Soehne manufactured 4 Swivel Joist Expansion Joints with a length of 24,40 m each. This cross-sectional width of the superstructure considers 4 highway traffic lanes and two lateral 3m - tracks for “other” traffic and pedestrians. Due to transport reasons, the joints were delivered in two pieces to be connected on job site. The joints can accommodate movements of 400 mm (at both abutments) and 360 mm and 600 mm respectively at the pylons. 27
  • 28. Operation and maintenance status On the Naini Bridge, weather observation devices, which check conditions and measure the weight and gradient of pylons, are set at seven positions and are monitored 24 hours from the observation equipment control room in the toll booth control building. 28
  • 29. Joint manufacture in the workshop Joint installation 29
  • 30. 30
  • 31. 31
  • 32. Effectiveness Traffic volume Time saving Congestion length decrease and time saving 32
  • 33. bibliography • Project planning, scheduling and control – James P. Lewis • http://www.cowi.com/menu/service/BridgeTunnelandMarineStr uctures/Bridges/Documents/BTM_Bridges_low.pdf • http://www.cowi.dk/menu/service/Brotunnelogvandbygning/Do cuments/021-1700-008e-07b_MajorBridges.pdf • http://sine.ni.com/cs/app/doc/p/id/cs-12653 • http://en.wikipedia.org/wiki/File:New_Yamuna_Bridge_details.j pg • http://structurae.net/structures/data/index.cfm?id=s0011445 33