SlideShare ist ein Scribd-Unternehmen logo
1 von 29
Downloaden Sie, um offline zu lesen
Chapter 2

Load Characteristics and Economic Aspects
Terms used commonly:

1. Connected load: Sum of the continuous rating of the entire load
consuming apparatus connected to the system.

2. Maximum demand: It means the maximum power that the circuit is
likely to draw at any time.

3. Demand factor: It is the ratio of maximum demand to connected load.
Demand factor has to be less than one.

4. Diversity factor: It is the ratio of sum of individual maximum
demand to the maximum demand of the whole power system. It is
always greater than one.

5. Coincidence factor: Coincidence factor is the ratio of the maximum
demand by the sum of the individual maximum demands. It is always
less than one.
6. Load diversity : It is defined mathematically as,
Load diversity = Sum of individual loads – Peak of the combined load

7. Contribution factor: It is the contribution of a particular load, in per
unit of the individual demand, to the group maximum demand.

8. Loss factor: It is the ratio of average power loss to power loss at peak
load.

9. Load factor: It is the ratio of average demand to maximum demand.
Load factor = Energy produced in a given time/(maximum demand *
hours of operation in the given period)

10. Plant capacity factor: It is the ratio of average annual load to the
plant rated capacity.
Also, Plant capacity factor = Energy produced in one year/(Plant rated
capacity * 8760)
11. Plant use factor: It is defined as,
Plant use factor =Actual energy produced/(Plant capacity * plant
operation time in hours)

12. Utilization factor: It is the ratio of maximum load to rated capacity.
Reserves:

•Spinning reserve: It is the generating capacity which is connected to a
bus (common connection) and is ready to take the load.

•Cold reserve: It is that reserve generating capacity which is available
for service but not in operation.

•Hot reserve: It is that reserve generating capacity which is in operation
but not in service.

• Firm power: It is the power intended to be always available (even
under emergency condition

• Reserve margin: It is the difference between the rated capacity and the
actual loading on the generator.
Load Curve:
It is useful as it gives –

1.Maximum demand (peak of the curve)
2.Energy produced (area under the curve)
3.Load factor (The ratio of the area under the curve to the total area under the rectangle
in which it is contained gives the Load factor for the period).
4.Average loading (The area under the curve divided by the number of hours gives the
average demand).




                   Load (kW)




                                Time (hrs)
Load Duration Curve:
All the loads are rearranged in descending order.


              Load (kW)



                          Time (hours)
Energy Load Curve:
It plots the cumulative integration of area under load curve starting at
zero load to a particular load and it is also called integrated duration
curve.



             Load (kW)




                          Energy (kWh)
1.A residential consumer has a connected load of 6 lamps each of 100W and 4 fans of
60W at his premises. His demand is as follows:
From midnight to 5 am – 120W
From 5 am to 6 pm – no load
From 6 pm to 7 pm – 380W
From 7 pm to 9 pm – 680W
From 9 pm to midnight – 420W
       a. Plot the load curve.
       b. Find the energy consumption in 24 hours:
        Area under curve = (5*120) + (380*1) +(680*2) +(420*3) = 3600Wh

       c. Calculate the demand factor, the average load, the maximum load and load
          factor.
       Maximum load = 680W (from load curve)

       Demand factor = Maximum Demand/ Connected Load = 680/(6*100 +4*60)
                    = 0.809

       Average load = Energy consumed/ no. of hours = 3600/24 = 150W

        Load factor = Average load/ Maximum load = 150/680 = 0.22
2. A generating station gas a maximum demand of 80MW, a load factor of 65%, a plant
capacity factor of 40% and a plant use factor of 85%. Find:
a.Daily energy produced.
b.Reserve capacity of plant.
c.The maximum energy that could be produced daily if the plant was running all the
time.
d.The maximum energy that could be produced daily if the plant was running as per
operating schedule.
a. Average demand = Load factor * Maximum demand = 0.65 * 80MW
                 = 52MW
   Daily energy produced = 52 * 24 = 1248MWh

b. Installed capacity = Average demand/ Plant capacity factor
                      = 52MW/ 0.4 = 130MW
   Reserve capacity = Installed capacity – Maximum demand
                     = 130MW – 80MW = 50MW

c. Maximum energy that could be produced daily if it was running all the time = Installed
   capacity * 24 = 130 * 24 = 3120MWh

d. Maximum energy that could be produced daily if the plant was running as per operating
  schedule = Daily energy produced/ plant use factor
                                    = 1248/ 0.85 = 1468.23MWh
3.Maximum demand of a generating station is 100MW. The load factor is 65%. The
plant capacity factor and the plant factor are 50% and 80% respectively. Determine:

a.The daily energy produced.
b.The installed capacity of the plant.
c.The reserve capacity of the plant.
d.The maximum energy that could be produced daily if the plant is running all the time.
e.The maximum energy that could be produced daily at full load (according to operating
schedule).
f. Utilisation factor.
a. Average demand = Load factor * Maximum demand = 0.65 * 100MW
              = 65MW
   The daily energy produced = Average demand * 24 = 65MW * 24
                     = 1560MWh


  b. The installed capacity = Average demand/ Plant capacity factor
                    = 65MW/0.5 = 130MW
c. Reserve capacity = Installed capacity – Maximum demand
                   = 130MW – 100MW = 30MW


d. Maximum energy that could be produced daily if it was running all the time =
Installed capacity * 24 = 130MW * 24 = 3120MWh

e. Maximum energy that could be produced daily if the plant was running as per
c.

operating schedule = Daily energy produced/ plant use factor

                   = 1560/ 0.85= 1950MWh


f. Utilisation factor = Maximum load/ Rated capacity

                     = 100/130 = 0.769
4.The load (in kW) on a substation is as follows:
   Time      Street lighting   Domestic   Commercial   Total
  12 am             400            600       400       1400
  1 am              400            500       400       1300
  2 am              400            450       400       1250
  3 am              400            450       400       1250
  4 am              400            500       400       1300
  5 am              400            700       500       1600
  6 am              400           1000       400       1800
  7 am                0            800       700       1500
  8 am                0            700       900       1600
  9 am                0            600      1200       1800
  10 am               0            500      1300       1800
  11 am               0            500      1200       1700
  12 pm               0            500      1100       1600
  1 pm                0            600       900       1500
  2 pm                0            600      1100       1700
  3 pm                0            600      1000       1600
  4 pm                0            600       900       1500
  5 pm                0            700       600       1300
  6 pm              400            800       500       1700
  7 pm              400           1050       500       1950
  8 pm              400           1200       500       2100
  9 pm              400           1100       500       2000
  10 pm             400            900       400       1700
  11 pm             400            700       400       1500
a. Find the maximum demand, average demand and the load factor pf the feeder
b. The class contribution factor for street lighting and the remaining load
c. The diversity factor of the feeder.
d. The coincidence factor of the load group.
e. If the feeder has the average loss of 14kW and annual loss factor of 0.14. Find the
following:
   1. The peak power loss of the feeder at peak load.
   2. Total annual loss of feeder.
   3. Demand factor of the feeder if the connected load is 2500kW.
Solution
a. Maximum demand = 2100kW
   Average demand = Sum of total demands/ 24 = 1602.08kW
   Load factor = Average demand/ Maximum demand
            = 1602.08/ 2100 = 0.763 =76.3%
 b. Class contribution factor = load of class at peak load/ maximum load of that class
                     CSL = 400/400 =1
            CDom = 1200/1200 = 1
            CCom = 500/1300 = 0.385
c. Diversity factor = Sum of maximum demands for each class/ Maximum demand
                 = (400 + 1200 + 1300)/2100 = 1.381

d. Coincidence factor = 1/Diversity factor = 0.724

e. 1. Power loss at peak load = average power loss/ loss factor
                                     = 14kW/0.14 = 100kW
   2. Total annual loss = Average loss * 365 = 5110kW
   3. Demand factor = Maximum demand/ Connected load
                                 = 2100/2500 = 0.84
5. A residential consumer has a connected load of 10 lamps of 100W each. his demand
is as follows:
    From midnight to 5am – 100W
    From 5am to 6pm – no load
    From 6pm to 7pm – 800W
    From 7pm to 9pm – 900W
    From 9pm to midnight – 400W
a. Plot the load curve.
b. Find the energy consumed during 24 hours.
c. Calculate the demand factor, average load, maximum load and load factor.

  Ans:

  b. Energy consumed = area under the curve = 100*5 + 1*800 + 2*900 + 3*400
                    = 4300Wh

  c. Demand factor = Maximum load/ Connected load = 900/(10*100) = 0.9
    Average load = Energy consumed/ no.of hours = 4300/24 = 179.167W
    Maximum load = 900W
    Load factor = Average demand/ Maximum demand = 179.167/900
             = 0.199
Power factor: For a 3 phase balanced system, if P is the power, VL and IL are the
 line voltage and current respectively and cosφ is the power factor then the above
 mentioned quantities can be related as follows:
                     P = √3VLILcosφ
                    cosφ = P/√3VLIL

 If P and VL are assumed to be constant (for transmitting the same power at the same
 voltage),
  IL α 1/cosφ.

 Hence it is very clear from the last equation that if power factor is decreased then
 the current increases, because of which the following drawbacks are there:

1. The ratings of the generators and transformers will increase.
2. Since IL increases the thickness of the conductor in the transmission lines will
increase. Due to this copper will be used more and cost of transmission lines will go up.
3. Since the losses in the transmission line directly proportional to the square of the
current, the loss increases.
4. The voltage regulation is poor because of more drop.
Various causes of low power factor:

1. Most of the induction motors operate at lagging power factor. The power factor
of these motors falls with decrease in load.
2. The arc and induction furnaces operate on very low lagging power factor.
3. Transformers draw magnetising current which causes the total current to lag behind.

Measures to avoid low power factor:

1.   By using synchronous motors instead of induction motors.
2.   By using high speed induction motors instead of low speed induction motors.
3.   By using operating the induction motor at rated output.
4.   By switching the induction motor from delta winding to star winding.
5.   By using dc motors instead of ac motors wherever possible.

Usually static capacitors, synchronous condensors, phase advancers or modifiers are
usually added to improve power factor of the entire power system.
Methods to improve power factor:

1.   Constant kW method:

OAB is the power triangle of the initial plant without phase modifier. P is the
real power in kW. φ1 is the power factor angle. S1 is the kVA power and C is the
 apparent power and AB is the reactive power in kVAr. After addition of phase
modifier, the new power triangle is OAC. It is clear that the kW power is not
changing but the kVA power is getting reduced from S1 to S2. The power factor
 is improved (cosφ2).

                             O               P
                                   φ2                 A
                                        φ1       S2

                                        S1            C

                                                      B
If ‘a’ is the rate of charge of kVA in Rs/kVA and ‘b’ is the expenditure associated
with the capacitor banks in Rs/kVAr then the net saving is
             c = a(S1-S2) – b(BC)
∆S = S1-S2 = (P/cosφ1) – (P/cosφ2)
BC = AB – AC = Ptanφ1 - Ptanφ2
Total saving : c = a((P/cosφ1) – (P/cosφ2)) – b(Ptanφ1 - Ptanφ2)
For maximum saving, differentiate ‘c’ with respect to φ2.
dc/dφ2 = 0
   Therefore when, sinφ2 = b/a
  saving is maximum.
2. Constant kVA method:
 Initially the power triangle of the plant is OAB where OA is the real power and AB is
the reactive power. The kVA power is S=OB and φ1 is the power factor angle. Now
assuming that there is a kW increase .this can be met by increasing the kVA
supply(addition of a new unit). Or by adding capacitor banks of reactive value CF
kVAr. The final vector diagram for the overall plant becomes ODF(after adding
capacitor banks/ phase advancing plant) and φ2 is the new power factor angle. It is clear
from the vector diagram that S is maintained constant, therefore we save on the
kVA(=BC new gen. plant/unit) and the expenditure is on the kVAr(=CF/ phase adv.
plant).
BC = BE/cosφ1
BE = AD = OD – OA = Scosφ2 -Scosφ1
BC = S(cosφ2 - cosφ1)/cosφ1
CF = DC – DF
tanφ1 = DC/OD
DC = ODtanφ1 = (OA + AD)tanφ1 = [P + S(cosφ2 – cosφ1)]tanφ1
DF = Ssinφ2
CF = [P + S(cosφ2 – cosφ1)]tanφ1 - Ssinφ2
A    D
              O
                            φ2
                       φ1
                                  S
                            S                  F

                                               E
                                      B

                                               C


If ‘a’ is the rate of charge in Rs/kVA and ‘b’ is the charge in Rs/kVAr (if it is
annual charge, then the interest and depreciation rate per annum has to be
considered), then the net saving is
Saving = a(BC) – b(CF) = a(S(cosφ2 - cosφ1)/cosφ1) – b([P + S(cosφ2 –
cosφ1)]tanφ1 - Ssinφ2)
Interconnections

Advantages of interconnection:
•The total reserve capacity can be reduced.
•The requirement of high installed capacity is also reduced.
•The most effective units can be used at high load factor and the
inefficient stations can be used only at peak hours.
•The reliability of the system is increased.
Drawbacks:
•Fault in one system gets transferred to other parts on the system.
•High switch gear rating equipment needs to be employed at various
parts of the system.
•Proper management is required.
Tariffs:
For proper management of any electricity utility it os important to have a source of
income to meet its expenses. It is also required for future expansion.
There are two types of charges:

1.Fixed: Fixed charges include the interest and depreciation, cost of plants, buildings,
transmission and distribution network, part of salary of staff, cost of meter, the billing
collection and service etc.
2.Running charges: It is also called variable cost or charge. It includes the operation,
fuel costs and maintainence.

                              General form of tariffs:
                                akWh + bkW + c
Types of tariffs:
1. Flat rate tariff: The electricity charge is directly the multiplication of energy
     consumption and the factor a.
2. Two part tariff: Apart from the energy consumed, there is charge for the maximum
     demand also.
3. Block rate tariff: Different blocks of energy consumption are charged at different
     rates. For example, for the first 50 units the charge will be Rs. 1.85 per unit and for
     the next 50 units the charge is Rs.2.90 per unit.
4. Maximum demand tariff: Power factor tariffs are calculated based on the maximum
     demand only (a and c only).
5. Power factor tariff: Power factor tariffs are devised to differentiate between the
     good power factor users and poor power factor users.
     a. kVA maximum demand tariff: Instead of charging the maximum real power
     demand, maximum kVA demand is charged in addition to the charge
     corresponding to energy.
    b. kWh and kVAr tariff: Both kWh and kVAh (the reactive power consumption
     are charged separately.
     c. Sliding or average power factor: There is some extra charge if the power factor
     is below the set value (0.8). If consumers improve the power factor an incentive
     will be given to those consumers.
1. The loads on the mains of a supply system is 1000kW at a power factor of 0.8
lagging. What must be the kVA rating of the phase advancing plant which takes leading
current at a power factor of 0.15 in order to increase power factor of the whole system
to 1.
             O         100kW    A                                  100kW         x kW
                  Φ1
                                          S kVA         y kVAr                          y kVAr

                                            Φ2
                                 B
                                                 x kW



           cosΦ1=0.8
           Φ1 = 36.89°
           AB = tan(36.89)*1000 = 750kVAr
           A phase advancing plant with y = 750kVAr has to be added to give a pf of 1
           cosΦ2 = 0.15
           Φ2 = 81.37°
           S = y/sin81.37 = 750/0.9887 = 758.58kVA
           Therefore kVA rating of phase advancing plant = 758.58kVA
2. A three phase synnchronous motor is connected in parallel with a load of 500kW at
0.8 power factor lagging and it’s field excitation is adjusted until it raises the total
power factor to 0.9 lagging. If the mechanical load on the motor including losses takes
125kW, calculate the kVA input to the motor.


            O   500kW     125kW B
                 Φ2 Φ                          S kVA
                      1                                     x kVAr

                                 C
                                 x kVAr         125kW
                                 D


          cosΦ1= 0.8
          Φ1 = 36.89°
          BD= tan(36.89)*500=375kVAr
          cosΦ2 = 0.9
          Φ2 = 25.84°
          BC = tan(25.84)*(500+125) = 302.67kVAr
          x = CD = BD-BC = 375-302.67 = 72.32kVAr
          S = √(72.322 +1252) = 144.41kVA
          Therefore kVA rating of synchronous motor = 144.41kVA
3. Load on a supply system is 1000kW at a power factor of 0.707 lagging. What must
be the kVA rating of the phase advancing plant which takes leading current at a power
factor of 0.1 in order to raise the power factor of the whole system to 0.95 lagging.


       O   1000kW       A                           O              Ax kW C
           Φ1                                           100kW
                                                          Φ3

                                              y kVAr                       D
                        B         Φ2                                       y kVAr
                                   x kW                                    B
  cosΦ1=0.707
  Φ1 = 45°
  AB = tan(45)*1000 = 1000kVAr
  cosΦ2 = 0.1
  Φ2 = 84.26°
  y = tan(84.26)*x = 9.949x
  cosΦ3 = 0.95
  Φ3 = 18.19°
  tan(18.19) = (1000-y)/(1000+x) = (1000-9.949x)/(1000+x)
  ∴x = 65.38
  y = 9.949*x = 650.59
  ∴S =√(65.32 +6502) = 653.86kVA
  Therefore kVA rating of phase advancing plant = 653.86kVA
4. The load on a certain installation may be considered constant at 1200 kVA, 0.75
lagging power factor for 8000 hours per annum. The tariff is Rs.65 per kVA maximum
demand + 2 paisa per kWh.
 a. Determine the annual charge for electric energy before installing any apparatus.
 b.Power factor improving apparatus is installed to improve the power factor to 0.95
 lagging from 0.75. Determine the kVAr required and the new annual charge if the
 power factor improvimg apparatus costs Rs. 65 per kVAr. The annual interest and
 depreciation charges are 10% of the capital cost and the losses in the apparatus are 5%
 of kVAr rating.

  a.                  O                 A
                          Φ1

                       1200kVA
                                        B
         cosΦ1=0.75
         Φ1 = 41.4°
         OA = 1200*0.75 = 900kW
         kVA maximum demand = 1200kVA
         kWh = 900*3000 = 2700000kWh
         Tariff = Rs.65/kVA maximum demand + 0.02Rs./kWh
         Annual charge = 65*1200 +0.02*2700000 = Rs.132000
b.


                           Q
                                   Let the kVAr rating of the power factor improving
               Φ2
                                   apparatus be Q.
                0.05Q              Therefore kW = 5% of kVAr = 0.05Q




         O       900kW         A 0.05Q D
                                              BD = tan(41.4)*900 = 793.73kVAr
                 Φ3
                                              cosΦ3=0.95
                                       C
                                              Φ3 = 18.19°
                                              tan(18.19) = (793.73 – Q)/(0.05Q + 900)
                                        Q
                                              ⇒ Q = 489.95kVAr
                                       B      Snew = (793.13 – Q)/sin(18.19) = 973.126kVA
Annual charge :                               OD = 900+0.05Q = 924.5kW
     1. Charge based on kVA demand : 60*973.126 = Rs.63245
     2. Charges due to energy consumption is = 0.02*924.5*3000=Rs.55470
     3. Charges due to depreciation rate of the capacitor banks = cost of
         the apparatus*kVAr*interest = 60*490*0.1 = Rs.2940
      Total annual charge = Rs 121655

Weitere ähnliche Inhalte

Was ist angesagt?

Load curve
Load curveLoad curve
Load curveboromama
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
input output characteristics of thermal plant
input output characteristics of thermal plantinput output characteristics of thermal plant
input output characteristics of thermal plantmathamramesh
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation ControlBirju Besra
 
Objectives of shunt compensation
Objectives of shunt compensationObjectives of shunt compensation
Objectives of shunt compensationAyyarao T S L V
 
Power factor presentation
Power factor presentationPower factor presentation
Power factor presentationAzhar Abbas
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curvesGPERI
 
economics of power generation
economics of power generationeconomics of power generation
economics of power generationjagniyant
 
Power electronics Phase Controlled Rectifiers - SCR
Power electronics   Phase Controlled Rectifiers - SCRPower electronics   Phase Controlled Rectifiers - SCR
Power electronics Phase Controlled Rectifiers - SCRBurdwan University
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power systemBalaram Das
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentSANTOSH GADEKAR
 
Speed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulatorSpeed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulatorShivagee Raj
 
Automatic load frequency control
Automatic load frequency controlAutomatic load frequency control
Automatic load frequency controlBalaram Das
 

Was ist angesagt? (20)

Load curve
Load curveLoad curve
Load curve
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Restructuring
RestructuringRestructuring
Restructuring
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
 
input output characteristics of thermal plant
input output characteristics of thermal plantinput output characteristics of thermal plant
input output characteristics of thermal plant
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
 
Load flow studies 19
Load flow studies 19Load flow studies 19
Load flow studies 19
 
Objectives of shunt compensation
Objectives of shunt compensationObjectives of shunt compensation
Objectives of shunt compensation
 
Power factor presentation
Power factor presentationPower factor presentation
Power factor presentation
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
Unit commitment
Unit commitmentUnit commitment
Unit commitment
 
Static relay
Static relayStatic relay
Static relay
 
economics of power generation
economics of power generationeconomics of power generation
economics of power generation
 
Power electronics Phase Controlled Rectifiers - SCR
Power electronics   Phase Controlled Rectifiers - SCRPower electronics   Phase Controlled Rectifiers - SCR
Power electronics Phase Controlled Rectifiers - SCR
 
Load flow study
Load flow studyLoad flow study
Load flow study
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit Commitment
 
Speed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulatorSpeed control of Three phase Induction motor using AC voltage regulator
Speed control of Three phase Induction motor using AC voltage regulator
 
induction generator
induction generatorinduction generator
induction generator
 
Automatic load frequency control
Automatic load frequency controlAutomatic load frequency control
Automatic load frequency control
 

Andere mochten auch

Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generationAFAQAHMED JAMADAR
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curveCraZzy Shubh
 
Load forecasting
Load forecastingLoad forecasting
Load forecastingsushrut p
 
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkMET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkIbrahim AboKhalil
 
AIUkraine 2015: Cut on burning your dinosaurs dude II
AIUkraine 2015: Cut on burning your dinosaurs dude IIAIUkraine 2015: Cut on burning your dinosaurs dude II
AIUkraine 2015: Cut on burning your dinosaurs dude IIIvan Sobolev
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdfAjay Bhatnagar
 
TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...
TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...
TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...Gildas POTIN
 
Energy & Water Auditing & Conservation
Energy & Water Auditing & ConservationEnergy & Water Auditing & Conservation
Energy & Water Auditing & ConservationAnngeo George
 
Short-term Load Forecasting based on Neural network and Local RegressionJie
Short-term Load Forecasting based on Neural network and Local RegressionJieShort-term Load Forecasting based on Neural network and Local RegressionJie
Short-term Load Forecasting based on Neural network and Local RegressionJieJie Bao
 
Perfect competition
Perfect competitionPerfect competition
Perfect competitionMadhu Bala
 
UBER vs LYFT 到底誰才是共享經濟?
UBER vs LYFT 到底誰才是共享經濟?UBER vs LYFT 到底誰才是共享經濟?
UBER vs LYFT 到底誰才是共享經濟?賢澔 陳
 
Load Forecasting II
Load Forecasting IILoad Forecasting II
Load Forecasting IIlinsstalex
 
Elasticity mcq
Elasticity mcqElasticity mcq
Elasticity mcqeclements
 

Andere mochten auch (20)

Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
 
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezkMET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
MET 401 Chapter 10 -_economics_of_power_generation_-_a._rezk
 
AIUkraine 2015: Cut on burning your dinosaurs dude II
AIUkraine 2015: Cut on burning your dinosaurs dude IIAIUkraine 2015: Cut on burning your dinosaurs dude II
AIUkraine 2015: Cut on burning your dinosaurs dude II
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
diversity
diversitydiversity
diversity
 
TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...
TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...
TINCE2016 - Impact load curve for commercial aircrafts: a normalized model – ...
 
Benefit-Cost Analysis of Curve Safety Treatments
Benefit-Cost Analysis of Curve Safety TreatmentsBenefit-Cost Analysis of Curve Safety Treatments
Benefit-Cost Analysis of Curve Safety Treatments
 
Energy & Water Auditing & Conservation
Energy & Water Auditing & ConservationEnergy & Water Auditing & Conservation
Energy & Water Auditing & Conservation
 
Energy Auditing 101
Energy Auditing 101Energy Auditing 101
Energy Auditing 101
 
PERFECT COMPETITION
PERFECT COMPETITIONPERFECT COMPETITION
PERFECT COMPETITION
 
Short-term Load Forecasting based on Neural network and Local RegressionJie
Short-term Load Forecasting based on Neural network and Local RegressionJieShort-term Load Forecasting based on Neural network and Local RegressionJie
Short-term Load Forecasting based on Neural network and Local RegressionJie
 
ANN load forecasting
ANN load forecastingANN load forecasting
ANN load forecasting
 
Perfect competition
Perfect competitionPerfect competition
Perfect competition
 
Electric Utility Solutions: Basics of Load Allocation
Electric Utility Solutions: Basics of Load AllocationElectric Utility Solutions: Basics of Load Allocation
Electric Utility Solutions: Basics of Load Allocation
 
UBER vs LYFT 到底誰才是共享經濟?
UBER vs LYFT 到底誰才是共享經濟?UBER vs LYFT 到底誰才是共享經濟?
UBER vs LYFT 到底誰才是共享經濟?
 
Load Forecasting II
Load Forecasting IILoad Forecasting II
Load Forecasting II
 
Elasticity mcq
Elasticity mcqElasticity mcq
Elasticity mcq
 

Ähnlich wie Load characteristics and Economic Aspects

Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxFelcherLayugan
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptxLucasMogaka
 
Load curve notes.pdf
Load curve notes.pdfLoad curve notes.pdf
Load curve notes.pdfaravind649229
 
Examples on load curve
Examples on load curveExamples on load curve
Examples on load curvedhirajthakkar1
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1NBoss
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsBalamurugan Subburaj
 
Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...
Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...
Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...Mario B.
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docxArpitaBanik8
 
Economics of power plant h.pptx
Economics of power plant   h.pptxEconomics of power plant   h.pptx
Economics of power plant h.pptxMahamad Jawhar
 
ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE ENERGY SOURCE (SOLAR, WIND &...
ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE  ENERGY SOURCE (SOLAR, WIND &...ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE  ENERGY SOURCE (SOLAR, WIND &...
ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE ENERGY SOURCE (SOLAR, WIND &...AMOGHA A K
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptxsurbhi agarwal
 
2850-107 Carrying out electrical assembly (H0) Solution.pptx
2850-107 Carrying out electrical assembly (H0) Solution.pptx2850-107 Carrying out electrical assembly (H0) Solution.pptx
2850-107 Carrying out electrical assembly (H0) Solution.pptxssuser758b44
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfTheBlank5
 
Hybrid power generation by and solar –wind
Hybrid power generation by and solar –windHybrid power generation by and solar –wind
Hybrid power generation by and solar –windUday Wankar
 
PV AND OTHER RENEWABLE ENERGY
 PV AND OTHER RENEWABLE ENERGY PV AND OTHER RENEWABLE ENERGY
PV AND OTHER RENEWABLE ENERGYH Janardan Prabhu
 
efficiency of various power plants
efficiency of various power plantsefficiency of various power plants
efficiency of various power plantsRadhika Chittora
 

Ähnlich wie Load characteristics and Economic Aspects (20)

Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptx
 
Load curve notes.pdf
Load curve notes.pdfLoad curve notes.pdf
Load curve notes.pdf
 
Examples on load curve
Examples on load curveExamples on load curve
Examples on load curve
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...
Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...
Energy for telecommunications systems - Wimax Systems, Presentation - Dimensi...
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
 
Economics of power plant h.pptx
Economics of power plant   h.pptxEconomics of power plant   h.pptx
Economics of power plant h.pptx
 
ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE ENERGY SOURCE (SOLAR, WIND &...
ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE  ENERGY SOURCE (SOLAR, WIND &...ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE  ENERGY SOURCE (SOLAR, WIND &...
ELECTRICAL POWER GENERATION BY HYBRID RENEWABLE ENERGY SOURCE (SOLAR, WIND &...
 
Ejemplo FD.pdf
Ejemplo FD.pdfEjemplo FD.pdf
Ejemplo FD.pdf
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptx
 
2850-107 Carrying out electrical assembly (H0) Solution.pptx
2850-107 Carrying out electrical assembly (H0) Solution.pptx2850-107 Carrying out electrical assembly (H0) Solution.pptx
2850-107 Carrying out electrical assembly (H0) Solution.pptx
 
Solar powered house
Solar powered houseSolar powered house
Solar powered house
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Hybrid power generation by and solar –wind
Hybrid power generation by and solar –windHybrid power generation by and solar –wind
Hybrid power generation by and solar –wind
 
Unit5ppts
Unit5pptsUnit5ppts
Unit5ppts
 
PV AND OTHER RENEWABLE ENERGY
 PV AND OTHER RENEWABLE ENERGY PV AND OTHER RENEWABLE ENERGY
PV AND OTHER RENEWABLE ENERGY
 
Unit1questions
Unit1questionsUnit1questions
Unit1questions
 
efficiency of various power plants
efficiency of various power plantsefficiency of various power plants
efficiency of various power plants
 

Mehr von Abha Tripathi

Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit iiAbha Tripathi
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit ivAbha Tripathi
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteriaAbha Tripathi
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutionsAbha Tripathi
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutionsAbha Tripathi
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system AnalysisAbha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical componentsAbha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system componentsAbha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel PlantAbha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, Abha Tripathi
 

Mehr von Abha Tripathi (20)

Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
 
Practice questions
Practice questionsPractice questions
Practice questions
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Questions unit4
Questions unit4Questions unit4
Questions unit4
 
Questions unit3
Questions unit3Questions unit3
Questions unit3
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutions
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 

Kürzlich hochgeladen

04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 

Kürzlich hochgeladen (20)

04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 

Load characteristics and Economic Aspects

  • 1. Chapter 2 Load Characteristics and Economic Aspects
  • 2. Terms used commonly: 1. Connected load: Sum of the continuous rating of the entire load consuming apparatus connected to the system. 2. Maximum demand: It means the maximum power that the circuit is likely to draw at any time. 3. Demand factor: It is the ratio of maximum demand to connected load. Demand factor has to be less than one. 4. Diversity factor: It is the ratio of sum of individual maximum demand to the maximum demand of the whole power system. It is always greater than one. 5. Coincidence factor: Coincidence factor is the ratio of the maximum demand by the sum of the individual maximum demands. It is always less than one.
  • 3. 6. Load diversity : It is defined mathematically as, Load diversity = Sum of individual loads – Peak of the combined load 7. Contribution factor: It is the contribution of a particular load, in per unit of the individual demand, to the group maximum demand. 8. Loss factor: It is the ratio of average power loss to power loss at peak load. 9. Load factor: It is the ratio of average demand to maximum demand. Load factor = Energy produced in a given time/(maximum demand * hours of operation in the given period) 10. Plant capacity factor: It is the ratio of average annual load to the plant rated capacity. Also, Plant capacity factor = Energy produced in one year/(Plant rated capacity * 8760)
  • 4. 11. Plant use factor: It is defined as, Plant use factor =Actual energy produced/(Plant capacity * plant operation time in hours) 12. Utilization factor: It is the ratio of maximum load to rated capacity.
  • 5. Reserves: •Spinning reserve: It is the generating capacity which is connected to a bus (common connection) and is ready to take the load. •Cold reserve: It is that reserve generating capacity which is available for service but not in operation. •Hot reserve: It is that reserve generating capacity which is in operation but not in service. • Firm power: It is the power intended to be always available (even under emergency condition • Reserve margin: It is the difference between the rated capacity and the actual loading on the generator.
  • 6. Load Curve: It is useful as it gives – 1.Maximum demand (peak of the curve) 2.Energy produced (area under the curve) 3.Load factor (The ratio of the area under the curve to the total area under the rectangle in which it is contained gives the Load factor for the period). 4.Average loading (The area under the curve divided by the number of hours gives the average demand). Load (kW) Time (hrs)
  • 7. Load Duration Curve: All the loads are rearranged in descending order. Load (kW) Time (hours) Energy Load Curve: It plots the cumulative integration of area under load curve starting at zero load to a particular load and it is also called integrated duration curve. Load (kW) Energy (kWh)
  • 8. 1.A residential consumer has a connected load of 6 lamps each of 100W and 4 fans of 60W at his premises. His demand is as follows: From midnight to 5 am – 120W From 5 am to 6 pm – no load From 6 pm to 7 pm – 380W From 7 pm to 9 pm – 680W From 9 pm to midnight – 420W a. Plot the load curve. b. Find the energy consumption in 24 hours: Area under curve = (5*120) + (380*1) +(680*2) +(420*3) = 3600Wh c. Calculate the demand factor, the average load, the maximum load and load factor. Maximum load = 680W (from load curve) Demand factor = Maximum Demand/ Connected Load = 680/(6*100 +4*60) = 0.809 Average load = Energy consumed/ no. of hours = 3600/24 = 150W Load factor = Average load/ Maximum load = 150/680 = 0.22
  • 9. 2. A generating station gas a maximum demand of 80MW, a load factor of 65%, a plant capacity factor of 40% and a plant use factor of 85%. Find: a.Daily energy produced. b.Reserve capacity of plant. c.The maximum energy that could be produced daily if the plant was running all the time. d.The maximum energy that could be produced daily if the plant was running as per operating schedule. a. Average demand = Load factor * Maximum demand = 0.65 * 80MW = 52MW Daily energy produced = 52 * 24 = 1248MWh b. Installed capacity = Average demand/ Plant capacity factor = 52MW/ 0.4 = 130MW Reserve capacity = Installed capacity – Maximum demand = 130MW – 80MW = 50MW c. Maximum energy that could be produced daily if it was running all the time = Installed capacity * 24 = 130 * 24 = 3120MWh d. Maximum energy that could be produced daily if the plant was running as per operating schedule = Daily energy produced/ plant use factor = 1248/ 0.85 = 1468.23MWh
  • 10. 3.Maximum demand of a generating station is 100MW. The load factor is 65%. The plant capacity factor and the plant factor are 50% and 80% respectively. Determine: a.The daily energy produced. b.The installed capacity of the plant. c.The reserve capacity of the plant. d.The maximum energy that could be produced daily if the plant is running all the time. e.The maximum energy that could be produced daily at full load (according to operating schedule). f. Utilisation factor. a. Average demand = Load factor * Maximum demand = 0.65 * 100MW = 65MW The daily energy produced = Average demand * 24 = 65MW * 24 = 1560MWh b. The installed capacity = Average demand/ Plant capacity factor = 65MW/0.5 = 130MW
  • 11. c. Reserve capacity = Installed capacity – Maximum demand = 130MW – 100MW = 30MW d. Maximum energy that could be produced daily if it was running all the time = Installed capacity * 24 = 130MW * 24 = 3120MWh e. Maximum energy that could be produced daily if the plant was running as per c. operating schedule = Daily energy produced/ plant use factor = 1560/ 0.85= 1950MWh f. Utilisation factor = Maximum load/ Rated capacity = 100/130 = 0.769
  • 12. 4.The load (in kW) on a substation is as follows: Time Street lighting Domestic Commercial Total 12 am 400 600 400 1400 1 am 400 500 400 1300 2 am 400 450 400 1250 3 am 400 450 400 1250 4 am 400 500 400 1300 5 am 400 700 500 1600 6 am 400 1000 400 1800 7 am 0 800 700 1500 8 am 0 700 900 1600 9 am 0 600 1200 1800 10 am 0 500 1300 1800 11 am 0 500 1200 1700 12 pm 0 500 1100 1600 1 pm 0 600 900 1500 2 pm 0 600 1100 1700 3 pm 0 600 1000 1600 4 pm 0 600 900 1500 5 pm 0 700 600 1300 6 pm 400 800 500 1700 7 pm 400 1050 500 1950 8 pm 400 1200 500 2100 9 pm 400 1100 500 2000 10 pm 400 900 400 1700 11 pm 400 700 400 1500
  • 13. a. Find the maximum demand, average demand and the load factor pf the feeder b. The class contribution factor for street lighting and the remaining load c. The diversity factor of the feeder. d. The coincidence factor of the load group. e. If the feeder has the average loss of 14kW and annual loss factor of 0.14. Find the following: 1. The peak power loss of the feeder at peak load. 2. Total annual loss of feeder. 3. Demand factor of the feeder if the connected load is 2500kW. Solution a. Maximum demand = 2100kW Average demand = Sum of total demands/ 24 = 1602.08kW Load factor = Average demand/ Maximum demand = 1602.08/ 2100 = 0.763 =76.3% b. Class contribution factor = load of class at peak load/ maximum load of that class CSL = 400/400 =1 CDom = 1200/1200 = 1 CCom = 500/1300 = 0.385
  • 14. c. Diversity factor = Sum of maximum demands for each class/ Maximum demand = (400 + 1200 + 1300)/2100 = 1.381 d. Coincidence factor = 1/Diversity factor = 0.724 e. 1. Power loss at peak load = average power loss/ loss factor = 14kW/0.14 = 100kW 2. Total annual loss = Average loss * 365 = 5110kW 3. Demand factor = Maximum demand/ Connected load = 2100/2500 = 0.84
  • 15. 5. A residential consumer has a connected load of 10 lamps of 100W each. his demand is as follows: From midnight to 5am – 100W From 5am to 6pm – no load From 6pm to 7pm – 800W From 7pm to 9pm – 900W From 9pm to midnight – 400W a. Plot the load curve. b. Find the energy consumed during 24 hours. c. Calculate the demand factor, average load, maximum load and load factor. Ans: b. Energy consumed = area under the curve = 100*5 + 1*800 + 2*900 + 3*400 = 4300Wh c. Demand factor = Maximum load/ Connected load = 900/(10*100) = 0.9 Average load = Energy consumed/ no.of hours = 4300/24 = 179.167W Maximum load = 900W Load factor = Average demand/ Maximum demand = 179.167/900 = 0.199
  • 16. Power factor: For a 3 phase balanced system, if P is the power, VL and IL are the line voltage and current respectively and cosφ is the power factor then the above mentioned quantities can be related as follows: P = √3VLILcosφ cosφ = P/√3VLIL If P and VL are assumed to be constant (for transmitting the same power at the same voltage), IL α 1/cosφ. Hence it is very clear from the last equation that if power factor is decreased then the current increases, because of which the following drawbacks are there: 1. The ratings of the generators and transformers will increase. 2. Since IL increases the thickness of the conductor in the transmission lines will increase. Due to this copper will be used more and cost of transmission lines will go up. 3. Since the losses in the transmission line directly proportional to the square of the current, the loss increases. 4. The voltage regulation is poor because of more drop.
  • 17. Various causes of low power factor: 1. Most of the induction motors operate at lagging power factor. The power factor of these motors falls with decrease in load. 2. The arc and induction furnaces operate on very low lagging power factor. 3. Transformers draw magnetising current which causes the total current to lag behind. Measures to avoid low power factor: 1. By using synchronous motors instead of induction motors. 2. By using high speed induction motors instead of low speed induction motors. 3. By using operating the induction motor at rated output. 4. By switching the induction motor from delta winding to star winding. 5. By using dc motors instead of ac motors wherever possible. Usually static capacitors, synchronous condensors, phase advancers or modifiers are usually added to improve power factor of the entire power system.
  • 18. Methods to improve power factor: 1. Constant kW method: OAB is the power triangle of the initial plant without phase modifier. P is the real power in kW. φ1 is the power factor angle. S1 is the kVA power and C is the apparent power and AB is the reactive power in kVAr. After addition of phase modifier, the new power triangle is OAC. It is clear that the kW power is not changing but the kVA power is getting reduced from S1 to S2. The power factor is improved (cosφ2). O P φ2 A φ1 S2 S1 C B
  • 19. If ‘a’ is the rate of charge of kVA in Rs/kVA and ‘b’ is the expenditure associated with the capacitor banks in Rs/kVAr then the net saving is c = a(S1-S2) – b(BC) ∆S = S1-S2 = (P/cosφ1) – (P/cosφ2) BC = AB – AC = Ptanφ1 - Ptanφ2 Total saving : c = a((P/cosφ1) – (P/cosφ2)) – b(Ptanφ1 - Ptanφ2) For maximum saving, differentiate ‘c’ with respect to φ2. dc/dφ2 = 0 Therefore when, sinφ2 = b/a saving is maximum.
  • 20. 2. Constant kVA method: Initially the power triangle of the plant is OAB where OA is the real power and AB is the reactive power. The kVA power is S=OB and φ1 is the power factor angle. Now assuming that there is a kW increase .this can be met by increasing the kVA supply(addition of a new unit). Or by adding capacitor banks of reactive value CF kVAr. The final vector diagram for the overall plant becomes ODF(after adding capacitor banks/ phase advancing plant) and φ2 is the new power factor angle. It is clear from the vector diagram that S is maintained constant, therefore we save on the kVA(=BC new gen. plant/unit) and the expenditure is on the kVAr(=CF/ phase adv. plant). BC = BE/cosφ1 BE = AD = OD – OA = Scosφ2 -Scosφ1 BC = S(cosφ2 - cosφ1)/cosφ1 CF = DC – DF tanφ1 = DC/OD DC = ODtanφ1 = (OA + AD)tanφ1 = [P + S(cosφ2 – cosφ1)]tanφ1 DF = Ssinφ2 CF = [P + S(cosφ2 – cosφ1)]tanφ1 - Ssinφ2
  • 21. A D O φ2 φ1 S S F E B C If ‘a’ is the rate of charge in Rs/kVA and ‘b’ is the charge in Rs/kVAr (if it is annual charge, then the interest and depreciation rate per annum has to be considered), then the net saving is Saving = a(BC) – b(CF) = a(S(cosφ2 - cosφ1)/cosφ1) – b([P + S(cosφ2 – cosφ1)]tanφ1 - Ssinφ2)
  • 22. Interconnections Advantages of interconnection: •The total reserve capacity can be reduced. •The requirement of high installed capacity is also reduced. •The most effective units can be used at high load factor and the inefficient stations can be used only at peak hours. •The reliability of the system is increased. Drawbacks: •Fault in one system gets transferred to other parts on the system. •High switch gear rating equipment needs to be employed at various parts of the system. •Proper management is required.
  • 23. Tariffs: For proper management of any electricity utility it os important to have a source of income to meet its expenses. It is also required for future expansion. There are two types of charges: 1.Fixed: Fixed charges include the interest and depreciation, cost of plants, buildings, transmission and distribution network, part of salary of staff, cost of meter, the billing collection and service etc. 2.Running charges: It is also called variable cost or charge. It includes the operation, fuel costs and maintainence. General form of tariffs: akWh + bkW + c
  • 24. Types of tariffs: 1. Flat rate tariff: The electricity charge is directly the multiplication of energy consumption and the factor a. 2. Two part tariff: Apart from the energy consumed, there is charge for the maximum demand also. 3. Block rate tariff: Different blocks of energy consumption are charged at different rates. For example, for the first 50 units the charge will be Rs. 1.85 per unit and for the next 50 units the charge is Rs.2.90 per unit. 4. Maximum demand tariff: Power factor tariffs are calculated based on the maximum demand only (a and c only). 5. Power factor tariff: Power factor tariffs are devised to differentiate between the good power factor users and poor power factor users. a. kVA maximum demand tariff: Instead of charging the maximum real power demand, maximum kVA demand is charged in addition to the charge corresponding to energy. b. kWh and kVAr tariff: Both kWh and kVAh (the reactive power consumption are charged separately. c. Sliding or average power factor: There is some extra charge if the power factor is below the set value (0.8). If consumers improve the power factor an incentive will be given to those consumers.
  • 25. 1. The loads on the mains of a supply system is 1000kW at a power factor of 0.8 lagging. What must be the kVA rating of the phase advancing plant which takes leading current at a power factor of 0.15 in order to increase power factor of the whole system to 1. O 100kW A 100kW x kW Φ1 S kVA y kVAr y kVAr Φ2 B x kW cosΦ1=0.8 Φ1 = 36.89° AB = tan(36.89)*1000 = 750kVAr A phase advancing plant with y = 750kVAr has to be added to give a pf of 1 cosΦ2 = 0.15 Φ2 = 81.37° S = y/sin81.37 = 750/0.9887 = 758.58kVA Therefore kVA rating of phase advancing plant = 758.58kVA
  • 26. 2. A three phase synnchronous motor is connected in parallel with a load of 500kW at 0.8 power factor lagging and it’s field excitation is adjusted until it raises the total power factor to 0.9 lagging. If the mechanical load on the motor including losses takes 125kW, calculate the kVA input to the motor. O 500kW 125kW B Φ2 Φ S kVA 1 x kVAr C x kVAr 125kW D cosΦ1= 0.8 Φ1 = 36.89° BD= tan(36.89)*500=375kVAr cosΦ2 = 0.9 Φ2 = 25.84° BC = tan(25.84)*(500+125) = 302.67kVAr x = CD = BD-BC = 375-302.67 = 72.32kVAr S = √(72.322 +1252) = 144.41kVA Therefore kVA rating of synchronous motor = 144.41kVA
  • 27. 3. Load on a supply system is 1000kW at a power factor of 0.707 lagging. What must be the kVA rating of the phase advancing plant which takes leading current at a power factor of 0.1 in order to raise the power factor of the whole system to 0.95 lagging. O 1000kW A O Ax kW C Φ1 100kW Φ3 y kVAr D B Φ2 y kVAr x kW B cosΦ1=0.707 Φ1 = 45° AB = tan(45)*1000 = 1000kVAr cosΦ2 = 0.1 Φ2 = 84.26° y = tan(84.26)*x = 9.949x cosΦ3 = 0.95 Φ3 = 18.19° tan(18.19) = (1000-y)/(1000+x) = (1000-9.949x)/(1000+x) ∴x = 65.38 y = 9.949*x = 650.59 ∴S =√(65.32 +6502) = 653.86kVA Therefore kVA rating of phase advancing plant = 653.86kVA
  • 28. 4. The load on a certain installation may be considered constant at 1200 kVA, 0.75 lagging power factor for 8000 hours per annum. The tariff is Rs.65 per kVA maximum demand + 2 paisa per kWh. a. Determine the annual charge for electric energy before installing any apparatus. b.Power factor improving apparatus is installed to improve the power factor to 0.95 lagging from 0.75. Determine the kVAr required and the new annual charge if the power factor improvimg apparatus costs Rs. 65 per kVAr. The annual interest and depreciation charges are 10% of the capital cost and the losses in the apparatus are 5% of kVAr rating. a. O A Φ1 1200kVA B cosΦ1=0.75 Φ1 = 41.4° OA = 1200*0.75 = 900kW kVA maximum demand = 1200kVA kWh = 900*3000 = 2700000kWh Tariff = Rs.65/kVA maximum demand + 0.02Rs./kWh Annual charge = 65*1200 +0.02*2700000 = Rs.132000
  • 29. b. Q Let the kVAr rating of the power factor improving Φ2 apparatus be Q. 0.05Q Therefore kW = 5% of kVAr = 0.05Q O 900kW A 0.05Q D BD = tan(41.4)*900 = 793.73kVAr Φ3 cosΦ3=0.95 C Φ3 = 18.19° tan(18.19) = (793.73 – Q)/(0.05Q + 900) Q ⇒ Q = 489.95kVAr B Snew = (793.13 – Q)/sin(18.19) = 973.126kVA Annual charge : OD = 900+0.05Q = 924.5kW 1. Charge based on kVA demand : 60*973.126 = Rs.63245 2. Charges due to energy consumption is = 0.02*924.5*3000=Rs.55470 3. Charges due to depreciation rate of the capacitor banks = cost of the apparatus*kVAr*interest = 60*490*0.1 = Rs.2940 Total annual charge = Rs 121655