SlideShare ist ein Scribd-Unternehmen logo
1 von 18
Downloaden Sie, um offline zu lesen
PROJECT MANAGEMENT




                Sydney Opera House
            Risk Management case study




By KHALED EID
Sydney opera case study analysis



1. Introduction

Risk management is one of the most critical project management practices, to ensure a
project be successfully completed Risk management is thus in direct relation to the
successful project completion. Project management literature describes a detailed and
widely accepted risk management process, which constructed from four iterative phases
known as risk management plan
            Risk identification
            Risk estimation
            Risk response
            Planning and execution

Risk Identification
In this stage, we identify and name the risks, there are different sorts of risks and we need
to decide on a project by project basis what to do with each type.

Risk Quantification
Risk need to be quantified in two dimensions. The impact of the risk needs to be
assessed. The probability of the risk occurring needs to be assessed. For simplicity, rate
each on a 1 to 4 scale. The larger the number, the larger the impact or probability. By
using a matrix, a priority can be established.




                        Fig 1 quantification scale matrix (Ref. 11)



Risk Response
There are four actions you can do about a risk. The strategies are:
    Avoid the risk. Do something to remove it. Use another supplier for example.



©Copywright to Steelnz ltd Email steelnz@gmail.com                                         1
Sydney opera case study analysis
      Deflect the risk. Make someone else responsible. Perhaps contracting out or
       insurance against (damage , liability, personnel liability etc)

      Mitigate the risk. Take actions to lessen the impact or chance of the risk
       occurring. If the risk relates to availability of resources, draw up an agreement
       and get sign-off for the resource to be available.
      Accept the risk. The risk might be so small the effort to do anything is not
       worthwhile or a contingency plan may be developed to deal with possible effects.

Risk Control
The final step is to continually monitor risks to identify any change in the status, or if
they turn into an issue. It is best to hold regular risk reviews to identify actions
outstanding, risk probability and impact, remove risks that have passed, and identify new
risks.


1.1 Risk management and construction
The construction industry is subjected to more risk and uncertainty than many other
industries. The process of taking a project from initial investment appraisal to completion
and into use is complex, generally bespoke, and entails time-consuming design and
production processes. It requires a multitude of people with different skills and interests
and the co-ordination of a wide range of disparate, yet interrelated, activities. Such
complexity is further compounded by many uncontrollable external factors (Flanagan and
Norman, 1983). The construction industry has a poor reputation in coping with risks,
many projects failing to meet deadlines and cost targets. Clients, contractors, the public
and others have suffered as a result (Edwards 1995). This study will focus on applying
project risk management strategies on construction of Sydney opera house which is a
well-known case for cost overrun.

1.2 The aim of the study
The aim of this study is not to reduce the great achievement of construction such a
complicated building that changed the face of the city but looking form management
point of view to
    Identify and quantify the project risks that been overlooked.
    Highlight the dangers associated with using poor estimate.


1.3 About the Sydney Opera House
      The owner :State government of New South Wales
      Architect :Jorn Utzon
      Engineer: Ove Arup & Parteners
      Cost: $102 million




©Copywright to Steelnz ltd Email steelnz@gmail.com                                       2
Sydney opera case study analysis
The Sydney Opera House is the busiest performing arts centre in the world. Since its
opening in 1973, it has brought countless hours of entertainment to millions of people
and has continued to attract the best in world class talent year after year.



1.4 About the Building

There are nearly 1000 rooms in the Opera House including the five main auditoria. There
is also a Reception Hall, five rehearsal studios, four restaurants, six theatre bars,
extensive foyer and lounge areas, sixty dressing rooms and suites, library, an artists'
lounge and canteen known as the "Green Room", administrative offices and extensive
plant and machinery areas. The building covers about 1.8 hectares (4.5 acres) of its 2.2
hectare (5.5 acre) site. It has about 4.5 hectares (11 acres) of usable floor space. It is
approximately 185 m (611 ft) long and 120m (380 ft) wide at its widest point. The
highest roof vault (above the Concert Hall) is 67m (221 ft) above sea level.

The roofs are made up of 2,194 pre-cast concrete sections. These sections weigh up to
15.5 tones (15 tons) each. They are held together by 350 km (217 miles) of tensioned
steel cable. The roofs weigh 27,230 tones and are covered with exactly 1,056,056
Swedish ceramic tiles arranged in 4,253 pre-cast lids.

The entire building weighs 161,000 tones. It is supported on 580 concrete piers sunk up
to 25 m (82 ft) below sea level. The roofs are supported on 32 concrete columns up to 2.5
m (8 ft) square. The exterior and interior walls, stairs and floors are faced with pink
aggregate granite which was quarried at Tarana in New South Wales. The two woods
used extensively to decorate the interiors are brush box and white birch plywood which
were both cut in northern NSW. There are 6,225 sq m (67,000 sq ft) of glass, made in
France, in the mouths of the roofs and other areas of the building. It is in two layers - one
plain and the other demi-topaz tinted. About 2,000 panes in 700 sizes were installed.

There are 645 km (400 miles) of electrical cable. 120 distribution boards regulate the
power supply, equivalent to the needs of a town of 25,000 people. Twenty-six air-
conditioning plant rooms move more than 28,500 cubic meters (1,000,000 cubic feet) of
air per minute through 19.5 km (12 miles) of ducting.




©Copywright to Steelnz ltd Email steelnz@gmail.com                                          3
Sydney opera case study analysis




                         Fig 2 Sydney opera house (Ref. 6)




                Fig 3 Sydney opera house during construction (Ref. 7)




©Copywright to Steelnz ltd Email steelnz@gmail.com                               4
Sydney opera case study analysis




                     Fig 4 Sydney opera house shells (Ref. 7)




                     Fig 4 Sydney opera house shells (Ref. 7)


©Copywright to Steelnz ltd Email steelnz@gmail.com                              5
Sydney opera case study analysis



1.5 Design Stage
The original concept for the project was a sketch submitted by Danish architect , Jorn
Utzon .Judges selected it from an international open competition that ended with 233
entries from 11 countries. Thought happy to win the competition Utzon was mildly
shocked .although his concept had caught the attention of the judges, it consisted only if
simple sketches with no plans or even perspective drawings , because the design was so
unique , some people presumed it would also be inexpensive to build. No one knew how
it would be build , and some experts questioned that it could be built at all.

In spite all uncertainty , the initial project cost estimate was pit at $7million.The
government would use profits from a series of state run lotteries to pay the project.
The government was worried that the people scrutinizing the design might raise question
about the potential problems hat would stall the project they thus quickly mover ahead
and divided the work into three main contracts :the foundation and the building except
the roof, the roof, and the interior and equipment.

1.6 Construction stage
Many of the world’s best-known construction companies were involved in building
Sydney Opera House including Arups Structural Engineering, Hornibrook and Rider
Hunt, the construction work of S.O.H was divided into three distinct stages as follows
(Ref. 19)
 Stage I
Sub structure , concrete structure from the foundation up to the auditoria seating levels
excluding any finishes.
 Stage II
Superstructure or shells , concrete roof vaults or major and minor halls an restaurants ,
including the claddings.
 Stage III
Everything not included in stages I and II , stage towers, all interior finishes, exterior
paving and cladding, glass walls , all electrical and mechanical services.

After he was elected premier of New South Wales in 1965, Askin attempted to force
Utzon reduce costs by withholding payments. In 1966 Utzon resigned and returned to his
native Denmark. He never even returned to see his masterpiece completed.
The construction of the Sydney Opera House was now handed over to a group or
Australian architects. Fortunately, the exterior had already been completed by then so that
the impact of the altered design on the overall structure was minimal. The project was
finally completed in 1973 after a construction period of 14 years and an expenditure of
over $A100 million, almost 15 times the estimated budget.




©Copywright to Steelnz ltd Email steelnz@gmail.com                                           6
Sydney opera case study analysis
2. Risk management strategies at S.O.H

2.1 Financial
Despite of all cost escalation , taxpayer had little to pay .Virtually all the costs were
covered by the proceeds of State Lotteries. The continued need to the subside the running
costs of the opera house were financed by the continuation of the Lottery State. The first
estimate for the Sydney Opera House was $7.2 million in Australian dollars. Once
started, however, costs kept rising and just to complete the building cost $102 million.

2.2 Political
Political risks are often occur in government project as they often hide information
affecting the community's support, which in turn affect the effectiveness of the feasibility
study . S.O.H we mostly severely effect by political decisions

2.2.1 Media and public deception
In S.O.H. the original budget of seven million Australian dollars was not a real but a
political budget .The labour government of New South Wales the main proponent of the
S.O.H, wanted the project started before elections in March 1959-this would reduce the
risk of the stopping the project in case Labour lost the elections (8).


2.2.2 Deceptive cost estimate
Kim Utzon explains in lieu of his father "It was a political decision to publicize a low
budget for the building, which was expected to gain approval in the political system, but
which very quickly was exceeded. So even if the cost overrun turned to be 1400% in
relation to the publicized budget, this budget was an eight of the real budget of the
building .So the real overrun is only 100% the rest was politics".


2.2.3 Political construction date
The start of construction for stage I was fixed ., largely for political reasons , as the 2nd
March 1959.Thus Proceeding with construction before completing the design process
which is a great risk .

2.2.4 Political design changes
On 1966 major hall was changed from dual purpose for concert and opera to a single
purpose concert hall, the dual purpose was a requirement of the competition .




©Copywright to Steelnz ltd Email steelnz@gmail.com                                              7
Sydney opera case study analysis


2.3 Structural

2.3.1 The Supporting points
Arup and his engineers knew very well that the cross-section shape Utzon chose was far
from ideal known structures, however they could not suggest changing to the shape as it
will alter the appearance of the roof drastically.

2.3.2 The roof
A question should be asked if this design is achievable?. The competition judges choose a
complex art design without asking how it will be deigned? later on it was a major cause
for delaying the roof design if this point was been considered they should either choose
a simple shape or a known geometry, at this stage computer program analysis was not
yet been introduced that means only manual process can be used to calculate the forces
acting on the structure.

2.3.3 Lack of suitable boundary condition.
Another technical problem that the engineer had to solve was the lack of boundary
condition that leads to some earthwork as sub base for the structure foundation.

2.4 Technical
Utzon, ware of possible technical problems since his design required advanced
technology not yet available, requested additional time to tackle those challenges Utzon
faced the task of converting the concept into a design form which a structure could be
built, but he had no prior experience in the design and construction of such a large
building. Because of this lack of plans, detailed design drawings, and estimates of
materials, little existed from which cost could be determined.

2.4.1 Design errors and omissions
   Unfortunately, the roof shells were too heavy for the supporting columns that were
    already built, so these were demolished and rebuilt. These and several other setbacks
    led to delays and increasing cost overruns.
   The original design called for two theatres. The government changed its mind and
    required the building to be altered and that four theatres now be incorporated into the
    design
   The foundation been demolished to suit the new roof design loads.

2.4.2 Fitness for purpose.
   The main design overlooked acoustic requirements which is the main purpose of the
    building and had to be altered at later stage.
   The Running costs for S.O.H proved expensive , it was a very labour intensive
    building .In 1974 , it operation cost was $A6M, of which only $A2M was covered by




©Copywright to Steelnz ltd Email steelnz@gmail.com                                        8
Sydney opera case study analysis
   the revenue. Thus costs ruled out small scale opera and the Australian Opera were
   forced to seek a cheaper venue.

2.5 Construction
Engineers who revised the concept noted that the roof shells were much larger and wider
than any shells seen so far. Further, because they stuck up so height, they would act like
sails in strong winds blowing up the harbour. Thus, the roof would have to be carefully
designed and constructed to resist such wind pressure.
The construction was estimated to take about five years at a cost of A$7 million. Ignoring
his request, the government pressured Utzon into starting construction in 1959, two years
ahead of the architect's proposed schedule.
 The lack of preparation soon backfired. After the completion of the grand podium
    with an enormous, 86 meter (282ft) wide stair, several years were spent reworking the
    design of the roof.
 Three tower cranes imported from France for this job costing $100,000 each and it
    was the first building constructed in Australia using tower cranes.
 Unfortunately the roof shells were too heavy for the supporting columns that were
    already built, so these were demolished and rebuilt.


2.6 What goes wrong Consequences?
 Coast overrun 1300% (Ref. 18)
 As feared many experts the project become an engineering financial debacle, lasting 15
years and costing $107 million ($100 million over the initial estimate).
 Schedule overrun 250% (Ref. 18)
 Media and public scandal


                            ESTIMATES AND EXPENDITURE 1957-1973

                   $120.0
        Millions




                   $100.0

                    $80.0

                    $60.0

                    $40.0

                    $20.0

                     $0.0
                      1/0/1900 1/2/1900 1/4/1900 1/6/1900 1/8/1900 1/10/1900 1/12/1900

                                     Fig 5 Time /cost Escalation




©Copywright to Steelnz ltd Email steelnz@gmail.com                                        9
Sydney opera case study analysis

       Management conflict occur between the client and the architect that cause him to
        resign before the end of stage III .


3. Risk identification quantification

3.1 Identification
By looking at the project there are some risks appear not used have the most adverse
effect on the project
1. Poor Cost Estimate.
2. Incomplete design.
3. Failure to keep within the cost estimate
4. Failure to achieve the required completion date.
5. Changes in project scope and requirements.
6. Design changes.
7. Pressure to deliver project on an accelerated schedule.
8. Inaccurate contract time estimate
9. Lack of communication between project participants.
10. Inadequately defined roles and responsibilities.
11. Insufficient skilled staff.
12. Political risks.

3.2 Qualitative risk analysis
Qualitative risk analysis assesses the importance of the identified risks and develops the
prioritized lists ,using the 1 to 4 scale matrix discussed above to quantify identified risks

                                                                                          Risk
 Risk                                                              Probability   Impact   Importance
    1. Poor Cost Estimate.                                            3          3           Critical
    2. Incomplete design.                                             1          3            High
    3. Failure to keep within the cost estimate                       3          4           Critical
    4. Failure to achieve the required completion date.               4          3           Critical
    5. Changes in project scope and requirements.                     1          3            High
    6. Design changes.                                                2          2            Low
    7. Pressure to deliver project on an accelerated schedule.        2          2            Low
    8. Inaccurate contract time estimate                              3          4           Critical
    9. Lack of communication between project participants.            3          4           Critical
    10. Inadequately defined roles and responsibilities.              1          4            High
    11. Insufficient skilled
 staff.                                                               1          2            Low
    12. Political risks.                                              4          2          Medium
Three risks were selected for detailed qualitative risk assessment (refer to sheet 1 , 2 and
3)


©Copywright to Steelnz ltd Email steelnz@gmail.com                                          10
Sydney opera case study analysis

                        Project Risks




                                                    Critical
                                                    High
                                                    Low
                                                    Meduim




      Risk                                                              Risk Control
       1. Poor Cost Estimate.                                        Client, Contractor
       2. Incomplete design.                                         Client , Contractor
       3. Failure to keep within the cost estimate                         Client
       4. Failure to achieve the required completion date.           Client, Contractor
       5. Changes in project scope and requirements.                     Engineers
       6. Design changes.                                                Contractor
       7. Pressure to deliver project on an accelerated
    schedule.                                                            Engineers
       8. Inaccurate contract time estimate                          Contractor, Client
       9. Lack of communication between project participants.   Engineers, Contractor, Client
       10. Inadequately defined roles and responsibilities.          Engineers, Client
       11. Insufficient skilled
    staff.                                                                 Client
       12. Political
    risks.                                                               Contractor




©Copywright to Steelnz ltd Email steelnz@gmail.com                                        11
Sydney opera case study analysis



                                Risk by effect




             engineer
                                                 client           client
                                                                  contractor
                                                                  engineer
            contractor




3.2 Risk response

3.2.1 Risk Avoidance
    As discussed most of the risk could be avoided by only
     Completed design .
     Estimating at a very detailed level.
     Not selecting untested design .
     Using local Architecture office will reduce many and more communication and
       experienced architecture designer

3.2.2 Risk transfer
       Using a fixed price contract will transfer construction risk to the contactor.
       Obtaining Insurance to cover costly risks.

3.2.3 Mitigate the risk
Risk analysis shows that no clear management process for controlling the project
however using an experienced project manager would effectively reduce probability or
impact of risks to an acceptable level.

4. Assessment forms
Following a three assessment forms for 3 of the significant risks




©Copywright to Steelnz ltd Email steelnz@gmail.com                                       12
Sydney opera case study analysis


Performa for a Qualitative Risk Assessment (sheet 1)
Reference No: 6                                      Date:25/06/2007
Potential risk:                                      Importance of Risk: Low

Design changes                                             Probability         Medium

                                                           Consequence         Medium

Stage of the project affected by this risk:

Construction stage



Statement of risk:
Cost and schedule overrun



(The factor that could cause it to occur)
Political business interest
Site problems

(any relationship or dependency on other risks)

 Incomplete design


(the likelihood of occurring)
Medium

(how it could be affected)

Design checking prior leaving the design office

       Project:                        Client:              Risk Analyzed by:
Sydney opera house              New South Wales             Khaled
                                government




©Copywright to Steelnz ltd Email steelnz@gmail.com                                   13
Sydney opera case study analysis

Performa for a Qualitative Risk Assessment (sheet 2)
Reference No:1                                        Date: 25/06/2007
Potential risk:                                       Importance of Risk: Critical
Poor Cost Estimate                                           Probability         High

                                                             Consequence         High

Stage of the project affected by this risk:

Design stage
Construction stage


Statement of risk:
major source of complaint
time consuming


(the factor that could cause it to occur)

Changes in project scope and requirements

(any relationship or dependency on other risks)
Inadequately defined roles and responsibilities.



(the likelihood of occurring)
Height

(how it could be affected)
Effective project management
Clearly defined roles

       Project:                         Client:              Risk Analyzed by:
Sydney opera house              New South Wales              Khaled
                                government




©Copywright to Steelnz ltd Email steelnz@gmail.com                                    14
Sydney opera case study analysis

Performa for a Qualitative Risk Assessment (sheet 3)
Reference No:9                                       Date: 25/06/2007
Potential risk:                                      Importance of Risk: Critical
Lack of communication between project                       Probability         high
participants.
                                                            Consequence         high

Stage of the project affected by this risk:

Construction stage
Design stage

Statement of risk:
Insufficient working drawing details
Late and in adequate information
Major costly errors.
(the factor that could cause it to occur)
Lack of management
Interest conflict between project participation

(any relationship or dependency on other risks)

 Incomplete design


(the likelihood of occurring)
Height

(how it could be affected)
Proper project management



       Project:                        Client:              Risk Analyzed by:
Sydney opera house              New South Wales             Khaled
                                government




©Copywright to Steelnz ltd Email steelnz@gmail.com                                     15
Sydney opera case study analysis


5. Lessons learned
   Risk must be identified to be managed
   A poorly defined risk structure will breed more risks.
   A proper risk management strategy would planning.
   All designs and calculations should be checked before they leave the design office
    further check calculation should be made by the authority , many errors that escape
    are picked up and corrected during construction .This often cause a delay to the
    project and might effect the cost.
   The goal is to prevent political and business interests from interfering with design and
    thus to arrive at an outcome as close as possible to the original design drawings.
   Continually monitor risks to identify any change in the status, or if they turn into an
    issue. It is best to hold regular risk reviews to identify actions outstanding, risk
    probability and impact, remove risks that have passed, and identify new risks.
   Risk management is not one off activity instead, it should be applied continuously
    through the project life.
   The best way to control budget is not to proceed with the building unlit you have all
    the drawings complete.

6. Conclusion
Study clearly identifies the great importance of risk management on construction
projects, negligence will lead to an expensive cost effecting the project successes.
A risk analysis project shows a large number qualitatively ranked as 1 , those risks have a
high probability of occurrence and height consequence shared between the client 42% ,
the contractor 36% and the engineer 21% .
This indicates that it was a very risky project nevertheless risks were either downplayed
or ignored , and not much was done to keep them under control, the project management
strategies was only focused on keeping the project going no matter how it is going .
Finally although the opera house put Sydney on the world map, both architecturally and
culturally but from project management perspective it was a spectacular failure as a
consequence of ignoring risk management.




©Copywright to Steelnz ltd Email steelnz@gmail.com                                       16
Sydney opera case study analysis


References
   1. http://www.abc.net.au/news/newsitems/200504/s1355304.htm [Accessed 2 May
      2007].
   2. http://en.wikipedia.org/wiki/Sydney_Opera_House [Accessed 2 May 2007].
   3. Edwards, L. (1995). Practical risk management in the construction industry,
      Thomas Telford, London
   4. Flyvbjerg, Bent, "Design by Deception: The Politics of Megaproject Approval",
      Harvard Design Magazine, Volume 22, 2005.
   5. http://www.hughpearman.com/articles/sydney.htm [Accessed 2 May 2007].
   6. http://www.greatbuildings.com/buildings/Sydney_Opera.html [Accessed 2 May
      2007].
   7. http://www.gids.nl/sydney/opera.html [Accessed 2 May 2007].
   8. Murray ,21-22.
   9. Murray, P: The Saga of the Sydney Opera House, 2004, Spon Press (UK), ISBN
      0415325218
   10. http://www.new7wonders.com/fileadmin/resources/finalists/Fun_Facts_about_Sydney_O
       pera_House.pdf [Accessed 25 Jun 2007].
   11. Neville Turbit http://www.projectperfect.com.au/info_risk_mgmt.php
   12. John Tookey civil 703 lecture notes University of Auckland.
   13. Office of Project Management Process Improvement "Project Risk Management
       Handbook"
   14. Peter Murray "The dramatic storey of the design and construction of the icon of
       modern Australia"(London and New York: Spon Press,2004),105.
   15. Roger Flangan & George Norman "Risk Management and Construction".
       Blackwell Scientific Publications ISBN 0-632-02816-5.
   16. http://www.theirm.org/publications/documents/Risk_Management_Standard_030820.pdf
       [Accessed 2 May 2007].
   17. http://www.wsws.org/arts/1998/dec1998/oper-d04.shtml [Accessed 2 May 2007].
   18. Woodward, Hugh PMP, PowerPoint Presentation to NASA on March 23, 2005,
   19. Yozo Mikami "Utzon's Sphere" page 46 Shokikusuha Tokyo ISBN 4-395-00712-
       0
   20. Ziegler, Oswald L. (ed) Sydney Builds an Opera House., page 25, Oswald Ziegler
       Publications, 1973




©Copywright to Steelnz ltd Email steelnz@gmail.com                                   17

Weitere ähnliche Inhalte

Was ist angesagt?

Case study on Mixed use building
Case study on Mixed use buildingCase study on Mixed use building
Case study on Mixed use buildingTonmoy Barua
 
college campus Case study
college campus Case studycollege campus Case study
college campus Case studyAdyasha Adyasha
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Prateek Srivastava
 
case study of School of planning and architecture, delhi
case study of School of planning and architecture, delhicase study of School of planning and architecture, delhi
case study of School of planning and architecture, delhiFaizan Ahmad
 
World trade centre,bahrain
World trade centre,bahrainWorld trade centre,bahrain
World trade centre,bahrainDishant Rautela
 
Yale Art + Architecture Building - Case Study
Yale Art + Architecture Building - Case StudyYale Art + Architecture Building - Case Study
Yale Art + Architecture Building - Case StudyVikram Bengani
 
architecture Case study yale university
architecture Case study yale universityarchitecture Case study yale university
architecture Case study yale universityNisarg bhavsar
 
CAMPUS DESIGN - CONCEPT STUDY
CAMPUS DESIGN - CONCEPT STUDYCAMPUS DESIGN - CONCEPT STUDY
CAMPUS DESIGN - CONCEPT STUDYSheraniDaniel
 
Walt Disney Concert Hall Case Study
Walt Disney Concert Hall Case StudyWalt Disney Concert Hall Case Study
Walt Disney Concert Hall Case StudyRajat Rana
 
AUDITORIUM DESIGN(1).pdf
AUDITORIUM DESIGN(1).pdfAUDITORIUM DESIGN(1).pdf
AUDITORIUM DESIGN(1).pdfAr Gouripur
 

Was ist angesagt? (20)

Case study on Mixed use building
Case study on Mixed use buildingCase study on Mixed use building
Case study on Mixed use building
 
Shanghai tower
Shanghai towerShanghai tower
Shanghai tower
 
Manaav sadhna, Ahmedabad
Manaav sadhna, AhmedabadManaav sadhna, Ahmedabad
Manaav sadhna, Ahmedabad
 
Campus planning
Campus planningCampus planning
Campus planning
 
college campus Case study
college campus Case studycollege campus Case study
college campus Case study
 
Rem koolhas
Rem koolhasRem koolhas
Rem koolhas
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
 
Cayan tower,dubai
Cayan tower,dubaiCayan tower,dubai
Cayan tower,dubai
 
case study of School of planning and architecture, delhi
case study of School of planning and architecture, delhicase study of School of planning and architecture, delhi
case study of School of planning and architecture, delhi
 
Parking standards
Parking standardsParking standards
Parking standards
 
World trade centre,bahrain
World trade centre,bahrainWorld trade centre,bahrain
World trade centre,bahrain
 
Folded plates
Folded platesFolded plates
Folded plates
 
Yale Art + Architecture Building - Case Study
Yale Art + Architecture Building - Case StudyYale Art + Architecture Building - Case Study
Yale Art + Architecture Building - Case Study
 
architecture Case study yale university
architecture Case study yale universityarchitecture Case study yale university
architecture Case study yale university
 
Sydney opera house
Sydney opera houseSydney opera house
Sydney opera house
 
CAMPUS DESIGN - CONCEPT STUDY
CAMPUS DESIGN - CONCEPT STUDYCAMPUS DESIGN - CONCEPT STUDY
CAMPUS DESIGN - CONCEPT STUDY
 
Shanghai tower
Shanghai towerShanghai tower
Shanghai tower
 
Walt Disney Concert Hall Case Study
Walt Disney Concert Hall Case StudyWalt Disney Concert Hall Case Study
Walt Disney Concert Hall Case Study
 
AUDITORIUM DESIGN(1).pdf
AUDITORIUM DESIGN(1).pdfAUDITORIUM DESIGN(1).pdf
AUDITORIUM DESIGN(1).pdf
 
Case study
Case studyCase study
Case study
 

Andere mochten auch

sydney opera house
sydney opera housesydney opera house
sydney opera houseBulbul Ahmed
 
Architectural Wonders - The Sydney Opera House
Architectural Wonders - The Sydney Opera HouseArchitectural Wonders - The Sydney Opera House
Architectural Wonders - The Sydney Opera HouseKenny Slaught
 
Sydney Opera House
Sydney Opera HouseSydney Opera House
Sydney Opera Housesudeepuid
 
Jorn utzon - Sydney Opera House
Jorn utzon - Sydney Opera HouseJorn utzon - Sydney Opera House
Jorn utzon - Sydney Opera HouseKinnari Wagh
 
Sydney opera house acoustical features
Sydney opera house acoustical featuresSydney opera house acoustical features
Sydney opera house acoustical featuresRohit Bhatt
 
Shell structures- advanced building construction
Shell structures- advanced building constructionShell structures- advanced building construction
Shell structures- advanced building constructionShweta Modi
 

Andere mochten auch (9)

Sydney opera house
Sydney opera houseSydney opera house
Sydney opera house
 
sydney opera house
sydney opera housesydney opera house
sydney opera house
 
Architectural Wonders - The Sydney Opera House
Architectural Wonders - The Sydney Opera HouseArchitectural Wonders - The Sydney Opera House
Architectural Wonders - The Sydney Opera House
 
Sydney Opera House
Sydney Opera HouseSydney Opera House
Sydney Opera House
 
Sidney
SidneySidney
Sidney
 
Jorn utzon - Sydney Opera House
Jorn utzon - Sydney Opera HouseJorn utzon - Sydney Opera House
Jorn utzon - Sydney Opera House
 
Sydney opera house acoustical features
Sydney opera house acoustical featuresSydney opera house acoustical features
Sydney opera house acoustical features
 
FOLDED PLATES TYPES
FOLDED PLATES TYPES FOLDED PLATES TYPES
FOLDED PLATES TYPES
 
Shell structures- advanced building construction
Shell structures- advanced building constructionShell structures- advanced building construction
Shell structures- advanced building construction
 

Ähnlich wie Sydney Opera Risks

COMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docx
COMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docxCOMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docx
COMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docxclarebernice
 
IEC International, Industrial and Housing Estates
IEC International, Industrial and Housing EstatesIEC International, Industrial and Housing Estates
IEC International, Industrial and Housing EstatesZikra Shahzadi
 
20150707 나는pm이다 박성호 교수님 발표자료
20150707 나는pm이다 박성호 교수님 발표자료20150707 나는pm이다 박성호 교수님 발표자료
20150707 나는pm이다 박성호 교수님 발표자료Dong-Hwan Han, Ph.D.
 
Industrial, housing states, water supply & waste management
Industrial, housing states, water supply & waste managementIndustrial, housing states, water supply & waste management
Industrial, housing states, water supply & waste managementZikra Shahzadi
 
Project Risk Management ( Sydney Opera House)
Project Risk Management ( Sydney Opera House) Project Risk Management ( Sydney Opera House)
Project Risk Management ( Sydney Opera House) SalmaKhalid10
 
Green Roofs and Vertical Gardens
Green Roofs and Vertical GardensGreen Roofs and Vertical Gardens
Green Roofs and Vertical GardensElisaMendelsohn
 
Nuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKeeNuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKeedignagni
 
2018 Summer Technical Paper
2018 Summer Technical Paper2018 Summer Technical Paper
2018 Summer Technical PaperJasonFan40
 
Prof Derek Clements-Croome - Intelligent building facades
Prof Derek Clements-Croome - Intelligent building facades Prof Derek Clements-Croome - Intelligent building facades
Prof Derek Clements-Croome - Intelligent building facades Derek Clements-Croome
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo
 
Reflections on lessons learnt from projects
Reflections on lessons learnt from projectsReflections on lessons learnt from projects
Reflections on lessons learnt from projectsDr David Hancock
 
Lessons learnt from projects
Lessons learnt from projectsLessons learnt from projects
Lessons learnt from projectsguestc3931a
 
Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?Dr David Hancock
 
Environmental Impact Assessment (Eia)
Environmental Impact Assessment (Eia)Environmental Impact Assessment (Eia)
Environmental Impact Assessment (Eia)Melissa Dudas
 
Newcastle Construction Division Newsletter Issue No.9
Newcastle Construction Division Newsletter Issue No.9Newcastle Construction Division Newsletter Issue No.9
Newcastle Construction Division Newsletter Issue No.9Alan Bassett
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Nicholas Phelan
 
1. Basic safety engineering.pptx
1. Basic safety engineering.pptx1. Basic safety engineering.pptx
1. Basic safety engineering.pptxEr. Bam Bhandari
 
20161020_SH_Portfolio
20161020_SH_Portfolio20161020_SH_Portfolio
20161020_SH_PortfolioShenpei Ha
 

Ähnlich wie Sydney Opera Risks (20)

COMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docx
COMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docxCOMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docx
COMMUNICATIONS PLAN AND FINAL KA2Christopher MihunCOMM.docx
 
Green Roofs and Vertical Gardens ~ Institute Overseas Fellowship
Green Roofs and Vertical Gardens ~ Institute Overseas FellowshipGreen Roofs and Vertical Gardens ~ Institute Overseas Fellowship
Green Roofs and Vertical Gardens ~ Institute Overseas Fellowship
 
IEC International, Industrial and Housing Estates
IEC International, Industrial and Housing EstatesIEC International, Industrial and Housing Estates
IEC International, Industrial and Housing Estates
 
20150707 나는pm이다 박성호 교수님 발표자료
20150707 나는pm이다 박성호 교수님 발표자료20150707 나는pm이다 박성호 교수님 발표자료
20150707 나는pm이다 박성호 교수님 발표자료
 
Industrial, housing states, water supply & waste management
Industrial, housing states, water supply & waste managementIndustrial, housing states, water supply & waste management
Industrial, housing states, water supply & waste management
 
Project Risk Management ( Sydney Opera House)
Project Risk Management ( Sydney Opera House) Project Risk Management ( Sydney Opera House)
Project Risk Management ( Sydney Opera House)
 
Green Roofs and Vertical Gardens
Green Roofs and Vertical GardensGreen Roofs and Vertical Gardens
Green Roofs and Vertical Gardens
 
Nuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKeeNuprecon - Presentation I gave at Camp Dresser McKee
Nuprecon - Presentation I gave at Camp Dresser McKee
 
2018 Summer Technical Paper
2018 Summer Technical Paper2018 Summer Technical Paper
2018 Summer Technical Paper
 
Prof Derek Clements-Croome - Intelligent building facades
Prof Derek Clements-Croome - Intelligent building facades Prof Derek Clements-Croome - Intelligent building facades
Prof Derek Clements-Croome - Intelligent building facades
 
Dr Christopher Dresser v3
Dr Christopher Dresser v3Dr Christopher Dresser v3
Dr Christopher Dresser v3
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
Reflections on lessons learnt from projects
Reflections on lessons learnt from projectsReflections on lessons learnt from projects
Reflections on lessons learnt from projects
 
Lessons learnt from projects
Lessons learnt from projectsLessons learnt from projects
Lessons learnt from projects
 
Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?
 
Environmental Impact Assessment (Eia)
Environmental Impact Assessment (Eia)Environmental Impact Assessment (Eia)
Environmental Impact Assessment (Eia)
 
Newcastle Construction Division Newsletter Issue No.9
Newcastle Construction Division Newsletter Issue No.9Newcastle Construction Division Newsletter Issue No.9
Newcastle Construction Division Newsletter Issue No.9
 
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
Undergraduate Senior Design Brief - Climate Change Impact Assesment - Infrast...
 
1. Basic safety engineering.pptx
1. Basic safety engineering.pptx1. Basic safety engineering.pptx
1. Basic safety engineering.pptx
 
20161020_SH_Portfolio
20161020_SH_Portfolio20161020_SH_Portfolio
20161020_SH_Portfolio
 

Mehr von Khaled Eid

What every engineer should know
What every engineer should know What every engineer should know
What every engineer should know Khaled Eid
 
Steel stacks guide
Steel stacks guideSteel stacks guide
Steel stacks guideKhaled Eid
 
Calculation note 29 11-2014
Calculation note 29 11-2014Calculation note 29 11-2014
Calculation note 29 11-2014Khaled Eid
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor boltKhaled Eid
 
Steel silo failure case study
Steel silo failure case study  Steel silo failure case study
Steel silo failure case study Khaled Eid
 
Quality managment impacts in construction
Quality managment impacts in constructionQuality managment impacts in construction
Quality managment impacts in constructionKhaled Eid
 
Cheq plate span
Cheq plate spanCheq plate span
Cheq plate spanKhaled Eid
 
Mathcad anchors (2)
Mathcad   anchors (2)Mathcad   anchors (2)
Mathcad anchors (2)Khaled Eid
 
Impact of new codes in silos design
Impact of new codes in silos designImpact of new codes in silos design
Impact of new codes in silos designKhaled Eid
 
Writing engineering report
Writing engineering reportWriting engineering report
Writing engineering reportKhaled Eid
 
Steel detailing guide scope document
Steel detailing guide scope documentSteel detailing guide scope document
Steel detailing guide scope documentKhaled Eid
 

Mehr von Khaled Eid (14)

What every engineer should know
What every engineer should know What every engineer should know
What every engineer should know
 
Steel stacks guide
Steel stacks guideSteel stacks guide
Steel stacks guide
 
Loading
LoadingLoading
Loading
 
Calculation note 29 11-2014
Calculation note 29 11-2014Calculation note 29 11-2014
Calculation note 29 11-2014
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
 
Steel silo failure case study
Steel silo failure case study  Steel silo failure case study
Steel silo failure case study
 
Estimation
EstimationEstimation
Estimation
 
Quality managment impacts in construction
Quality managment impacts in constructionQuality managment impacts in construction
Quality managment impacts in construction
 
Cheq plate span
Cheq plate spanCheq plate span
Cheq plate span
 
Mathcad anchors (2)
Mathcad   anchors (2)Mathcad   anchors (2)
Mathcad anchors (2)
 
Impact of new codes in silos design
Impact of new codes in silos designImpact of new codes in silos design
Impact of new codes in silos design
 
Writing engineering report
Writing engineering reportWriting engineering report
Writing engineering report
 
Steel detailing guide scope document
Steel detailing guide scope documentSteel detailing guide scope document
Steel detailing guide scope document
 
Khaled(beca)
Khaled(beca)Khaled(beca)
Khaled(beca)
 

Kürzlich hochgeladen

SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managmentfactical
 
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...First NO1 World Amil baba in Faisalabad
 
House of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview documentHouse of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview documentHenry Tapper
 
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Sapana Sha
 
government_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfgovernment_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfshaunmashale756
 
Vp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppVp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppmiss dipika
 
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Sonam Pathan
 
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...Amil Baba Dawood bangali
 
Call Girls Near Me WhatsApp:+91-9833363713
Call Girls Near Me WhatsApp:+91-9833363713Call Girls Near Me WhatsApp:+91-9833363713
Call Girls Near Me WhatsApp:+91-9833363713Sonam Pathan
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithAdamYassin2
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economiccinemoviesu
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...Amil baba
 
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证jdkhjh
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex
 
The Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarThe Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarHarsh Kumar
 
The Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng PilipinasThe Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng PilipinasCherylouCamus
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Commonwealth
 
(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)twfkn8xj
 

Kürzlich hochgeladen (20)

SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managment
 
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
 
House of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview documentHouse of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview document
 
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111Call Girls In Yusuf Sarai Women Seeking Men 9654467111
Call Girls In Yusuf Sarai Women Seeking Men 9654467111
 
government_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfgovernment_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdf
 
Vp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppVp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsApp
 
🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road
 
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
 
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
 
Call Girls Near Me WhatsApp:+91-9833363713
Call Girls Near Me WhatsApp:+91-9833363713Call Girls Near Me WhatsApp:+91-9833363713
Call Girls Near Me WhatsApp:+91-9833363713
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam Smith
 
Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economic
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
 
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
 
Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024Bladex Earnings Call Presentation 1Q2024
Bladex Earnings Call Presentation 1Q2024
 
The Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarThe Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh Kumar
 
The Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng PilipinasThe Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng Pilipinas
 
Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]Monthly Market Risk Update: April 2024 [SlideShare]
Monthly Market Risk Update: April 2024 [SlideShare]
 
(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)
 

Sydney Opera Risks

  • 1. PROJECT MANAGEMENT Sydney Opera House Risk Management case study By KHALED EID
  • 2. Sydney opera case study analysis 1. Introduction Risk management is one of the most critical project management practices, to ensure a project be successfully completed Risk management is thus in direct relation to the successful project completion. Project management literature describes a detailed and widely accepted risk management process, which constructed from four iterative phases known as risk management plan  Risk identification  Risk estimation  Risk response  Planning and execution Risk Identification In this stage, we identify and name the risks, there are different sorts of risks and we need to decide on a project by project basis what to do with each type. Risk Quantification Risk need to be quantified in two dimensions. The impact of the risk needs to be assessed. The probability of the risk occurring needs to be assessed. For simplicity, rate each on a 1 to 4 scale. The larger the number, the larger the impact or probability. By using a matrix, a priority can be established. Fig 1 quantification scale matrix (Ref. 11) Risk Response There are four actions you can do about a risk. The strategies are:  Avoid the risk. Do something to remove it. Use another supplier for example. ©Copywright to Steelnz ltd Email steelnz@gmail.com 1
  • 3. Sydney opera case study analysis  Deflect the risk. Make someone else responsible. Perhaps contracting out or insurance against (damage , liability, personnel liability etc)  Mitigate the risk. Take actions to lessen the impact or chance of the risk occurring. If the risk relates to availability of resources, draw up an agreement and get sign-off for the resource to be available.  Accept the risk. The risk might be so small the effort to do anything is not worthwhile or a contingency plan may be developed to deal with possible effects. Risk Control The final step is to continually monitor risks to identify any change in the status, or if they turn into an issue. It is best to hold regular risk reviews to identify actions outstanding, risk probability and impact, remove risks that have passed, and identify new risks. 1.1 Risk management and construction The construction industry is subjected to more risk and uncertainty than many other industries. The process of taking a project from initial investment appraisal to completion and into use is complex, generally bespoke, and entails time-consuming design and production processes. It requires a multitude of people with different skills and interests and the co-ordination of a wide range of disparate, yet interrelated, activities. Such complexity is further compounded by many uncontrollable external factors (Flanagan and Norman, 1983). The construction industry has a poor reputation in coping with risks, many projects failing to meet deadlines and cost targets. Clients, contractors, the public and others have suffered as a result (Edwards 1995). This study will focus on applying project risk management strategies on construction of Sydney opera house which is a well-known case for cost overrun. 1.2 The aim of the study The aim of this study is not to reduce the great achievement of construction such a complicated building that changed the face of the city but looking form management point of view to  Identify and quantify the project risks that been overlooked.  Highlight the dangers associated with using poor estimate. 1.3 About the Sydney Opera House  The owner :State government of New South Wales  Architect :Jorn Utzon  Engineer: Ove Arup & Parteners  Cost: $102 million ©Copywright to Steelnz ltd Email steelnz@gmail.com 2
  • 4. Sydney opera case study analysis The Sydney Opera House is the busiest performing arts centre in the world. Since its opening in 1973, it has brought countless hours of entertainment to millions of people and has continued to attract the best in world class talent year after year. 1.4 About the Building There are nearly 1000 rooms in the Opera House including the five main auditoria. There is also a Reception Hall, five rehearsal studios, four restaurants, six theatre bars, extensive foyer and lounge areas, sixty dressing rooms and suites, library, an artists' lounge and canteen known as the "Green Room", administrative offices and extensive plant and machinery areas. The building covers about 1.8 hectares (4.5 acres) of its 2.2 hectare (5.5 acre) site. It has about 4.5 hectares (11 acres) of usable floor space. It is approximately 185 m (611 ft) long and 120m (380 ft) wide at its widest point. The highest roof vault (above the Concert Hall) is 67m (221 ft) above sea level. The roofs are made up of 2,194 pre-cast concrete sections. These sections weigh up to 15.5 tones (15 tons) each. They are held together by 350 km (217 miles) of tensioned steel cable. The roofs weigh 27,230 tones and are covered with exactly 1,056,056 Swedish ceramic tiles arranged in 4,253 pre-cast lids. The entire building weighs 161,000 tones. It is supported on 580 concrete piers sunk up to 25 m (82 ft) below sea level. The roofs are supported on 32 concrete columns up to 2.5 m (8 ft) square. The exterior and interior walls, stairs and floors are faced with pink aggregate granite which was quarried at Tarana in New South Wales. The two woods used extensively to decorate the interiors are brush box and white birch plywood which were both cut in northern NSW. There are 6,225 sq m (67,000 sq ft) of glass, made in France, in the mouths of the roofs and other areas of the building. It is in two layers - one plain and the other demi-topaz tinted. About 2,000 panes in 700 sizes were installed. There are 645 km (400 miles) of electrical cable. 120 distribution boards regulate the power supply, equivalent to the needs of a town of 25,000 people. Twenty-six air- conditioning plant rooms move more than 28,500 cubic meters (1,000,000 cubic feet) of air per minute through 19.5 km (12 miles) of ducting. ©Copywright to Steelnz ltd Email steelnz@gmail.com 3
  • 5. Sydney opera case study analysis Fig 2 Sydney opera house (Ref. 6) Fig 3 Sydney opera house during construction (Ref. 7) ©Copywright to Steelnz ltd Email steelnz@gmail.com 4
  • 6. Sydney opera case study analysis Fig 4 Sydney opera house shells (Ref. 7) Fig 4 Sydney opera house shells (Ref. 7) ©Copywright to Steelnz ltd Email steelnz@gmail.com 5
  • 7. Sydney opera case study analysis 1.5 Design Stage The original concept for the project was a sketch submitted by Danish architect , Jorn Utzon .Judges selected it from an international open competition that ended with 233 entries from 11 countries. Thought happy to win the competition Utzon was mildly shocked .although his concept had caught the attention of the judges, it consisted only if simple sketches with no plans or even perspective drawings , because the design was so unique , some people presumed it would also be inexpensive to build. No one knew how it would be build , and some experts questioned that it could be built at all. In spite all uncertainty , the initial project cost estimate was pit at $7million.The government would use profits from a series of state run lotteries to pay the project. The government was worried that the people scrutinizing the design might raise question about the potential problems hat would stall the project they thus quickly mover ahead and divided the work into three main contracts :the foundation and the building except the roof, the roof, and the interior and equipment. 1.6 Construction stage Many of the world’s best-known construction companies were involved in building Sydney Opera House including Arups Structural Engineering, Hornibrook and Rider Hunt, the construction work of S.O.H was divided into three distinct stages as follows (Ref. 19)  Stage I Sub structure , concrete structure from the foundation up to the auditoria seating levels excluding any finishes.  Stage II Superstructure or shells , concrete roof vaults or major and minor halls an restaurants , including the claddings.  Stage III Everything not included in stages I and II , stage towers, all interior finishes, exterior paving and cladding, glass walls , all electrical and mechanical services. After he was elected premier of New South Wales in 1965, Askin attempted to force Utzon reduce costs by withholding payments. In 1966 Utzon resigned and returned to his native Denmark. He never even returned to see his masterpiece completed. The construction of the Sydney Opera House was now handed over to a group or Australian architects. Fortunately, the exterior had already been completed by then so that the impact of the altered design on the overall structure was minimal. The project was finally completed in 1973 after a construction period of 14 years and an expenditure of over $A100 million, almost 15 times the estimated budget. ©Copywright to Steelnz ltd Email steelnz@gmail.com 6
  • 8. Sydney opera case study analysis 2. Risk management strategies at S.O.H 2.1 Financial Despite of all cost escalation , taxpayer had little to pay .Virtually all the costs were covered by the proceeds of State Lotteries. The continued need to the subside the running costs of the opera house were financed by the continuation of the Lottery State. The first estimate for the Sydney Opera House was $7.2 million in Australian dollars. Once started, however, costs kept rising and just to complete the building cost $102 million. 2.2 Political Political risks are often occur in government project as they often hide information affecting the community's support, which in turn affect the effectiveness of the feasibility study . S.O.H we mostly severely effect by political decisions 2.2.1 Media and public deception In S.O.H. the original budget of seven million Australian dollars was not a real but a political budget .The labour government of New South Wales the main proponent of the S.O.H, wanted the project started before elections in March 1959-this would reduce the risk of the stopping the project in case Labour lost the elections (8). 2.2.2 Deceptive cost estimate Kim Utzon explains in lieu of his father "It was a political decision to publicize a low budget for the building, which was expected to gain approval in the political system, but which very quickly was exceeded. So even if the cost overrun turned to be 1400% in relation to the publicized budget, this budget was an eight of the real budget of the building .So the real overrun is only 100% the rest was politics". 2.2.3 Political construction date The start of construction for stage I was fixed ., largely for political reasons , as the 2nd March 1959.Thus Proceeding with construction before completing the design process which is a great risk . 2.2.4 Political design changes On 1966 major hall was changed from dual purpose for concert and opera to a single purpose concert hall, the dual purpose was a requirement of the competition . ©Copywright to Steelnz ltd Email steelnz@gmail.com 7
  • 9. Sydney opera case study analysis 2.3 Structural 2.3.1 The Supporting points Arup and his engineers knew very well that the cross-section shape Utzon chose was far from ideal known structures, however they could not suggest changing to the shape as it will alter the appearance of the roof drastically. 2.3.2 The roof A question should be asked if this design is achievable?. The competition judges choose a complex art design without asking how it will be deigned? later on it was a major cause for delaying the roof design if this point was been considered they should either choose a simple shape or a known geometry, at this stage computer program analysis was not yet been introduced that means only manual process can be used to calculate the forces acting on the structure. 2.3.3 Lack of suitable boundary condition. Another technical problem that the engineer had to solve was the lack of boundary condition that leads to some earthwork as sub base for the structure foundation. 2.4 Technical Utzon, ware of possible technical problems since his design required advanced technology not yet available, requested additional time to tackle those challenges Utzon faced the task of converting the concept into a design form which a structure could be built, but he had no prior experience in the design and construction of such a large building. Because of this lack of plans, detailed design drawings, and estimates of materials, little existed from which cost could be determined. 2.4.1 Design errors and omissions  Unfortunately, the roof shells were too heavy for the supporting columns that were already built, so these were demolished and rebuilt. These and several other setbacks led to delays and increasing cost overruns.  The original design called for two theatres. The government changed its mind and required the building to be altered and that four theatres now be incorporated into the design  The foundation been demolished to suit the new roof design loads. 2.4.2 Fitness for purpose.  The main design overlooked acoustic requirements which is the main purpose of the building and had to be altered at later stage.  The Running costs for S.O.H proved expensive , it was a very labour intensive building .In 1974 , it operation cost was $A6M, of which only $A2M was covered by ©Copywright to Steelnz ltd Email steelnz@gmail.com 8
  • 10. Sydney opera case study analysis the revenue. Thus costs ruled out small scale opera and the Australian Opera were forced to seek a cheaper venue. 2.5 Construction Engineers who revised the concept noted that the roof shells were much larger and wider than any shells seen so far. Further, because they stuck up so height, they would act like sails in strong winds blowing up the harbour. Thus, the roof would have to be carefully designed and constructed to resist such wind pressure. The construction was estimated to take about five years at a cost of A$7 million. Ignoring his request, the government pressured Utzon into starting construction in 1959, two years ahead of the architect's proposed schedule.  The lack of preparation soon backfired. After the completion of the grand podium with an enormous, 86 meter (282ft) wide stair, several years were spent reworking the design of the roof.  Three tower cranes imported from France for this job costing $100,000 each and it was the first building constructed in Australia using tower cranes.  Unfortunately the roof shells were too heavy for the supporting columns that were already built, so these were demolished and rebuilt. 2.6 What goes wrong Consequences?  Coast overrun 1300% (Ref. 18) As feared many experts the project become an engineering financial debacle, lasting 15 years and costing $107 million ($100 million over the initial estimate).  Schedule overrun 250% (Ref. 18)  Media and public scandal ESTIMATES AND EXPENDITURE 1957-1973 $120.0 Millions $100.0 $80.0 $60.0 $40.0 $20.0 $0.0 1/0/1900 1/2/1900 1/4/1900 1/6/1900 1/8/1900 1/10/1900 1/12/1900 Fig 5 Time /cost Escalation ©Copywright to Steelnz ltd Email steelnz@gmail.com 9
  • 11. Sydney opera case study analysis  Management conflict occur between the client and the architect that cause him to resign before the end of stage III . 3. Risk identification quantification 3.1 Identification By looking at the project there are some risks appear not used have the most adverse effect on the project 1. Poor Cost Estimate. 2. Incomplete design. 3. Failure to keep within the cost estimate 4. Failure to achieve the required completion date. 5. Changes in project scope and requirements. 6. Design changes. 7. Pressure to deliver project on an accelerated schedule. 8. Inaccurate contract time estimate 9. Lack of communication between project participants. 10. Inadequately defined roles and responsibilities. 11. Insufficient skilled staff. 12. Political risks. 3.2 Qualitative risk analysis Qualitative risk analysis assesses the importance of the identified risks and develops the prioritized lists ,using the 1 to 4 scale matrix discussed above to quantify identified risks Risk Risk Probability Impact Importance 1. Poor Cost Estimate. 3 3 Critical 2. Incomplete design. 1 3 High 3. Failure to keep within the cost estimate 3 4 Critical 4. Failure to achieve the required completion date. 4 3 Critical 5. Changes in project scope and requirements. 1 3 High 6. Design changes. 2 2 Low 7. Pressure to deliver project on an accelerated schedule. 2 2 Low 8. Inaccurate contract time estimate 3 4 Critical 9. Lack of communication between project participants. 3 4 Critical 10. Inadequately defined roles and responsibilities. 1 4 High 11. Insufficient skilled staff. 1 2 Low 12. Political risks. 4 2 Medium Three risks were selected for detailed qualitative risk assessment (refer to sheet 1 , 2 and 3) ©Copywright to Steelnz ltd Email steelnz@gmail.com 10
  • 12. Sydney opera case study analysis Project Risks Critical High Low Meduim Risk Risk Control 1. Poor Cost Estimate. Client, Contractor 2. Incomplete design. Client , Contractor 3. Failure to keep within the cost estimate Client 4. Failure to achieve the required completion date. Client, Contractor 5. Changes in project scope and requirements. Engineers 6. Design changes. Contractor 7. Pressure to deliver project on an accelerated schedule. Engineers 8. Inaccurate contract time estimate Contractor, Client 9. Lack of communication between project participants. Engineers, Contractor, Client 10. Inadequately defined roles and responsibilities. Engineers, Client 11. Insufficient skilled staff. Client 12. Political risks. Contractor ©Copywright to Steelnz ltd Email steelnz@gmail.com 11
  • 13. Sydney opera case study analysis Risk by effect engineer client client contractor engineer contractor 3.2 Risk response 3.2.1 Risk Avoidance As discussed most of the risk could be avoided by only  Completed design .  Estimating at a very detailed level.  Not selecting untested design .  Using local Architecture office will reduce many and more communication and experienced architecture designer 3.2.2 Risk transfer  Using a fixed price contract will transfer construction risk to the contactor.  Obtaining Insurance to cover costly risks. 3.2.3 Mitigate the risk Risk analysis shows that no clear management process for controlling the project however using an experienced project manager would effectively reduce probability or impact of risks to an acceptable level. 4. Assessment forms Following a three assessment forms for 3 of the significant risks ©Copywright to Steelnz ltd Email steelnz@gmail.com 12
  • 14. Sydney opera case study analysis Performa for a Qualitative Risk Assessment (sheet 1) Reference No: 6 Date:25/06/2007 Potential risk: Importance of Risk: Low Design changes Probability Medium Consequence Medium Stage of the project affected by this risk: Construction stage Statement of risk: Cost and schedule overrun (The factor that could cause it to occur) Political business interest Site problems (any relationship or dependency on other risks) Incomplete design (the likelihood of occurring) Medium (how it could be affected) Design checking prior leaving the design office Project: Client: Risk Analyzed by: Sydney opera house New South Wales Khaled government ©Copywright to Steelnz ltd Email steelnz@gmail.com 13
  • 15. Sydney opera case study analysis Performa for a Qualitative Risk Assessment (sheet 2) Reference No:1 Date: 25/06/2007 Potential risk: Importance of Risk: Critical Poor Cost Estimate Probability High Consequence High Stage of the project affected by this risk: Design stage Construction stage Statement of risk: major source of complaint time consuming (the factor that could cause it to occur) Changes in project scope and requirements (any relationship or dependency on other risks) Inadequately defined roles and responsibilities. (the likelihood of occurring) Height (how it could be affected) Effective project management Clearly defined roles Project: Client: Risk Analyzed by: Sydney opera house New South Wales Khaled government ©Copywright to Steelnz ltd Email steelnz@gmail.com 14
  • 16. Sydney opera case study analysis Performa for a Qualitative Risk Assessment (sheet 3) Reference No:9 Date: 25/06/2007 Potential risk: Importance of Risk: Critical Lack of communication between project Probability high participants. Consequence high Stage of the project affected by this risk: Construction stage Design stage Statement of risk: Insufficient working drawing details Late and in adequate information Major costly errors. (the factor that could cause it to occur) Lack of management Interest conflict between project participation (any relationship or dependency on other risks) Incomplete design (the likelihood of occurring) Height (how it could be affected) Proper project management Project: Client: Risk Analyzed by: Sydney opera house New South Wales Khaled government ©Copywright to Steelnz ltd Email steelnz@gmail.com 15
  • 17. Sydney opera case study analysis 5. Lessons learned  Risk must be identified to be managed  A poorly defined risk structure will breed more risks.  A proper risk management strategy would planning.  All designs and calculations should be checked before they leave the design office further check calculation should be made by the authority , many errors that escape are picked up and corrected during construction .This often cause a delay to the project and might effect the cost.  The goal is to prevent political and business interests from interfering with design and thus to arrive at an outcome as close as possible to the original design drawings.  Continually monitor risks to identify any change in the status, or if they turn into an issue. It is best to hold regular risk reviews to identify actions outstanding, risk probability and impact, remove risks that have passed, and identify new risks.  Risk management is not one off activity instead, it should be applied continuously through the project life.  The best way to control budget is not to proceed with the building unlit you have all the drawings complete. 6. Conclusion Study clearly identifies the great importance of risk management on construction projects, negligence will lead to an expensive cost effecting the project successes. A risk analysis project shows a large number qualitatively ranked as 1 , those risks have a high probability of occurrence and height consequence shared between the client 42% , the contractor 36% and the engineer 21% . This indicates that it was a very risky project nevertheless risks were either downplayed or ignored , and not much was done to keep them under control, the project management strategies was only focused on keeping the project going no matter how it is going . Finally although the opera house put Sydney on the world map, both architecturally and culturally but from project management perspective it was a spectacular failure as a consequence of ignoring risk management. ©Copywright to Steelnz ltd Email steelnz@gmail.com 16
  • 18. Sydney opera case study analysis References 1. http://www.abc.net.au/news/newsitems/200504/s1355304.htm [Accessed 2 May 2007]. 2. http://en.wikipedia.org/wiki/Sydney_Opera_House [Accessed 2 May 2007]. 3. Edwards, L. (1995). Practical risk management in the construction industry, Thomas Telford, London 4. Flyvbjerg, Bent, "Design by Deception: The Politics of Megaproject Approval", Harvard Design Magazine, Volume 22, 2005. 5. http://www.hughpearman.com/articles/sydney.htm [Accessed 2 May 2007]. 6. http://www.greatbuildings.com/buildings/Sydney_Opera.html [Accessed 2 May 2007]. 7. http://www.gids.nl/sydney/opera.html [Accessed 2 May 2007]. 8. Murray ,21-22. 9. Murray, P: The Saga of the Sydney Opera House, 2004, Spon Press (UK), ISBN 0415325218 10. http://www.new7wonders.com/fileadmin/resources/finalists/Fun_Facts_about_Sydney_O pera_House.pdf [Accessed 25 Jun 2007]. 11. Neville Turbit http://www.projectperfect.com.au/info_risk_mgmt.php 12. John Tookey civil 703 lecture notes University of Auckland. 13. Office of Project Management Process Improvement "Project Risk Management Handbook" 14. Peter Murray "The dramatic storey of the design and construction of the icon of modern Australia"(London and New York: Spon Press,2004),105. 15. Roger Flangan & George Norman "Risk Management and Construction". Blackwell Scientific Publications ISBN 0-632-02816-5. 16. http://www.theirm.org/publications/documents/Risk_Management_Standard_030820.pdf [Accessed 2 May 2007]. 17. http://www.wsws.org/arts/1998/dec1998/oper-d04.shtml [Accessed 2 May 2007]. 18. Woodward, Hugh PMP, PowerPoint Presentation to NASA on March 23, 2005, 19. Yozo Mikami "Utzon's Sphere" page 46 Shokikusuha Tokyo ISBN 4-395-00712- 0 20. Ziegler, Oswald L. (ed) Sydney Builds an Opera House., page 25, Oswald Ziegler Publications, 1973 ©Copywright to Steelnz ltd Email steelnz@gmail.com 17