PMO - PROJECT IMPLEMENTATION PROCESS
Nov 2015
Version: 1.0
Version: 1.0
Tata ConsultancyServicesrequiresthatall of itsemployeesadheretoastrict setof ethical guidelines
(“Tata Code of Conduct” http://www.tata.com/aboutus/articles/inside.aspx?artid=NyGNnLHkaAc=).
We requestyoursupportinhelpingusmaintainourCode of Conduct.Shouldyounote anyviolation,
or potential violation, by a Tata employee, please promptly report it to your TCS contact or to the
CEO of TCS.All reportswill be keptstrictlyconfidential andwill helpusensure acorporate culture of
high standards.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page i
Abbreviations
Abbreviation Description
PMO Project Management Office
PM Project Manager
TM Telekom Malaysia Berhad
TCS TATA Consultancy Services
PM Project Manager
PSC Project Steering Committee
AR Accounts Receivable
AP Accounts Payable
CRP Client Retention Program
LOA Letter of Awards
SWON Service Work Order Number
RFQ Request for Quotation
RFP Request for Proposal
RFI Request for Information
SoW Scope of Work
MOM Minutes of Meeting
WBS Work Breakdown Structure
COA Certificate of Acceptance
PO Purchase Order
CFOA Certificate of Final Acceptance
CCB Change Control Board
CR Change Request
SLA Service Level Agreement
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page ii
Revision History
Version Revision Description Revision By and Date
1.0 Newly Created Rahmat Hashim - 03-Nov-15
Document Sign Off
Document Approver Sign Off Status Sign off Date
Nadeem Khan
Jawahar Hussain
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page iii
Table of Contents
1. Introduction ................................................................................................................1
1.1 Roles of PMO..........................................................................................................3
1.2 PMO Processes Structure ........................................................................................3
1.2.1.Project Implementation.....................................................................................................................3
1.2.2.Pre-sales and Bidding Management..............................................................................................4
1.2.3.Departmental Management..............................................................................................................5
2. Project Implementation Process (Pre-Delivery).....................................................7
2.1 LOA Process Flow...................................................................................................7
2.2 Scope of Work (SoW) Confirmation Process .............................................................9
2.3 Contract Preparation Process................................................................................. 11
3. Project Implementation Process (Delivery) ..........................................................15
3.1 Project Management Process................................................................................. 15
3.1.1.Project Management Process – Initiating....................................................................................15
3.1.2.Project Management Process – Planning...................................................................................18
3.1.3.Project Management Process – Executing .................................................................................20
3.1.4.Project Management Process – Monitoring and Controlling (Timeline).................................22
3.1.5.Project Management Process – Monitoring and Controlling (Risks / Issues)........................25
3.1.6.Project Management Process – Monitoring and Controlling (Change Request)...................27
3.1.7.Project Management Process – Monitoring and Controlling (Quality Assurance)................30
3.1.8.Project Management Process – Closing......................................................................................33
3.2 Project Financial Management ............................................................................... 35
3.2.1.Project Financial Management Process – Accounts Receivable (AR) ...................................36
3.2.2.Project Financial Management Process – Accounts Payable (AP).........................................38
4. Project Implementation Process (Post-Delivery).................................................41
4.1 Post-Delivery (Warranty Support) ........................................................................... 41
4.1.1.Post-Delivery – Warranty Support for Corrective Maintenance...............................................42
4.1.2.Post-Delivery – Warranty Support for Preventive Maintenance...............................................44
4.2 Post-Delivery (Client Retention Program) ................................................................ 46
Annex A – Listing of Documents and Templates ........................................................50
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page iv
List of Figures
Figure 1 : PMO high-level processesframework ........................................................................1
Figure 2 : Detail PMO Components and Processes.....................................................................2
Figure 3 : Detail process framework for Project Implementation ................................................4
Figure 4 : Detail process framework for Pre-Sales and Bidding Management...............................5
Figure 5 : Detail process framework for Departmental Management..........................................6
Figure 6 : Process Flowfor Letter of Awards(LOA).....................................................................7
Figure 7 : Process flow for Scope of Works (SoW) Confirmation................................................10
Figure 8 : Process flow for Contract Preparation......................................................................12
Figure 9 : Project Management Process Framework.................................................................15
Figure 10 : Process Flow for Project Initiating..........................................................................16
Figure 11 : Process flow for Project Planning...........................................................................18
Figure 12 : Process Flow for Project Executing.........................................................................20
Figure 13 : Process Flow for Monitoring and Controlling for Timeline........................................23
Figure 14 : Process Flow for Monitoring and Closing for Risks and Issues...................................25
Figure 15 : Process Flow for Monitoring & Controlling for Change Requests..............................28
Figure 16 : Process flow for Monitoring & Controlling for Quality Assurance .............................31
Figure 17 : Process Flow for Project Closing.............................................................................33
Figure 18 : Project Financial ManagementProcess Framework.................................................35
Figure 19 : Process Flow for Project Accounts Receivable.........................................................36
Figure 20 : Process flow for Project Accounts Payable..............................................................38
Figure 21 : Warranty Support Process Framework ...................................................................41
Figure 22 : Process flow for Warranty Support (Corrective Maintenance)..................................43
Figure 23 : Process flow for Warranty Support (Preventive Maintenance) .................................45
Figure 24 : Process framework for Client Retention Program....................................................47
Figure 25 : Process flow for Client Retention Program..............................................................48
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page v
List of Tables
Table 1 : PMO Components and Processes................................................................................2
Table 2 : Process components and standard processes in Project Implementation ......................4
Table 3 : Process components and standard processes in Departmental Management ................6
Table 4 : LOA Process Flow.......................................................................................................7
Table 5 : Scope of Works Confirmation Process Flow ...............................................................10
Table 6 : Contract Preparation Process Flow............................................................................12
Table 7 : Project InitiatingProcess Flow ..................................................................................16
Table 8 : Project Planning Process Flow...................................................................................18
Table 9 : Project Executing Process Flow.................................................................................21
Table 10 : Monitoring & Controlling (Timeline) Process Flow....................................................23
Table 11 : Monitoring & Controlling (Risks / Issues) Process Flow .............................................26
Table 12 : Monitoring & Controlling (Change Requests) Process Flow.......................................28
Table 13 : Monitoring & Controlling (Quality Assurance) Process Flow......................................31
Table 14 : Project Closing Process Flow...................................................................................34
Table 15 : ProjectAccounts Receivable Process Flow...............................................................37
Table 16 : ProjectAccounts Payable Process flow....................................................................39
Table 17 : Warranty Support (Corrective Maintenance) Process Flow .......................................43
Table 18 : Warranty Support (Preventive Maintenance) Process Flow.......................................45
Table 19 : Client Retention ProgramProcess Flow ...................................................................48
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 1
1. Introduction
PMO is an organizational unit that centralise and coordinate the management of projects
underitsdomain.Sometimesit’scalledProgrammeManagementOfficeorProgrammeOffice
but most of the time it’s known as Project Management Office.
The objectives for establishing PMO are:
 To streamline and standardise project processes
 To govern rules and procedures in project delivery
 To monitor and control project delivery processes
 To be the custodian of project Knowledge Base
 To develop appropriate skillsets for project team
 To advise High-level Management on resources allocation in regards to project
As depictedin Figure 1below,there are 3componentswithinthe PMO process framework.
These components are Project Implementation, Pre-Sales & Bidding Management, and
Departmental Management. The detail breakdownof eachcomponentisshowninFigure 2.
Figure 1 : PMO high-level processes framework
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 2
Figure 2 : Detail PMO Components and Processes
Each processesineverycomponentwillbe monitoredandcontrolledbyPMO.The mainfocus
will be the ProjectImplementationasitinvolvescustomersandcompany’sfinancial benefit.
As mentioned in Table 1 below, the Project Implementation covers processesin the Pre-
delivery, Delivery and Post-delivery.
Table 1 : PMO Components and Processes
PMO Component Standard Processes
Project Implementation  Pre-delivery process
 Delivery process
 Post-delivery process
Pre-SalesandBidding
Management
 Customer RFI (Request for Information) process
 Customer RFQ (Request for Quotation) process
 Customer RFP (Request for Proposal) process
Departmental
Management
 Resource Management
 Governance and Reporting
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 3
The stakeholdersdefinedinthe PMOprocesses framework are shownbelow.Theywill have
direct impact in all processes defined within each component of the framework.
− Customer
− Project Manager
− Project Office
− Project team (i.e. Subject-Matter Expert, Team Leads, Technical Team,
Documenter, QA/QC, etc.)
− Client Partner
− Sales Director
− Head of ASEAN Delivery & Operations
1.1 Roles of PMO
The roles of PMO comprises of the following:
 Manage the interdependencies between projects and have view of all projects.
 Provide training, guidance and mentoring to project managers.
 Provides the methodology, standards, and policies to be followed by the
stakeholders.
 Helpgatherlessonslearned,andmakethemavailable forreference tootherprojects.
 Help provide resources and standard document templates.
 Provide inputtohighermanagementforcritical decisiontoproceedorterminatethe
project.
 Provide quantitative methods to continue improving for Project Management
processes.
 Establishcentralized repositoryandmanagementof sharedprojectdocumentations
and unique project risks.
1.2 PMO Processes Structure
As mentioned earlier, PMO processes are defined based on these critical components:
− Project Implementation
− Pre-sales and Bidding Management
− Departmental Management
1.2.1 Project Implementation
Project implementation involves standard processes in pre-delivery, delivery and post-
deliveryof a project. This component is critical to project delivery as it involves delivery of
business solution to customer and ensuring cash-flow to company.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 4
The following Figure 3, shows the process framework for Project Implementation.
There are 3 componentsinProjectImplementation whichare Pre-DeliveryProcess,Delivery
Process and Post Delivery Process.
These components are linkedtogethertoensure effectiveprocessmanagementandcontrol.
Details of standard processes for each of these components are shown in Table 2 below.
Table 2 : Process components and standard processes in Project Implementation
Process Component Standard Processes
Pre-Delivery Process  Letter of Award (LOA) process
 Scope of Work (SoW) process
 Contract Preparation process
DeliveryProcess  Project Management process
 Project Financial Management
Post Delivery Process  Warranty Support process
 Client Retention Program (CRP)
1.2.2 Pre-sales and Bidding Management
A projectnormallyinitiatedasa resultof businessproposal fromvendorto customer.It isa
normal cycle in resolving business issues faced by the customer. There are 3 processes that
commonly used by customer to engage vendor for business solution.
Figure 3 : Detail process framework for Project Implementation
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 5
As such, PMO needs to be involved in these processes to advise in term of resources
capability, timeline, and potential risks.
These 3 processes are:
− Request for Information (RFI)
− Request for Quotation (RFQ)
− Request for Proposal (RFP)
Normally,PMOwill worktogetherwiththe respective ClientPartnerorSalesDirectorwho’s
responsible forthe respectivecustomer’saccount. The followingFigure4, showsthe process
components for Pre-Sales and Bidding Management.
The outputfrom each componentwill be a proposal documentto customer. Thisdocument
will specifies information required by customer that include business solution proposal,
deployment strategy, timeline, solution cost and benefit.
1.2.3 Departmental Management
PMO will also handles the routine operation of a business unit. The administration of a
business unit or departmental management will be required when managing project
operation. A project is considered as businessunit since Project Manager is assignedwith a
groupof resources,scope of delivery, timeline, and budget to deliver a successful project.
The important components in Departmental Management are:
− Resource Management
− Governance and Reporting
Figure 4 : Detail process framework for Pre-Sales and Bidding Management
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 6
The following Figure 5, shows the process components for Departmental Management.
PMO needs to ensure projects are delivered successfully to avoid any delay and additional
cost to the project. In Governance and Reporting, internal reporting structure has been
defined to monitor and control each of the project within PMO purview.
In addition, Knowledge Management and Project Process Auditing are part of Governance
and Reporting process component. List of processes in the Departmental Management is
shown in Table 3 below.
Table 3 : Process components and standard processes in Departmental Management
Process Component Standard Processes
Governance and Reporting  Reporting Management
 Project Process Auditing
 Knowledge Management
Resource Management  Skills Development Program
 Tasks Management
 Timesheet Management
 Resource Requisition and Allocation Management
Figure 5 : Detail process framework for Departmental Management
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 7
2. Project Implementation Process (Pre-Delivery)
There are 3 components in Project Implementation Process. It starts with Pre-delivery
Process, then continue to Delivery Process and ended with Post-deliveryProcess. We will
begin with the Pre-Delivery Process components i.e. the LOA Process Flow.
2.1 LOA Process Flow
Project Implementation process starts upon receiving of Letter of Awards (LOA) from the
customer, in this case we’ll use Telekom Malaysia (TM) project as the model project.
Normally, LOA is the initial step of engaging vendor for services with terms and conditions
that need to be fulfilled by vendor prior to the acceptance of service award.
In this topic, detail processes and procedures will be described together with the list of
documentation needtobe producedfromthe respectiveprocesses. Figure 6depictsthe LOA
process flow.
Detail process description for LOA as per Table 4.
Table 4 : LOA Process Flow
No. Process Description Entity Output / Report /
Document
1. ProcurementproducedLetterof Award(LOA)
andsubmittedtothe selectedvendori.e.TCS
Customer i.e.
TM
Letter of Award (LOA)
2. a. Scan the LOA and upload to Central
Repository (i.e. Knowledge Center)
TCS Client
Partner / Sales
Director
 LOA (Scanned Copy).
 Central Repository
Server
Figure 6 : Process Flow for Letter of Awards (LOA)
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 8
No. Process Description Entity Output / Report /
Document
b. TCS Client Partner / Sales Director will
conduct briefing session with Head of
ASEAN Delivery & Operations, and PMO
Head pertaining to LOA scope and
requirements. The output of the briefing
will be the Actions List or Minutes of
Meeting.
TCS Client
Partner / Sales
Director
 Minutes of Meeting /
Actions List
3. Head of ASEAN Delivery & Operations
registerthe ServiceWorkOrderinthe system
for the respective LOA received from
Customer i.e. TM.
Head of ASEAN
Delivery &
Operations
 New Service Work
Order No. i.e. SWON
no.
4. Head of ASEAN Delivery & Operations
prepares :
 Supplementary documents as required
by LOA.
 Letter of Acceptance accepting the
projectinitiative mentionedin the LOA.
Head of ASEAN
Delivery &
Operations
 Letterof Acceptance
 Scope of Works
 Insurance policies(i.e.
Workman
Compensations,
Comprehensive
General Liability
Insurance,
Professional
IndemnityInsurance),
 Declarationof
Independency,and
 IntegrityAgreement –
Vendor’sDeclaration
 Otherdocuments.
5. Client Partner / Sales Director submit the
Letter of Acceptance and supplementary
documents as required in the LOA.
TCS Client
Partner / Sales
Director
6. Head of PMO performs the following :
 Assigna ProjectManagerfor the project
 Establish a Project Office for the project
administrative matters.
 Establish Internal Project Reporting
structure.
Head of
Program
Management
Office (PMO)
 Letterof Assignment
to ProjectManager
 Letterof Assignment
to Project
Administrator
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 9
No. Process Description Entity Output / Report /
Document
7. Project Manager establish Project
Organization Structure.
Project
Manager
 ProjectOrganization
Structure
8. Project Manager prepares Project Resource
requirements and submit to PMO.
Project
Manager
 ProjectResource
Requirementform
 ProjectResourcesPlan
9. Head of PMO raises the Project Resource
Requisition to Head of ASEAN Delivery and
Operations for project resources.
Head of
Program
Management
Office (PMO)
 ProjectResource
Requisitionform
10. Head of ASEAN Delivery & Operations
proceed with HR Recruitment process.
Head of ASEAN
Delivery &
Operations
 List of Resources(i.e.
On-Site,Off-shore)
2.2 Scope of Work (SoW) Confirmation Process
Once we sentthe Letterof Acceptance to Customer(i.e.TM), the nextactivityis to conduct
projectscopes confirmation withtheCustomer.Often,aRequirementTraceabilityMatrix will
be prepared by the Project Manager as term of reference in accordance to the official
proposal submitted earlier.
The purpose of this exercise is to baseline the high-level scope of works in regards to the
businessproposal submittedearlierduringthe RFQ(RequestforQuotation)orRFP (Request
for Proposal). The confirmation process is an avenue for Customer to sometime revise the
initial Scope of Work in the RFQ or RFP due to requirement changes. Often,the durationof
preparingthe tenderspecificationandprocessof awardingto vendormaytake more than 6
months. As such, requirements may change due to new technology or may be the
requirements may not be applicable anymore. The SoW Confirmation Process is shown in
Figure 7.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 10
Figure 7 : Process flow for Scope of Works (SoW) Confirmation
Detail process description for SOW confirmation as per Table 5.
Table 5 : Scope of Works Confirmation Process Flow
No. Process Description Entity Output / Report /
Document
1. Project Manager prepares Requirement
Traceability Matrix (RTM) based on the
submitted proposal.
Project
Manager
 Requirement
TraceabilityMatrix
(RTM)
2. Client Partner/Sales Director conduct
meeting session with Customer (i.e. TM) to
baseline the high-level scope.
 Decision from the meeting can be
− Scope of Work revision, or
− Scope of Work sign-off.
 Discussion will be based on Scope of
Work document from LOA and RTM
document.
Client Partner /
Sales Director
 Minutes of Meeting
 Sign-off Scope of Work
document
a. If Customer request changes to scope,
formal request will be captured in the
Minutes of Meeting.
Client Partner /
Sales Director
 Minutes of Meeting
(MOM)
 List of changes to SoW.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 11
No. Process Description Entity Output / Report /
Document
b. Furtherassessmentwill be donebyClient
Partner / Sales Director pertinent to
additional cost and other factors.
3. Scope Changesi.e.additional requirements.
a. ClientPartner/SalesDirectorrequestfor
other vendors additional cost to include
additional requirementsfromCustomer.
Client Partner /
Sales Director
 Email or formal letter
with MOM of SoW
confirmation.
b. Partners / 3rd
party vendor prepare
Propose Cost Revision for inclusion of
additional requirements into scope.
Partners / 3rd
Party Vendors
 Propose Cost Revision
letter or e-mail.
c. Client Partner / Sales Director submit to
Customer the propose revised Selling
Price inclusive of additionalrequirements
Client Partner /
Sales Director
 Revised Bill of Material
(BOM) / Bill of Quantity
(BQ))
d. Customeracceptedthe proposedrevised
SellingPrice andprovide newLOA to TCS
Client Partner / Sales Director.
Customer
(i.e. TM)
 Revised LOA
4. Client Partner / Sales Director perform
a. Scan relateddocumentsinto.pdf format,
b. UploadintoCentral Repository all related
document the Official SoW approved by
Customer (i.e. TM)
Client Partner /
Sales Director
 RevisedLOA (scanned
copy)
 SoW Sign-off page
(scannedcopy).
 SoW softcopy
 Central Repository
Server
2.3 Contract Preparation Process
Normally, contract preparation process starts upon SOW Confirmation process. It is
consideredaslegalisingthe agreementbetweenbothpartiesi.e.the CustomerandVendor.
We’ve divided this process into 2 areas i.e. Main Contract and Sub-Contract agreements.
A sub-contractagreementwill onlybe signed-off afterthe Main Contract is signedbetween
Customerand the selectedVendori.e. TCS.The sub-contractagreementislinkedtothe Main
Contract. Often, sub-contract agreement is signed betweenvendor and its partners or 3rd
party vendors providing the service to the Customer. Figure 8 shows the process flow for
Contract Preparation.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 12
Figure 8 : Process flow for Contract Preparation
Detail process description for Contract Preparation as per Table 6.
Table 6 : Contract Preparation Process Flow
No. Process Description Entity Output / Report /
Document
1. Customer provides the Agreement template
to Vendor(i.e.ClientPartner/SalesDirector)
for preparation.
Customer  Template Agreement
2. Client Partner / Sales Director prepares draft
Contract based on template agreement
received from Customer.
 Standard Contract Clause will be based
on template agreement.
 Specific Clause will be based on LOA and
agreed SOW.
 Include Payment Schedule as agreed.
Client Partner /
Sales Director
 Draft Main Contract
Agreement
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 13
No. Process Description Entity Output / Report /
Document
3. Customer reviews draft Main Contract
agreement with Client Partner / Sales
Director.
 If need modification, Client Partner /
SalesDirectorwill amendthe draftasper
requested amendment.
 If both parties agreed, then Contract
Agreement will be signed-off by the
Customer.
Customer  Contract Agreement
(withCustomer
authorisedsignatures)
4. ClientPartner/SalesDirectorsubmittoHead
of ASEAN Delivery & Operations for signed-
off and stamping the Contract document.
Client Partner /
Sales Director
5. Headof ASEAN Delivery&Operationsobtains
TCS authorised signatures on the Contract
document and send for stamping.
Head of ASEAN
Delivery &
Operations
 Contract Agreement
(withbothCustomers
and TCS authorised
signatures, and
stamped)
6. Client Partner / Sales Director performs :
 Submit stamped Contract document to
Customer.
 Submit a copy of Contract document to
Project Manager for keeping.
Client Partner /
Sales Director
 Contract Agreement
(Stamped).
7. ProjectManagerscanthe Contractdocument
& upload to Central Repository server.
Project
Manager
 Contract Agreement
(scannedcopy)
 Central Repository
server
8. Head of ASEAN Delivery & Operations
prepares draft sub-contract agreement and
submit the draft to partners / 3rd
party
vendors for review & sign-off.
Head of ASEAN
Delivery &
Operations
 Draft Sub-contract
Agreement
9. Partners / 3rd
party vendors review and sign-
off the document.
Partners / 3rd
party vendors
 Sub-Contract
Agreement(with
Partners/ 3rd
Party
vendorssignatures)
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 14
No. Process Description Entity Output / Report /
Document
10. Headof ASEAN Delivery&Operationsobtains
TCS authorised signatures on the Contract
document and send for stamping.
Head of ASEAN
Delivery &
Operations
 Sub-Contract
Agreement(withboth
Partners/3rd
party
vendorsandTCS
authorisedsignatures,
and stamped)
11. Head of ASEAN Delivery & Operations
performs :
 Submit stamped Sub-Contract document
to Partners / 3rd
Party vendors.
 Submita copyof Sub-Contractdocument
to Project Manager for keeping.
Head of ASEAN
Delivery &
Operations
 Sub-Contract
Agreement(Stamped).
12. Project Manager scan the Sub-Contract
document & upload to Central Repository
server.
Project
Manager
 Contract Agreement
(scannedcopy)
 Central Repository
server
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 15
3. Project Implementation Process (Delivery)
As showninTable 2, there are 2 standard processes for the Delivery component. They are:
 Project Management Process
 Project Financial Management
Both processes are linked since Project Management Process focus on delivery of end-
product to Customer and Project Financial Management involves the financial aspects with
regards to project cash-flows.
3.1 Project Management Process
A standard methodology for Project Management divides delivery processes into 5 group
processes which are:
− Initiating
− Planning
− Executing
− Monitoring and Controlling
− Closing
The following Figure 9, highlights the project management process framework.
3.1.1 Project Management Process – Initiating
Project initiating is the commencement of project delivery. The formal project
commencementorkick-offisdone toformalise the importantaspectof a projecti.e. project
implementation strategy, project organization structure, project timeline, milestones,
deliverables and stakeholders’ expectations. Figure 10 shows the process flow for Project
Initiating Process.
Figure 9 : Project Management Process Framework
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 16
Detail process description for Project Initiating as per Table 7.
Table 7 : Project Initiating Process Flow
No. Process Description Entity Output / Report /
Document
1. Client Partner / Sales Director organizes
project kick-off session with Customer.
Client Partner /
Sales Director
 Kick-off Slide
Presentation
2. Customer performs the following:
 Identify the required stakeholders to
attend the project kick-off session.
 Circulate calendar invite to stakeholders
and TCS’sClientPartner/ Sales Director.
Customer
(Project
Manager)
 CalendarInvite
3. Project Office creates respective Project
Folders in Central Repository server.
Project office  ProjectFolders
 Central Repository
server
4. ProjectManagerrequestsfromthefollowing: Project
Manager
 Resource Planning
document
Figure 10 : Process Flow for Project Initiating
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 17
No. Process Description Entity Output / Report /
Document
 Head of ASEAN Delivery& Operations to
provide listof available resourcesforthe
project.
 Partners / 3rd
Party vendors to provide
theirResource Planningandthe available
resources for the project.
4. Project Manager then prepares the Project
Charter document and obtains endorsement
from Client Partner / Sales Director.
Project
Manager
 Draft ProjectCharter
 ResourcesPlanning
 High-level project
timeline
5. ClientPartner/ SalesDirectorsubmitProject
Charter document to Customer for sign-off.
Client Partner /
Sales Director
 ProjectCharter
document(incl.
Resource Planning,
High-Level project
timeline)
6. Customer produce Certificate of Acceptance
to accept and approve the deliveryof Project
Charter document.
Customer  COA for ProjectCharter
 ProjectCharter
document(Signed-off).
7. Project Office perform the following:
 Scan Certificate of Acceptance (signed
copy) for Project Charter.
 Upload the scan copy of COA, and
softcopy(final version) ProjectCharterto
Project Folder in Central Repository
server
Project Office  COA for ProjectCharter
(scannedcopy)
 Softcopy(final version)
ProjectCharter
document.
 Central Repository
server
8. Head of ASEAN Delivery & Operations
proceedthe arrangementforOff-shoreTeam
that will be stationed On-site.
 Accommodation, work permit, work
location etc.
Head of ASEAN
Delivery &
Operations
 Official documentsfor
Off-shore team.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 18
3.1.2 Project Management Process – Planning
At thisstage,ProjectManager starts the detail planningwithall TeamLeadsand Partners or
3rd
Party vendors. During the project kick-off session and acceptance of Project Charter,
Customer has endorsed the high-level project timeline.
Basedon the agreedmilestonesanddue date,ProjectManagerdefinesthe startdate & end
date for each task from the detail timeline provided by Team Leads and Partners / 3rd
Party
vendors. Figure 11 shows the process flow for Planning Process.
Figure 11 : Process flow for Project Planning
Detail process description for Project Planning as per Table 8.
Table 8 : Project Planning Process Flow
No. Process Description Entity Output / Report /
Document
1. Project Manager prepares WBS based on
high-level milestones.
Project
Manager
 Work Breakdown
Structure list
2. TeamLeads & 3rd
PartyVendorspreparesthe
detail tasks GanttChartinaccordance to WBS
Structure list & submit to Project Manager.
Team Leads,
3rd
Party
Vendors
 Gantt Chart on Detail
Tasks
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 19
No. Process Description Entity Output / Report /
Document
3. Project Manager prepares Project Quality
Plan Management document by
consolidating the following :
 Project Schedule
 Resource Plan
 Communication Plan
 Change Management Plan
 Quality Plan
 Risk Register
 Payment Milestones
Project
Manager
 ProjectQualityPlan
Management
document(Draft)
a. Team Leads prepares project technical
document templates.
b. ProjectOffice preparesprojectdocument
templates
Team Leads,
Project Office
 Technical document
templates
 Projectdocument
templates
4. Project Manager submit Project Quality Plan
Management document to Customer for
acceptance sign-off.
Project
Manager
 ProjectQualityPlan
Management
document(Final)
5. Customer produce Certificate of Acceptance
to accept and approve the deliveryof Project
Quality Plan Management document.
Customer  COA for ProjectQuality
PlanManagement
document
 ProjectQualityPlan
Management
document(Signed-off)
6. Project Office perform the following:
 Scan Certificate of Acceptance (signed
copy) for Project Quality Plan
Management document.
 Upload the scan copy of COA, and
softcopy (final version) Project Quality
Plan Management document to Project
Folder in Central Repository server.
Project Office  COA for ProjectQuality
PlanManagement
(Scancopy)
 Softcopy(Final version)
ProjectQualityPlan
Management.
 Central Repository
server.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 20
No. Process Description Entity Output / Report /
Document
7. Head of ASEAN Delivery & Operations
allocatesresourcesaccordingtothe Resource
Planning.
Head of ASEAN
Delivery &
Operations
3.1.3 Project Management Process – Executing
In projectexecution,ProjectManager mustmanage projectactivitiesinaccordance todetail
planagreedby the stakeholdersthatincludeCustomer,ProjectTeam,andPartners/3rd
Party
vendors. At this stage, Project Manager needs to communicate effectively with the
stakeholders. Thus, 90% of Project Manager’s effort will be on communication. Figure 12
shows the Project Executing process flow.
During project execution, Project Manager prepares progress status reporting & presented
to Customer and Internal PSC. Progress reporting will also include highlighting risks, issues
that project team is facing and requires Customer to endorse the mitigation plan to avoid
delayinprojectdelivery.ProjectManagerwillinvokethe respectiveMonitoring&Controlling
procedures with regards to Risks/Issues Mitigation, Quality Assurance as well as Timeline
control.
Figure 12 : Process Flow for Project Executing
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 21
Detail process description for Project Executing as per Table 9.
Table 9 : Project Executing Process Flow
No. Process Description Entity Output / Report /
Document
1. Project Manager manages project activities
according to Project Plan & Timeline &
monitor tasks, risks & issues continuously.
Project
Manager
2. Project Team executes tasks as per planned
start date.The followingtaskswill be doneby
the project team:
 Prepare required deliverables as per
project document template.
 Reportingtasksprogressstatusto Project
Manager.
 Highlights on risks & issues to Project
Manager
Project Team  Risksform
 Issuesform
 Timesheet
 Milestonesdeliverables
3. Project Manager performs the following :
 Prepare Progress Status Report and
updates Customer.
 Prepare Progress Status Report and
updates Internal PSC.
 Invoke QA Proceduresforall deliverables
prepared by the Project Team
 Invoke Risks Control procedures for
project risks monitoring & control.
 Invoke Timeline control procedures for
schedule monitoring and control.
Project
Manager
 ProjectStatusReport
 RiskRegister
 IssuesRegister
 ProjectTimeline
(Actual vs.Planned)
 ProjectQuality
ManagementPlan
document(revised).
a. Headof ASEAN Delivery&Operationswill
resolves issues in regards to Inter-
departments and Inter-organisations
raised by Project Manager in Internal
Project Status Report.
Head of ASEAN
Delivery &
Operations
 IssuesRegister
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 22
No. Process Description Entity Output / Report /
Document
b. Project Office prepares the Minutes of
Meeting for all project status meeting
sessions with Customer.
Project Office  Minutes of Meeting
4. Customer review progress status.
 Approve the revised schedule, if any.
 Approve risk mitigation plan, if any.
Customer,
Project
Manager
 Approval Sign-offform
5. Customer raises new requirements due to
various reasons.
 Project Manager invokes the Change
Request Control procedures
 Internal PSC reviews and endorses the
additional project costs & revised
timeline submitted by Project Manager.
 Head of ASEAN Delivery & Operations
proceed Variation Order process with
Customer.
Customer,
Project
Manager,
Internal PSC
 Change Requestform
 Change Request
Proposal
 Change Request
Approval
 VariationOrder
6. Project Office maintains the Project Central
Repository for all deliverables submitted to
Customer for review and acceptance.
Project Office  Scanneddocuments
 Minutesof Meetings
 Central Repository
server
3.1.4 Project Management Process – Monitoring and Controlling (Timeline)
Project Manager must monitor & control project timeline accordingly.Time is one of the
componentinthe Triple Constraintsi.e.Scope,Time and Budget.Hence,propermonitoring
& controlling procedures must be invoked so that Project Manager can be alerted when
there’s a possibilities of slippage in the project schedule.
Varioustoolscan be utilizedbyProjectManagerto detectthe slippage,especiallyinregards
todetail tasksthathave dependenciesanddue date.Normally,taskdependencyisone of the
tool that alwaysprovide red lighttoProjectManager wheneverapotential slippage isabout
to happen.
Any delay of project task that have dependency can be screened earlier through Timesheet
of each teammembersince everyteammemberswill have tosubmittheirTimesheetatend
of week.Basedonthe Timesheet,ProjectManagerwill be able todetermine the completion
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 23
of each task performed by the team member whether as per planned or otherwise. Hence,
Project Manager needs strategy to put project back on-track when the slippage occurs.
The following Figure 13 shows the Monitoring & Controlling Process for Timeline.
Figure 13 : Process Flow for Monitoring and Controlling for Timeline
Detail process description for Monitoring and Controlling for Timeline as per Table 10.
Table 10 : Monitoring & Controlling (Timeline) Process Flow
No. Process Description Entity Output / Report /
Document
1. Project Office prepares Timesheet template
and circulates to Project Team members to
fill-in for weekly planned tasks execution.
Project Office  Timesheettemplate
2. Project Team filled in the Timesheet for
weekly activities planned and actual.
 Monday morning submission for plan
tasks for the week.
Project Team  Weekly Timesheet
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 24
No. Process Description Entity Output / Report /
Document
 Friday evening submission for actual
tasks progressing.
3. Project Manager reviews Weekly Timesheet
with Project Team on Monday morning.
 If slippage, Project Manager will cross-
check with the Overall Project Plan
whether impacted or otherwise.
 If Overall Planimpacted,ProjectManager
revises the Overall Plan and obtain
endorsement from Internal PSC prior to
Customer endorsement. Cost impact
report will be submitted to Internal PSC
for review and endorsement.
Project
Manager
 ProjectTimeline
(Actual vs.Planned)
 IssuesRegister
 RisksRegister
 Cost impactreport
4. ProjectManagerpresentsthe RevisedProject
Schedule to Customer for approval.
Project Office noted the approval in Minutes
of Meeting.
Project
Manager,
Project Office
 RevisedProject
Schedule
 Minutesof Meeting
5. Customer review and approve the revised
schedule.
Often, project schedule revision will be
presented in Project Status Meeting.
Customer  Approval on Revised
ProjectSchedule
6. Project Team executes mitigation plan to
bring project back on track.
Project Team  IssuesRegister
 ProjectSchedule
7. Internal PSC and Head of ASEAN Delivery &
Operation approved on the utilisation of
Contingency Reserve fund for Revised
Schedule that require additional project
budget.
Internal PSC,
Head of ASEAN
Delivery &
Operation
 Internal Memo
8. Project Office maintains the Project Central
Repository for all deliverables submitted to
Customer for review and acceptance.
Project Office  Scanneddocuments
 Minutesof Meetings
 Central Repository
server
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 25
3.1.5 Project Management Process – Monitoring and Controlling (Risks / Issues)
Risks & Issues are potential elements that impact to project delivery. Monitoring and
Controlling risks and issues are critical tasks that Project Manager needs to perform during
project implementation.
Often, frequency of risks & issues monitoring and controlling are done weekly to ensure
project healthiness. Risks & issues that have been identified and resolved will be logged in
each registers. Whenever identified risks emerge, Project Manager will reviews overall
project timeline to assess whether any adverse impact to it. If there is impact, then Project
Manager will executes mitigation plan as agreed by Customer.
Sometime,mitigationplanrequiresadditionaltime tobe addedintooverall projectschedule
and milestonesdue date must be revised.If thishappens,ProjectManager needsto invoke
necessary procedures to obtain endorsement from Customer and Internal PSC before the
mitigationplancanbe loggedinthe RisksRegister. Similarprocedureappliestoprojectissues
as well. Figure 14 shows the process flow for Monitoring and Closing for Risks and Issues.
Figure 14 : Process Flow for Monitoring and Closing for Risks and Issues
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 26
Detail process description for Monitoring and Controlling for Timeline as per Table 11.
Table 11 : Monitoring & Controlling (Risks / Issues) Process Flow
No. Process Description Entity Output / Report /
Document
1. Project Manager reviews risks and issues
weekly with Project Team.
ProjectOffice updatesbothregistersforrisks
and issues that have been closed.
Project
Manager,
Project Office
 RisksRegister
 Issues /ActionItem
Register
a. Project Team raises :
 Risks Form when there’s a new risk
identified.
 IssuesFormwhenthere’sanew issue
identified.
Project Team  Risks/ IssuesForm
2. ProjectManagerdetermineswhetherOverall
Project Schedule will be impacted by the
identified risks or issues.
 If impact to Overall Schedule, then the
mitigation plan will be prepared for the
respective risks or issues.
 If Overall Planimpacted,ProjectManager
revises the Overall Plan and obtain
endorsement from Internal PSC prior to
Customer endorsement. Cost impact
report will be submitted to Internal PSC
for review and endorsement.
 Project Manager presents the Revised
Schedule toCustomerfor approval,after
endorsement of Revised Schedule from
Internal PSC.
 ProjectOffice willloggedinbothregisters
for all newly identified risks or issues.
Project
Manager,
Project Office
 RisksRegister
 Issues/ActionItem
Register
 Cost impactreport
3. Project Manager presents Risks and Issues
registers to Customer for endorsement on
mitigation plan for new risks and issues.
Project Office noted the endorsement in
Minutes of Meeting.
Project
Manager,
Project Office
 RisksRegister
 Issues/ActionItems
Register
 Minutesof Meeting
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 27
No. Process Description Entity Output / Report /
Document
4. Customer reviews and approves the
Mitigation Plan inclusive of Revised Project
Schedule.
Often, Risks/Issues Mitigation Plan will be
presented in Project Status Meeting.
Customer  Approval on
Risks/Issues Mitigation
Plan
5. Internal PSC and Head of ASEAN Delivery &
Operation approved on the utilisation of
Contingency Reserve fund for Risks / Issues
Mitigation Plan that require additional
project budget.
Internal PSC,
Head of ASEAN
Delivery &
Operation
 Internal Memo
6. Project Office maintains the Project Central
Repository for all deliverables submitted to
Customer for review and acceptance.
Project Office  Scanneddocuments
 Minutesof Meetings
 Central Repository
server
3.1.6 Project Management Process – Monitoring and Controlling (Change
Request)
Often, there are new requests raised during project implementation. Sometimes, change
requestsraisedbyCustomerduetopolicychange andProjectManagerneedstohandlethese
new requests accordingly. Suddenchange to project tasks may impact to the whole project
deliverymilestones.Hence,properchangerequestproceduremustbeinvokedbeforeallnew
requests can be considered as part of project delivery commitments.
The mostimportantcomponentinthe Change RequestsProcessisthe ChangeControl Board
(CCB). A CCB must be formed at earlier stage so that any new requirement raised can be
addressedearlierpriorto projectexecution.Thiswill easesthe pressure to ProjectManager
and projectteamasnewcritical requirementscanbe includedinthe projectscheduleduring
planning stage. All change requests raised by users are reviewed by CCB to determine
whetherthese requestscanbe endorsedfor furtheractionsordeclined. Figure 15showsthe
process flow for Monitoring and Closing for Change Request.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 28
Figure 15 : Process Flow for Monitoring & Controlling for Change Requests
Detail processdescriptionforMonitoring&ControllingforChange RequestsasperTable 12.
Table 12 : Monitoring & Controlling (Change Requests) Process Flow
No. Process Description Entity Output / Report /
Document
1. Customer raised new requirements during
meetingsessions,workshopsessions,orUAT
sessions.
 Newrequirementswillbe capturedinthe
standardChange Requestformandto be
filled in by the Requestor.
Customer  Change Requestform
2. Project Team evaluates the efforts on new
requests based on duration, complexity,
impact to other delivery components and
number of resources required.
Project Team  Timeline (fornew
requests)
3. Project Office gives a unique ID for each CRs
and loggedin the Change Requests register.
Project Office  Change Request
Register
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 29
No. Process Description Entity Output / Report /
Document
4. ProjectManagerdetermineswhetherOverall
ProjectSchedule willbe impactedbythe new
requirements.
 If Overall Planimpacted,ProjectManager
developspropose revisedOverall Project
Schedule to include the new requests
implementation.
Project
Manager
 Propose Revised
ProjectSchedule
5. Project Manager conducts the following for
the new requirements.
 Project Manager estimates the cost for
the new requirements and obtain
endorsement from Internal PSC prior to
Customer endorsement. Cost impact
report will be submitted to Internal PSC
for review and endorsement.
 Project Manager compiles all Change
Request forms and presents to CCB for
approval.
 Project Office updates the Change
Requests register for all CR forms
submitted for CCB review and
endorsement.
Project
Manager,
Project Office
 Cost impactreport
 Change Request
Register
 CompiledChange
Requestsforms.
6. Change Control Board reviews and endorses
eachChange RequestinCCBMeetingsession.
Change Control
Board
 ApprovedandRejected
CR forms
 Minutesof Meeting
a. Project Office updates the Change
RequestRegisteronall CRs(i.e.Approved
and Rejected).
Project Office  Change Request
Register
7. Project Manager obtain sign-off from
Customer on revised project schedule for
implementation of the approved Change
Requests.
Project
Manager
 Propose Revised
ProjectSchedule
8. Customer signed-off the Revised Project
Schedule.
Customer  Sign-off document.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 30
No. Process Description Entity Output / Report /
Document
a. Project Manager must update the
Internal PSCand Head of ASEAN Delivery
& OperationinregardstoRevisedProject
Schedule.
b. Project Manager informs the Project
Team of the Revised Project Schedule.
Project
Manager
 ApprovedRevised
ProjectSchedule
9. Project Office maintains the Project Central
Repository for all deliverables submitted to
Customer for review and acceptance.
Project Office  Scanneddocuments
 Minutesof Meetings
 Central Repository
server
10. Project Team executes all approved CRs. Project Team
3.1.7 Project Management Process – Monitoring and Controlling (Quality
Assurance)
Quality Assurance is part of the activity to ensure all deliverables adhered to the quality
standard practiced by the Customer. In Project Management process, Quality Assurance is
deployed under the Monitoring and Controlling process. Quality is emphasized in every
project as to ensure Customer satisfaction of the delivered product or services. The very
minimum is to have all submitted deliverables complied the industry’s standard. As such,
standarddocumenttemplatesneedtobe definedandsharedwiththe ProjectTeamforthem
to use when preparing the deliverables.
The processstarts withProjectOffice preparesthe templatesanduploadedintothe Central
Repository server. Often, these defined templates are endorsed during Project Kick-off
Meeting to make known to stakeholders and Project Team that consistencies in project
deliverablesare important.Furthermore,itisaformof goodpractice that can be transferred
to Customer as well.
Types of deliverables vary as they depend on delivery scope. For example, a software
development project is based on the SDLC methodology whereby the standard deliverables
are; User Functional Specification, System Design Specification, User Acceptance Testing,
Data Migration Specification, Training Manual, User Manual, and Hand-over Document. A
part from that, there are generic documentsin Project Managementprocesses that include
Project Charter, Project Quality Plan Management, Certificate of Acceptance, Risk Profile
form, Change Request form, and Minutes of Meeting.
Often,the ProjectManager mustwork togetherwithProjectOffice todetermine what,how
and when these documents will be used. Figure 16 shows the process flow for Monitoring
and Closing for Quality Assurance.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 31
Figure 16 : Process flow for Monitoring & Controlling for Quality Assurance
Detail processdescriptionforMonitoring&Controllingfor QualityAssurance asperTable 13.
Table 13 : Monitoring & Controlling (Quality Assurance) Process Flow
No. Process Description Entity Output / Report /
Document
1. Project Office defines standardized project
document templates and uploads into
Central Repository.
Often, standardization of document
templatesisdone at Project Initiating stage.
Project Office  Documenttemplates
 Central Repository
server
2. Project Team prepares the document for
Customer sign-off upon completion of each
project milestone.
Project Team  Draft Technical
Documents
3. Team Lead reviews contents and endorses
the document before releasing to Project
Manager for approval.
Project Team
Lead
 Draft Technical
Documents
4. Project Manager reviews and approves
documents for submission to Customer.
Project
Manager
 Technical Documents
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 32
No. Process Description Entity Output / Report /
Document
Often, Project Manager reviews contents in
regards to delivery scope compliance and
standardised document layout.
5. Customer circulates the documents to the
relevant stakeholders for reviews and
verifications. Often, they are :
 QA/QC team, and
 User team
Customer  Technical Documents
 Feedbackform
6. User Team and QA/QC Team reviews and
verifies the documents.
 QA/QC team – reviews on document’s
Quality.
 User team – reviews on user
requirements compliance.
User Team and
QA/QC Team
 DocumentSign-off
Page
(ReviewedSection)
 Feedbackform
a. If amendments required, User Team and
QA/QC Team will list out comments in
feedback form.
b. Document& Feedbackformare reverted
to TCS for further amendments.
User Team and
QA/QC Team
 FeedbackForm
 Technical Documents
(Modificationrequired)
c. Project Team modify documents as per
Feedback form and repeat the internal
reviewprocessas per processes 3 and 4.
Project Team  RevisedTechnical
Documents
7. Customer produce Certificate of Acceptance
to accept and approve the deliverables.
Customer  COA as per deliverable
milestones
8. Project Office perform the following:
 Scan Certificate of Acceptance (signed
copy) for technical document
deliverables.
 Upload the scan copy of COA, and
softcopy (final version) of technical
document deliverables to Project Folder
in Central Repository server.
Project Office  COA technical
documentdeliverables
(scannedcopy)
 Softcopy(final version)
technical document
deliverables.
 Central Repository
server
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 33
No. Process Description Entity Output / Report /
Document
9. Project Manager informs relevant parties in
TCS for project billing process.
Project
Manager
 Email
3.1.8 Project Management Process – Closing
When project successfully completed, it shows that all delivery commitments have been
deliveredtoCustomer.The endorsementinaformof COA indicatesCustomersatisfactionon
quality compliances shown on all submitted deliverables. Hence, a proper project closing
procedure should be commenced. Figure 17 shows the process flow for Project Closing.
Often, Project Closing involves the following:
− Final Acceptance process
− Handing over to Operational Support Team
− Starting of Warranty Support period.
− Project Team disbanding.
Figure 17 : Process Flow for Project Closing
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 34
Detail process description for Project Closing as per Table 14.
Table 14 : Project Closing Process Flow
No. Process Description Entity Output / Report /
Document
1. ProjectManager will coordinate withproject
stakeholders for the Final Acceptance
session.
 ProjectOffice circulatescalendarinviteto
all stakeholders.
Project
Manager,
Project Office
 Calendarinvite and
Final Acceptance
Agenda.
2. Project Team prepares technical documents
for Final Acceptance & submit these
documents to Customer.
 Project Team performs Final Acceptance
with Customer.
Project Team  DocumentsforFinal
Acceptance
3. CustomerperformsFinal Acceptance process
and sign-off the Certificate of Final
Acceptance
Customer  CFOA (Signed-off)
4. Project Office performs the following:
 Scan Certificate of Final Acceptance
(signed copy).
 Upload the scan copy of Certificate of
Final Acceptance to Project Folder in
Central Repository server.
Project Office  CFOA (scannedcopy)
 Central Repository
server
5. Internal PSCestablishesthe SupportServices
Team for Warranty Period.
Internal PSC  SupportServices
Organizationstructure
a. Head of ASEAN Delivery & Operations
allocatespeople forthe SupportServices
during Warranty Period.
Head of ASEAN
Delivery &
Operations
 Listingof Resources
withRoles&
Responsibilities
6. Project Manager conduct the Handover
SessionwiththeCustomerandSupportTeam
for the Warranty Support.
 Project Team disbanded
 Warranty Period commences
Project
Manager,
Project Office
 Handoverdocument
 ProjectFile Folder
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 35
No. Process Description Entity Output / Report /
Document
7. Head of ASEAN Delivery & Operations
invoked the Final Billing process.
Head of ASEAN
Delivery &
Operations
 Final Billing
3.2 Project Financial Management
Often,projectfinancial managementinvolvesmanagingthe monetaryaspectof a project.It
involves managing Accounts Receivable (AR) and Accounts Payable (AP) with regards to
project.ProjectManagerneedstokeeptrackof project billings/collectionsas wellas3rd
party
vendor billings and payments.
Figure 18 showsthe processframeworkforbothAccountsReceivable andAccountsPayable.
Figure 18 : Project Financial Management Process Framework
This process framework applies to both processes:
− Customer’s Invoicing, and
− Billings from Partners / 3rd
party vendors.
In general, the framework shows the sequence of processes that need to be completed
before proceedingtothe nextstage.Invoicingandbillingprocessescanproceeduponsigning
of contract betweenbothparties,asmentionedearlierinthe ContractPreparationProcess.
Often,paymentmilestonesare settotriggerthe invoicingandbillingprocesses. Forexample,
the payment schedule between Customer and TCS, is formalisedin Contract and become
Customer’s commitment to pay TCS upon completion of each milestone. Pre-requisite
documentsneedtobe submittedtogetherwiththe invoice toensure paymentcanbe made
to TCS. Hence, Project Manager needs to be aware of these pre-requisite documents.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 36
For example, the following pre-requisite documents are required when invoicing TM:
− TM’s Purchase Order (PO)
− COA (Certificate of Acceptance)
− TCS’s Invoice
Once these documentsare prepared,TCS’s ProjectManagermustobtainsign-off onCOA and
TCS’s Invoice from the respective TM Project Manager before proceeding to upload the
scanned copies of these documents into TM’s Portal. Often, uploading these documents is
done by TCS Client Partner or Sales Director since they have the User Login to TM’s Portal.
3.2.1 Project Financial Management Process – Accounts Receivable (AR)
Project cash-flow is important in every project since resources costs are budgeted in the
project.ItisimportantforProjectManagertokeeptrack onprojectinvoicingandcollections.
Hence,astandardtool totrack ProjectCash-flowneedtobe usedasithelpsProjectManager
to determine due date for invoicing process.
Often,invoicingCustomerisbasedonthe paymentscheduleagreedinthe Contract. Relevant
documents to be submitted together with invoice are stated in the Contract as well. The
Accounts Receivable process is shown in Figure 19.
Figure 19 : Process Flow for Project Accounts Receivable
Detail process description for Project Accounts Receivable as per Table 15.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 37
Table 15 : Project Accounts Receivable Process Flow
No. Process Description Entity Output / Report /
Document
1. Client Partner/Sales Director starts with
signingof Contract for the project initiative.
Client Partner /
Sales Director
 Contract
2. Project Manager prepares the Billing /
Collection Milestones Tracking sheet based
on Payment Schedule in Contract.
 Project Manager shares the
Billing/Collection Milestones tracking
sheet with Head of ASEAN Delivery &
Operations
Project
Manager
 Project
Billing/Collection
MilestonesTracking
sheet
3. Customerprepares POafterContract signed-
off.
Customer  Purchase Order
4. ProjectOffice preparesCOA upon completion
of delivery milestone.
Project Office  COA
5. Project Manager informs Head of ASEAN
Delivery & Operations to prepare Invoice
based on payment schedule.
Project
Manager
 Email
a. Head of ASEAN Delivery & Operations
prepares Invoice and revert the Invoice
document to Project Manager for
Customer sign-off.
Head of ASEAN
Delivery &
Operations
 Invoice
b. ProjectManager submit COA and Invoice
document to Customer for sign-off
together with relevant PO.
Project
Manager
 Compileddocuments
(i.e.Invoice,COA,PO)
6. Customer’s PM sign-off Invoice and COA,
then revert to Client Partner / Sales Director
for submission to Customer’s Finance.
Customer
Project
Manager
 Invoice (Signed-off)
 COA (Signed-off)
7. Client Partner / Sales Director submit to
Customer Finance all documents (Invoice,
COA and PO) for payment process.
In TM, documentsubmissionis viaTMPortal.
Client Partner /
Sales Director
 Scanneddocuments
(i.e.Invoice,COA,PO)
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 38
No. Process Description Entity Output / Report /
Document
8. Project Office updates relevant information
in the Billing/Collections Milestones tracking
sheet.
Project Office  Billing/Collection
Milestonestracking
sheet
9. Project Office upload to Central Repository
the scanned copies of Invoice, COA and PO.
Project Office  Scanneddocuments
(i.e.COA,Invoice,PO)
 Central Repository
server.
3.2.2 Project Financial Management Process – Accounts Payable (AP)
Often, cash-flow management also involves processing payments to 3rd
party vendors or
Partners. The process flow is similar to Accounts Receivable except that TCS will be the
paymaster. All projectpaymentsto3rd
partyvendorsor Partnersshouldbe basedon agreed
payment terms and schedule.
Normally, the agreement between TCS and 3rd
party vendors is signed under sub-contract
agreement. Hence, payment terms will always be ‘back-to-back’ i.e. TCS pays 3rd
party
vendorsafterpaymentmade by the Customer.Pre-requisite documenttoprocesspayment
mustbe submittedtogetherwithvendor’sinvoice andthese documentwill be basedonTCS
internal procedure. The Accounts Payable process is shown in Figure 20.
Figure 20 : Process flow for Project Accounts Payable
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 39
Detail process description for Project Accounts Payable as per Table 16.
Table 16 : Project Accounts Payable Process flow
No. Process Description Entity Output / Report /
Document
1. Head of ASEAN Delivery & Operations starts
with signing of Sub-Contract agreement for
the project initiative.
Head of ASEAN
Delivery &
Operations
 Sub-Contract
Agreement
2. Project Manager prepares the Payment
MilestonesTrackingsheetbasedonPayment
Schedule in Sub-Contract.
 Project Manager shares the Payment
Milestones tracking sheet with Head of
ASEAN Delivery & Operations
Project
Manager
 ProjectPayment
MilestonesTracking
sheet
3. Partners / 3rd
Party Vendors delivers tasks as
per milestone.
 Partners / 3rd
Party Vendors obtains
endorsement from TCS Project Manager
Partners / 3rd
party vendors
 Milestone deliverables
4. TCS Project Manager endorses the delivery
milestone completion.
Project
Manager
 DeliverablesSign-off
a. Client Partner / Sales Director produce
and sign-off the Delivery Acceptance
form & submit to 3rd
party vendors /
partners.
Client Partner /
Sales Director
 DeliveryAcceptance
form(signed)
5. Partners/ 3rd
partyVendorssubmitinvoice &
relevant documents as per Payment
Schedule.
Partners / 3rd
party vendors
 Invoice
 Supportingdocuments
a. TCS Project Manager instruct Head of
ASEAN Delivery & Operations to process
paymentfor3rd
party vendors/Partners.
b. Project Office updates the Payment
Milestone tracking sheet.
Project
Manager,
Project Office
 Email
 Invoice
 Supportingdocuments
 ProjectPayment
MilestonesTracking
sheet
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 40
No. Process Description Entity Output / Report /
Document
6. Head of ASEAN Delivery & Operations
proceed with payment process to 3rd
Party
Vendors / Partners.
Head of ASEAN
Delivery &
Operations
 PaymentAdvice
9. Project Office upload to Central Repository
the scanned copies of Invoice, and Delivery
Acceptance form.
Project Office  Scanneddocuments
(i.e.Invoice,Delivery
Acceptance form)
 Central Repository
server.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 41
4. Project Implementation Process (Post-Delivery)
Post-delivery commences upon project closing. It has 2 components:
− Warranty Support Process
− Client Retention Program
Usually,Warranty Supportcovers Corrective Maintenance ondeliveredproduct.Sometime,
italsocoversPreventive Maintenancedependingonterms&conditionsagreedbetweenTCS
andCustomer. The WarrantySupportperiodcanbe 6months,12months,oreven24months.
Often,retainingthe existingCustomerisa challengetocompany.Therefore,ClientRetention
Program should starts immediately i.e. during Post-Delivery. At this stage i.e. Post-Delivery,
TCS Support Team can identify room for improvement on areas that were not in previous
deliveryproject.Aswell,gapsorweaknessesdiscovered duringPreventiveMaintenancecan
triggered business opportunities for TCS to propose ultimate solution. Hence,proper Client
RetentionProgramshouldbedevelopedtoensurecontinuousbusinessventure betweenTCS
and the Customer.
4.1 Post-Delivery (Warranty Support)
As mentioned earlier, Warranty Support is part of delivery that TCS needs to provide after
project completion. We are aware that during project closing, the Project Team has been
disbanded.Duringproject,all issueswere beingattendedbytheassignedteaminthe project.
But once project has been closed, the responsibility to service the Customer has shifted to
the Support Team for the duration agreed in the Contract.
As mentioned earlier, Warranty Support Service covers Corrective Maintenance and
Preventive Maintenance. Figure 21 shows the Warranty Support process framework.
Figure 21 : Warranty Support Process Framework
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 42
Critical component in Warranty Support Services is the SLA (Service Level Agreement)
management. CustomerexpectingTCStoresponse fastwhenproblemsare loggedin.Often,
the response timetoproblemresolutiondependsonseverityof aproblemandeachproblem
will be classifiedintoCritical,Major,MediumandLow.Basedontheseclassifications, the SLA
will be determined.Often,all critical issueswill needfastresponsesfromTCSSupportTeam
and these issues to be resolved within agreed duration since critical issues will disrupt the
daily operations.
Apart from SLA Management, there is Preventive Maintenance that TCS must perform for
Customer. Normally, frequency for Preventive Maintenance is set as Yearly, Half-Yearly,or
Quarterly. The reason for Preventive Maintenance is to identify potential problems before
they emerge. As such, risks of operational disruption can be avoided.
In general, TCS Helpdesks will escalate all problems logged by Customer based on severity
classification.Routingproblem ticketswithSLA tothe respective SupportTeamwill be done
via Helpdesks system. Hence, status of each ticket can be tracked and report can be
generateddaily,monthlyaswell asyearly.Furthermore,analysisreportonperformancecan
be produced to Customer as evidence of Warranty Support being done in accordance to
contract.
OnPreventiveMaintenanceSupport,schedule forPreventiveMaintenanceissharedwithTCS
Helpdesks byTCS Service Manager. A ticketon Preventive Maintenance will be escalatedto
TCS SupportTeamas preventivesupporttasks.Listof taskswillneedtobe performedduring
Preventive Maintenance support and once completed, the TCS Support Team obtains
endorsement from Customer for work done.
4.1.1 Post-Delivery – Warranty Support for Corrective Maintenance
Warranty Support for Corrective Maintenance involves activities of resolving Customer’s
operational problems of the delivered product. These problems will be raised as incident
tickets via TCS Helpdesks. The severity of every problems will be determined based on the
impactof the problemtooperation.Eachticketwillhave the SLA thatneedstobe fulfilledby
TCS Support Team. Otherwise, TCS will be considered as non-compliance to Contract and
having risks of being litigated.
Figure 22 shows the process flow for Corrective Maintenance.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 43
Figure 22 : Process flow for Warranty Support (Corrective Maintenance)
Detail processdescriptionforWarrantySupportfor Corrective MaintenanceasperTable 17.
Table 17 : Warranty Support (Corrective Maintenance) Process Flow
No. Process Description Entity Output / Report /
Document
1. Customer logged in incident to obtain
Incident Ticket via :
 Helpdesks Hotline no.
 Website Portal.
Customer  IncidentTicket
2. HelpdesksSupportConsultantwill accessthe
Incident tickets and performs the following
based on severity:
 Resolve issue at 1st
Level Support
 Escalation to the 2nd
Level Support
Helpdesk  IncidentTicket
 Escalationemail
 IncidentManagement
Database
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 44
No. Process Description Entity Output / Report /
Document
 Escalation to the 3rd
Level Support
a. Helpdesks updates status for 1st
Level
Supportafterproblemhasbeenresolved.
b. Internal SupportTeamupdatesstatusfor
2nd
Level Supportafterproblemhasbeen
resolved.
c. 3rd
party vendor updates status for 3rd
Level Support after problem has been
resolved.
Helpdesk,
Internal Support
Team,
3rd
Party Vendor
 IncidentReport
 IncidentManagement
Database
3. CustomerclosedallIncidentTicketsthathave
been resolved.
Customer  IncidentTicketstatus
 IncidentManagement
Database
4. Service Managerproduce MonthlyReporton
Incidents Management and submit to
Customer.
Service
Manager
 MonthlyReport
IncidentsManagement
4.1.2 Post-Delivery – Warranty Support for Preventive Maintenance
Preventive Maintenance during Warranty Support is based on agreed frequency of
maintenance supportrequiredbyCustomerduringwarrantyperiod.Itinvolvesseveralcritical
tasks to avoid operational disruption on the delivered product. As well, potential risks that
may cause disruptiontothe product operationare beingidentifiedbefore theycanbecome
operational issues. We can also consider Preventive Maintenance Support as risks
identification process on the delivered product.
During Preventive Maintenance Support, a schedule system outage will be invoked. TCS
SupportTeam will performs some critical tasksto detectpotential problemsthatmayoccur
on the delivered product.
Figure 23 shows the process flow for Preventive Maintenance Support.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 45
Figure 23 : Process flow for Warranty Support (Preventive Maintenance)
Detail processdescriptionforWarrantySupportforPreventiveMaintenance asperTable 18.
Table 18 : Warranty Support (Preventive Maintenance) Process Flow
No. Process Description Entity Output / Report /
Document
1. Service Manager performs the following:
 Prepares Preventive Maintenance
Schedule &Maintenance TasksChecklist.
 Obtain endorsement from Customer
Service
manager
 Preventive
Maintenance Schedule
 Maintenance Tasks
Checklist
2. Customer endorses the following :
 Preventive Maintenance Schedule
 Maintenance Tasks Checklist.
Customer  Preventive
Maintenance Schedule
(Sign-off)
 Maintenance Tasks
Checklist(Sign-off)
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 46
No. Process Description Entity Output / Report /
Document
3. Service Manager shares the Preventive
Maintenance Schedule with Helpdesks.
Service
Manager
 Preventive
Maintenance Schedule
 Maintenance Tasks
Checklist
4. HelpdeskConsultantraisedIncidentTicketon
Preventive Maintenance when it’s due.
 Escalation to Internal Support team
 Escalation to 3rd
party vendors
Helpdesk  IncidentTickets
 Escalationemail
a. Internal Support team perform the
Preventive Maintenance as per Tasks
Checklist and update status for tasks
completion.
b. 3rd
party vendors perform Preventive
Maintenance as per Tasks Checklist and
update status for tasks completion.
Internal Support
Team,
3rd
Party
Vendors
 Preventive
Maintenance report
5. Service Manager produce Monthly
Preventive Maintenance Report and submit
to Customer.
 Service Manager upload into Central
Repository.
Service
Manager
 Monthly Preventive
Maintenance Report
 Central Repository
Server
4.2 Post-Delivery (Client Retention Program)
It is important to ensure the existing Customer remains in TCS’s Client Database. Often,
company assumes that a successful delivered project ensures business continuity with the
Customer. At times, it is true but ensuring continuous business with the present Customer
must be solidified with a Client Retention Program.
As such, duringPost-Deliveryperiod will be the besttime to have effective ClientRetention
Program. TCS will be able to anticipate business opportunities from the business issues
emerged during Warranty Support period. Hence, Service Manager will be able to provide
inputtoClientPartnerorSalesDirectorpertainingtoopportunitythatarisewhenperforming
the Preventive Maintenance Support and the Preventive Maintenance report can be the
triggering point to initiate a business proposal to Customer.
The following Figure 24 depicts the Client Retention Program process framework for TCS’s
benefit.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 47
Figure 24 : Process framework for Client Retention Program
This program starts by Service Manager gathering information from Customer pertinent to
operational issuestheyare facingwhetherdirectlyfromTCS’sdeliveredproductorindirectly
from other business support systems. Operational system issues can be related to policy
change or maybe newrequirements raisedfrombusinessusers. Gatheringinformationfrom
Customer can be in a form of Customer Surveys.
Another source of input on business opportunities can be derived as well from the Service
Reports shared in the Central Repository. During Warranty Support, it is essential for TCS
Support Team to determine areas of opportunity that can be explored by TCS. Hence,
information compiled from Service Reports will be the basis for Client Partner or Sales
Director to develop a business proposal and submit to Customer for further decision.
The Client Retention Program process flow is shown in Figure 25.
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 48
Figure 25 : Process flow for Client Retention Program
Detail process description for Client Retention Program is shown in Table 19.
Table 19 : Client Retention Program Process Flow
No. Process Description Entity Output / Report /
Document
1. TCS Service Manager develop Customer
SatisfactionSurveyformderivedfromService
Reports in Central Repository.
 Submit to Customer the Customer
Satisfaction Survey form.
Service
Manager
 CustomerSatisfaction
Surveyform
2. Customer discusses face-to-face with TCS
Service Manager to complete the Customer
Satisfaction Survey form.
Customer,
Service
Manager
 CustomerSatisfaction
Surveyform(filled)
3. TCS Service Manager performs :
 Compile data from both sources i.e.
Service Report Central Repository and
Customer Satisfaction Survey.
Service
Manager
 BusinessOpportunity
Report
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 49
No. Process Description Entity Output / Report /
Document
 Produce Business Opportunity Report
and submit to Client Partner / Sales
Director.
4. Client Partner / Sales Director performs :
 Review Business Opportunity Report
from TCS Service Manager.
 Produce a Business Support System
Improvement proposal and submit to
Customer.
 Review the proposal with Customer and
obtain feedback.
Client Partner /
Sales Director
 BusinessSupport
SystemImprovement
Proposal
5. Customer decides to proceed :
 Request for Information (RFI) initiative.
 Request for Quotation (RFQ) initiative.
 Request for Proposal (RFP) initiative.
Customer  RFI document
 RFQ document
 RFP document
6. Client Partner / Sales Director invokes the
process of :
 RFI
 RFQ
 RFP
Client Partner /
Sales Director
 Business Proposal
documentfor(RFI,
RFQ, or RFP).
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 50
Annex A – Listing of Documents and Templates
No. Document Name Process Document Templates
1. a. StandardDocumentTemplate General
TCS-TM
Document-Template.docx
b. Certificate of Acceptance User Acceptance Sign-off
COA
TEMPLATE.docx
c. Invoice document Milestone Billing
Invoice_Template.d
ocx
d. Induction Manual General
Induction
Manual.doc
2. Requirement Traceability Matrix SOW Confirmation
Requirements
Traceability Matrix.doc
3. Project Charter Project Initiating
Project Charter.doc
4. ProjectQualityManagementPlan Project Planning
TM Project Plan -
Template.docx
5. Minutes of Meeting Project Executing
MOM_Project
Status_Template.docx
6. ProjectStatusReport Project Executing
Project Performance
Report.doc
PMO - PROJECT IMPLEMENTATION PROCESS
Ver.1.0 TCS Internal Page 51
No. Document Name Process Document Templates
7. ProjectRiskProfile Project Monitoring &
Controlling
Risk Data Sheet.doc
8. ProjectRiskRegister Project Monitoring &
Controlling
Risk Register.doc
9. ProjectIssuesForm Project Monitoring &
Controlling
Issue Log.doc
10. Change RequestForm Project Monitoring &
Controlling
Change
Request.doc
11. Change RequestLog Project Monitoring &
Controlling
Change Log.doc

Weitere ähnliche Inhalte

Was ist angesagt?

PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)Dilawar Abbas
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMOTURKI , PMP
 
PMO Charter Template
PMO Charter TemplatePMO Charter Template
PMO Charter TemplateDemand Metric
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmoErin Jones
 
Project Management Centre of Excellence
Project Management Centre of ExcellenceProject Management Centre of Excellence
Project Management Centre of ExcellenceProject Management CoE
 
Program & project management (pmo)
Program & project management (pmo)Program & project management (pmo)
Program & project management (pmo)flexibleresources
 
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesProject Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesSlideTeam
 
Roles and-responsibilities-project manager
Roles and-responsibilities-project managerRoles and-responsibilities-project manager
Roles and-responsibilities-project managerobsession56
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmocrmackenzie
 
PMO Presentation
PMO PresentationPMO Presentation
PMO PresentationTURKI , PMP
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
PMO - Added value instead of administration
PMO - Added value instead of administrationPMO - Added value instead of administration
PMO - Added value instead of administrationAndreas Splett
 
Change Management Strategy/Plan
Change Management Strategy/PlanChange Management Strategy/Plan
Change Management Strategy/Plansheliashelton
 
Project Management Office (PMO) for Management Consultants
Project Management Office (PMO) for Management ConsultantsProject Management Office (PMO) for Management Consultants
Project Management Office (PMO) for Management ConsultantsAsen Gyczew
 
Project Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation SlidesProject Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation SlidesSlideTeam
 
Discovery Workshop Template
Discovery Workshop TemplateDiscovery Workshop Template
Discovery Workshop Templatedesigner DATA
 

Was ist angesagt? (20)

PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMO
 
PMO Charter Template
PMO Charter TemplatePMO Charter Template
PMO Charter Template
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmo
 
Project Management Centre of Excellence
Project Management Centre of ExcellenceProject Management Centre of Excellence
Project Management Centre of Excellence
 
Program & project management (pmo)
Program & project management (pmo)Program & project management (pmo)
Program & project management (pmo)
 
AXELOS - MSP® - Managing Successful Programmes - Foundation
AXELOS - MSP® - Managing Successful Programmes - FoundationAXELOS - MSP® - Managing Successful Programmes - Foundation
AXELOS - MSP® - Managing Successful Programmes - Foundation
 
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation SlidesProject Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
 
Roles and-responsibilities-project manager
Roles and-responsibilities-project managerRoles and-responsibilities-project manager
Roles and-responsibilities-project manager
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
Project governance
Project governanceProject governance
Project governance
 
Building your Center of Excellence
Building your Center of ExcellenceBuilding your Center of Excellence
Building your Center of Excellence
 
PMO - Added value instead of administration
PMO - Added value instead of administrationPMO - Added value instead of administration
PMO - Added value instead of administration
 
Change Management Strategy/Plan
Change Management Strategy/PlanChange Management Strategy/Plan
Change Management Strategy/Plan
 
PMO & CMMI
PMO & CMMIPMO & CMMI
PMO & CMMI
 
Project Management Office (PMO) for Management Consultants
Project Management Office (PMO) for Management ConsultantsProject Management Office (PMO) for Management Consultants
Project Management Office (PMO) for Management Consultants
 
Project Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation SlidesProject Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation Slides
 
Discovery Workshop Template
Discovery Workshop TemplateDiscovery Workshop Template
Discovery Workshop Template
 

Andere mochten auch

Best Practices - Project Management & Implementation
Best Practices - Project Management & ImplementationBest Practices - Project Management & Implementation
Best Practices - Project Management & ImplementationSynerion North America Inc.
 
Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Processeklaksh
 
The software Implementation Process
The software Implementation ProcessThe software Implementation Process
The software Implementation Processrthompson604
 
Knowledge management using enterprise content management system
Knowledge management using enterprise content management systemKnowledge management using enterprise content management system
Knowledge management using enterprise content management systemSejal Kulkarni
 
Open Group Presentation Iterative Approach To Build An Ea For Hix Final
Open Group Presentation  Iterative Approach To Build An Ea For Hix   FinalOpen Group Presentation  Iterative Approach To Build An Ea For Hix   Final
Open Group Presentation Iterative Approach To Build An Ea For Hix Finalmdesai005
 
Quality policy statement
Quality policy statementQuality policy statement
Quality policy statementSG-S
 
Marlabs Capabilities Overview: IT Services
Marlabs Capabilities Overview: IT ServicesMarlabs Capabilities Overview: IT Services
Marlabs Capabilities Overview: IT ServicesMarlabs
 
The PMO & project stakeholder management
The PMO & project stakeholder managementThe PMO & project stakeholder management
The PMO & project stakeholder managementLouise Worsley
 
Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services Marlabs
 
Service Marketing Management - Managing Customer Satisfaction at a authorized...
Service Marketing Management - Managing Customer Satisfaction at a authorized...Service Marketing Management - Managing Customer Satisfaction at a authorized...
Service Marketing Management - Managing Customer Satisfaction at a authorized...Gopalakrishnan D
 
IT PMO (SAP) Success Story
IT PMO (SAP) Success StoryIT PMO (SAP) Success Story
IT PMO (SAP) Success Storyrlosch10
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeTheodore Van Patten, Jr.
 
Develop a Project Portfolio Management Strategy
Develop a Project Portfolio Management StrategyDevelop a Project Portfolio Management Strategy
Develop a Project Portfolio Management StrategyInfo-Tech Research Group
 
Medical Store Presentation ppt
Medical Store Presentation pptMedical Store Presentation ppt
Medical Store Presentation pptSk Habib
 

Andere mochten auch (20)

Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Best Practices - Project Management & Implementation
Best Practices - Project Management & ImplementationBest Practices - Project Management & Implementation
Best Practices - Project Management & Implementation
 
Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Process
 
The software Implementation Process
The software Implementation ProcessThe software Implementation Process
The software Implementation Process
 
Escalations for sb co.
Escalations for sb co.Escalations for sb co.
Escalations for sb co.
 
Knowledge management using enterprise content management system
Knowledge management using enterprise content management systemKnowledge management using enterprise content management system
Knowledge management using enterprise content management system
 
Project Plan
Project PlanProject Plan
Project Plan
 
Open Group Presentation Iterative Approach To Build An Ea For Hix Final
Open Group Presentation  Iterative Approach To Build An Ea For Hix   FinalOpen Group Presentation  Iterative Approach To Build An Ea For Hix   Final
Open Group Presentation Iterative Approach To Build An Ea For Hix Final
 
Quality policy statement
Quality policy statementQuality policy statement
Quality policy statement
 
Marlabs Capabilities Overview: IT Services
Marlabs Capabilities Overview: IT ServicesMarlabs Capabilities Overview: IT Services
Marlabs Capabilities Overview: IT Services
 
The PMO & project stakeholder management
The PMO & project stakeholder managementThe PMO & project stakeholder management
The PMO & project stakeholder management
 
Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services Marlabs Capabilities Overview: Application Maintenance Support Services
Marlabs Capabilities Overview: Application Maintenance Support Services
 
Rasna project report
Rasna project reportRasna project report
Rasna project report
 
Service Marketing Management - Managing Customer Satisfaction at a authorized...
Service Marketing Management - Managing Customer Satisfaction at a authorized...Service Marketing Management - Managing Customer Satisfaction at a authorized...
Service Marketing Management - Managing Customer Satisfaction at a authorized...
 
IT PMO (SAP) Success Story
IT PMO (SAP) Success StoryIT PMO (SAP) Success Story
IT PMO (SAP) Success Story
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
Develop a Project Portfolio Management Strategy
Develop a Project Portfolio Management StrategyDevelop a Project Portfolio Management Strategy
Develop a Project Portfolio Management Strategy
 
Site selection
Site selectionSite selection
Site selection
 
Medical Store Presentation ppt
Medical Store Presentation pptMedical Store Presentation ppt
Medical Store Presentation ppt
 
Ppt of medical store
Ppt of medical storePpt of medical store
Ppt of medical store
 

Ähnlich wie TCS-PMO Document V1.0 - Project Implementation

MyCiti Business Plan 2012 - City of Cape Town
MyCiti Business Plan 2012 - City of Cape TownMyCiti Business Plan 2012 - City of Cape Town
MyCiti Business Plan 2012 - City of Cape TownFanus van Straten
 
Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}
Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}
Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}Mumbai B.Sc.IT Study
 
Plc and scada report
Plc and scada reportPlc and scada report
Plc and scada reportIndira Kundu
 
Excellence in customer service award malek mohammed ghazo
Excellence in customer service award  malek mohammed ghazo Excellence in customer service award  malek mohammed ghazo
Excellence in customer service award malek mohammed ghazo Malek Ghazo
 
Plc report with project
Plc report with projectPlc report with project
Plc report with projectPriya Hada
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...Wan Yusoff Wan Mahmood
 
Plc project report
Plc project reportPlc project report
Plc project reportUmair Rashid
 
CIMA_unlocking_business_intelligence
CIMA_unlocking_business_intelligenceCIMA_unlocking_business_intelligence
CIMA_unlocking_business_intelligenceMohsin Kara, ACMA
 
170537122 study-notes
170537122 study-notes170537122 study-notes
170537122 study-noteshomeworkping8
 
01 content analytics-iw2015
01 content analytics-iw201501 content analytics-iw2015
01 content analytics-iw2015Kaizenlogcom
 
9607 guideto supplierdevelopment
9607 guideto supplierdevelopment9607 guideto supplierdevelopment
9607 guideto supplierdevelopmentSherri Dobroskay
 
It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975Kellermann Robert
 
Optimizing the Benefits of EDM and SOA Strategies Through Coordination
Optimizing the Benefits of EDM and SOA Strategies Through CoordinationOptimizing the Benefits of EDM and SOA Strategies Through Coordination
Optimizing the Benefits of EDM and SOA Strategies Through CoordinationKeith Worfolk
 
Control engineering assignment
Control engineering assignment Control engineering assignment
Control engineering assignment Abdo Ali Alsharai
 
Chat Application [Full Documentation]
Chat Application [Full Documentation]Chat Application [Full Documentation]
Chat Application [Full Documentation]Rajon
 
Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016Clint Britt
 

Ähnlich wie TCS-PMO Document V1.0 - Project Implementation (20)

MyCiti Business Plan 2012 - City of Cape Town
MyCiti Business Plan 2012 - City of Cape TownMyCiti Business Plan 2012 - City of Cape Town
MyCiti Business Plan 2012 - City of Cape Town
 
Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}
Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}
Project Management (October - 2017) [CBSGS - Paper Solution] {Mumbai University}
 
GCH 12418139 INSM025-SPRDL
GCH 12418139 INSM025-SPRDLGCH 12418139 INSM025-SPRDL
GCH 12418139 INSM025-SPRDL
 
Plc and scada report
Plc and scada reportPlc and scada report
Plc and scada report
 
Draft Deliverable : IT Cost Recovery Process Implementation Playbook
Draft Deliverable : IT Cost Recovery Process Implementation PlaybookDraft Deliverable : IT Cost Recovery Process Implementation Playbook
Draft Deliverable : IT Cost Recovery Process Implementation Playbook
 
Excellence in customer service award malek mohammed ghazo
Excellence in customer service award  malek mohammed ghazo Excellence in customer service award  malek mohammed ghazo
Excellence in customer service award malek mohammed ghazo
 
Plc report with project
Plc report with projectPlc report with project
Plc report with project
 
Us gsa (1992) value engineering program guide for design and construction -...
Us gsa (1992)   value engineering program guide for design and construction -...Us gsa (1992)   value engineering program guide for design and construction -...
Us gsa (1992) value engineering program guide for design and construction -...
 
Plc project report
Plc project reportPlc project report
Plc project report
 
CIMA_unlocking_business_intelligence
CIMA_unlocking_business_intelligenceCIMA_unlocking_business_intelligence
CIMA_unlocking_business_intelligence
 
Plc report
Plc reportPlc report
Plc report
 
170537122 study-notes
170537122 study-notes170537122 study-notes
170537122 study-notes
 
01 content analytics-iw2015
01 content analytics-iw201501 content analytics-iw2015
01 content analytics-iw2015
 
9607 guideto supplierdevelopment
9607 guideto supplierdevelopment9607 guideto supplierdevelopment
9607 guideto supplierdevelopment
 
It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975It Handbook On Mergers Acqui 130975
It Handbook On Mergers Acqui 130975
 
Report on new Business plan to set up a 7 star hotels
Report on new Business plan to set up a 7 star hotels Report on new Business plan to set up a 7 star hotels
Report on new Business plan to set up a 7 star hotels
 
Optimizing the Benefits of EDM and SOA Strategies Through Coordination
Optimizing the Benefits of EDM and SOA Strategies Through CoordinationOptimizing the Benefits of EDM and SOA Strategies Through Coordination
Optimizing the Benefits of EDM and SOA Strategies Through Coordination
 
Control engineering assignment
Control engineering assignment Control engineering assignment
Control engineering assignment
 
Chat Application [Full Documentation]
Chat Application [Full Documentation]Chat Application [Full Documentation]
Chat Application [Full Documentation]
 
Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016Clint Britt _ Six Sigma Project _ MFP_ June2016
Clint Britt _ Six Sigma Project _ MFP_ June2016
 

TCS-PMO Document V1.0 - Project Implementation

  • 1. PMO - PROJECT IMPLEMENTATION PROCESS Nov 2015 Version: 1.0 Version: 1.0
  • 2. Tata ConsultancyServicesrequiresthatall of itsemployeesadheretoastrict setof ethical guidelines (“Tata Code of Conduct” http://www.tata.com/aboutus/articles/inside.aspx?artid=NyGNnLHkaAc=). We requestyoursupportinhelpingusmaintainourCode of Conduct.Shouldyounote anyviolation, or potential violation, by a Tata employee, please promptly report it to your TCS contact or to the CEO of TCS.All reportswill be keptstrictlyconfidential andwill helpusensure acorporate culture of high standards.
  • 3. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page i Abbreviations Abbreviation Description PMO Project Management Office PM Project Manager TM Telekom Malaysia Berhad TCS TATA Consultancy Services PM Project Manager PSC Project Steering Committee AR Accounts Receivable AP Accounts Payable CRP Client Retention Program LOA Letter of Awards SWON Service Work Order Number RFQ Request for Quotation RFP Request for Proposal RFI Request for Information SoW Scope of Work MOM Minutes of Meeting WBS Work Breakdown Structure COA Certificate of Acceptance PO Purchase Order CFOA Certificate of Final Acceptance CCB Change Control Board CR Change Request SLA Service Level Agreement
  • 4. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page ii Revision History Version Revision Description Revision By and Date 1.0 Newly Created Rahmat Hashim - 03-Nov-15 Document Sign Off Document Approver Sign Off Status Sign off Date Nadeem Khan Jawahar Hussain
  • 5. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page iii Table of Contents 1. Introduction ................................................................................................................1 1.1 Roles of PMO..........................................................................................................3 1.2 PMO Processes Structure ........................................................................................3 1.2.1.Project Implementation.....................................................................................................................3 1.2.2.Pre-sales and Bidding Management..............................................................................................4 1.2.3.Departmental Management..............................................................................................................5 2. Project Implementation Process (Pre-Delivery).....................................................7 2.1 LOA Process Flow...................................................................................................7 2.2 Scope of Work (SoW) Confirmation Process .............................................................9 2.3 Contract Preparation Process................................................................................. 11 3. Project Implementation Process (Delivery) ..........................................................15 3.1 Project Management Process................................................................................. 15 3.1.1.Project Management Process – Initiating....................................................................................15 3.1.2.Project Management Process – Planning...................................................................................18 3.1.3.Project Management Process – Executing .................................................................................20 3.1.4.Project Management Process – Monitoring and Controlling (Timeline).................................22 3.1.5.Project Management Process – Monitoring and Controlling (Risks / Issues)........................25 3.1.6.Project Management Process – Monitoring and Controlling (Change Request)...................27 3.1.7.Project Management Process – Monitoring and Controlling (Quality Assurance)................30 3.1.8.Project Management Process – Closing......................................................................................33 3.2 Project Financial Management ............................................................................... 35 3.2.1.Project Financial Management Process – Accounts Receivable (AR) ...................................36 3.2.2.Project Financial Management Process – Accounts Payable (AP).........................................38 4. Project Implementation Process (Post-Delivery).................................................41 4.1 Post-Delivery (Warranty Support) ........................................................................... 41 4.1.1.Post-Delivery – Warranty Support for Corrective Maintenance...............................................42 4.1.2.Post-Delivery – Warranty Support for Preventive Maintenance...............................................44 4.2 Post-Delivery (Client Retention Program) ................................................................ 46 Annex A – Listing of Documents and Templates ........................................................50
  • 6. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page iv List of Figures Figure 1 : PMO high-level processesframework ........................................................................1 Figure 2 : Detail PMO Components and Processes.....................................................................2 Figure 3 : Detail process framework for Project Implementation ................................................4 Figure 4 : Detail process framework for Pre-Sales and Bidding Management...............................5 Figure 5 : Detail process framework for Departmental Management..........................................6 Figure 6 : Process Flowfor Letter of Awards(LOA).....................................................................7 Figure 7 : Process flow for Scope of Works (SoW) Confirmation................................................10 Figure 8 : Process flow for Contract Preparation......................................................................12 Figure 9 : Project Management Process Framework.................................................................15 Figure 10 : Process Flow for Project Initiating..........................................................................16 Figure 11 : Process flow for Project Planning...........................................................................18 Figure 12 : Process Flow for Project Executing.........................................................................20 Figure 13 : Process Flow for Monitoring and Controlling for Timeline........................................23 Figure 14 : Process Flow for Monitoring and Closing for Risks and Issues...................................25 Figure 15 : Process Flow for Monitoring & Controlling for Change Requests..............................28 Figure 16 : Process flow for Monitoring & Controlling for Quality Assurance .............................31 Figure 17 : Process Flow for Project Closing.............................................................................33 Figure 18 : Project Financial ManagementProcess Framework.................................................35 Figure 19 : Process Flow for Project Accounts Receivable.........................................................36 Figure 20 : Process flow for Project Accounts Payable..............................................................38 Figure 21 : Warranty Support Process Framework ...................................................................41 Figure 22 : Process flow for Warranty Support (Corrective Maintenance)..................................43 Figure 23 : Process flow for Warranty Support (Preventive Maintenance) .................................45 Figure 24 : Process framework for Client Retention Program....................................................47 Figure 25 : Process flow for Client Retention Program..............................................................48
  • 7. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page v List of Tables Table 1 : PMO Components and Processes................................................................................2 Table 2 : Process components and standard processes in Project Implementation ......................4 Table 3 : Process components and standard processes in Departmental Management ................6 Table 4 : LOA Process Flow.......................................................................................................7 Table 5 : Scope of Works Confirmation Process Flow ...............................................................10 Table 6 : Contract Preparation Process Flow............................................................................12 Table 7 : Project InitiatingProcess Flow ..................................................................................16 Table 8 : Project Planning Process Flow...................................................................................18 Table 9 : Project Executing Process Flow.................................................................................21 Table 10 : Monitoring & Controlling (Timeline) Process Flow....................................................23 Table 11 : Monitoring & Controlling (Risks / Issues) Process Flow .............................................26 Table 12 : Monitoring & Controlling (Change Requests) Process Flow.......................................28 Table 13 : Monitoring & Controlling (Quality Assurance) Process Flow......................................31 Table 14 : Project Closing Process Flow...................................................................................34 Table 15 : ProjectAccounts Receivable Process Flow...............................................................37 Table 16 : ProjectAccounts Payable Process flow....................................................................39 Table 17 : Warranty Support (Corrective Maintenance) Process Flow .......................................43 Table 18 : Warranty Support (Preventive Maintenance) Process Flow.......................................45 Table 19 : Client Retention ProgramProcess Flow ...................................................................48
  • 8. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 1 1. Introduction PMO is an organizational unit that centralise and coordinate the management of projects underitsdomain.Sometimesit’scalledProgrammeManagementOfficeorProgrammeOffice but most of the time it’s known as Project Management Office. The objectives for establishing PMO are:  To streamline and standardise project processes  To govern rules and procedures in project delivery  To monitor and control project delivery processes  To be the custodian of project Knowledge Base  To develop appropriate skillsets for project team  To advise High-level Management on resources allocation in regards to project As depictedin Figure 1below,there are 3componentswithinthe PMO process framework. These components are Project Implementation, Pre-Sales & Bidding Management, and Departmental Management. The detail breakdownof eachcomponentisshowninFigure 2. Figure 1 : PMO high-level processes framework
  • 9. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 2 Figure 2 : Detail PMO Components and Processes Each processesineverycomponentwillbe monitoredandcontrolledbyPMO.The mainfocus will be the ProjectImplementationasitinvolvescustomersandcompany’sfinancial benefit. As mentioned in Table 1 below, the Project Implementation covers processesin the Pre- delivery, Delivery and Post-delivery. Table 1 : PMO Components and Processes PMO Component Standard Processes Project Implementation  Pre-delivery process  Delivery process  Post-delivery process Pre-SalesandBidding Management  Customer RFI (Request for Information) process  Customer RFQ (Request for Quotation) process  Customer RFP (Request for Proposal) process Departmental Management  Resource Management  Governance and Reporting
  • 10. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 3 The stakeholdersdefinedinthe PMOprocesses framework are shownbelow.Theywill have direct impact in all processes defined within each component of the framework. − Customer − Project Manager − Project Office − Project team (i.e. Subject-Matter Expert, Team Leads, Technical Team, Documenter, QA/QC, etc.) − Client Partner − Sales Director − Head of ASEAN Delivery & Operations 1.1 Roles of PMO The roles of PMO comprises of the following:  Manage the interdependencies between projects and have view of all projects.  Provide training, guidance and mentoring to project managers.  Provides the methodology, standards, and policies to be followed by the stakeholders.  Helpgatherlessonslearned,andmakethemavailable forreference tootherprojects.  Help provide resources and standard document templates.  Provide inputtohighermanagementforcritical decisiontoproceedorterminatethe project.  Provide quantitative methods to continue improving for Project Management processes.  Establishcentralized repositoryandmanagementof sharedprojectdocumentations and unique project risks. 1.2 PMO Processes Structure As mentioned earlier, PMO processes are defined based on these critical components: − Project Implementation − Pre-sales and Bidding Management − Departmental Management 1.2.1 Project Implementation Project implementation involves standard processes in pre-delivery, delivery and post- deliveryof a project. This component is critical to project delivery as it involves delivery of business solution to customer and ensuring cash-flow to company.
  • 11. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 4 The following Figure 3, shows the process framework for Project Implementation. There are 3 componentsinProjectImplementation whichare Pre-DeliveryProcess,Delivery Process and Post Delivery Process. These components are linkedtogethertoensure effectiveprocessmanagementandcontrol. Details of standard processes for each of these components are shown in Table 2 below. Table 2 : Process components and standard processes in Project Implementation Process Component Standard Processes Pre-Delivery Process  Letter of Award (LOA) process  Scope of Work (SoW) process  Contract Preparation process DeliveryProcess  Project Management process  Project Financial Management Post Delivery Process  Warranty Support process  Client Retention Program (CRP) 1.2.2 Pre-sales and Bidding Management A projectnormallyinitiatedasa resultof businessproposal fromvendorto customer.It isa normal cycle in resolving business issues faced by the customer. There are 3 processes that commonly used by customer to engage vendor for business solution. Figure 3 : Detail process framework for Project Implementation
  • 12. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 5 As such, PMO needs to be involved in these processes to advise in term of resources capability, timeline, and potential risks. These 3 processes are: − Request for Information (RFI) − Request for Quotation (RFQ) − Request for Proposal (RFP) Normally,PMOwill worktogetherwiththe respective ClientPartnerorSalesDirectorwho’s responsible forthe respectivecustomer’saccount. The followingFigure4, showsthe process components for Pre-Sales and Bidding Management. The outputfrom each componentwill be a proposal documentto customer. Thisdocument will specifies information required by customer that include business solution proposal, deployment strategy, timeline, solution cost and benefit. 1.2.3 Departmental Management PMO will also handles the routine operation of a business unit. The administration of a business unit or departmental management will be required when managing project operation. A project is considered as businessunit since Project Manager is assignedwith a groupof resources,scope of delivery, timeline, and budget to deliver a successful project. The important components in Departmental Management are: − Resource Management − Governance and Reporting Figure 4 : Detail process framework for Pre-Sales and Bidding Management
  • 13. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 6 The following Figure 5, shows the process components for Departmental Management. PMO needs to ensure projects are delivered successfully to avoid any delay and additional cost to the project. In Governance and Reporting, internal reporting structure has been defined to monitor and control each of the project within PMO purview. In addition, Knowledge Management and Project Process Auditing are part of Governance and Reporting process component. List of processes in the Departmental Management is shown in Table 3 below. Table 3 : Process components and standard processes in Departmental Management Process Component Standard Processes Governance and Reporting  Reporting Management  Project Process Auditing  Knowledge Management Resource Management  Skills Development Program  Tasks Management  Timesheet Management  Resource Requisition and Allocation Management Figure 5 : Detail process framework for Departmental Management
  • 14. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 7 2. Project Implementation Process (Pre-Delivery) There are 3 components in Project Implementation Process. It starts with Pre-delivery Process, then continue to Delivery Process and ended with Post-deliveryProcess. We will begin with the Pre-Delivery Process components i.e. the LOA Process Flow. 2.1 LOA Process Flow Project Implementation process starts upon receiving of Letter of Awards (LOA) from the customer, in this case we’ll use Telekom Malaysia (TM) project as the model project. Normally, LOA is the initial step of engaging vendor for services with terms and conditions that need to be fulfilled by vendor prior to the acceptance of service award. In this topic, detail processes and procedures will be described together with the list of documentation needtobe producedfromthe respectiveprocesses. Figure 6depictsthe LOA process flow. Detail process description for LOA as per Table 4. Table 4 : LOA Process Flow No. Process Description Entity Output / Report / Document 1. ProcurementproducedLetterof Award(LOA) andsubmittedtothe selectedvendori.e.TCS Customer i.e. TM Letter of Award (LOA) 2. a. Scan the LOA and upload to Central Repository (i.e. Knowledge Center) TCS Client Partner / Sales Director  LOA (Scanned Copy).  Central Repository Server Figure 6 : Process Flow for Letter of Awards (LOA)
  • 15. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 8 No. Process Description Entity Output / Report / Document b. TCS Client Partner / Sales Director will conduct briefing session with Head of ASEAN Delivery & Operations, and PMO Head pertaining to LOA scope and requirements. The output of the briefing will be the Actions List or Minutes of Meeting. TCS Client Partner / Sales Director  Minutes of Meeting / Actions List 3. Head of ASEAN Delivery & Operations registerthe ServiceWorkOrderinthe system for the respective LOA received from Customer i.e. TM. Head of ASEAN Delivery & Operations  New Service Work Order No. i.e. SWON no. 4. Head of ASEAN Delivery & Operations prepares :  Supplementary documents as required by LOA.  Letter of Acceptance accepting the projectinitiative mentionedin the LOA. Head of ASEAN Delivery & Operations  Letterof Acceptance  Scope of Works  Insurance policies(i.e. Workman Compensations, Comprehensive General Liability Insurance, Professional IndemnityInsurance),  Declarationof Independency,and  IntegrityAgreement – Vendor’sDeclaration  Otherdocuments. 5. Client Partner / Sales Director submit the Letter of Acceptance and supplementary documents as required in the LOA. TCS Client Partner / Sales Director 6. Head of PMO performs the following :  Assigna ProjectManagerfor the project  Establish a Project Office for the project administrative matters.  Establish Internal Project Reporting structure. Head of Program Management Office (PMO)  Letterof Assignment to ProjectManager  Letterof Assignment to Project Administrator
  • 16. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 9 No. Process Description Entity Output / Report / Document 7. Project Manager establish Project Organization Structure. Project Manager  ProjectOrganization Structure 8. Project Manager prepares Project Resource requirements and submit to PMO. Project Manager  ProjectResource Requirementform  ProjectResourcesPlan 9. Head of PMO raises the Project Resource Requisition to Head of ASEAN Delivery and Operations for project resources. Head of Program Management Office (PMO)  ProjectResource Requisitionform 10. Head of ASEAN Delivery & Operations proceed with HR Recruitment process. Head of ASEAN Delivery & Operations  List of Resources(i.e. On-Site,Off-shore) 2.2 Scope of Work (SoW) Confirmation Process Once we sentthe Letterof Acceptance to Customer(i.e.TM), the nextactivityis to conduct projectscopes confirmation withtheCustomer.Often,aRequirementTraceabilityMatrix will be prepared by the Project Manager as term of reference in accordance to the official proposal submitted earlier. The purpose of this exercise is to baseline the high-level scope of works in regards to the businessproposal submittedearlierduringthe RFQ(RequestforQuotation)orRFP (Request for Proposal). The confirmation process is an avenue for Customer to sometime revise the initial Scope of Work in the RFQ or RFP due to requirement changes. Often,the durationof preparingthe tenderspecificationandprocessof awardingto vendormaytake more than 6 months. As such, requirements may change due to new technology or may be the requirements may not be applicable anymore. The SoW Confirmation Process is shown in Figure 7.
  • 17. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 10 Figure 7 : Process flow for Scope of Works (SoW) Confirmation Detail process description for SOW confirmation as per Table 5. Table 5 : Scope of Works Confirmation Process Flow No. Process Description Entity Output / Report / Document 1. Project Manager prepares Requirement Traceability Matrix (RTM) based on the submitted proposal. Project Manager  Requirement TraceabilityMatrix (RTM) 2. Client Partner/Sales Director conduct meeting session with Customer (i.e. TM) to baseline the high-level scope.  Decision from the meeting can be − Scope of Work revision, or − Scope of Work sign-off.  Discussion will be based on Scope of Work document from LOA and RTM document. Client Partner / Sales Director  Minutes of Meeting  Sign-off Scope of Work document a. If Customer request changes to scope, formal request will be captured in the Minutes of Meeting. Client Partner / Sales Director  Minutes of Meeting (MOM)  List of changes to SoW.
  • 18. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 11 No. Process Description Entity Output / Report / Document b. Furtherassessmentwill be donebyClient Partner / Sales Director pertinent to additional cost and other factors. 3. Scope Changesi.e.additional requirements. a. ClientPartner/SalesDirectorrequestfor other vendors additional cost to include additional requirementsfromCustomer. Client Partner / Sales Director  Email or formal letter with MOM of SoW confirmation. b. Partners / 3rd party vendor prepare Propose Cost Revision for inclusion of additional requirements into scope. Partners / 3rd Party Vendors  Propose Cost Revision letter or e-mail. c. Client Partner / Sales Director submit to Customer the propose revised Selling Price inclusive of additionalrequirements Client Partner / Sales Director  Revised Bill of Material (BOM) / Bill of Quantity (BQ)) d. Customeracceptedthe proposedrevised SellingPrice andprovide newLOA to TCS Client Partner / Sales Director. Customer (i.e. TM)  Revised LOA 4. Client Partner / Sales Director perform a. Scan relateddocumentsinto.pdf format, b. UploadintoCentral Repository all related document the Official SoW approved by Customer (i.e. TM) Client Partner / Sales Director  RevisedLOA (scanned copy)  SoW Sign-off page (scannedcopy).  SoW softcopy  Central Repository Server 2.3 Contract Preparation Process Normally, contract preparation process starts upon SOW Confirmation process. It is consideredaslegalisingthe agreementbetweenbothpartiesi.e.the CustomerandVendor. We’ve divided this process into 2 areas i.e. Main Contract and Sub-Contract agreements. A sub-contractagreementwill onlybe signed-off afterthe Main Contract is signedbetween Customerand the selectedVendori.e. TCS.The sub-contractagreementislinkedtothe Main Contract. Often, sub-contract agreement is signed betweenvendor and its partners or 3rd party vendors providing the service to the Customer. Figure 8 shows the process flow for Contract Preparation.
  • 19. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 12 Figure 8 : Process flow for Contract Preparation Detail process description for Contract Preparation as per Table 6. Table 6 : Contract Preparation Process Flow No. Process Description Entity Output / Report / Document 1. Customer provides the Agreement template to Vendor(i.e.ClientPartner/SalesDirector) for preparation. Customer  Template Agreement 2. Client Partner / Sales Director prepares draft Contract based on template agreement received from Customer.  Standard Contract Clause will be based on template agreement.  Specific Clause will be based on LOA and agreed SOW.  Include Payment Schedule as agreed. Client Partner / Sales Director  Draft Main Contract Agreement
  • 20. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 13 No. Process Description Entity Output / Report / Document 3. Customer reviews draft Main Contract agreement with Client Partner / Sales Director.  If need modification, Client Partner / SalesDirectorwill amendthe draftasper requested amendment.  If both parties agreed, then Contract Agreement will be signed-off by the Customer. Customer  Contract Agreement (withCustomer authorisedsignatures) 4. ClientPartner/SalesDirectorsubmittoHead of ASEAN Delivery & Operations for signed- off and stamping the Contract document. Client Partner / Sales Director 5. Headof ASEAN Delivery&Operationsobtains TCS authorised signatures on the Contract document and send for stamping. Head of ASEAN Delivery & Operations  Contract Agreement (withbothCustomers and TCS authorised signatures, and stamped) 6. Client Partner / Sales Director performs :  Submit stamped Contract document to Customer.  Submit a copy of Contract document to Project Manager for keeping. Client Partner / Sales Director  Contract Agreement (Stamped). 7. ProjectManagerscanthe Contractdocument & upload to Central Repository server. Project Manager  Contract Agreement (scannedcopy)  Central Repository server 8. Head of ASEAN Delivery & Operations prepares draft sub-contract agreement and submit the draft to partners / 3rd party vendors for review & sign-off. Head of ASEAN Delivery & Operations  Draft Sub-contract Agreement 9. Partners / 3rd party vendors review and sign- off the document. Partners / 3rd party vendors  Sub-Contract Agreement(with Partners/ 3rd Party vendorssignatures)
  • 21. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 14 No. Process Description Entity Output / Report / Document 10. Headof ASEAN Delivery&Operationsobtains TCS authorised signatures on the Contract document and send for stamping. Head of ASEAN Delivery & Operations  Sub-Contract Agreement(withboth Partners/3rd party vendorsandTCS authorisedsignatures, and stamped) 11. Head of ASEAN Delivery & Operations performs :  Submit stamped Sub-Contract document to Partners / 3rd Party vendors.  Submita copyof Sub-Contractdocument to Project Manager for keeping. Head of ASEAN Delivery & Operations  Sub-Contract Agreement(Stamped). 12. Project Manager scan the Sub-Contract document & upload to Central Repository server. Project Manager  Contract Agreement (scannedcopy)  Central Repository server
  • 22. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 15 3. Project Implementation Process (Delivery) As showninTable 2, there are 2 standard processes for the Delivery component. They are:  Project Management Process  Project Financial Management Both processes are linked since Project Management Process focus on delivery of end- product to Customer and Project Financial Management involves the financial aspects with regards to project cash-flows. 3.1 Project Management Process A standard methodology for Project Management divides delivery processes into 5 group processes which are: − Initiating − Planning − Executing − Monitoring and Controlling − Closing The following Figure 9, highlights the project management process framework. 3.1.1 Project Management Process – Initiating Project initiating is the commencement of project delivery. The formal project commencementorkick-offisdone toformalise the importantaspectof a projecti.e. project implementation strategy, project organization structure, project timeline, milestones, deliverables and stakeholders’ expectations. Figure 10 shows the process flow for Project Initiating Process. Figure 9 : Project Management Process Framework
  • 23. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 16 Detail process description for Project Initiating as per Table 7. Table 7 : Project Initiating Process Flow No. Process Description Entity Output / Report / Document 1. Client Partner / Sales Director organizes project kick-off session with Customer. Client Partner / Sales Director  Kick-off Slide Presentation 2. Customer performs the following:  Identify the required stakeholders to attend the project kick-off session.  Circulate calendar invite to stakeholders and TCS’sClientPartner/ Sales Director. Customer (Project Manager)  CalendarInvite 3. Project Office creates respective Project Folders in Central Repository server. Project office  ProjectFolders  Central Repository server 4. ProjectManagerrequestsfromthefollowing: Project Manager  Resource Planning document Figure 10 : Process Flow for Project Initiating
  • 24. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 17 No. Process Description Entity Output / Report / Document  Head of ASEAN Delivery& Operations to provide listof available resourcesforthe project.  Partners / 3rd Party vendors to provide theirResource Planningandthe available resources for the project. 4. Project Manager then prepares the Project Charter document and obtains endorsement from Client Partner / Sales Director. Project Manager  Draft ProjectCharter  ResourcesPlanning  High-level project timeline 5. ClientPartner/ SalesDirectorsubmitProject Charter document to Customer for sign-off. Client Partner / Sales Director  ProjectCharter document(incl. Resource Planning, High-Level project timeline) 6. Customer produce Certificate of Acceptance to accept and approve the deliveryof Project Charter document. Customer  COA for ProjectCharter  ProjectCharter document(Signed-off). 7. Project Office perform the following:  Scan Certificate of Acceptance (signed copy) for Project Charter.  Upload the scan copy of COA, and softcopy(final version) ProjectCharterto Project Folder in Central Repository server Project Office  COA for ProjectCharter (scannedcopy)  Softcopy(final version) ProjectCharter document.  Central Repository server 8. Head of ASEAN Delivery & Operations proceedthe arrangementforOff-shoreTeam that will be stationed On-site.  Accommodation, work permit, work location etc. Head of ASEAN Delivery & Operations  Official documentsfor Off-shore team.
  • 25. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 18 3.1.2 Project Management Process – Planning At thisstage,ProjectManager starts the detail planningwithall TeamLeadsand Partners or 3rd Party vendors. During the project kick-off session and acceptance of Project Charter, Customer has endorsed the high-level project timeline. Basedon the agreedmilestonesanddue date,ProjectManagerdefinesthe startdate & end date for each task from the detail timeline provided by Team Leads and Partners / 3rd Party vendors. Figure 11 shows the process flow for Planning Process. Figure 11 : Process flow for Project Planning Detail process description for Project Planning as per Table 8. Table 8 : Project Planning Process Flow No. Process Description Entity Output / Report / Document 1. Project Manager prepares WBS based on high-level milestones. Project Manager  Work Breakdown Structure list 2. TeamLeads & 3rd PartyVendorspreparesthe detail tasks GanttChartinaccordance to WBS Structure list & submit to Project Manager. Team Leads, 3rd Party Vendors  Gantt Chart on Detail Tasks
  • 26. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 19 No. Process Description Entity Output / Report / Document 3. Project Manager prepares Project Quality Plan Management document by consolidating the following :  Project Schedule  Resource Plan  Communication Plan  Change Management Plan  Quality Plan  Risk Register  Payment Milestones Project Manager  ProjectQualityPlan Management document(Draft) a. Team Leads prepares project technical document templates. b. ProjectOffice preparesprojectdocument templates Team Leads, Project Office  Technical document templates  Projectdocument templates 4. Project Manager submit Project Quality Plan Management document to Customer for acceptance sign-off. Project Manager  ProjectQualityPlan Management document(Final) 5. Customer produce Certificate of Acceptance to accept and approve the deliveryof Project Quality Plan Management document. Customer  COA for ProjectQuality PlanManagement document  ProjectQualityPlan Management document(Signed-off) 6. Project Office perform the following:  Scan Certificate of Acceptance (signed copy) for Project Quality Plan Management document.  Upload the scan copy of COA, and softcopy (final version) Project Quality Plan Management document to Project Folder in Central Repository server. Project Office  COA for ProjectQuality PlanManagement (Scancopy)  Softcopy(Final version) ProjectQualityPlan Management.  Central Repository server.
  • 27. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 20 No. Process Description Entity Output / Report / Document 7. Head of ASEAN Delivery & Operations allocatesresourcesaccordingtothe Resource Planning. Head of ASEAN Delivery & Operations 3.1.3 Project Management Process – Executing In projectexecution,ProjectManager mustmanage projectactivitiesinaccordance todetail planagreedby the stakeholdersthatincludeCustomer,ProjectTeam,andPartners/3rd Party vendors. At this stage, Project Manager needs to communicate effectively with the stakeholders. Thus, 90% of Project Manager’s effort will be on communication. Figure 12 shows the Project Executing process flow. During project execution, Project Manager prepares progress status reporting & presented to Customer and Internal PSC. Progress reporting will also include highlighting risks, issues that project team is facing and requires Customer to endorse the mitigation plan to avoid delayinprojectdelivery.ProjectManagerwillinvokethe respectiveMonitoring&Controlling procedures with regards to Risks/Issues Mitigation, Quality Assurance as well as Timeline control. Figure 12 : Process Flow for Project Executing
  • 28. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 21 Detail process description for Project Executing as per Table 9. Table 9 : Project Executing Process Flow No. Process Description Entity Output / Report / Document 1. Project Manager manages project activities according to Project Plan & Timeline & monitor tasks, risks & issues continuously. Project Manager 2. Project Team executes tasks as per planned start date.The followingtaskswill be doneby the project team:  Prepare required deliverables as per project document template.  Reportingtasksprogressstatusto Project Manager.  Highlights on risks & issues to Project Manager Project Team  Risksform  Issuesform  Timesheet  Milestonesdeliverables 3. Project Manager performs the following :  Prepare Progress Status Report and updates Customer.  Prepare Progress Status Report and updates Internal PSC.  Invoke QA Proceduresforall deliverables prepared by the Project Team  Invoke Risks Control procedures for project risks monitoring & control.  Invoke Timeline control procedures for schedule monitoring and control. Project Manager  ProjectStatusReport  RiskRegister  IssuesRegister  ProjectTimeline (Actual vs.Planned)  ProjectQuality ManagementPlan document(revised). a. Headof ASEAN Delivery&Operationswill resolves issues in regards to Inter- departments and Inter-organisations raised by Project Manager in Internal Project Status Report. Head of ASEAN Delivery & Operations  IssuesRegister
  • 29. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 22 No. Process Description Entity Output / Report / Document b. Project Office prepares the Minutes of Meeting for all project status meeting sessions with Customer. Project Office  Minutes of Meeting 4. Customer review progress status.  Approve the revised schedule, if any.  Approve risk mitigation plan, if any. Customer, Project Manager  Approval Sign-offform 5. Customer raises new requirements due to various reasons.  Project Manager invokes the Change Request Control procedures  Internal PSC reviews and endorses the additional project costs & revised timeline submitted by Project Manager.  Head of ASEAN Delivery & Operations proceed Variation Order process with Customer. Customer, Project Manager, Internal PSC  Change Requestform  Change Request Proposal  Change Request Approval  VariationOrder 6. Project Office maintains the Project Central Repository for all deliverables submitted to Customer for review and acceptance. Project Office  Scanneddocuments  Minutesof Meetings  Central Repository server 3.1.4 Project Management Process – Monitoring and Controlling (Timeline) Project Manager must monitor & control project timeline accordingly.Time is one of the componentinthe Triple Constraintsi.e.Scope,Time and Budget.Hence,propermonitoring & controlling procedures must be invoked so that Project Manager can be alerted when there’s a possibilities of slippage in the project schedule. Varioustoolscan be utilizedbyProjectManagerto detectthe slippage,especiallyinregards todetail tasksthathave dependenciesanddue date.Normally,taskdependencyisone of the tool that alwaysprovide red lighttoProjectManager wheneverapotential slippage isabout to happen. Any delay of project task that have dependency can be screened earlier through Timesheet of each teammembersince everyteammemberswill have tosubmittheirTimesheetatend of week.Basedonthe Timesheet,ProjectManagerwill be able todetermine the completion
  • 30. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 23 of each task performed by the team member whether as per planned or otherwise. Hence, Project Manager needs strategy to put project back on-track when the slippage occurs. The following Figure 13 shows the Monitoring & Controlling Process for Timeline. Figure 13 : Process Flow for Monitoring and Controlling for Timeline Detail process description for Monitoring and Controlling for Timeline as per Table 10. Table 10 : Monitoring & Controlling (Timeline) Process Flow No. Process Description Entity Output / Report / Document 1. Project Office prepares Timesheet template and circulates to Project Team members to fill-in for weekly planned tasks execution. Project Office  Timesheettemplate 2. Project Team filled in the Timesheet for weekly activities planned and actual.  Monday morning submission for plan tasks for the week. Project Team  Weekly Timesheet
  • 31. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 24 No. Process Description Entity Output / Report / Document  Friday evening submission for actual tasks progressing. 3. Project Manager reviews Weekly Timesheet with Project Team on Monday morning.  If slippage, Project Manager will cross- check with the Overall Project Plan whether impacted or otherwise.  If Overall Planimpacted,ProjectManager revises the Overall Plan and obtain endorsement from Internal PSC prior to Customer endorsement. Cost impact report will be submitted to Internal PSC for review and endorsement. Project Manager  ProjectTimeline (Actual vs.Planned)  IssuesRegister  RisksRegister  Cost impactreport 4. ProjectManagerpresentsthe RevisedProject Schedule to Customer for approval. Project Office noted the approval in Minutes of Meeting. Project Manager, Project Office  RevisedProject Schedule  Minutesof Meeting 5. Customer review and approve the revised schedule. Often, project schedule revision will be presented in Project Status Meeting. Customer  Approval on Revised ProjectSchedule 6. Project Team executes mitigation plan to bring project back on track. Project Team  IssuesRegister  ProjectSchedule 7. Internal PSC and Head of ASEAN Delivery & Operation approved on the utilisation of Contingency Reserve fund for Revised Schedule that require additional project budget. Internal PSC, Head of ASEAN Delivery & Operation  Internal Memo 8. Project Office maintains the Project Central Repository for all deliverables submitted to Customer for review and acceptance. Project Office  Scanneddocuments  Minutesof Meetings  Central Repository server
  • 32. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 25 3.1.5 Project Management Process – Monitoring and Controlling (Risks / Issues) Risks & Issues are potential elements that impact to project delivery. Monitoring and Controlling risks and issues are critical tasks that Project Manager needs to perform during project implementation. Often, frequency of risks & issues monitoring and controlling are done weekly to ensure project healthiness. Risks & issues that have been identified and resolved will be logged in each registers. Whenever identified risks emerge, Project Manager will reviews overall project timeline to assess whether any adverse impact to it. If there is impact, then Project Manager will executes mitigation plan as agreed by Customer. Sometime,mitigationplanrequiresadditionaltime tobe addedintooverall projectschedule and milestonesdue date must be revised.If thishappens,ProjectManager needsto invoke necessary procedures to obtain endorsement from Customer and Internal PSC before the mitigationplancanbe loggedinthe RisksRegister. Similarprocedureappliestoprojectissues as well. Figure 14 shows the process flow for Monitoring and Closing for Risks and Issues. Figure 14 : Process Flow for Monitoring and Closing for Risks and Issues
  • 33. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 26 Detail process description for Monitoring and Controlling for Timeline as per Table 11. Table 11 : Monitoring & Controlling (Risks / Issues) Process Flow No. Process Description Entity Output / Report / Document 1. Project Manager reviews risks and issues weekly with Project Team. ProjectOffice updatesbothregistersforrisks and issues that have been closed. Project Manager, Project Office  RisksRegister  Issues /ActionItem Register a. Project Team raises :  Risks Form when there’s a new risk identified.  IssuesFormwhenthere’sanew issue identified. Project Team  Risks/ IssuesForm 2. ProjectManagerdetermineswhetherOverall Project Schedule will be impacted by the identified risks or issues.  If impact to Overall Schedule, then the mitigation plan will be prepared for the respective risks or issues.  If Overall Planimpacted,ProjectManager revises the Overall Plan and obtain endorsement from Internal PSC prior to Customer endorsement. Cost impact report will be submitted to Internal PSC for review and endorsement.  Project Manager presents the Revised Schedule toCustomerfor approval,after endorsement of Revised Schedule from Internal PSC.  ProjectOffice willloggedinbothregisters for all newly identified risks or issues. Project Manager, Project Office  RisksRegister  Issues/ActionItem Register  Cost impactreport 3. Project Manager presents Risks and Issues registers to Customer for endorsement on mitigation plan for new risks and issues. Project Office noted the endorsement in Minutes of Meeting. Project Manager, Project Office  RisksRegister  Issues/ActionItems Register  Minutesof Meeting
  • 34. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 27 No. Process Description Entity Output / Report / Document 4. Customer reviews and approves the Mitigation Plan inclusive of Revised Project Schedule. Often, Risks/Issues Mitigation Plan will be presented in Project Status Meeting. Customer  Approval on Risks/Issues Mitigation Plan 5. Internal PSC and Head of ASEAN Delivery & Operation approved on the utilisation of Contingency Reserve fund for Risks / Issues Mitigation Plan that require additional project budget. Internal PSC, Head of ASEAN Delivery & Operation  Internal Memo 6. Project Office maintains the Project Central Repository for all deliverables submitted to Customer for review and acceptance. Project Office  Scanneddocuments  Minutesof Meetings  Central Repository server 3.1.6 Project Management Process – Monitoring and Controlling (Change Request) Often, there are new requests raised during project implementation. Sometimes, change requestsraisedbyCustomerduetopolicychange andProjectManagerneedstohandlethese new requests accordingly. Suddenchange to project tasks may impact to the whole project deliverymilestones.Hence,properchangerequestproceduremustbeinvokedbeforeallnew requests can be considered as part of project delivery commitments. The mostimportantcomponentinthe Change RequestsProcessisthe ChangeControl Board (CCB). A CCB must be formed at earlier stage so that any new requirement raised can be addressedearlierpriorto projectexecution.Thiswill easesthe pressure to ProjectManager and projectteamasnewcritical requirementscanbe includedinthe projectscheduleduring planning stage. All change requests raised by users are reviewed by CCB to determine whetherthese requestscanbe endorsedfor furtheractionsordeclined. Figure 15showsthe process flow for Monitoring and Closing for Change Request.
  • 35. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 28 Figure 15 : Process Flow for Monitoring & Controlling for Change Requests Detail processdescriptionforMonitoring&ControllingforChange RequestsasperTable 12. Table 12 : Monitoring & Controlling (Change Requests) Process Flow No. Process Description Entity Output / Report / Document 1. Customer raised new requirements during meetingsessions,workshopsessions,orUAT sessions.  Newrequirementswillbe capturedinthe standardChange Requestformandto be filled in by the Requestor. Customer  Change Requestform 2. Project Team evaluates the efforts on new requests based on duration, complexity, impact to other delivery components and number of resources required. Project Team  Timeline (fornew requests) 3. Project Office gives a unique ID for each CRs and loggedin the Change Requests register. Project Office  Change Request Register
  • 36. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 29 No. Process Description Entity Output / Report / Document 4. ProjectManagerdetermineswhetherOverall ProjectSchedule willbe impactedbythe new requirements.  If Overall Planimpacted,ProjectManager developspropose revisedOverall Project Schedule to include the new requests implementation. Project Manager  Propose Revised ProjectSchedule 5. Project Manager conducts the following for the new requirements.  Project Manager estimates the cost for the new requirements and obtain endorsement from Internal PSC prior to Customer endorsement. Cost impact report will be submitted to Internal PSC for review and endorsement.  Project Manager compiles all Change Request forms and presents to CCB for approval.  Project Office updates the Change Requests register for all CR forms submitted for CCB review and endorsement. Project Manager, Project Office  Cost impactreport  Change Request Register  CompiledChange Requestsforms. 6. Change Control Board reviews and endorses eachChange RequestinCCBMeetingsession. Change Control Board  ApprovedandRejected CR forms  Minutesof Meeting a. Project Office updates the Change RequestRegisteronall CRs(i.e.Approved and Rejected). Project Office  Change Request Register 7. Project Manager obtain sign-off from Customer on revised project schedule for implementation of the approved Change Requests. Project Manager  Propose Revised ProjectSchedule 8. Customer signed-off the Revised Project Schedule. Customer  Sign-off document.
  • 37. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 30 No. Process Description Entity Output / Report / Document a. Project Manager must update the Internal PSCand Head of ASEAN Delivery & OperationinregardstoRevisedProject Schedule. b. Project Manager informs the Project Team of the Revised Project Schedule. Project Manager  ApprovedRevised ProjectSchedule 9. Project Office maintains the Project Central Repository for all deliverables submitted to Customer for review and acceptance. Project Office  Scanneddocuments  Minutesof Meetings  Central Repository server 10. Project Team executes all approved CRs. Project Team 3.1.7 Project Management Process – Monitoring and Controlling (Quality Assurance) Quality Assurance is part of the activity to ensure all deliverables adhered to the quality standard practiced by the Customer. In Project Management process, Quality Assurance is deployed under the Monitoring and Controlling process. Quality is emphasized in every project as to ensure Customer satisfaction of the delivered product or services. The very minimum is to have all submitted deliverables complied the industry’s standard. As such, standarddocumenttemplatesneedtobe definedandsharedwiththe ProjectTeamforthem to use when preparing the deliverables. The processstarts withProjectOffice preparesthe templatesanduploadedintothe Central Repository server. Often, these defined templates are endorsed during Project Kick-off Meeting to make known to stakeholders and Project Team that consistencies in project deliverablesare important.Furthermore,itisaformof goodpractice that can be transferred to Customer as well. Types of deliverables vary as they depend on delivery scope. For example, a software development project is based on the SDLC methodology whereby the standard deliverables are; User Functional Specification, System Design Specification, User Acceptance Testing, Data Migration Specification, Training Manual, User Manual, and Hand-over Document. A part from that, there are generic documentsin Project Managementprocesses that include Project Charter, Project Quality Plan Management, Certificate of Acceptance, Risk Profile form, Change Request form, and Minutes of Meeting. Often,the ProjectManager mustwork togetherwithProjectOffice todetermine what,how and when these documents will be used. Figure 16 shows the process flow for Monitoring and Closing for Quality Assurance.
  • 38. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 31 Figure 16 : Process flow for Monitoring & Controlling for Quality Assurance Detail processdescriptionforMonitoring&Controllingfor QualityAssurance asperTable 13. Table 13 : Monitoring & Controlling (Quality Assurance) Process Flow No. Process Description Entity Output / Report / Document 1. Project Office defines standardized project document templates and uploads into Central Repository. Often, standardization of document templatesisdone at Project Initiating stage. Project Office  Documenttemplates  Central Repository server 2. Project Team prepares the document for Customer sign-off upon completion of each project milestone. Project Team  Draft Technical Documents 3. Team Lead reviews contents and endorses the document before releasing to Project Manager for approval. Project Team Lead  Draft Technical Documents 4. Project Manager reviews and approves documents for submission to Customer. Project Manager  Technical Documents
  • 39. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 32 No. Process Description Entity Output / Report / Document Often, Project Manager reviews contents in regards to delivery scope compliance and standardised document layout. 5. Customer circulates the documents to the relevant stakeholders for reviews and verifications. Often, they are :  QA/QC team, and  User team Customer  Technical Documents  Feedbackform 6. User Team and QA/QC Team reviews and verifies the documents.  QA/QC team – reviews on document’s Quality.  User team – reviews on user requirements compliance. User Team and QA/QC Team  DocumentSign-off Page (ReviewedSection)  Feedbackform a. If amendments required, User Team and QA/QC Team will list out comments in feedback form. b. Document& Feedbackformare reverted to TCS for further amendments. User Team and QA/QC Team  FeedbackForm  Technical Documents (Modificationrequired) c. Project Team modify documents as per Feedback form and repeat the internal reviewprocessas per processes 3 and 4. Project Team  RevisedTechnical Documents 7. Customer produce Certificate of Acceptance to accept and approve the deliverables. Customer  COA as per deliverable milestones 8. Project Office perform the following:  Scan Certificate of Acceptance (signed copy) for technical document deliverables.  Upload the scan copy of COA, and softcopy (final version) of technical document deliverables to Project Folder in Central Repository server. Project Office  COA technical documentdeliverables (scannedcopy)  Softcopy(final version) technical document deliverables.  Central Repository server
  • 40. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 33 No. Process Description Entity Output / Report / Document 9. Project Manager informs relevant parties in TCS for project billing process. Project Manager  Email 3.1.8 Project Management Process – Closing When project successfully completed, it shows that all delivery commitments have been deliveredtoCustomer.The endorsementinaformof COA indicatesCustomersatisfactionon quality compliances shown on all submitted deliverables. Hence, a proper project closing procedure should be commenced. Figure 17 shows the process flow for Project Closing. Often, Project Closing involves the following: − Final Acceptance process − Handing over to Operational Support Team − Starting of Warranty Support period. − Project Team disbanding. Figure 17 : Process Flow for Project Closing
  • 41. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 34 Detail process description for Project Closing as per Table 14. Table 14 : Project Closing Process Flow No. Process Description Entity Output / Report / Document 1. ProjectManager will coordinate withproject stakeholders for the Final Acceptance session.  ProjectOffice circulatescalendarinviteto all stakeholders. Project Manager, Project Office  Calendarinvite and Final Acceptance Agenda. 2. Project Team prepares technical documents for Final Acceptance & submit these documents to Customer.  Project Team performs Final Acceptance with Customer. Project Team  DocumentsforFinal Acceptance 3. CustomerperformsFinal Acceptance process and sign-off the Certificate of Final Acceptance Customer  CFOA (Signed-off) 4. Project Office performs the following:  Scan Certificate of Final Acceptance (signed copy).  Upload the scan copy of Certificate of Final Acceptance to Project Folder in Central Repository server. Project Office  CFOA (scannedcopy)  Central Repository server 5. Internal PSCestablishesthe SupportServices Team for Warranty Period. Internal PSC  SupportServices Organizationstructure a. Head of ASEAN Delivery & Operations allocatespeople forthe SupportServices during Warranty Period. Head of ASEAN Delivery & Operations  Listingof Resources withRoles& Responsibilities 6. Project Manager conduct the Handover SessionwiththeCustomerandSupportTeam for the Warranty Support.  Project Team disbanded  Warranty Period commences Project Manager, Project Office  Handoverdocument  ProjectFile Folder
  • 42. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 35 No. Process Description Entity Output / Report / Document 7. Head of ASEAN Delivery & Operations invoked the Final Billing process. Head of ASEAN Delivery & Operations  Final Billing 3.2 Project Financial Management Often,projectfinancial managementinvolvesmanagingthe monetaryaspectof a project.It involves managing Accounts Receivable (AR) and Accounts Payable (AP) with regards to project.ProjectManagerneedstokeeptrackof project billings/collectionsas wellas3rd party vendor billings and payments. Figure 18 showsthe processframeworkforbothAccountsReceivable andAccountsPayable. Figure 18 : Project Financial Management Process Framework This process framework applies to both processes: − Customer’s Invoicing, and − Billings from Partners / 3rd party vendors. In general, the framework shows the sequence of processes that need to be completed before proceedingtothe nextstage.Invoicingandbillingprocessescanproceeduponsigning of contract betweenbothparties,asmentionedearlierinthe ContractPreparationProcess. Often,paymentmilestonesare settotriggerthe invoicingandbillingprocesses. Forexample, the payment schedule between Customer and TCS, is formalisedin Contract and become Customer’s commitment to pay TCS upon completion of each milestone. Pre-requisite documentsneedtobe submittedtogetherwiththe invoice toensure paymentcanbe made to TCS. Hence, Project Manager needs to be aware of these pre-requisite documents.
  • 43. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 36 For example, the following pre-requisite documents are required when invoicing TM: − TM’s Purchase Order (PO) − COA (Certificate of Acceptance) − TCS’s Invoice Once these documentsare prepared,TCS’s ProjectManagermustobtainsign-off onCOA and TCS’s Invoice from the respective TM Project Manager before proceeding to upload the scanned copies of these documents into TM’s Portal. Often, uploading these documents is done by TCS Client Partner or Sales Director since they have the User Login to TM’s Portal. 3.2.1 Project Financial Management Process – Accounts Receivable (AR) Project cash-flow is important in every project since resources costs are budgeted in the project.ItisimportantforProjectManagertokeeptrack onprojectinvoicingandcollections. Hence,astandardtool totrack ProjectCash-flowneedtobe usedasithelpsProjectManager to determine due date for invoicing process. Often,invoicingCustomerisbasedonthe paymentscheduleagreedinthe Contract. Relevant documents to be submitted together with invoice are stated in the Contract as well. The Accounts Receivable process is shown in Figure 19. Figure 19 : Process Flow for Project Accounts Receivable Detail process description for Project Accounts Receivable as per Table 15.
  • 44. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 37 Table 15 : Project Accounts Receivable Process Flow No. Process Description Entity Output / Report / Document 1. Client Partner/Sales Director starts with signingof Contract for the project initiative. Client Partner / Sales Director  Contract 2. Project Manager prepares the Billing / Collection Milestones Tracking sheet based on Payment Schedule in Contract.  Project Manager shares the Billing/Collection Milestones tracking sheet with Head of ASEAN Delivery & Operations Project Manager  Project Billing/Collection MilestonesTracking sheet 3. Customerprepares POafterContract signed- off. Customer  Purchase Order 4. ProjectOffice preparesCOA upon completion of delivery milestone. Project Office  COA 5. Project Manager informs Head of ASEAN Delivery & Operations to prepare Invoice based on payment schedule. Project Manager  Email a. Head of ASEAN Delivery & Operations prepares Invoice and revert the Invoice document to Project Manager for Customer sign-off. Head of ASEAN Delivery & Operations  Invoice b. ProjectManager submit COA and Invoice document to Customer for sign-off together with relevant PO. Project Manager  Compileddocuments (i.e.Invoice,COA,PO) 6. Customer’s PM sign-off Invoice and COA, then revert to Client Partner / Sales Director for submission to Customer’s Finance. Customer Project Manager  Invoice (Signed-off)  COA (Signed-off) 7. Client Partner / Sales Director submit to Customer Finance all documents (Invoice, COA and PO) for payment process. In TM, documentsubmissionis viaTMPortal. Client Partner / Sales Director  Scanneddocuments (i.e.Invoice,COA,PO)
  • 45. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 38 No. Process Description Entity Output / Report / Document 8. Project Office updates relevant information in the Billing/Collections Milestones tracking sheet. Project Office  Billing/Collection Milestonestracking sheet 9. Project Office upload to Central Repository the scanned copies of Invoice, COA and PO. Project Office  Scanneddocuments (i.e.COA,Invoice,PO)  Central Repository server. 3.2.2 Project Financial Management Process – Accounts Payable (AP) Often, cash-flow management also involves processing payments to 3rd party vendors or Partners. The process flow is similar to Accounts Receivable except that TCS will be the paymaster. All projectpaymentsto3rd partyvendorsor Partnersshouldbe basedon agreed payment terms and schedule. Normally, the agreement between TCS and 3rd party vendors is signed under sub-contract agreement. Hence, payment terms will always be ‘back-to-back’ i.e. TCS pays 3rd party vendorsafterpaymentmade by the Customer.Pre-requisite documenttoprocesspayment mustbe submittedtogetherwithvendor’sinvoice andthese documentwill be basedonTCS internal procedure. The Accounts Payable process is shown in Figure 20. Figure 20 : Process flow for Project Accounts Payable
  • 46. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 39 Detail process description for Project Accounts Payable as per Table 16. Table 16 : Project Accounts Payable Process flow No. Process Description Entity Output / Report / Document 1. Head of ASEAN Delivery & Operations starts with signing of Sub-Contract agreement for the project initiative. Head of ASEAN Delivery & Operations  Sub-Contract Agreement 2. Project Manager prepares the Payment MilestonesTrackingsheetbasedonPayment Schedule in Sub-Contract.  Project Manager shares the Payment Milestones tracking sheet with Head of ASEAN Delivery & Operations Project Manager  ProjectPayment MilestonesTracking sheet 3. Partners / 3rd Party Vendors delivers tasks as per milestone.  Partners / 3rd Party Vendors obtains endorsement from TCS Project Manager Partners / 3rd party vendors  Milestone deliverables 4. TCS Project Manager endorses the delivery milestone completion. Project Manager  DeliverablesSign-off a. Client Partner / Sales Director produce and sign-off the Delivery Acceptance form & submit to 3rd party vendors / partners. Client Partner / Sales Director  DeliveryAcceptance form(signed) 5. Partners/ 3rd partyVendorssubmitinvoice & relevant documents as per Payment Schedule. Partners / 3rd party vendors  Invoice  Supportingdocuments a. TCS Project Manager instruct Head of ASEAN Delivery & Operations to process paymentfor3rd party vendors/Partners. b. Project Office updates the Payment Milestone tracking sheet. Project Manager, Project Office  Email  Invoice  Supportingdocuments  ProjectPayment MilestonesTracking sheet
  • 47. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 40 No. Process Description Entity Output / Report / Document 6. Head of ASEAN Delivery & Operations proceed with payment process to 3rd Party Vendors / Partners. Head of ASEAN Delivery & Operations  PaymentAdvice 9. Project Office upload to Central Repository the scanned copies of Invoice, and Delivery Acceptance form. Project Office  Scanneddocuments (i.e.Invoice,Delivery Acceptance form)  Central Repository server.
  • 48. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 41 4. Project Implementation Process (Post-Delivery) Post-delivery commences upon project closing. It has 2 components: − Warranty Support Process − Client Retention Program Usually,Warranty Supportcovers Corrective Maintenance ondeliveredproduct.Sometime, italsocoversPreventive Maintenancedependingonterms&conditionsagreedbetweenTCS andCustomer. The WarrantySupportperiodcanbe 6months,12months,oreven24months. Often,retainingthe existingCustomerisa challengetocompany.Therefore,ClientRetention Program should starts immediately i.e. during Post-Delivery. At this stage i.e. Post-Delivery, TCS Support Team can identify room for improvement on areas that were not in previous deliveryproject.Aswell,gapsorweaknessesdiscovered duringPreventiveMaintenancecan triggered business opportunities for TCS to propose ultimate solution. Hence,proper Client RetentionProgramshouldbedevelopedtoensurecontinuousbusinessventure betweenTCS and the Customer. 4.1 Post-Delivery (Warranty Support) As mentioned earlier, Warranty Support is part of delivery that TCS needs to provide after project completion. We are aware that during project closing, the Project Team has been disbanded.Duringproject,all issueswere beingattendedbytheassignedteaminthe project. But once project has been closed, the responsibility to service the Customer has shifted to the Support Team for the duration agreed in the Contract. As mentioned earlier, Warranty Support Service covers Corrective Maintenance and Preventive Maintenance. Figure 21 shows the Warranty Support process framework. Figure 21 : Warranty Support Process Framework
  • 49. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 42 Critical component in Warranty Support Services is the SLA (Service Level Agreement) management. CustomerexpectingTCStoresponse fastwhenproblemsare loggedin.Often, the response timetoproblemresolutiondependsonseverityof aproblemandeachproblem will be classifiedintoCritical,Major,MediumandLow.Basedontheseclassifications, the SLA will be determined.Often,all critical issueswill needfastresponsesfromTCSSupportTeam and these issues to be resolved within agreed duration since critical issues will disrupt the daily operations. Apart from SLA Management, there is Preventive Maintenance that TCS must perform for Customer. Normally, frequency for Preventive Maintenance is set as Yearly, Half-Yearly,or Quarterly. The reason for Preventive Maintenance is to identify potential problems before they emerge. As such, risks of operational disruption can be avoided. In general, TCS Helpdesks will escalate all problems logged by Customer based on severity classification.Routingproblem ticketswithSLA tothe respective SupportTeamwill be done via Helpdesks system. Hence, status of each ticket can be tracked and report can be generateddaily,monthlyaswell asyearly.Furthermore,analysisreportonperformancecan be produced to Customer as evidence of Warranty Support being done in accordance to contract. OnPreventiveMaintenanceSupport,schedule forPreventiveMaintenanceissharedwithTCS Helpdesks byTCS Service Manager. A ticketon Preventive Maintenance will be escalatedto TCS SupportTeamas preventivesupporttasks.Listof taskswillneedtobe performedduring Preventive Maintenance support and once completed, the TCS Support Team obtains endorsement from Customer for work done. 4.1.1 Post-Delivery – Warranty Support for Corrective Maintenance Warranty Support for Corrective Maintenance involves activities of resolving Customer’s operational problems of the delivered product. These problems will be raised as incident tickets via TCS Helpdesks. The severity of every problems will be determined based on the impactof the problemtooperation.Eachticketwillhave the SLA thatneedstobe fulfilledby TCS Support Team. Otherwise, TCS will be considered as non-compliance to Contract and having risks of being litigated. Figure 22 shows the process flow for Corrective Maintenance.
  • 50. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 43 Figure 22 : Process flow for Warranty Support (Corrective Maintenance) Detail processdescriptionforWarrantySupportfor Corrective MaintenanceasperTable 17. Table 17 : Warranty Support (Corrective Maintenance) Process Flow No. Process Description Entity Output / Report / Document 1. Customer logged in incident to obtain Incident Ticket via :  Helpdesks Hotline no.  Website Portal. Customer  IncidentTicket 2. HelpdesksSupportConsultantwill accessthe Incident tickets and performs the following based on severity:  Resolve issue at 1st Level Support  Escalation to the 2nd Level Support Helpdesk  IncidentTicket  Escalationemail  IncidentManagement Database
  • 51. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 44 No. Process Description Entity Output / Report / Document  Escalation to the 3rd Level Support a. Helpdesks updates status for 1st Level Supportafterproblemhasbeenresolved. b. Internal SupportTeamupdatesstatusfor 2nd Level Supportafterproblemhasbeen resolved. c. 3rd party vendor updates status for 3rd Level Support after problem has been resolved. Helpdesk, Internal Support Team, 3rd Party Vendor  IncidentReport  IncidentManagement Database 3. CustomerclosedallIncidentTicketsthathave been resolved. Customer  IncidentTicketstatus  IncidentManagement Database 4. Service Managerproduce MonthlyReporton Incidents Management and submit to Customer. Service Manager  MonthlyReport IncidentsManagement 4.1.2 Post-Delivery – Warranty Support for Preventive Maintenance Preventive Maintenance during Warranty Support is based on agreed frequency of maintenance supportrequiredbyCustomerduringwarrantyperiod.Itinvolvesseveralcritical tasks to avoid operational disruption on the delivered product. As well, potential risks that may cause disruptiontothe product operationare beingidentifiedbefore theycanbecome operational issues. We can also consider Preventive Maintenance Support as risks identification process on the delivered product. During Preventive Maintenance Support, a schedule system outage will be invoked. TCS SupportTeam will performs some critical tasksto detectpotential problemsthatmayoccur on the delivered product. Figure 23 shows the process flow for Preventive Maintenance Support.
  • 52. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 45 Figure 23 : Process flow for Warranty Support (Preventive Maintenance) Detail processdescriptionforWarrantySupportforPreventiveMaintenance asperTable 18. Table 18 : Warranty Support (Preventive Maintenance) Process Flow No. Process Description Entity Output / Report / Document 1. Service Manager performs the following:  Prepares Preventive Maintenance Schedule &Maintenance TasksChecklist.  Obtain endorsement from Customer Service manager  Preventive Maintenance Schedule  Maintenance Tasks Checklist 2. Customer endorses the following :  Preventive Maintenance Schedule  Maintenance Tasks Checklist. Customer  Preventive Maintenance Schedule (Sign-off)  Maintenance Tasks Checklist(Sign-off)
  • 53. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 46 No. Process Description Entity Output / Report / Document 3. Service Manager shares the Preventive Maintenance Schedule with Helpdesks. Service Manager  Preventive Maintenance Schedule  Maintenance Tasks Checklist 4. HelpdeskConsultantraisedIncidentTicketon Preventive Maintenance when it’s due.  Escalation to Internal Support team  Escalation to 3rd party vendors Helpdesk  IncidentTickets  Escalationemail a. Internal Support team perform the Preventive Maintenance as per Tasks Checklist and update status for tasks completion. b. 3rd party vendors perform Preventive Maintenance as per Tasks Checklist and update status for tasks completion. Internal Support Team, 3rd Party Vendors  Preventive Maintenance report 5. Service Manager produce Monthly Preventive Maintenance Report and submit to Customer.  Service Manager upload into Central Repository. Service Manager  Monthly Preventive Maintenance Report  Central Repository Server 4.2 Post-Delivery (Client Retention Program) It is important to ensure the existing Customer remains in TCS’s Client Database. Often, company assumes that a successful delivered project ensures business continuity with the Customer. At times, it is true but ensuring continuous business with the present Customer must be solidified with a Client Retention Program. As such, duringPost-Deliveryperiod will be the besttime to have effective ClientRetention Program. TCS will be able to anticipate business opportunities from the business issues emerged during Warranty Support period. Hence, Service Manager will be able to provide inputtoClientPartnerorSalesDirectorpertainingtoopportunitythatarisewhenperforming the Preventive Maintenance Support and the Preventive Maintenance report can be the triggering point to initiate a business proposal to Customer. The following Figure 24 depicts the Client Retention Program process framework for TCS’s benefit.
  • 54. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 47 Figure 24 : Process framework for Client Retention Program This program starts by Service Manager gathering information from Customer pertinent to operational issuestheyare facingwhetherdirectlyfromTCS’sdeliveredproductorindirectly from other business support systems. Operational system issues can be related to policy change or maybe newrequirements raisedfrombusinessusers. Gatheringinformationfrom Customer can be in a form of Customer Surveys. Another source of input on business opportunities can be derived as well from the Service Reports shared in the Central Repository. During Warranty Support, it is essential for TCS Support Team to determine areas of opportunity that can be explored by TCS. Hence, information compiled from Service Reports will be the basis for Client Partner or Sales Director to develop a business proposal and submit to Customer for further decision. The Client Retention Program process flow is shown in Figure 25.
  • 55. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 48 Figure 25 : Process flow for Client Retention Program Detail process description for Client Retention Program is shown in Table 19. Table 19 : Client Retention Program Process Flow No. Process Description Entity Output / Report / Document 1. TCS Service Manager develop Customer SatisfactionSurveyformderivedfromService Reports in Central Repository.  Submit to Customer the Customer Satisfaction Survey form. Service Manager  CustomerSatisfaction Surveyform 2. Customer discusses face-to-face with TCS Service Manager to complete the Customer Satisfaction Survey form. Customer, Service Manager  CustomerSatisfaction Surveyform(filled) 3. TCS Service Manager performs :  Compile data from both sources i.e. Service Report Central Repository and Customer Satisfaction Survey. Service Manager  BusinessOpportunity Report
  • 56. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 49 No. Process Description Entity Output / Report / Document  Produce Business Opportunity Report and submit to Client Partner / Sales Director. 4. Client Partner / Sales Director performs :  Review Business Opportunity Report from TCS Service Manager.  Produce a Business Support System Improvement proposal and submit to Customer.  Review the proposal with Customer and obtain feedback. Client Partner / Sales Director  BusinessSupport SystemImprovement Proposal 5. Customer decides to proceed :  Request for Information (RFI) initiative.  Request for Quotation (RFQ) initiative.  Request for Proposal (RFP) initiative. Customer  RFI document  RFQ document  RFP document 6. Client Partner / Sales Director invokes the process of :  RFI  RFQ  RFP Client Partner / Sales Director  Business Proposal documentfor(RFI, RFQ, or RFP).
  • 57. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 50 Annex A – Listing of Documents and Templates No. Document Name Process Document Templates 1. a. StandardDocumentTemplate General TCS-TM Document-Template.docx b. Certificate of Acceptance User Acceptance Sign-off COA TEMPLATE.docx c. Invoice document Milestone Billing Invoice_Template.d ocx d. Induction Manual General Induction Manual.doc 2. Requirement Traceability Matrix SOW Confirmation Requirements Traceability Matrix.doc 3. Project Charter Project Initiating Project Charter.doc 4. ProjectQualityManagementPlan Project Planning TM Project Plan - Template.docx 5. Minutes of Meeting Project Executing MOM_Project Status_Template.docx 6. ProjectStatusReport Project Executing Project Performance Report.doc
  • 58. PMO - PROJECT IMPLEMENTATION PROCESS Ver.1.0 TCS Internal Page 51 No. Document Name Process Document Templates 7. ProjectRiskProfile Project Monitoring & Controlling Risk Data Sheet.doc 8. ProjectRiskRegister Project Monitoring & Controlling Risk Register.doc 9. ProjectIssuesForm Project Monitoring & Controlling Issue Log.doc 10. Change RequestForm Project Monitoring & Controlling Change Request.doc 11. Change RequestLog Project Monitoring & Controlling Change Log.doc