CONSTRUCTION SCHEDULING &
COST CONTROL
By
PROF. LIAQAT ALI QURESHI
UET TAXILA
Planning & Scheduling
Planning:
Process of choosing the method and
order of work
Scheduling:
Process of determining the interrelationship
of associated timings of operations.
Steps in Construction Scheduling
 Splitting of the project into work activities
 Determining logic relationships/interrelationships
between activities.
 Construction of Network Diagrams.
 Assigning durations to work activities.
 CPM Calculations resulting in start times, finish
times and float calculations of activities.
 Marking of critical Path
 Construction of Bar Charts / Time phased
diagrams.
Activity
An element of work performed during the
course of a project. Or
An amount of work that can be identified so that
we know what it involves and can recognize,
when it starts and finishes.
An activity normally has an expected duration,
an expected cost, and expected resource
requirements
Network Diagrams
 Any schematic display of the logical relationship
of project activities.
 Always drawn from left to right to reflect project
chronology.
 Usually a combination of arrows and nodes.
 Mainly of two types:
1. Arrow Diagram
2. Node Diagram / Precedence Diagram
Arrow Diagrams
 Activities shown by Arrows. Relationship
between activities shown by nodes / events.
 Length of arrows does not obey any scale.
 Start-to-finish relationships.
 Dummies.
 Numbering of nodes / events.
 Milestones
Use of Dummy Activity
Activity Durations
 Activity duration is forecasted by any of the several means, including:
(1) Check Past Records.
(2) Check Standards and / or cost guides, if available.
(3) Ask the workers, who will do it
(4) make an educated guess
 Any time units may be allotted to activity durations like days, hours, weeks,
months, shifts, etc.
 In CPM, a single duration is forecasted for an activity.
 In PERT (Program Evaluation & Review Techniques), 3 durations are
forecasted for an activity and mean taken by weighted average method.
Then, Project’s Duration or any Event Completion Time is calculated by
probability distribution.
CPM Calculations
 Calculates the following for each activity
EST = Earliest Starting Time
EFT = Earliest Finishing Time
LST = Latest Starting Time
LFT = Latest Finishing Time
TF = Total Float
FF = Free Float
 Total Float is Maximum time for which an activity can be
delayed without delaying the project.
 Free Float is maximum time for which an activity cane be
delayed without delaying the start of proceeding activity.
 Total Float = Free Float + Interfering Float
Critical Path
 The path (or paths) in the network diagram,
from start to finish, on which all the activities
have zero total and free floats, is called
Critical Path.
 It is the longest path (or paths) from start to
finish in a net work diagram.
 It gives minimum normal time to complete a
project.
 It is usually marked by double lined arrows in
a network diagram.
SINGLE SPAN BRIDGE PROJECT
(ACTIVITY DESCRIPTION)
Activity Code Operation Dependence Est. Dur.
(Days)
ENA Earthworks, north abutment - 5
ESA Earthworks, south abutment ENA 4
CONN Construction, north abutment ENA 14
CONS Construction, south abutment ESA, CONN 12
COMN Compaction, north abutment CONN 2
CIMS Compaction, south abutment CONS, COMN 2
RNB Road, north of bridge COMN 2
RSB Road, south of bridge RNB,COMS 2
PB Prefabricate bridge deck - 18
TD Transport deck to site PB 2
EB Erect bridge deck TD, CONN,
CONS,
COMN
3
LBS Lay bridge surface EB, RNB, RSB 2
ICB Install crash barriers etc. EB 1
L Landscape RNB, RSB 1
Node Diagrams
 Activities shown by Nodes, relationship
between Activities shown by arrows or links.
 Easier to construct.
 Generally no need of dummies. Instead
dummies used only to give single start or
finish.
 CPM Calculations similar to Arrow diagrams.
Bar Chart
 Gives Pictorial Representation of Activities.
 Activities begin at EST and show their EFT, FF,
TF, Durations, etc.
 Arrows at the relative ends to show dependency.
 Status Line Concept
 Unable to show complete interdependency
between Activities.
 Time-scaled Network Diagrams show complete
interdependency between Activities.
COST MANAGEMENT
COST MANAGEMENT
 Includes processes required to ensure that
the project is completed within the approved
budget.
 Processes involved are:
1- Resource Planning
2- Cost Estimating
3- Cost Budgeting
4- Cost Control
1- Resource Planning
Involves determining what physical resources
(people, equipment, materials etc) and what
quantities of each should be used to perform
project activities.
Inputs to Resource Planning
1. Work Breakdown Structure:
A deliverable-oriented grouping of project
elements that organizes and defines the
total scope of the project. It Identifies the
project elements that will need resources.
2. Historical Information
3. Scope Statement:
Contains the project justification and the
project objectives.
Inputs to Resource Planning
4. Resource Pool Description:
Knowledge of what resources are
potentially available.
5. Organizational Policies:
The policies of the performing organization
regarding staffing and the rental or
purchase of supplies and equipment.
Tools and Techniques to Resource Planning
1. Expert Judgment
2. Alternative identifications:
To adopt different approaches for
the same problem.
Outputs from Resource Planning
1. Resource Requirements:
Description of what types of resources
are required and in what quantities for
each element of the work break down
structure.
Cost Estimating
 Developing an approximation (estimates) of
the costs of the resources needed to
complete project activities.
 Includes identifying and considering various
costing alternatives.
Cost Estimating and Pricing
 Cost Estimating involves developing an
assessment of the likely quantitative result-how
much will it cost the performing organization to
provide the product or service involved.
 Pricing is a business decision-how much will
the performing organization charge for the
product or service
Inputs to Cost Estimating
 Work Breakdown Structure
 Resource Requirement
 Resource Rates:
scheduled or non-scheduled
 Activity Duration Estimates
 Historical Information
 Chart of Accounts:
Describes the coding structure used by the performing
organization to report financial information in its general
ledger
Tools and Techniques for Cost Estimating
 Analogous Estimating / Top-down Estimating:
Using the actual cost of a previous, similar
project as the basis for estimating the cost of
the current project. It is less costly but less
accurate. (Rough-cost Estimate)
 Parametric Modeling:
Using project characteristics (parameters) in
a mathematical model to predict project
costs.
Tools and Techniques for Cost Estimating
 Bottom-up Estimating:
Estimating the cost of individual work
items, then summarizing or rolling up the
individual estimates to get a project title.
(Detailed Estimate)
 Computerized Tools:
Use of computerized tools such as
project management software and
spreadsheets to assist with cost estimating.
Outputs from Cost Estimating
 Cost Estimates
 Supporting Details like Scope of work,
Calculation sheet, Assumptions made,
Possible range of results, etc.
 Cost Management Plan describing how cost
variances will be managed.
Cost Budgeting
Allocation of overall cost estimates to
individual work items in order to establish a
cost baseline for measuring project
performances.
Inputs to Cost Budgeting
 Cost Estimates
 Work Breakdown Structure
 Project Schedule
Tools and Techniques for Cost Budgeting
Tools and Techniques for developing project
Cost Estimates are used to develop budgets
for work items as well
Outputs from Cost Budgeting
 Cost Baseline
A time-phased budget that will be used to
measure and monitor cost performance
on the project. It is developed by
summing estimated costs by period and
is usually displayed in the form of an S-
curve.
Cost Control
Cost Control is concerned with
(a) Influencing the factors which create
changes to the cost baseline to ensure that
changes are beneficial.
(b) Determining that the cost baseline has
changed
(c) Managing the actual changes when and
as they occur
Cost Control
Cost Control includes:
 Monitoring cost performances to detect
variances from plan.
 Ensuring that all appropriate changes are
recorded accurately in the cost baseline
 Preventing incorrect, inappropriate, or
unauthorized changes from being included in the
cost baseline.
 Informing appropriate stakeholders of authorized
changes.
Inputs to Cost Control
 Cost Baseline
 Performance Reports
Provide information about cost performance
such as which budgets have been met and
which have not. It also alerts the project team
to issues which may cause problems in the
future.
Inputs to Cost Control
 Change Requests
These may occur in many forms-oral or
written, direct or indirect, externally or
internally initiated, and legally mandated
or optional. These may require increasing
the budget or may allow decreasing it.
Tools and Techniques for Cost Control
 Cost Change Control System
It defines the procedures by which the cost
baseline may be changed. It includes the
paperwork, tracking systems, and approval
levels necessary for authorizing changes.
 Performance Measurement
It helps to assess the magnitude of any
variations which do occur.
Tools and Techniques for Cost Control
 Additional Planning
Perspective changes may require new or
revised cost estimates or analysis of
alternate approaches.
 Computerized Tools
Outputs from Cost Control
 Revised Cost Estimates
 Budget Updates
 Corrective Action
 Estimate at Completion
It is a forecast of total project costs based
on project performance.
 Lessons Learned
OBJECTS OF COST CONTROL
1 – To have a knowledge of the profit and loss of the
project throughout the duration of the project.
PROJECT PROFITS
1) Client payments.
2) Sale of surplus or scrap material and plant
3) Payments for plants or labor by others, where, this plant or labor is ,
from time to time not required for the project.
PROJECT LOSSES
1) Labor and site office costs
2) Plant costs
3) Site overheads i.e. site facilities, access roads and office etc
4) Cost of tendering including bonds, insurance, etc.
5) Material costs.
6) Head office overheads proportioned over all current projects.
OBJECTS OF COST CONTROL
2 – To have a comparison between the actual
project performance and that conceived in the
original project plan.
Comparison is basically done according to the following
bases:
1) According to units of production
2) According to line items; e.g., labour, material,
equipment, overheads, ---
3 – Provides feedback data on actual project
performance to future project planning
THANK YOUTHANK YOU

Weitere ähnliche Inhalte

Was ist angesagt?

Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptssuserb4074f
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...A Makwana
 
Line of Balance
Line of BalanceLine of Balance
Line of BalanceIJMER
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 

Was ist angesagt? (20)

Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Construction contract
Construction contract Construction contract
Construction contract
 
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
Bar chart
Bar chartBar chart
Bar chart
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 

Ähnlich wie Construction Scheduling & Cost Control Guide

Ähnlich wie Construction Scheduling & Cost Control Guide (20)

project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Cost management
Cost managementCost management
Cost management
 
Control techniques
Control techniquesControl techniques
Control techniques
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 

Kürzlich hochgeladen

『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfBalamuruganV28
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 

Kürzlich hochgeladen (20)

『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdf
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 

Construction Scheduling & Cost Control Guide

  • 1. CONSTRUCTION SCHEDULING & COST CONTROL By PROF. LIAQAT ALI QURESHI UET TAXILA
  • 2. Planning & Scheduling Planning: Process of choosing the method and order of work Scheduling: Process of determining the interrelationship of associated timings of operations.
  • 3. Steps in Construction Scheduling  Splitting of the project into work activities  Determining logic relationships/interrelationships between activities.  Construction of Network Diagrams.  Assigning durations to work activities.  CPM Calculations resulting in start times, finish times and float calculations of activities.  Marking of critical Path  Construction of Bar Charts / Time phased diagrams.
  • 4. Activity An element of work performed during the course of a project. Or An amount of work that can be identified so that we know what it involves and can recognize, when it starts and finishes. An activity normally has an expected duration, an expected cost, and expected resource requirements
  • 5. Network Diagrams  Any schematic display of the logical relationship of project activities.  Always drawn from left to right to reflect project chronology.  Usually a combination of arrows and nodes.  Mainly of two types: 1. Arrow Diagram 2. Node Diagram / Precedence Diagram
  • 6. Arrow Diagrams  Activities shown by Arrows. Relationship between activities shown by nodes / events.  Length of arrows does not obey any scale.  Start-to-finish relationships.  Dummies.  Numbering of nodes / events.  Milestones
  • 7.
  • 8. Use of Dummy Activity
  • 9. Activity Durations  Activity duration is forecasted by any of the several means, including: (1) Check Past Records. (2) Check Standards and / or cost guides, if available. (3) Ask the workers, who will do it (4) make an educated guess  Any time units may be allotted to activity durations like days, hours, weeks, months, shifts, etc.  In CPM, a single duration is forecasted for an activity.  In PERT (Program Evaluation & Review Techniques), 3 durations are forecasted for an activity and mean taken by weighted average method. Then, Project’s Duration or any Event Completion Time is calculated by probability distribution.
  • 10. CPM Calculations  Calculates the following for each activity EST = Earliest Starting Time EFT = Earliest Finishing Time LST = Latest Starting Time LFT = Latest Finishing Time TF = Total Float FF = Free Float  Total Float is Maximum time for which an activity can be delayed without delaying the project.  Free Float is maximum time for which an activity cane be delayed without delaying the start of proceeding activity.  Total Float = Free Float + Interfering Float
  • 11. Critical Path  The path (or paths) in the network diagram, from start to finish, on which all the activities have zero total and free floats, is called Critical Path.  It is the longest path (or paths) from start to finish in a net work diagram.  It gives minimum normal time to complete a project.  It is usually marked by double lined arrows in a network diagram.
  • 12. SINGLE SPAN BRIDGE PROJECT (ACTIVITY DESCRIPTION) Activity Code Operation Dependence Est. Dur. (Days) ENA Earthworks, north abutment - 5 ESA Earthworks, south abutment ENA 4 CONN Construction, north abutment ENA 14 CONS Construction, south abutment ESA, CONN 12 COMN Compaction, north abutment CONN 2 CIMS Compaction, south abutment CONS, COMN 2 RNB Road, north of bridge COMN 2 RSB Road, south of bridge RNB,COMS 2 PB Prefabricate bridge deck - 18 TD Transport deck to site PB 2 EB Erect bridge deck TD, CONN, CONS, COMN 3 LBS Lay bridge surface EB, RNB, RSB 2 ICB Install crash barriers etc. EB 1 L Landscape RNB, RSB 1
  • 13.
  • 14.
  • 15. Node Diagrams  Activities shown by Nodes, relationship between Activities shown by arrows or links.  Easier to construct.  Generally no need of dummies. Instead dummies used only to give single start or finish.  CPM Calculations similar to Arrow diagrams.
  • 16.
  • 17.
  • 18.
  • 19. Bar Chart  Gives Pictorial Representation of Activities.  Activities begin at EST and show their EFT, FF, TF, Durations, etc.  Arrows at the relative ends to show dependency.  Status Line Concept  Unable to show complete interdependency between Activities.  Time-scaled Network Diagrams show complete interdependency between Activities.
  • 20.
  • 21.
  • 23. COST MANAGEMENT  Includes processes required to ensure that the project is completed within the approved budget.  Processes involved are: 1- Resource Planning 2- Cost Estimating 3- Cost Budgeting 4- Cost Control
  • 24. 1- Resource Planning Involves determining what physical resources (people, equipment, materials etc) and what quantities of each should be used to perform project activities.
  • 25. Inputs to Resource Planning 1. Work Breakdown Structure: A deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. It Identifies the project elements that will need resources. 2. Historical Information 3. Scope Statement: Contains the project justification and the project objectives.
  • 26. Inputs to Resource Planning 4. Resource Pool Description: Knowledge of what resources are potentially available. 5. Organizational Policies: The policies of the performing organization regarding staffing and the rental or purchase of supplies and equipment.
  • 27. Tools and Techniques to Resource Planning 1. Expert Judgment 2. Alternative identifications: To adopt different approaches for the same problem.
  • 28. Outputs from Resource Planning 1. Resource Requirements: Description of what types of resources are required and in what quantities for each element of the work break down structure.
  • 29. Cost Estimating  Developing an approximation (estimates) of the costs of the resources needed to complete project activities.  Includes identifying and considering various costing alternatives.
  • 30. Cost Estimating and Pricing  Cost Estimating involves developing an assessment of the likely quantitative result-how much will it cost the performing organization to provide the product or service involved.  Pricing is a business decision-how much will the performing organization charge for the product or service
  • 31. Inputs to Cost Estimating  Work Breakdown Structure  Resource Requirement  Resource Rates: scheduled or non-scheduled  Activity Duration Estimates  Historical Information  Chart of Accounts: Describes the coding structure used by the performing organization to report financial information in its general ledger
  • 32. Tools and Techniques for Cost Estimating  Analogous Estimating / Top-down Estimating: Using the actual cost of a previous, similar project as the basis for estimating the cost of the current project. It is less costly but less accurate. (Rough-cost Estimate)  Parametric Modeling: Using project characteristics (parameters) in a mathematical model to predict project costs.
  • 33. Tools and Techniques for Cost Estimating  Bottom-up Estimating: Estimating the cost of individual work items, then summarizing or rolling up the individual estimates to get a project title. (Detailed Estimate)  Computerized Tools: Use of computerized tools such as project management software and spreadsheets to assist with cost estimating.
  • 34. Outputs from Cost Estimating  Cost Estimates  Supporting Details like Scope of work, Calculation sheet, Assumptions made, Possible range of results, etc.  Cost Management Plan describing how cost variances will be managed.
  • 35. Cost Budgeting Allocation of overall cost estimates to individual work items in order to establish a cost baseline for measuring project performances.
  • 36. Inputs to Cost Budgeting  Cost Estimates  Work Breakdown Structure  Project Schedule
  • 37. Tools and Techniques for Cost Budgeting Tools and Techniques for developing project Cost Estimates are used to develop budgets for work items as well
  • 38. Outputs from Cost Budgeting  Cost Baseline A time-phased budget that will be used to measure and monitor cost performance on the project. It is developed by summing estimated costs by period and is usually displayed in the form of an S- curve.
  • 39.
  • 40. Cost Control Cost Control is concerned with (a) Influencing the factors which create changes to the cost baseline to ensure that changes are beneficial. (b) Determining that the cost baseline has changed (c) Managing the actual changes when and as they occur
  • 41. Cost Control Cost Control includes:  Monitoring cost performances to detect variances from plan.  Ensuring that all appropriate changes are recorded accurately in the cost baseline  Preventing incorrect, inappropriate, or unauthorized changes from being included in the cost baseline.  Informing appropriate stakeholders of authorized changes.
  • 42. Inputs to Cost Control  Cost Baseline  Performance Reports Provide information about cost performance such as which budgets have been met and which have not. It also alerts the project team to issues which may cause problems in the future.
  • 43. Inputs to Cost Control  Change Requests These may occur in many forms-oral or written, direct or indirect, externally or internally initiated, and legally mandated or optional. These may require increasing the budget or may allow decreasing it.
  • 44. Tools and Techniques for Cost Control  Cost Change Control System It defines the procedures by which the cost baseline may be changed. It includes the paperwork, tracking systems, and approval levels necessary for authorizing changes.  Performance Measurement It helps to assess the magnitude of any variations which do occur.
  • 45. Tools and Techniques for Cost Control  Additional Planning Perspective changes may require new or revised cost estimates or analysis of alternate approaches.  Computerized Tools
  • 46. Outputs from Cost Control  Revised Cost Estimates  Budget Updates  Corrective Action  Estimate at Completion It is a forecast of total project costs based on project performance.  Lessons Learned
  • 47. OBJECTS OF COST CONTROL 1 – To have a knowledge of the profit and loss of the project throughout the duration of the project. PROJECT PROFITS 1) Client payments. 2) Sale of surplus or scrap material and plant 3) Payments for plants or labor by others, where, this plant or labor is , from time to time not required for the project. PROJECT LOSSES 1) Labor and site office costs 2) Plant costs 3) Site overheads i.e. site facilities, access roads and office etc 4) Cost of tendering including bonds, insurance, etc. 5) Material costs. 6) Head office overheads proportioned over all current projects.
  • 48. OBJECTS OF COST CONTROL 2 – To have a comparison between the actual project performance and that conceived in the original project plan. Comparison is basically done according to the following bases: 1) According to units of production 2) According to line items; e.g., labour, material, equipment, overheads, --- 3 – Provides feedback data on actual project performance to future project planning