SlideShare a Scribd company logo
1 of 21
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 1 of 21
Examples of Lean Six Sigma projects
1. Lean - Packaging Productivity Improvement ----Consumer Goods Packaging ( $250K/Year savings)
 Converted Batch & Queue into continuous flow production which reduced total cycle time from 3
days to 12hrs/order
 Increased shift capacity by 82%
 Eliminated 3rd shift (14 operators + temps)
 Redesigned the layout into LEAN Flexible CELLS with cross functional trained workers, rotation
schedule to manage bottlenecks and 5S
 Reduced online “hidden rework” costs by 40% and implemented in-process checks to ensure a
“check and balance” system
 Reduced inventory by 30% ($1Mil inventory reduction)
BEFORE LEAN MANUFACTURING
AFTER LEAN IMPLEMENTATION
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 2 of 21
EQUIPMENT RELIABILITY IMPROVEMENT
PROBLEM STATEMENT:
1. Film Shrink Packaging 14% Machine Downtime
2. Poor reliability ɳ < 62%, Average time between failures = 21hrs
OBJECTIVE:
1. Reduce downtime from 14% to < 3%
2. Optimize reliability of machine
IMPROVEMENTS:
1. Conducted FMEA, Root Caused the top 80% machine downtime causes
2. Improved film feed roller y, redesigned new robust cutting knives
3. Implemented condition based preventative maintenance to monitor faults
4. Utilized Weibull distribution to validate reliability
5. Optimized machine process parameters
RESULTS: Reduced downtime from 14% to 2.3 %, increased reliability from ɳ =62% to 97%
Total savings= $740K in machine downtime reduction
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 3 of 21
ARPAC VSM –CURRENT STATE VSM
31% EFFICIECNY 20% Rework + 14% DOWNTIME
Customer Demand
Total Non-Value Add Time = 3HRS
Value Added Time = 173 min (4.5Hrs)
2 operator
C/T = 34 min
C/O = 0.5 hr
Uptime = 81%
PALLETIZER
2 operator
FILM
RACK
C/T = 52 min
C/O = 0.5 hr
Uptime = 86%
1 operator
C/T = 47 min
C/O = 0 hr
Uptime = 78%
OVEN
1 OPERATOR
WRAP
DEFECTS
47 min34 min52 min
1 day 2 day1 day 0.5 days
Production
Order
D
Wk
FILM ROLL
C/T = 40 min
C/O = 0 min
Uptime = 83%
OVERWRAP
CONVEYOR
40
FG
FILM
ROLLS
SHINGLES
VA Time
NVA Time
I
10% SCRAP
20% REWORK
SCRAP
LINEHIGH ROLL DAMAGED
ARPAC VSM –FUTURE STATE VSM
0% Rework - 2% DOWNTIME
Customer Demand
Total Non-Value Add Time = 0.5HRS
Value Added Time = 7Hrs
2 operator
C/T = 34 min
C/O = 0.5 hr
Uptime = 81%
PALLETIZER
2 operator
FILM
RACK
C/T = 52 min
C/O = 0.5 hr
Uptime = 86%
1 operator
C/T = 47 min
C/O = 0 hr
Uptime = 78%
OVEN
1 OPERATOR
47 min34 min52 min
1 day 2 day1 day 0.5 days
Production
Order
D
Wk
FILM ROLL
C/T = 40 min
C/O = 0 min
Uptime = 83%
OVERWRAP
CONVEYOR
40
DC
FILM
ROLLS
SHINGLES
VA Time
NVA Time
CONTINUOUS FLOWKANBAN ROLLS
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 4 of 21
BEFORE
AFTER IMPROVEMENT
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 5 of 21
2. LARGE FORMAT OPERATIONAL TRANSFORMATION - Printing/Packaging - 2015
Problem Statement -
• New Business unit -Large Format “LGF” department running at a loss for 2 years consecutively
• Current capacity 72 shipped items/day, Customer demand =100 items/day
• Currently Average lead time (LT)= 13 days , customer demand = 2-4 days
• New $2Mil equipment underutilized Overall Equipment Efficiency (OEE) = 37%
• Internal Quality Reject Rate = 42%, causing high rework, scrap rate = 33%
Results:
 Increased capacity from 72 to 131 items/day –> (83%)
 Reduced lead time from 13 days to <1 day Implemented NEXT DAY delivery for all orders
 Increased Gross Margin from -$30K to +$35.6K/PD ($70K/month swing) $840K/year
 Transformed Large Format from cost centre into Profit centre and achieved
BEFORE LEAN
AFTER LEAN
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 6 of 21
3. DESIGN FOR SIX SIGMA SWITCHABLE WATER PUMP PULLEY
Problem Statement Current Switchable Water Pump Pulley has design reliability failure rate of 11%,
causing engine overheating and high warranty costs, resulting in over $1.4Mil losses
Objective: Improve design reliability from Identify design failure modes, optimize design yield and validate
design reliability in order to relaunch within 8 months
Results: Successfully improved the design using Design for Six Sigma (DFSS), fixed previous design
failures using Failure Mode Effects Analysis (FMEA) and validated new design robustness using Design
of Experiment (DOE).
The end result: increased overall reliability from 89% to 98.7% over life cycle of the engine resulting
in 60% faster warm-up
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 7 of 21
4. EATS LEAN TRANSFORMATION EATS (Exhaust After Treatment System)
Problem Statement
1. Product/design issues causing 30% internal Quality reject rate , limiting throughput 8 sets/day
2. Unable to meet increased VOLVO demand 60pcs/week, causing shut down Volvo plant 2 days
3. Unable to meet delivery time < 3 days, Currently total cycle time= 4.5 days + rework
BEFORE LEAN TRANSFORMATION
Custom order fitting issues
Backed up orders
HIGH SCRAP and REWORK
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 8 of 21
AFTER LEAN TRANSFORMATION (12 WEEKS)
CUSTOM TOOL CARTS and VISUAL CONTROLS
TRANSFORMATION RESULTS
1. Reduced quality reject rate from 30% down to 3%
2. Reduced total lead time from 4.5 down to < 2 days
3. Reduced total cycle time from 3Hrs to 0.7Hrs/pc
4. TOTAL SAVINGS= $840K/YEAR
CUSTOM ASSEMBLY FIXTURE
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 9 of 21
5. QUALITY IMPROVEMENT CUSTOMER VOLVO---$200,000 SAVINGS
PROBLEM: Missing critical truck component , front-end plate causing customer VOLVO a 2 day shut down
and $100,000 in fines and chargeback
ISSUES: customer requires critical component shipped loose, manual assembly operation not capable of 100%
detecting missing part
SOLUTION: Error proofed assembly process to prevent missing component
RESULTS:
 Added presence sensor for detecting if Missing front-end plate. Connected to shut off valve to prevent
further assembly if Missing front-end plate
 Added visual RED/GREEN light display notification
 Verified over 12 shipments and 5000 pcs shipped problem eliminated
 Cost Avoidance = $ 200,000
ERROR PROOF MANUAL ASSEMBLY PROCESS
POKA YOKE Final Assembly
MISSING PART
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 10 of 21
6. BIO MANUFACTURING BATCH CYCLE TIME REDUCTION — March 2015
Problem:
1. Low Suite utilization 11%, causing capacity constraints with other products
2. Batch cycle time = 5 days per batch, customer Takt Time= 4 days/batch
Objective: Increase utilization and production capacity by 30% without additional capital
RESULTS:
 increased Final Yield by 19%,
 increased suite utilization from 11% to 62%, and
 Reduced total batch processing time from 5 to 3.5 days/batch (42%)
 Total Operational savings = $1.4Mil/year
 Project completion time= 3.5 months
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 11 of 21
7. LEAN LOGISTICS MANUFACTURING (DPM) AND DISTRIBUTION (NT) 2013-2014
Streamlined a complex Canada wide Manufacturing-Supply Chain-Logistics replenishment
operation, which reduced storage/transportation costs by $920K, inventory levels by $2.2Mil (from
$3.4Mil to $1.2Mil). Total Operational savings= $3.1Mil
Problem Statement:
Transportation Logistics from DP Manufacturing to NT Distribution centres inefficient. Customer same
day orders and replenishment being picked up from DP Manufacturing delivered to NT Distribution
Centre, then reloaded onto an outbound carrier resulting in either late deliveries, lost shipments or
delivered to wrong address, resulting in shortages 50%, high WIP levels and excessive transportation
costs.
Improvements:
 Implemented Lean Logistics using 1-step cross-docking distribution from DP to final
destination, which eliminated shortages, reduced delivery time from 4 days to < 1 day
 Integrated Manufacturing-Supply Chain with Warehouse Management System which reduced
total WIP inventory by $2Mil, eliminated 2 carriers, utilized same carrier for Inbound/Outbound
 Implemented Advanced shipping notice (ASN) which enabled Synchronized inbound delivery with
outbound shipments, bar code tracking with shipment RFID chips from supplier
NT DISTRIBUTION CENTERS
DP PRE-PAID CUSTOMERS
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 12 of 21
8. FCI AUTOMOTIVE – QS9001/ISO14000 2000-2004
NEW PROGRAM LAUNCH
 Successfully managed a $22M USD FORD/TRW new ABS/VSC program for 2005 FORD Windstar
minivan, from Design to full PPAP launch on-time & within budget.
 Took over a complex FORD program in jeopardy of being lost, gained the trust and credibility of
FORD/TRW Program managers and successfully PPAP launched the program on-time
 Successfully improved a previously strained customer relationship with honesty, integrity trust
 Developed a mandrel prototype concept for insert moulding 52 connector pins, 4 power blades, and 4
bushings for the Automatic Breaking systems ABS & Vehicle System Control VSC CONNECTORS
 Developed & managed all APQP & PPAP documentation including: Design reviews, PFMEA DVP&R,
SPC, Control Plans, SOP, and production tooling design
 Developed automation specifications, RFQ, vendor selection, managed the design, build & installation of
the custom full-automated assembly line Total budget for automation worth over $2.3M USD
ABS & VCS Connector module
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 13 of 21
9. INJECTION MOULD SET-UP REDUCTION PROJECT --($500K/annual savings)
 Problem Statement: 22 injection moulds ranging from 93 weeks new to moulds over 10 years
old), varied in sizes & capacities, had set-up/changeover times from 4-6hrs, resulting over $500K
machine inefficiencies and productivity losses
 Objective: Reduce the set-up time from 6hrs to under 2hrs
 Significant Improvements: over 4.5hrs of Set-Up Time was reduced by the following
 IMPROVEMENTS:
o Implemented SMED principles, 5S SHADOW BOARDS, standardized, Set-Up
o New water manifolds with shorter hoses and different IN/OUT connectors
o Standardized bolt lengths and utilized quick-connect clamps
o Interchangeable inserts and standardized back plates with different hole pattern
o Standardized Mould kits & implemented shadow boards
o Documented SOP and validated set-up/changeover on different shifts
 These improvements resulted in over $500K annual savings
Setup/Changeover Tooling Improvements
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 14 of 21
10. Robot Welding Setup Time Reduction ----Tier 1 Automotive $650K/year savings
PROBLEM STATEMENT
2 station robot weld down 38min between changeovers, 6 changeovers/day = 3.8hrs downtime/day
 Current setup time= 38min
 Standard Time= 15min
 Target setup Time < 5min
IMPROVEMENTS:
 Designed 6 SIGMA modular welding fixtures, with quick connect clamps and eliminated bolts, screws
and
 combined tacking with robot welding into 1 operation
 Implemented SMED external setup and eliminated internal setup time
 Standardized welding fixtures, eliminated bolts, screws and
 implemented , 5S shadow board, tooling push-pin toggle clamps
RESULTS: ZERO SETUP TIME ACHIEVED
Robot 9 SMED SOP=ZERO SETUP TIME
SIDE A CHANGEOVER
step # Operation Est Time (min)
1 PREPARE NEXT WO MATERIAL 4
2 GET NEEDED FIXTURES/TOOLS/CLAMPS 3
3 UNLOAD LAST PARTS FROM SIDE 1 1
4 INSPECT AND TOUCH UP PARTS 2
5 TACK PARTS 2 (EXTERNAL SETUP)
6 TAKE DOWN FIXTURE FROM SIDE 1 4 BEING DONE
7 LOAD PARTS ONTO SIDE 1 1 WHILE ROBOT rUNNING
8 START WELDING SIDE 1 0
TOTAL TIME FOR SETUP= 16
WELD CYCLE STARTED = 8 T SETUP TIME CLOCK STARTS
AFTER 8 MIN
SIDE B CHANGEOVER
EXTERNAL SETUP
7 TAKE DOWN FIXTURE FROM SIDE 2 5 INCLUDED IN
8 LOAD PARTS ONTO SIDE21 1 WELD CYCLE (8MIN)
9 START WELDING SIDE 2 0
TOTAL SETUP TIME SIDE B= 6
TOTAL INTERNAL SETUP TIME= 0
TOTAL EXTERNAL SETUP TIME= 12
OLD SETUP TIME (MIN)= 38
DEC 4 SETUP (MIN) = 0
SETUP TIME IMPROVEMENT (MIN) = -38
WHILE THE ROBOT IS WELDING SIDE B, LOST TIME=0 MIN
GOAL IS TO CHANGE STATION A BEFORE ROBOT FINISHES WELDING SIDE B
DURING WELD CYCLE (8MIN) THE FOLLOWING WAS DONE
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 15 of 21
11. BLACK CLAWSON EXTRUSION LAMINATOR SAFEGUARDING
 PROBLEM STATEMENT: Used Laminator purchased by company without proper
safeguarding and shut down by Ministry of Labour ordering a PSHR by a P.Eng
 OBJECTIVE: Design machine safeguarding to enable Laminator compliance with OHSA
section 851 Industrial Establishments
LAMINATOR BEFORE PSHR
CRITICAL AREAS TO BE GUARDED
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 16 of 21
12. NEW PRODUCT LAUNCH IMPROVEMENT –(Water Pump Bearings)
TIER 1 AUTOMOTIVE SUPPLIER --(TS-16949 REGISTERED)
Problem Statement: On RED LIST due to late deliveries & poor quality to customer STACKPOLE causing
“RUSH” orders and constant panic mode
 1st
Pass Quality Yield machining = 62%, using 100% inspection to sort out defects
 Lack of Process Control, relying on QC Inspector to find defects
 Premature Tool wear causing defects and downtime
Rotary Transfer Machines:
o 16 Station Hydromat CNC
o Buffoli Transfer Machine CNC
o Hydromat - 10 Station
o Hydromat - 12 Station
Other Equipment:
• In-feed and thru-feed grinding equipment
• Durr parts washer
• Full chip and oil recovery systems
• Fully integrated MRP system
Improvements:
1. Developed VSM of current process and reviewed NVA areas
2. Implemented in-process sampling checks based on AQL of 0.4 (99.6% confidence level) using
GO/NO-GO gauges, vernier measurements
3. Set-up and Implemented SPC for in-process checks which allowed operators to monitor trends and
adjust tooling as needed before it’s too late
4. Redesigned tooling for a 16 station CNC HYDROMAT which reduced premature tool wear by 25%
5. Developed & Implemented Preventative Maintenance which reduced downtime by 30%
6. Designed Rough Grinding and Finish Grinding process parameters for machining water pump
bearings achieving surface finishes of 0.1-0.2µm Ra (4-8 µin) consistently
7. Eliminated 100% inspection
8. Validated Testing through Reliability studies and implemented statistical process controls which
reduced leak test failures from 14% to less than 0.5% improved packaging productivity by 32%
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 17 of 21
CAPITAL EQUIPMENT PROJECT EXAMPLES
13. DESIGN FOR SIX SIGMA MANUFACUTING WORK CELL (Total Savings= $840 K)
Noble Fire (June 2012)
 Problem Statement: Production capacity unknown, sales increasing rapidly
 Objective: Determine Current Plant Capacity and Increase production capacity by meet
customer demand
 Project duration < 6 months
 Prepared Engineering report listing all the issues and recommendations
Main Improvements:
o Increased productivity by 28% in less than 2 months
o Designed, tested and validated new NFPA Approved sprinkler head outlets which
reduced field repairs by 95%-over $40K/year
o Reduced Cycle time on an Automated Burn/Weld Machine by 30% resulting in over
$100K/year in increased productivity
o Implemented new BURN/WELD machines which increased production capacity by 80%
and reduced labour costs by over $230K, with a ROI of 78% (Payback= 0.3 years)
o Total Project Savings = $840K
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 18 of 21
14. PROGRESSIVE STAMPING DIE DESIGN --$900K savings
PROBLEM STATEMENT:
 Unable to support Home Depot Demand increased by 30%, requiring 1Mil units/year
 Current capacity = 550,000 pcs/year , High labour cost/pc = $2.28/pc
 2 critical labour intensive BOTTLENECK operations preventing additional capacity
 High Labour cost: band saw cutting ($1.5/pc) + 3 stage forming ($0.78/pc)= $2.28
Objective: Increase capacity from 550K to 1.3Mil without adding cost
IMPROVEMENT Progressive Stamping Die –eliminating 2 labour intensive operations
RESULTS
1. Increased capacity from 550,000 to 1,8Mil units/year (300%)
2. Combined 2 labour intensive operations into 1 progressive die cycle
3. Reduced labour cost by from $2.28 to $0.29/pc =$2
4. Payback period < 1 year, ROI= 27%
5. TOTAL ANNUAL SAVINGS AFTER PAYBACK= $910K/year
2 Operations @ 1 cycle
1 Band Saw 2 Forming with 3 setups
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 19 of 21
15. INJECTION MOULD SET-UP REDUCTION PROJECT --($500K/annual savings)
 Problem Statement: 22 injection moulds ranging from 93 weeks new to moulds over 10 years
old), varied in sizes & capacities, had set-up/changeover times from 4-6hrs, resulting over $500K
machine inefficiencies and productivity losses
 Objective: Reduce the set-up time from 6hrs to under 2hrs
 Significant Improvements: over 4.5hrs of Set-Up Time was reduced by the following
 IMPROVEMENTS:
o Implemented SMED principles, 5S SHADOW BOARDS, standardized, Set-Up
o New water manifolds with shorter hoses and different IN/OUT connectors
o Standardized bolt lengths and utilized quick-connect clamps
o Interchangeable inserts and standardized back plates with different hole pattern
o Standardized Mould kits & implemented shadow boards
o Documented SOP and validated set-up/changeover on different shifts
 These improvements resulted in over $500K annual savings
Quick Setup/Changeover Tooling Improvements
JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018
Page 20 of 21
16. Noble Fire Production Capacity
Problem Statement: Production capacity unknown, sales increasing rapidly
Objective: Increase production welding capacity by 25% without any new equipment
Project duration < 4 months
Main Improvements:
o Increased productivity by 28% in less than 2 months
o Designed, tested and validated new NFPA Approved sprinkler head outlets which reduced
field repairs by 95%- over $40K/year
o Reduced Cycle time on an Automated Burn/Weld Machine by 30% resulting in over
$100K/year in increased productivity
o Developed a plan that would increase production capacity by 80% and reduce OT costs by over
$230K, with a ROI of 78% (Payback= 0.3 years)
o Total Project Savings = $840K
OLD OUTLETS NEW OUTLETS
JULIAN KALAC LEAN SIX SIGMA IN FABRICATION 1-May-18
Page 21 of 21
17.PLASTIC FILM WRAP UNWINDER SAFEGUARDING
BEFORE SAFEGUARDING
AFTER SAFEGUARDING

More Related Content

What's hot

Brake drum project
Brake drum projectBrake drum project
Brake drum projectS R Jain
 
How A Single Black Belt Project Jump Starts a Successful Lean Six Sigma Effort
How A Single Black Belt Project Jump Starts a Successful Lean Six Sigma EffortHow A Single Black Belt Project Jump Starts a Successful Lean Six Sigma Effort
How A Single Black Belt Project Jump Starts a Successful Lean Six Sigma EffortGoLeanSixSigma.com
 
Brake drum project
Brake drum projectBrake drum project
Brake drum projectS R Jain
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
Saivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; MachiningSaivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; Machininghuhangcheng
 
WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...
WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...
WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...Dubai Quality Group
 
Graham Harker Resume RB 15
Graham Harker Resume RB 15Graham Harker Resume RB 15
Graham Harker Resume RB 15Graham Harker
 
CV of Donervon Gounden 30-4-2015
CV of Donervon Gounden  30-4-2015CV of Donervon Gounden  30-4-2015
CV of Donervon Gounden 30-4-2015Donervon Gounden
 
Garner Osborne Assembly Brochure
Garner Osborne Assembly BrochureGarner Osborne Assembly Brochure
Garner Osborne Assembly BrochureLaura Goslin
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industryGanesh TN
 

What's hot (18)

Brake drum project
Brake drum projectBrake drum project
Brake drum project
 
How A Single Black Belt Project Jump Starts a Successful Lean Six Sigma Effort
How A Single Black Belt Project Jump Starts a Successful Lean Six Sigma EffortHow A Single Black Belt Project Jump Starts a Successful Lean Six Sigma Effort
How A Single Black Belt Project Jump Starts a Successful Lean Six Sigma Effort
 
Brake drum project
Brake drum projectBrake drum project
Brake drum project
 
Resume 2.0
Resume 2.0Resume 2.0
Resume 2.0
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
smed
smedsmed
smed
 
Saivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; MachiningSaivs Sand Casting &amp; Machining
Saivs Sand Casting &amp; Machining
 
WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...
WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...
WQD2011 - KAIZEN - EMAL - To improve the slot cleaning quality of slotted ano...
 
Graham Harker Resume RB 15
Graham Harker Resume RB 15Graham Harker Resume RB 15
Graham Harker Resume RB 15
 
Why Choose Flowmeter Remanufacturing?
Why Choose Flowmeter Remanufacturing?Why Choose Flowmeter Remanufacturing?
Why Choose Flowmeter Remanufacturing?
 
Diecraft Australia
Diecraft AustraliaDiecraft Australia
Diecraft Australia
 
CV of Donervon Gounden 30-4-2015
CV of Donervon Gounden  30-4-2015CV of Donervon Gounden  30-4-2015
CV of Donervon Gounden 30-4-2015
 
SMED Kaizen Event
SMED Kaizen EventSMED Kaizen Event
SMED Kaizen Event
 
Garner Osborne Assembly Brochure
Garner Osborne Assembly BrochureGarner Osborne Assembly Brochure
Garner Osborne Assembly Brochure
 
RES
RESRES
RES
 
Resume_ Girish
Resume_ GirishResume_ Girish
Resume_ Girish
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
m.bendris
m.bendrism.bendris
m.bendris
 

Similar to Julian Kalac lean 6 sigma project list--2018

Production Performance Results Internet Sample
Production Performance Results   Internet SampleProduction Performance Results   Internet Sample
Production Performance Results Internet Sampleantonioharenas
 
Operational Excellence Consultant
Operational Excellence ConsultantOperational Excellence Consultant
Operational Excellence Consultantbharat kumar
 
GregorySusa-Portfolio
GregorySusa-PortfolioGregorySusa-Portfolio
GregorySusa-PortfolioGregory Susa
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integrationEdward Jones
 
KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808Gregory King II
 
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on AutomationGot 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on AutomationCAPINC
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project ValueLeanleaders.org
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project ValueLeanleaders.org
 
American Connector Company
American Connector CompanyAmerican Connector Company
American Connector CompanySubhradeep Mitra
 
Best Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptxBest Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptxsonutyagi20
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industryGanesh TN
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integrationEdward Jones
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integrationEdward Jones
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integrationEdward Jones
 

Similar to Julian Kalac lean 6 sigma project list--2018 (20)

Muhammad Portfolio
Muhammad PortfolioMuhammad Portfolio
Muhammad Portfolio
 
dapski042116
dapski042116dapski042116
dapski042116
 
Production Performance Results Internet Sample
Production Performance Results   Internet SampleProduction Performance Results   Internet Sample
Production Performance Results Internet Sample
 
Operational Excellence Consultant
Operational Excellence ConsultantOperational Excellence Consultant
Operational Excellence Consultant
 
GregorySusa-Portfolio
GregorySusa-PortfolioGregorySusa-Portfolio
GregorySusa-Portfolio
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integration
 
KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808KingGregory_ExpandedResume 20160808
KingGregory_ExpandedResume 20160808
 
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on AutomationGot 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project Value
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project Value
 
MY CV
MY CVMY CV
MY CV
 
American Connector Company
American Connector CompanyAmerican Connector Company
American Connector Company
 
Projects summary
Projects summaryProjects summary
Projects summary
 
Best Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptxBest Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptx
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
TS 7.27 PDF
TS 7.27 PDFTS 7.27 PDF
TS 7.27 PDF
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integration
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integration
 
Strategic project integration
Strategic project integrationStrategic project integration
Strategic project integration
 

More from Julian Kalac P.Eng

1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment Julian Kalac P.Eng
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS Julian Kalac P.Eng
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVERJulian Kalac P.Eng
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureJulian Kalac P.Eng
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutJulian Kalac P.Eng
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverJulian Kalac P.Eng
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHJulian Kalac P.Eng
 
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over timeJulian Kalac P.Eng
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACJulian Kalac P.Eng
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian KalacJulian Kalac P.Eng
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACJulian Kalac P.Eng
 
Lean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACLean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACJulian Kalac P.Eng
 
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALACMACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALACJulian Kalac P.Eng
 
Current & Future State Machining VSM (Value Stream Map)
Current & Future State Machining VSM (Value Stream Map)Current & Future State Machining VSM (Value Stream Map)
Current & Future State Machining VSM (Value Stream Map)Julian Kalac P.Eng
 

More from Julian Kalac P.Eng (20)

1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment
 
Lean logistics
Lean logisticsLean logistics
Lean logistics
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedure
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag Out
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeover
 
MWV CONTROL VS SPEC
MWV CONTROL VS SPECMWV CONTROL VS SPEC
MWV CONTROL VS SPEC
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
 
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
 
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over time
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian Kalac
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALAC
 
Lean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACLean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALAC
 
LOTO LIVE WIRE CS
LOTO LIVE WIRE CSLOTO LIVE WIRE CS
LOTO LIVE WIRE CS
 
1 piece flow training
1 piece flow training1 piece flow training
1 piece flow training
 
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALACMACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
 
Current & Future State Machining VSM (Value Stream Map)
Current & Future State Machining VSM (Value Stream Map)Current & Future State Machining VSM (Value Stream Map)
Current & Future State Machining VSM (Value Stream Map)
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 

Julian Kalac lean 6 sigma project list--2018

  • 1. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 1 of 21 Examples of Lean Six Sigma projects 1. Lean - Packaging Productivity Improvement ----Consumer Goods Packaging ( $250K/Year savings)  Converted Batch & Queue into continuous flow production which reduced total cycle time from 3 days to 12hrs/order  Increased shift capacity by 82%  Eliminated 3rd shift (14 operators + temps)  Redesigned the layout into LEAN Flexible CELLS with cross functional trained workers, rotation schedule to manage bottlenecks and 5S  Reduced online “hidden rework” costs by 40% and implemented in-process checks to ensure a “check and balance” system  Reduced inventory by 30% ($1Mil inventory reduction) BEFORE LEAN MANUFACTURING AFTER LEAN IMPLEMENTATION
  • 2. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 2 of 21 EQUIPMENT RELIABILITY IMPROVEMENT PROBLEM STATEMENT: 1. Film Shrink Packaging 14% Machine Downtime 2. Poor reliability ɳ < 62%, Average time between failures = 21hrs OBJECTIVE: 1. Reduce downtime from 14% to < 3% 2. Optimize reliability of machine IMPROVEMENTS: 1. Conducted FMEA, Root Caused the top 80% machine downtime causes 2. Improved film feed roller y, redesigned new robust cutting knives 3. Implemented condition based preventative maintenance to monitor faults 4. Utilized Weibull distribution to validate reliability 5. Optimized machine process parameters RESULTS: Reduced downtime from 14% to 2.3 %, increased reliability from ɳ =62% to 97% Total savings= $740K in machine downtime reduction
  • 3. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 3 of 21 ARPAC VSM –CURRENT STATE VSM 31% EFFICIECNY 20% Rework + 14% DOWNTIME Customer Demand Total Non-Value Add Time = 3HRS Value Added Time = 173 min (4.5Hrs) 2 operator C/T = 34 min C/O = 0.5 hr Uptime = 81% PALLETIZER 2 operator FILM RACK C/T = 52 min C/O = 0.5 hr Uptime = 86% 1 operator C/T = 47 min C/O = 0 hr Uptime = 78% OVEN 1 OPERATOR WRAP DEFECTS 47 min34 min52 min 1 day 2 day1 day 0.5 days Production Order D Wk FILM ROLL C/T = 40 min C/O = 0 min Uptime = 83% OVERWRAP CONVEYOR 40 FG FILM ROLLS SHINGLES VA Time NVA Time I 10% SCRAP 20% REWORK SCRAP LINEHIGH ROLL DAMAGED ARPAC VSM –FUTURE STATE VSM 0% Rework - 2% DOWNTIME Customer Demand Total Non-Value Add Time = 0.5HRS Value Added Time = 7Hrs 2 operator C/T = 34 min C/O = 0.5 hr Uptime = 81% PALLETIZER 2 operator FILM RACK C/T = 52 min C/O = 0.5 hr Uptime = 86% 1 operator C/T = 47 min C/O = 0 hr Uptime = 78% OVEN 1 OPERATOR 47 min34 min52 min 1 day 2 day1 day 0.5 days Production Order D Wk FILM ROLL C/T = 40 min C/O = 0 min Uptime = 83% OVERWRAP CONVEYOR 40 DC FILM ROLLS SHINGLES VA Time NVA Time CONTINUOUS FLOWKANBAN ROLLS
  • 4. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 4 of 21 BEFORE AFTER IMPROVEMENT
  • 5. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 5 of 21 2. LARGE FORMAT OPERATIONAL TRANSFORMATION - Printing/Packaging - 2015 Problem Statement - • New Business unit -Large Format “LGF” department running at a loss for 2 years consecutively • Current capacity 72 shipped items/day, Customer demand =100 items/day • Currently Average lead time (LT)= 13 days , customer demand = 2-4 days • New $2Mil equipment underutilized Overall Equipment Efficiency (OEE) = 37% • Internal Quality Reject Rate = 42%, causing high rework, scrap rate = 33% Results:  Increased capacity from 72 to 131 items/day –> (83%)  Reduced lead time from 13 days to <1 day Implemented NEXT DAY delivery for all orders  Increased Gross Margin from -$30K to +$35.6K/PD ($70K/month swing) $840K/year  Transformed Large Format from cost centre into Profit centre and achieved BEFORE LEAN AFTER LEAN
  • 6. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 6 of 21 3. DESIGN FOR SIX SIGMA SWITCHABLE WATER PUMP PULLEY Problem Statement Current Switchable Water Pump Pulley has design reliability failure rate of 11%, causing engine overheating and high warranty costs, resulting in over $1.4Mil losses Objective: Improve design reliability from Identify design failure modes, optimize design yield and validate design reliability in order to relaunch within 8 months Results: Successfully improved the design using Design for Six Sigma (DFSS), fixed previous design failures using Failure Mode Effects Analysis (FMEA) and validated new design robustness using Design of Experiment (DOE). The end result: increased overall reliability from 89% to 98.7% over life cycle of the engine resulting in 60% faster warm-up
  • 7. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 7 of 21 4. EATS LEAN TRANSFORMATION EATS (Exhaust After Treatment System) Problem Statement 1. Product/design issues causing 30% internal Quality reject rate , limiting throughput 8 sets/day 2. Unable to meet increased VOLVO demand 60pcs/week, causing shut down Volvo plant 2 days 3. Unable to meet delivery time < 3 days, Currently total cycle time= 4.5 days + rework BEFORE LEAN TRANSFORMATION Custom order fitting issues Backed up orders HIGH SCRAP and REWORK
  • 8. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 8 of 21 AFTER LEAN TRANSFORMATION (12 WEEKS) CUSTOM TOOL CARTS and VISUAL CONTROLS TRANSFORMATION RESULTS 1. Reduced quality reject rate from 30% down to 3% 2. Reduced total lead time from 4.5 down to < 2 days 3. Reduced total cycle time from 3Hrs to 0.7Hrs/pc 4. TOTAL SAVINGS= $840K/YEAR CUSTOM ASSEMBLY FIXTURE
  • 9. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 9 of 21 5. QUALITY IMPROVEMENT CUSTOMER VOLVO---$200,000 SAVINGS PROBLEM: Missing critical truck component , front-end plate causing customer VOLVO a 2 day shut down and $100,000 in fines and chargeback ISSUES: customer requires critical component shipped loose, manual assembly operation not capable of 100% detecting missing part SOLUTION: Error proofed assembly process to prevent missing component RESULTS:  Added presence sensor for detecting if Missing front-end plate. Connected to shut off valve to prevent further assembly if Missing front-end plate  Added visual RED/GREEN light display notification  Verified over 12 shipments and 5000 pcs shipped problem eliminated  Cost Avoidance = $ 200,000 ERROR PROOF MANUAL ASSEMBLY PROCESS POKA YOKE Final Assembly MISSING PART
  • 10. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 10 of 21 6. BIO MANUFACTURING BATCH CYCLE TIME REDUCTION — March 2015 Problem: 1. Low Suite utilization 11%, causing capacity constraints with other products 2. Batch cycle time = 5 days per batch, customer Takt Time= 4 days/batch Objective: Increase utilization and production capacity by 30% without additional capital RESULTS:  increased Final Yield by 19%,  increased suite utilization from 11% to 62%, and  Reduced total batch processing time from 5 to 3.5 days/batch (42%)  Total Operational savings = $1.4Mil/year  Project completion time= 3.5 months
  • 11. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 11 of 21 7. LEAN LOGISTICS MANUFACTURING (DPM) AND DISTRIBUTION (NT) 2013-2014 Streamlined a complex Canada wide Manufacturing-Supply Chain-Logistics replenishment operation, which reduced storage/transportation costs by $920K, inventory levels by $2.2Mil (from $3.4Mil to $1.2Mil). Total Operational savings= $3.1Mil Problem Statement: Transportation Logistics from DP Manufacturing to NT Distribution centres inefficient. Customer same day orders and replenishment being picked up from DP Manufacturing delivered to NT Distribution Centre, then reloaded onto an outbound carrier resulting in either late deliveries, lost shipments or delivered to wrong address, resulting in shortages 50%, high WIP levels and excessive transportation costs. Improvements:  Implemented Lean Logistics using 1-step cross-docking distribution from DP to final destination, which eliminated shortages, reduced delivery time from 4 days to < 1 day  Integrated Manufacturing-Supply Chain with Warehouse Management System which reduced total WIP inventory by $2Mil, eliminated 2 carriers, utilized same carrier for Inbound/Outbound  Implemented Advanced shipping notice (ASN) which enabled Synchronized inbound delivery with outbound shipments, bar code tracking with shipment RFID chips from supplier NT DISTRIBUTION CENTERS DP PRE-PAID CUSTOMERS
  • 12. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 12 of 21 8. FCI AUTOMOTIVE – QS9001/ISO14000 2000-2004 NEW PROGRAM LAUNCH  Successfully managed a $22M USD FORD/TRW new ABS/VSC program for 2005 FORD Windstar minivan, from Design to full PPAP launch on-time & within budget.  Took over a complex FORD program in jeopardy of being lost, gained the trust and credibility of FORD/TRW Program managers and successfully PPAP launched the program on-time  Successfully improved a previously strained customer relationship with honesty, integrity trust  Developed a mandrel prototype concept for insert moulding 52 connector pins, 4 power blades, and 4 bushings for the Automatic Breaking systems ABS & Vehicle System Control VSC CONNECTORS  Developed & managed all APQP & PPAP documentation including: Design reviews, PFMEA DVP&R, SPC, Control Plans, SOP, and production tooling design  Developed automation specifications, RFQ, vendor selection, managed the design, build & installation of the custom full-automated assembly line Total budget for automation worth over $2.3M USD ABS & VCS Connector module
  • 13. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 13 of 21 9. INJECTION MOULD SET-UP REDUCTION PROJECT --($500K/annual savings)  Problem Statement: 22 injection moulds ranging from 93 weeks new to moulds over 10 years old), varied in sizes & capacities, had set-up/changeover times from 4-6hrs, resulting over $500K machine inefficiencies and productivity losses  Objective: Reduce the set-up time from 6hrs to under 2hrs  Significant Improvements: over 4.5hrs of Set-Up Time was reduced by the following  IMPROVEMENTS: o Implemented SMED principles, 5S SHADOW BOARDS, standardized, Set-Up o New water manifolds with shorter hoses and different IN/OUT connectors o Standardized bolt lengths and utilized quick-connect clamps o Interchangeable inserts and standardized back plates with different hole pattern o Standardized Mould kits & implemented shadow boards o Documented SOP and validated set-up/changeover on different shifts  These improvements resulted in over $500K annual savings Setup/Changeover Tooling Improvements
  • 14. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 14 of 21 10. Robot Welding Setup Time Reduction ----Tier 1 Automotive $650K/year savings PROBLEM STATEMENT 2 station robot weld down 38min between changeovers, 6 changeovers/day = 3.8hrs downtime/day  Current setup time= 38min  Standard Time= 15min  Target setup Time < 5min IMPROVEMENTS:  Designed 6 SIGMA modular welding fixtures, with quick connect clamps and eliminated bolts, screws and  combined tacking with robot welding into 1 operation  Implemented SMED external setup and eliminated internal setup time  Standardized welding fixtures, eliminated bolts, screws and  implemented , 5S shadow board, tooling push-pin toggle clamps RESULTS: ZERO SETUP TIME ACHIEVED Robot 9 SMED SOP=ZERO SETUP TIME SIDE A CHANGEOVER step # Operation Est Time (min) 1 PREPARE NEXT WO MATERIAL 4 2 GET NEEDED FIXTURES/TOOLS/CLAMPS 3 3 UNLOAD LAST PARTS FROM SIDE 1 1 4 INSPECT AND TOUCH UP PARTS 2 5 TACK PARTS 2 (EXTERNAL SETUP) 6 TAKE DOWN FIXTURE FROM SIDE 1 4 BEING DONE 7 LOAD PARTS ONTO SIDE 1 1 WHILE ROBOT rUNNING 8 START WELDING SIDE 1 0 TOTAL TIME FOR SETUP= 16 WELD CYCLE STARTED = 8 T SETUP TIME CLOCK STARTS AFTER 8 MIN SIDE B CHANGEOVER EXTERNAL SETUP 7 TAKE DOWN FIXTURE FROM SIDE 2 5 INCLUDED IN 8 LOAD PARTS ONTO SIDE21 1 WELD CYCLE (8MIN) 9 START WELDING SIDE 2 0 TOTAL SETUP TIME SIDE B= 6 TOTAL INTERNAL SETUP TIME= 0 TOTAL EXTERNAL SETUP TIME= 12 OLD SETUP TIME (MIN)= 38 DEC 4 SETUP (MIN) = 0 SETUP TIME IMPROVEMENT (MIN) = -38 WHILE THE ROBOT IS WELDING SIDE B, LOST TIME=0 MIN GOAL IS TO CHANGE STATION A BEFORE ROBOT FINISHES WELDING SIDE B DURING WELD CYCLE (8MIN) THE FOLLOWING WAS DONE
  • 15. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 15 of 21 11. BLACK CLAWSON EXTRUSION LAMINATOR SAFEGUARDING  PROBLEM STATEMENT: Used Laminator purchased by company without proper safeguarding and shut down by Ministry of Labour ordering a PSHR by a P.Eng  OBJECTIVE: Design machine safeguarding to enable Laminator compliance with OHSA section 851 Industrial Establishments LAMINATOR BEFORE PSHR CRITICAL AREAS TO BE GUARDED
  • 16. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 16 of 21 12. NEW PRODUCT LAUNCH IMPROVEMENT –(Water Pump Bearings) TIER 1 AUTOMOTIVE SUPPLIER --(TS-16949 REGISTERED) Problem Statement: On RED LIST due to late deliveries & poor quality to customer STACKPOLE causing “RUSH” orders and constant panic mode  1st Pass Quality Yield machining = 62%, using 100% inspection to sort out defects  Lack of Process Control, relying on QC Inspector to find defects  Premature Tool wear causing defects and downtime Rotary Transfer Machines: o 16 Station Hydromat CNC o Buffoli Transfer Machine CNC o Hydromat - 10 Station o Hydromat - 12 Station Other Equipment: • In-feed and thru-feed grinding equipment • Durr parts washer • Full chip and oil recovery systems • Fully integrated MRP system Improvements: 1. Developed VSM of current process and reviewed NVA areas 2. Implemented in-process sampling checks based on AQL of 0.4 (99.6% confidence level) using GO/NO-GO gauges, vernier measurements 3. Set-up and Implemented SPC for in-process checks which allowed operators to monitor trends and adjust tooling as needed before it’s too late 4. Redesigned tooling for a 16 station CNC HYDROMAT which reduced premature tool wear by 25% 5. Developed & Implemented Preventative Maintenance which reduced downtime by 30% 6. Designed Rough Grinding and Finish Grinding process parameters for machining water pump bearings achieving surface finishes of 0.1-0.2µm Ra (4-8 µin) consistently 7. Eliminated 100% inspection 8. Validated Testing through Reliability studies and implemented statistical process controls which reduced leak test failures from 14% to less than 0.5% improved packaging productivity by 32%
  • 17. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 17 of 21 CAPITAL EQUIPMENT PROJECT EXAMPLES 13. DESIGN FOR SIX SIGMA MANUFACUTING WORK CELL (Total Savings= $840 K) Noble Fire (June 2012)  Problem Statement: Production capacity unknown, sales increasing rapidly  Objective: Determine Current Plant Capacity and Increase production capacity by meet customer demand  Project duration < 6 months  Prepared Engineering report listing all the issues and recommendations Main Improvements: o Increased productivity by 28% in less than 2 months o Designed, tested and validated new NFPA Approved sprinkler head outlets which reduced field repairs by 95%-over $40K/year o Reduced Cycle time on an Automated Burn/Weld Machine by 30% resulting in over $100K/year in increased productivity o Implemented new BURN/WELD machines which increased production capacity by 80% and reduced labour costs by over $230K, with a ROI of 78% (Payback= 0.3 years) o Total Project Savings = $840K
  • 18. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 18 of 21 14. PROGRESSIVE STAMPING DIE DESIGN --$900K savings PROBLEM STATEMENT:  Unable to support Home Depot Demand increased by 30%, requiring 1Mil units/year  Current capacity = 550,000 pcs/year , High labour cost/pc = $2.28/pc  2 critical labour intensive BOTTLENECK operations preventing additional capacity  High Labour cost: band saw cutting ($1.5/pc) + 3 stage forming ($0.78/pc)= $2.28 Objective: Increase capacity from 550K to 1.3Mil without adding cost IMPROVEMENT Progressive Stamping Die –eliminating 2 labour intensive operations RESULTS 1. Increased capacity from 550,000 to 1,8Mil units/year (300%) 2. Combined 2 labour intensive operations into 1 progressive die cycle 3. Reduced labour cost by from $2.28 to $0.29/pc =$2 4. Payback period < 1 year, ROI= 27% 5. TOTAL ANNUAL SAVINGS AFTER PAYBACK= $910K/year 2 Operations @ 1 cycle 1 Band Saw 2 Forming with 3 setups
  • 19. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 19 of 21 15. INJECTION MOULD SET-UP REDUCTION PROJECT --($500K/annual savings)  Problem Statement: 22 injection moulds ranging from 93 weeks new to moulds over 10 years old), varied in sizes & capacities, had set-up/changeover times from 4-6hrs, resulting over $500K machine inefficiencies and productivity losses  Objective: Reduce the set-up time from 6hrs to under 2hrs  Significant Improvements: over 4.5hrs of Set-Up Time was reduced by the following  IMPROVEMENTS: o Implemented SMED principles, 5S SHADOW BOARDS, standardized, Set-Up o New water manifolds with shorter hoses and different IN/OUT connectors o Standardized bolt lengths and utilized quick-connect clamps o Interchangeable inserts and standardized back plates with different hole pattern o Standardized Mould kits & implemented shadow boards o Documented SOP and validated set-up/changeover on different shifts  These improvements resulted in over $500K annual savings Quick Setup/Changeover Tooling Improvements
  • 20. JULIAN KALAC LEAN SIX SIGMA PROJECTS APRIL 2018 Page 20 of 21 16. Noble Fire Production Capacity Problem Statement: Production capacity unknown, sales increasing rapidly Objective: Increase production welding capacity by 25% without any new equipment Project duration < 4 months Main Improvements: o Increased productivity by 28% in less than 2 months o Designed, tested and validated new NFPA Approved sprinkler head outlets which reduced field repairs by 95%- over $40K/year o Reduced Cycle time on an Automated Burn/Weld Machine by 30% resulting in over $100K/year in increased productivity o Developed a plan that would increase production capacity by 80% and reduce OT costs by over $230K, with a ROI of 78% (Payback= 0.3 years) o Total Project Savings = $840K OLD OUTLETS NEW OUTLETS
  • 21. JULIAN KALAC LEAN SIX SIGMA IN FABRICATION 1-May-18 Page 21 of 21 17.PLASTIC FILM WRAP UNWINDER SAFEGUARDING BEFORE SAFEGUARDING AFTER SAFEGUARDING