Civilverse Admin 21 July 2020
Project Schedule- Scope, Steps, Tools & Techniques
civilverse.org/project-schedule-scope-steps-tools-techniques
Table of Content for Project Schedule & Techniquesโ€“
What is Project Schedule?
Why use a Project Schedule?
Steps of Project Scheduling
Linking of Activities
Tools of Project Scheduling
Techniques of Project Scheduling- CPM & PERT
What is Project Schedule?
A project schedule is a list of work activities to be done for the completion of the project
arranged in a logical and sequential manner with a specified timeline. The project
schedule aligns the scope and cost of the project in a timeline. It is an important part of
project planning and management.
The project planning helps in defining the methodologies and procedures and the
schedule sets them in the timeline. Thus, in broad terms, it can be said that the planning
answers the โ€˜whatโ€™ and โ€˜howโ€™ aspects whereas the project schedule answers โ€˜whenโ€™ and
โ€˜whoโ€™.
2/6
A project schedule is made on the assumptions. The assumptions are estimated duration
of the activities, inter-dependency of the activities, availability of resources, allocation,
and leveling of the resources, time constraint, budget constraint, etc. The overall project
completion timeline is based on all of the above-mentioned assumptions. The project
timeline can be altered by changing any of these assumptions.
Why use Project Schedule?
It helps in achieving the following objectives-
Project Schedule defines the work activities in a logical manner; thus, it makes the
project run smoothly.
The commitment of the project timeline to stakeholders.
Planning of resources. The what, when, where, how much, who for a resource can
be decided.
Optimum utilization of resources. The activities are scheduled in such a way that the
resources can be utilized to itsโ€™ full potential.
Cashflow projections.
Identification of occurrence of risks and mitigation plans.
Monitoring and reporting. The schedule can be used for tracking the work progress.
Weekly, fortnightly, or monthly targets and progress reports can be generated.
Prevention of delay. If the project is getting delayed then it can be brought back on
track by crashing activities or rescheduling the activities.
Steps of Project Scheduling
The project schedule should be DCMA guideline compliant. The steps of making a project
schedule are as follows-
Identifying the scope of the project, objective, project start date, mobilization time,
working and non-working days, etc.
Creating a Work Breakdown Structure (WBS). The WBS of a project is the
breakdown of the project into measurable, easily estimated, and deliverable
activities.
Define the interdependency of the activities. This step helps in linking activities to
each other. It determines the time-behaviour of activity with respect to another
activity.
Estimation of resources. The estimation of resources should be done keeping in
mind the availability of the resources, cost-effectiveness, work-space constraint, etc.
Estimation of the duration of activities. The duration estimation of the activities is
to be done as per the earlier estimated resources. It is a very important step as the
under-estimation of the duration can lead to delay in the project and over-
estimation of the duration can lead to underutilization of the resources.
Monitoring & controlling the schedule. This step continues until the completion of
the project. Target setting, progress reporting, mitigation to delay, mitigation of
risks, planning for resource mobilization when required, etc. come under this step.
3/6
Linking of Activities in a Project Schedule-
The project activities can be linked with each other by following-
Inter-dependency of Activities
1. Start to Start (SS)- It is used when two activities can be started simultaneously.
2. Finish to Finish (FF)- It is used when two activities are to be finished at the same
time.
3. Finish to Start (FS)- FS is used when an activity starts when another activity
ends.
4. Start to Finish (SF)- SF is used when an activity finishes when another starts. It
is rarely used.
Tools of Project Scheduling-
Task List-
Project Schedule Task List
The task lists are the simplest method of project scheduling. The tasks to be performed to
complete the project are documented. The tasks are documented for each resource
separately. It is a feasible method for small scale projects.
4/6
The overall timeline of the project canโ€™t be defined in this method. With the increase in
the scale of the project, the activities become complicated due to inter-dependencies and
hence this method becomes inefficient. Project tracking and collaboration among
resources are also very difficult.
Gantt Chart-
Gantt Chart
It is the most popular tool for the project schedule. Gantt Chart is a horizontal bar chart
having activities on the vertical axis and the timeline on the horizontal axis. It is also very
helpful in monitoring, controlling, and reporting. The popularity of the Gantt chart is due
to its easy adaptability, easy modification, and ability to assign resource(s) to an activity.
The Gantt chart has itsโ€™ own set of limitations such as limited collaboration and no
versioning.
Calendar-
Project Schedule Calendar
The calendar is used as a tool for project scheduling for defining the duration of the tasks
and overall project timeline. The calendar can be modified as per the project requirement
such as working and non-working days and renamed as required. The team members can
share the calendars and can visualize the task overlaps. It is easier to modify.
5/6
The calendars are limited in defining inter-dependency of the activities.
Techniques of Project Scheduling-
Critical Path Method (CPM)-
The Critical Path Method defines the shortest timeline to complete a project. The flow
diagram of the activities is used for defining the timeline. In the flow diagram, the
activities of a project are linked to each other with the estimated duration of each activity.
The milestones are also defined.
The path representing the sequence of activities defines the different timelines of the
project. The longest path is known as the โ€˜Critical Pathโ€™. The duration of the critical path is
the minimum duration for a project. The activities lying on the critical path are called
critical activities. The delay in critical activities delays the whole project. These activities
are said to have zero float.
The critical path method is reliable for the projects which have a well-defined duration for
each activity. The infrastructure industry uses CPM frequently.
Program Evaluation & Review Technique (PERT)โ€“
PERT is similar to the CPM except in estimation of the duration of an activity. The PERT
uses three-time estimates for an activity. These time estimates are-
Optimistic Time (t )- The minimum possible time to complete an activity.
Most-likely Time (t )- The most likely duration of activity for completion under
normal conditions.
Pessimistic Time (t )- The duration to complete an activity under the adverse
conditions.
The duration taken into account is the weighted average of the above three estimates.
o
m
p
6/6
The variance of an activity is defined as-
The project duration is the total duration of critical
activities. And the sum of variances of critical activities
is the variance of the project.
The PERT is generally used in projects in which the
duration of activities cannot be accurately determined. Such projects can be product
development, defence system implementation, etc.
Liked the article? Or got a suggestion or doubt? Let me know in the comment below.
Dive deeper into the project scheduling with this construction project schedule example.
MS Project Terminology- Top 20 Terms Everyone Must Know Part-1 & Part-2
Happy Engineering!

More Related Content

What's hot

Chapt7 slides
Chapt7 slidesChapt7 slides
Chapt7 slidesEngr Razaque
ย 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
ย 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
ย 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project scheduleNirtiSingla
ย 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
ย 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
ย 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
ย 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
ย 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
ย 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
ย 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHARTNAVANEETA KUSUM
ย 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yฤฑldฤฑz
ย 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and trackingComputer_ at_home
ย 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
ย 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
ย 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gertPranav Krishna
ย 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
ย 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
ย 

What's hot (19)

Chapt7 slides
Chapt7 slidesChapt7 slides
Chapt7 slides
ย 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
ย 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
ย 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
ย 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project schedule
ย 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
ย 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
ย 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
ย 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
ย 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
ย 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
ย 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
ย 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
ย 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and tracking
ย 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
ย 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
ย 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
ย 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
ย 
construction project planing
 construction project planing construction project planing
construction project planing
ย 

Similar to Project schedule- What, How, Tools & Techniques

Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
ย 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.NIILM University
ย 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
ย 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and ManagementGBPUA&T, Pantnagar
ย 
project management.pptx
project management.pptxproject management.pptx
project management.pptxrekhaSathish1
ย 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
ย 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
ย 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
ย 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...Golam Bitonsir
ย 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
ย 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 NotesSamarthVarpe
ย 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanityRenzo Streglio
ย 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pertSantosh Kumari
ย 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...IJSRD
ย 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
ย 

Similar to Project schedule- What, How, Tools & Techniques (20)

Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
ย 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.
ย 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
ย 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
ย 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
ย 
project management.pptx
project management.pptxproject management.pptx
project management.pptx
ย 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
ย 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
ย 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
ย 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
ย 
Project time
Project timeProject time
Project time
ย 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
ย 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
ย 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
ย 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
ย 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
ย 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
ย 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
ย 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
ย 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
ย 

More from SHAZEBALIKHAN1

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
ย 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
ย 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
ย 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
ย 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
ย 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
ย 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
ย 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
ย 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
ย 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
ย 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
ย 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
ย 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
ย 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
ย 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
ย 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
ย 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
ย 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
ย 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
ย 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
ย 

More from SHAZEBALIKHAN1 (20)

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
ย 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
ย 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
ย 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
ย 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
ย 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
ย 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
ย 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
ย 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
ย 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
ย 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
ย 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
ย 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
ย 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
ย 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
ย 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
ย 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
ย 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
ย 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
ย 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
ย 

Recently uploaded

chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
ย 
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night StandCall Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Standamitlee9823
ย 
Call Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
ย 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfrs7054576148
ย 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
ย 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
ย 
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoordharasingh5698
ย 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
ย 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsArindam Chakraborty, Ph.D., P.E. (CA, TX)
ย 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7Call Girls in Nagpur High Profile Call Girls
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 

Recently uploaded (20)

chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
ย 
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night StandCall Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
ย 
Call Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Netaji Nagar, Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
ย 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
ย 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
ย 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
ย 
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor ๐Ÿ“ฑ {7001035870} VIP Escorts chittoor
ย 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
ย 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
ย 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
ย 

Project schedule- What, How, Tools & Techniques

  • 1. 1/6 Civilverse Admin 21 July 2020 Project Schedule- Scope, Steps, Tools & Techniques civilverse.org/project-schedule-scope-steps-tools-techniques Table of Content for Project Schedule & Techniquesโ€“ What is Project Schedule? Why use a Project Schedule? Steps of Project Scheduling Linking of Activities Tools of Project Scheduling Techniques of Project Scheduling- CPM & PERT What is Project Schedule? A project schedule is a list of work activities to be done for the completion of the project arranged in a logical and sequential manner with a specified timeline. The project schedule aligns the scope and cost of the project in a timeline. It is an important part of project planning and management. The project planning helps in defining the methodologies and procedures and the schedule sets them in the timeline. Thus, in broad terms, it can be said that the planning answers the โ€˜whatโ€™ and โ€˜howโ€™ aspects whereas the project schedule answers โ€˜whenโ€™ and โ€˜whoโ€™.
  • 2. 2/6 A project schedule is made on the assumptions. The assumptions are estimated duration of the activities, inter-dependency of the activities, availability of resources, allocation, and leveling of the resources, time constraint, budget constraint, etc. The overall project completion timeline is based on all of the above-mentioned assumptions. The project timeline can be altered by changing any of these assumptions. Why use Project Schedule? It helps in achieving the following objectives- Project Schedule defines the work activities in a logical manner; thus, it makes the project run smoothly. The commitment of the project timeline to stakeholders. Planning of resources. The what, when, where, how much, who for a resource can be decided. Optimum utilization of resources. The activities are scheduled in such a way that the resources can be utilized to itsโ€™ full potential. Cashflow projections. Identification of occurrence of risks and mitigation plans. Monitoring and reporting. The schedule can be used for tracking the work progress. Weekly, fortnightly, or monthly targets and progress reports can be generated. Prevention of delay. If the project is getting delayed then it can be brought back on track by crashing activities or rescheduling the activities. Steps of Project Scheduling The project schedule should be DCMA guideline compliant. The steps of making a project schedule are as follows- Identifying the scope of the project, objective, project start date, mobilization time, working and non-working days, etc. Creating a Work Breakdown Structure (WBS). The WBS of a project is the breakdown of the project into measurable, easily estimated, and deliverable activities. Define the interdependency of the activities. This step helps in linking activities to each other. It determines the time-behaviour of activity with respect to another activity. Estimation of resources. The estimation of resources should be done keeping in mind the availability of the resources, cost-effectiveness, work-space constraint, etc. Estimation of the duration of activities. The duration estimation of the activities is to be done as per the earlier estimated resources. It is a very important step as the under-estimation of the duration can lead to delay in the project and over- estimation of the duration can lead to underutilization of the resources. Monitoring & controlling the schedule. This step continues until the completion of the project. Target setting, progress reporting, mitigation to delay, mitigation of risks, planning for resource mobilization when required, etc. come under this step.
  • 3. 3/6 Linking of Activities in a Project Schedule- The project activities can be linked with each other by following- Inter-dependency of Activities 1. Start to Start (SS)- It is used when two activities can be started simultaneously. 2. Finish to Finish (FF)- It is used when two activities are to be finished at the same time. 3. Finish to Start (FS)- FS is used when an activity starts when another activity ends. 4. Start to Finish (SF)- SF is used when an activity finishes when another starts. It is rarely used. Tools of Project Scheduling- Task List- Project Schedule Task List The task lists are the simplest method of project scheduling. The tasks to be performed to complete the project are documented. The tasks are documented for each resource separately. It is a feasible method for small scale projects.
  • 4. 4/6 The overall timeline of the project canโ€™t be defined in this method. With the increase in the scale of the project, the activities become complicated due to inter-dependencies and hence this method becomes inefficient. Project tracking and collaboration among resources are also very difficult. Gantt Chart- Gantt Chart It is the most popular tool for the project schedule. Gantt Chart is a horizontal bar chart having activities on the vertical axis and the timeline on the horizontal axis. It is also very helpful in monitoring, controlling, and reporting. The popularity of the Gantt chart is due to its easy adaptability, easy modification, and ability to assign resource(s) to an activity. The Gantt chart has itsโ€™ own set of limitations such as limited collaboration and no versioning. Calendar- Project Schedule Calendar The calendar is used as a tool for project scheduling for defining the duration of the tasks and overall project timeline. The calendar can be modified as per the project requirement such as working and non-working days and renamed as required. The team members can share the calendars and can visualize the task overlaps. It is easier to modify.
  • 5. 5/6 The calendars are limited in defining inter-dependency of the activities. Techniques of Project Scheduling- Critical Path Method (CPM)- The Critical Path Method defines the shortest timeline to complete a project. The flow diagram of the activities is used for defining the timeline. In the flow diagram, the activities of a project are linked to each other with the estimated duration of each activity. The milestones are also defined. The path representing the sequence of activities defines the different timelines of the project. The longest path is known as the โ€˜Critical Pathโ€™. The duration of the critical path is the minimum duration for a project. The activities lying on the critical path are called critical activities. The delay in critical activities delays the whole project. These activities are said to have zero float. The critical path method is reliable for the projects which have a well-defined duration for each activity. The infrastructure industry uses CPM frequently. Program Evaluation & Review Technique (PERT)โ€“ PERT is similar to the CPM except in estimation of the duration of an activity. The PERT uses three-time estimates for an activity. These time estimates are- Optimistic Time (t )- The minimum possible time to complete an activity. Most-likely Time (t )- The most likely duration of activity for completion under normal conditions. Pessimistic Time (t )- The duration to complete an activity under the adverse conditions. The duration taken into account is the weighted average of the above three estimates. o m p
  • 6. 6/6 The variance of an activity is defined as- The project duration is the total duration of critical activities. And the sum of variances of critical activities is the variance of the project. The PERT is generally used in projects in which the duration of activities cannot be accurately determined. Such projects can be product development, defence system implementation, etc. Liked the article? Or got a suggestion or doubt? Let me know in the comment below. Dive deeper into the project scheduling with this construction project schedule example. MS Project Terminology- Top 20 Terms Everyone Must Know Part-1 & Part-2 Happy Engineering!