SlideShare ist ein Scribd-Unternehmen logo
1 von 22
Downloaden Sie, um offline zu lesen
UTTAR PRADESH POWER 
TRANSMISSION 
CORPORATION LIMITED 
132KV VAISHALI SUBSTATION 
Presented By 
Aman Rajput
INTRODUCTION 
 The creation of Uttar Pradesh Power Corporation Ltd. (UPPCL) on January 
14, 2000 is the result of power sector reforms and restructuring in UP (India) 
which is the focal point of the Power Sector, responsible for planning and 
managing the sector through its transmission, distribution and supply of 
electricity. 
 UPPCL will be professionally managed utility supplying reliable and cost 
efficient electricity to every citizen of the state through highly motivated 
employees and state of art technologies, providing an economic return to 
our owners and maintaining leadership in the country.
About 132KV Vaishali Substation 
 132KV Vaishali Substation is one important substation of UPPTCL. It is situated 
at Vaishali sector-1, near U.P Gate, Ghaziabad. 
 The whole substation is divided in to two parts – 132 KV Switchyard & 33 KV 
Switchyard.
 The incoming lines for Vaishali: 
1. Noida (132KV line) 
2. Shahibabad (132KV line) 
 The outgoing lines of Vaishali: 
1. Vaishali-I 
2. Indirapuram-I 
3. Shipra Mall 
4. Vaishali-II 
5. Indirapuram-II 
6. Kalapather 
7. Nitikhand 
8. Mahagun Mall
SINGLE LINE DIAGRAM OF 132KV VAISHALI SUBSTATION
TRANSFORMER 
Two transformer are used in 132KV Vaishali substation : 
 40MVA Transformer (ALSTOM) 
 63MVA Transformer (Transformers & Rectifiers Ltd.) 
As we know, MVA= 3푉퐼 
For 63MVA, For 40MVA, 
63× 106 = √3 ×132×103×I 40× 106 = √3 ×132×103×I 
I = 275A (HV) I = 175A (HV) 
63× 106 = √3 × 33 ×103×I 40× 106 = √3 × 33 ×103×I 
I = 1100A (LV) I = 700A (LV) 
Therefore, total current across LV side = 1800A
LIGHTNING ARRESTOR 
 A lightning arrester is a device used on electrical 
power systems and telecommunications systems 
to protect the insulation and conductors of the 
system from the damaging effects of lightning. 
 The typical lightning arrester has a high-voltage 
terminal and a ground terminal. 
 When a lightning surge (or switching surge, which 
is very similar) travels along the power line to the 
arrester, the current from the surge is diverted 
through the arrestor, in most cases to earth. 
Lightning 
Arrestor
CURRENT TRANSFORMER 
 A current transformer (CT) is used for measurement of 
alternating electric currents. 
 When current in a circuit is too high to apply directly to 
measuring instruments, a current transformer produces 
a reduced current accurately proportional to the 
current in the circuit, which can be conveniently 
connected to measuring and recording instruments. 
 A current transformer isolates the measuring instruments 
from what may be very high voltage in the monitored 
circuit. 
 The primary circuit is largely unaffected by the insertion 
of the CT. The rated secondary current is commonly 
standardized at 1 or 5 amperes. For example, a 4000:5 
CT secondary winding will supply an output current of 5 
amperes when the primary winding current is 4000 
amperes.
POTENTIAL TRANSFORMER 
 Potential transformers (PT) (also called voltage 
transformers (VT)) are a parallel connected type of 
instrument transformer. 
 They are designed to present negligible load to the 
supply being measured and have an accurate voltage 
ratio and phase relationship to enable accurate 
secondary connected metering. 
 The PT is typically described by its voltage ratio from 
primary to secondary. Standard secondary voltage 
ratings are 120 volts and 70 volts, compatible with 
standard measuring instruments. 
 For example, a 600:120 PT would provide an output 
voltage of 120 volts when 600 volts are impressed 
across its primary winding.
CIRCUIT BREAKER 
 A circuit breaker is an automatically operated electrical switch designed to protect 
an electrical circuit from damage caused by overload or short circuit. Its basic 
function is to detect a fault condition and interrupt current flow. 
 Unlike a fuse, which operates once and then must be replaced, a circuit breaker can 
be reset (either manually or automatically) to resume normal operation. 
 A circuit breaker essentially consists of fixed and moving contacts. These contacts 
can be opened manually or by remote control whenever desired. When a fault 
occurs on any part of the system, the trip coils of breaker get energized and the 
moving contacts are pulled apart by some mechanism, thus opening the circuit. 
 When contacts of a circuit breaker are separated, an arc is struck; the current is thus 
able to continue. The production of arcs are not only delays the current interruption, 
but is also generates the heat. Therefore, the main problem is to distinguish the arc 
within the shortest possible time so that it may not reach a dangerous value.
 According to their arc quenching media the circuit 
breaker can be divided as- 
1. Oil circuit breaker 
2. Air circuit breaker 
3. SF6 circuit breaker 
4. Vacuum circuit breaker 
Oil circuit breaker 
 In oil circuit breaker the fixed contact and moving 
contact are immerged inside the insulating oil. Whenever 
there is a separation of electric current carrying contacts 
in the oil, the arc in circuit breaker is initialized at the 
moment of separation of contacts, and due to this arc 
the oil is vaporized and decomposed in mostly hydrogen 
gas and ultimately creates a hydrogen bubble around 
the arc. This highly compressed gas bubble around the 
arc prevents re-striking of the arc after electric 
current reaches zero crossing of the cycle.
Air circuit breaker 
For interrupting arc it creates an arc voltage in 
excess of the supply voltage. Arc voltage is 
defined as the minimum voltage required 
maintaining the arc. This circuit breaker increases 
the arc voltage by mainly three different ways: 
 It may increase the arc voltage by cooling the arc 
plasma. As the temperature of arc plasma is 
decreased, the mobility of the particle in arc 
plasma is reduced, hence more voltage gradient 
is required to maintain the arc. 
 It may increase the arc voltage by lengthening 
the arc path. As the length of arc path is 
increased, the resistance of the path is increased, 
and hence to maintain the same arc electric 
current more voltage is required to be applied 
across the arc path. That means arc voltage is 
increased. 
 Splitting up the arc into a number of series arcs 
also increases the arc voltage.
SF6 circuit breaker 
 In such circuit breaker, sulphur hexafluoride (SF6) 
gas is used as the arc quenching medium. The 
SF6 is an electronegative gas and has a strong 
tendency to absorb free electrons. 
 It consists of fixed and moving contacts. It has 
chamber, contains SF6 gas. When the contacts 
are opened, the mechanism permits a high 
pressure SF6 gas from reservoir to flow towards 
the arc interruption chamber. The moving 
contact permits the SF6 gas to let through these 
holes. 
 These circuit breakers are available for 
the voltage ranges from 33KV to 800KV and 
even more. 
132KV SF6 CB
Vacuum circuit breaker 
 Vacuum circuit breakers are circuit breakers which are used to protect 
medium and high voltage circuits from dangerous electrical situations. Like 
other types of circuit breakers, vacuum circuit breakers literally break the 
circuit so that energy cannot continue flowing through it, thereby 
preventing fires, power surges, and other problems which may emerge. 
 The operation of opening and closing of electric current carrying contacts 
and associated arc interruption take place in a vacuum chamber in the 
breaker which is called vacuum interrupter.
ISOLATOR 
 It is an off-load device. 
 It disconnects or isolates the circuit from the main power supply. 
 Even though, isolators is a switch, it is not used as a normal on off 
switch. 
 It is used only when the electrical system has to be disconnected 
from the main supply, to perform maintenance or related activities, 
which involve direct contact with the current carrying components 
of machinery. 
 Isolators may provide additional safety features like, when switched 
off the trapped charge will be ground through a ground terminal in 
the isolator. 
 Isolators are normally placed after the circuit breaker allowing the 
internal circuit to be disconnected from the main supply without 
affecting the breaker.
CAPACITOR BANK 
 The load on the power system is varying being high during 
morning and low in evening which increases the load 
current. This result in the decreased power factor. 
 The low power factor is mainly due to the fact most of the 
power loads are inductive and therefore take lagging 
currents. 
 In order to ensure most favorable conditions for a supply 
system from engineering and economic stand point it is 
important to have power factor as close to unity as possible. 
 In order to improve the power factor come device taking 
leading power should be connected in parallel with the 
load. One of the device can be capacitor bank. 
 The capacitor draws a leading current and partly or 
completely neutralize the lagging reactive component of 
load current. 
Capacitor bank accomplishes following operations: 
 Supply reactive power 
 Increases terminal voltage 
 Improve power factor
 FUSE 
A fuse is a short piece of wire or thin strip which melts when 
excessive current through it for sufficient time. It is inserted in 
series with the circuit under normal operating conditions; the fuse 
element is at a nature below its melting point. Therefore it carries 
the normal load current overheating. It is worthwhile to note that 
a fuse performs both detection and interruption functions. 
 BUS COUPLER 
The bus coupler consists of circuit breaker and isolator. Each 
generator and feeder may be connected to either main bus bar 
or spar bus bar with the help of bus coupler. Repairing, 
maintenance and testing of feeder circuit or other section can 
be done by putting them on spar bus bar, thus keeping the main 
bus bar undisturbed. Bus coupler is a device which is used switch 
from one bus to the other without any interruption in power 
supply and without creating hazardous arcs. It is achieved with 
the help of circuit breaker and isolators.
RELAY 
 When a failure occurs on any part of the system, it must be quickly 
detected and disconnected from the system. 
 Rapid disconnection of faulted apparatus limits the amount of 
damage to it and prevents the effects of fault from spreading into 
the system. 
 For high voltage circuits relays are employed to serve the desired 
function of automatic protective gear. The relays detect the fault 
and supply the information to the circuit breaker. 
 When a short circuit occurs at any point on the transmission line the 
current flowing in the line increases to the enormous value. This 
result in a heavy current flow through the relay coil, causing the 
relay to operate by closing its contacts. This in turn closes the trip 
circuit of the breaker making the circuit breaker open and isolating 
the faulty section from the rest of the system.
Relays used in control panel of the substation: 
 Differential Relay 
A differential relay is one that operates when vector difference of 
the two or more electrical quantities exceeds a predetermined 
value. If this differential quantity is equal or greater than the pickup 
value, the relay will operate and open the circuit breaker to isolate 
the faulty section. 
 Overcurrent Relay 
This type of relay works when current in the circuit exceeds the 
predetermined value. The actuating source is the current in the 
circuit supplied to the relay from a current transformer. These relay 
are used on A.C. circuit only and can operate for fault flow in the 
either direction. This relay operates when phase to phase fault 
occurs.
 Directional Relay 
This relay operates during earth faults. If one phase 
touch the earth due to any fault. A directional power 
relay is so designed that it obtains its operating 
torque by the interaction of magnetic field derived 
from both voltage and current source of the circuit it 
protects. The direction of torque depends upon the 
current relative to voltage. 
 Tripping Relay 
This type of relay is in the conjunction with main 
relay. When main relay sense any fault in the system, 
it immediately operates the trip relay to disconnect 
the faulty section from the section. 
 Auxiliary Relay 
An auxiliary relay is used to indicate the fault by 
glowing bulb alert the employee.
CONCLUSION 
 We can conclude that electricity plays an important role in our life. We are 
made aware of how the transmission of electricity is done. We too came to 
know about the various parts of the Substation system. 
 The Uttar Pradesh Cooperation Limited has got radio communication in 
microwave range in order to transmit and receive data with various 
Substations in Uttar Pradesh to get reliable transmission and distribution of 
electricity.
132KV SUBSTATION UPPTCL

Weitere ähnliche Inhalte

Was ist angesagt?

Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a SubstationMd. Atiqur Rahman
 
132 kv substation
132 kv substation132 kv substation
132 kv substationWipro
 
Load Distribution
Load DistributionLoad Distribution
Load DistributionArpit Gupta
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overviewMilind Punj
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devicesRahul Aman
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgearAdnan Sayed
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppclSunny Daksh
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurkishankky
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substationsvishalgohel12195
 
Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad ADARSH KUMAR
 

Was ist angesagt? (20)

Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a Substation
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
Load Distribution
Load DistributionLoad Distribution
Load Distribution
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
 
Substation
Substation Substation
Substation
 
Switchyard
SwitchyardSwitchyard
Switchyard
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devices
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
substation internship report
substation internship report substation internship report
substation internship report
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad
 

Ähnlich wie 132KV SUBSTATION UPPTCL

Presentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationPresentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationRahul Prajapati
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Rahul Prajapati
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving stationH.C.Naveen Kumar
 
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)Sogendra Rajput
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOWSatya Prakash Chaurasia
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014pinki199319
 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptxAsif682330
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptxAsif682330
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxfallinhay
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...rohit nadella
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Sachin Airan
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...Rishabhlko
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limitedVSRAGHU
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 

Ähnlich wie 132KV SUBSTATION UPPTCL (20)

Presentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationPresentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-Station
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
 
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
 
UPPTCL CHAKIA 132KV
UPPTCL CHAKIA 132KVUPPTCL CHAKIA 132KV
UPPTCL CHAKIA 132KV
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
 
Design of substation
Design of substationDesign of substation
Design of substation
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptx
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 

Kürzlich hochgeladen

Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...soumyapottola
 
General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per MVidyaAdsule1
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE
 
Scootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City DeliveryScootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City Deliveryrishi338139
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...Sebastiano Panichella
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptxerickamwana1
 
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Sebastiano Panichella
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitysandeepnani2260
 
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08LloydHelferty
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityApp Ethena
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxRoquia Salam
 

Kürzlich hochgeladen (11)

Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
 
General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per M
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024
 
Scootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City DeliveryScootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City Delivery
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
 
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber security
 
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptx
 

132KV SUBSTATION UPPTCL

  • 1. UTTAR PRADESH POWER TRANSMISSION CORPORATION LIMITED 132KV VAISHALI SUBSTATION Presented By Aman Rajput
  • 2. INTRODUCTION  The creation of Uttar Pradesh Power Corporation Ltd. (UPPCL) on January 14, 2000 is the result of power sector reforms and restructuring in UP (India) which is the focal point of the Power Sector, responsible for planning and managing the sector through its transmission, distribution and supply of electricity.  UPPCL will be professionally managed utility supplying reliable and cost efficient electricity to every citizen of the state through highly motivated employees and state of art technologies, providing an economic return to our owners and maintaining leadership in the country.
  • 3. About 132KV Vaishali Substation  132KV Vaishali Substation is one important substation of UPPTCL. It is situated at Vaishali sector-1, near U.P Gate, Ghaziabad.  The whole substation is divided in to two parts – 132 KV Switchyard & 33 KV Switchyard.
  • 4.  The incoming lines for Vaishali: 1. Noida (132KV line) 2. Shahibabad (132KV line)  The outgoing lines of Vaishali: 1. Vaishali-I 2. Indirapuram-I 3. Shipra Mall 4. Vaishali-II 5. Indirapuram-II 6. Kalapather 7. Nitikhand 8. Mahagun Mall
  • 5. SINGLE LINE DIAGRAM OF 132KV VAISHALI SUBSTATION
  • 6. TRANSFORMER Two transformer are used in 132KV Vaishali substation :  40MVA Transformer (ALSTOM)  63MVA Transformer (Transformers & Rectifiers Ltd.) As we know, MVA= 3푉퐼 For 63MVA, For 40MVA, 63× 106 = √3 ×132×103×I 40× 106 = √3 ×132×103×I I = 275A (HV) I = 175A (HV) 63× 106 = √3 × 33 ×103×I 40× 106 = √3 × 33 ×103×I I = 1100A (LV) I = 700A (LV) Therefore, total current across LV side = 1800A
  • 7. LIGHTNING ARRESTOR  A lightning arrester is a device used on electrical power systems and telecommunications systems to protect the insulation and conductors of the system from the damaging effects of lightning.  The typical lightning arrester has a high-voltage terminal and a ground terminal.  When a lightning surge (or switching surge, which is very similar) travels along the power line to the arrester, the current from the surge is diverted through the arrestor, in most cases to earth. Lightning Arrestor
  • 8. CURRENT TRANSFORMER  A current transformer (CT) is used for measurement of alternating electric currents.  When current in a circuit is too high to apply directly to measuring instruments, a current transformer produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments.  A current transformer isolates the measuring instruments from what may be very high voltage in the monitored circuit.  The primary circuit is largely unaffected by the insertion of the CT. The rated secondary current is commonly standardized at 1 or 5 amperes. For example, a 4000:5 CT secondary winding will supply an output current of 5 amperes when the primary winding current is 4000 amperes.
  • 9. POTENTIAL TRANSFORMER  Potential transformers (PT) (also called voltage transformers (VT)) are a parallel connected type of instrument transformer.  They are designed to present negligible load to the supply being measured and have an accurate voltage ratio and phase relationship to enable accurate secondary connected metering.  The PT is typically described by its voltage ratio from primary to secondary. Standard secondary voltage ratings are 120 volts and 70 volts, compatible with standard measuring instruments.  For example, a 600:120 PT would provide an output voltage of 120 volts when 600 volts are impressed across its primary winding.
  • 10. CIRCUIT BREAKER  A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit. Its basic function is to detect a fault condition and interrupt current flow.  Unlike a fuse, which operates once and then must be replaced, a circuit breaker can be reset (either manually or automatically) to resume normal operation.  A circuit breaker essentially consists of fixed and moving contacts. These contacts can be opened manually or by remote control whenever desired. When a fault occurs on any part of the system, the trip coils of breaker get energized and the moving contacts are pulled apart by some mechanism, thus opening the circuit.  When contacts of a circuit breaker are separated, an arc is struck; the current is thus able to continue. The production of arcs are not only delays the current interruption, but is also generates the heat. Therefore, the main problem is to distinguish the arc within the shortest possible time so that it may not reach a dangerous value.
  • 11.  According to their arc quenching media the circuit breaker can be divided as- 1. Oil circuit breaker 2. Air circuit breaker 3. SF6 circuit breaker 4. Vacuum circuit breaker Oil circuit breaker  In oil circuit breaker the fixed contact and moving contact are immerged inside the insulating oil. Whenever there is a separation of electric current carrying contacts in the oil, the arc in circuit breaker is initialized at the moment of separation of contacts, and due to this arc the oil is vaporized and decomposed in mostly hydrogen gas and ultimately creates a hydrogen bubble around the arc. This highly compressed gas bubble around the arc prevents re-striking of the arc after electric current reaches zero crossing of the cycle.
  • 12. Air circuit breaker For interrupting arc it creates an arc voltage in excess of the supply voltage. Arc voltage is defined as the minimum voltage required maintaining the arc. This circuit breaker increases the arc voltage by mainly three different ways:  It may increase the arc voltage by cooling the arc plasma. As the temperature of arc plasma is decreased, the mobility of the particle in arc plasma is reduced, hence more voltage gradient is required to maintain the arc.  It may increase the arc voltage by lengthening the arc path. As the length of arc path is increased, the resistance of the path is increased, and hence to maintain the same arc electric current more voltage is required to be applied across the arc path. That means arc voltage is increased.  Splitting up the arc into a number of series arcs also increases the arc voltage.
  • 13. SF6 circuit breaker  In such circuit breaker, sulphur hexafluoride (SF6) gas is used as the arc quenching medium. The SF6 is an electronegative gas and has a strong tendency to absorb free electrons.  It consists of fixed and moving contacts. It has chamber, contains SF6 gas. When the contacts are opened, the mechanism permits a high pressure SF6 gas from reservoir to flow towards the arc interruption chamber. The moving contact permits the SF6 gas to let through these holes.  These circuit breakers are available for the voltage ranges from 33KV to 800KV and even more. 132KV SF6 CB
  • 14. Vacuum circuit breaker  Vacuum circuit breakers are circuit breakers which are used to protect medium and high voltage circuits from dangerous electrical situations. Like other types of circuit breakers, vacuum circuit breakers literally break the circuit so that energy cannot continue flowing through it, thereby preventing fires, power surges, and other problems which may emerge.  The operation of opening and closing of electric current carrying contacts and associated arc interruption take place in a vacuum chamber in the breaker which is called vacuum interrupter.
  • 15. ISOLATOR  It is an off-load device.  It disconnects or isolates the circuit from the main power supply.  Even though, isolators is a switch, it is not used as a normal on off switch.  It is used only when the electrical system has to be disconnected from the main supply, to perform maintenance or related activities, which involve direct contact with the current carrying components of machinery.  Isolators may provide additional safety features like, when switched off the trapped charge will be ground through a ground terminal in the isolator.  Isolators are normally placed after the circuit breaker allowing the internal circuit to be disconnected from the main supply without affecting the breaker.
  • 16. CAPACITOR BANK  The load on the power system is varying being high during morning and low in evening which increases the load current. This result in the decreased power factor.  The low power factor is mainly due to the fact most of the power loads are inductive and therefore take lagging currents.  In order to ensure most favorable conditions for a supply system from engineering and economic stand point it is important to have power factor as close to unity as possible.  In order to improve the power factor come device taking leading power should be connected in parallel with the load. One of the device can be capacitor bank.  The capacitor draws a leading current and partly or completely neutralize the lagging reactive component of load current. Capacitor bank accomplishes following operations:  Supply reactive power  Increases terminal voltage  Improve power factor
  • 17.  FUSE A fuse is a short piece of wire or thin strip which melts when excessive current through it for sufficient time. It is inserted in series with the circuit under normal operating conditions; the fuse element is at a nature below its melting point. Therefore it carries the normal load current overheating. It is worthwhile to note that a fuse performs both detection and interruption functions.  BUS COUPLER The bus coupler consists of circuit breaker and isolator. Each generator and feeder may be connected to either main bus bar or spar bus bar with the help of bus coupler. Repairing, maintenance and testing of feeder circuit or other section can be done by putting them on spar bus bar, thus keeping the main bus bar undisturbed. Bus coupler is a device which is used switch from one bus to the other without any interruption in power supply and without creating hazardous arcs. It is achieved with the help of circuit breaker and isolators.
  • 18. RELAY  When a failure occurs on any part of the system, it must be quickly detected and disconnected from the system.  Rapid disconnection of faulted apparatus limits the amount of damage to it and prevents the effects of fault from spreading into the system.  For high voltage circuits relays are employed to serve the desired function of automatic protective gear. The relays detect the fault and supply the information to the circuit breaker.  When a short circuit occurs at any point on the transmission line the current flowing in the line increases to the enormous value. This result in a heavy current flow through the relay coil, causing the relay to operate by closing its contacts. This in turn closes the trip circuit of the breaker making the circuit breaker open and isolating the faulty section from the rest of the system.
  • 19. Relays used in control panel of the substation:  Differential Relay A differential relay is one that operates when vector difference of the two or more electrical quantities exceeds a predetermined value. If this differential quantity is equal or greater than the pickup value, the relay will operate and open the circuit breaker to isolate the faulty section.  Overcurrent Relay This type of relay works when current in the circuit exceeds the predetermined value. The actuating source is the current in the circuit supplied to the relay from a current transformer. These relay are used on A.C. circuit only and can operate for fault flow in the either direction. This relay operates when phase to phase fault occurs.
  • 20.  Directional Relay This relay operates during earth faults. If one phase touch the earth due to any fault. A directional power relay is so designed that it obtains its operating torque by the interaction of magnetic field derived from both voltage and current source of the circuit it protects. The direction of torque depends upon the current relative to voltage.  Tripping Relay This type of relay is in the conjunction with main relay. When main relay sense any fault in the system, it immediately operates the trip relay to disconnect the faulty section from the section.  Auxiliary Relay An auxiliary relay is used to indicate the fault by glowing bulb alert the employee.
  • 21. CONCLUSION  We can conclude that electricity plays an important role in our life. We are made aware of how the transmission of electricity is done. We too came to know about the various parts of the Substation system.  The Uttar Pradesh Cooperation Limited has got radio communication in microwave range in order to transmit and receive data with various Substations in Uttar Pradesh to get reliable transmission and distribution of electricity.