SlideShare a Scribd company logo
1 of 29
Adrias Tan
MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Senior Legal Counsel, Hyundai Engg & Construction Co Ltd
Variations Under FIDIC Forms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Adrias Tan
MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Senior Legal Counsel, Hyundai Engineering & Construction Co Ltd
Fellow, Chartered Institute of Arbitrators
Fellow, Singapore Institute of Arbitrators
Fellow, Singapore Institute of Builders
Member, Society of Construction Law, UK
Member, Society of Construction Law, Singapore
Associate Member, Singapore Academy of Law
Associate Lecturer, Royal Melbourne Institute of Technology (SIM Singapore)
Panel of Arbitrators, SIArb
Variations give Contractor a right to additional money. How
does entitlement to compensation interrelate with other FIDIC
clauses? Can Contractor avoid the problems associated with
Clause 20.1 notice by claiming as a Variation instead?
• Variations compared to “Claims” under FIDIC.
• Does Contractor have to give notice under clause 20 in order
to get money or time for a Variation?
• Does Contractor have a choice as to whether it recovers as a
Variation or a “Claim”?
• Different approaches to valuing variations and “Claims”
• Claiming for Variation in absence of an Engineer’s instruction
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
ADRIAS TAN
Variations Under FIDIC Forms
Variations Compared to Claims
• Definition of Variation
― Defined as any change in form, character, kind, quality,
quantity, line, level, position, alignment, or dimension
of existing work or any additional work which vary the
Original Scope and Extent of Works that the Engineer
finds necessary, appropriate or desirable to complete
the works
― May be initiated by Employer’s Representative at any
time during the Contract Period, either by instruction or
by a request for the Contractor to submit a proposal
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variations Compared to Claims
• Contractual Basis for Variations
– Changes in quantities of any item of work included in the
Contract
– Changes to quality and other characteristics of any item of
work
– Changes to levels, positions and/or dimensions of any part of
work
– Omission of any work unless it is to be carried out by others
– Any additional work, Plant, Materials or services necessary for
Permanent Works, including any associated Tests on
Completion, boreholes and other testing and exploratory work
– Changes to sequence or timing of execution of works
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variations Compared to Claims
• Engineer’s Instruction
– If Engineer’s Instruction constitutes as Variation, then
contract provisions on Variations and Adjustments shall
apply
– Contractor may be requested to submit a proposal
constituting as a Variation
– Engineer’s Instruction constituting as a Variation issued
for an approved Contractor’s Value Engineering Proposal
– Variations evaluated in accordance with the Contract
provisions governing Measurement and Evaluation, for
re-measurement of the as-built Works executed
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variations Compared to Claims
• Definition of Claims
– Claims arise when Contractor considers himself to be
entitled to time, cost and compensation for reasonable
profit, under any FIDIC Clauses or otherwise in
connection with the Contract
– Claims can also incur cost or time implications arising
from Variations, such as abortive works, disruption,
prolongation, suspension, re-engineering works
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variations Compared to Claims
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
• Contractual Basis for Claims
– Delayed drawings or instructions
– Right of access
– Setting out
– Unforeseen physical conditions
– Fossils
– Testing
– Extension of Time for Completion
– Loss and Expense due to
Variations
– Delay caused by Authorities
– Suspension of works
– Evaluation and
Measurement
– Omissions
– Value Engineering
– Interference with
tests on completion
– Changes in legislation
– Employer’s Risks
Variations Under FIDIC Forms
Variations Compared to Claims
• Scope of Claims
– loss and expense claims, breaches under general law, or
under the prevailing Conditions of Contract
– Time related claims, extension of the Time for
Completion
– Time related costs, loss and expense
– Contractor notifies Engineer where work has been
delayed by reasons beyond his control
– Failure to do so would render Contractor liable for
liquidated damages for delay
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variations Compared to Claims
• Variations and Claims Conflated
– Distinction between evaluation of Variation Claims under
Clause 12 [Measurement and Evaluation] and Claims for
Additional Compensation arising from Variations such as
abortive works, prolongation, suspension, disruption,
delay under Clause 20.1
– Claims for Variations not administered under Clause 20.1,
a commonly misunderstood procedure
– Claims for Compensation due to Additional Costs arising
from Variations administered under Clause 20.1
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Clause 20.1 Notice for Variation Claims
• Prevailing Express Contract Provisions
– Cost compensation for Variations evaluated pursuant
with contract provisions on Measurement and
Evaluation, for re-measurement of as-built Works
executed, including omission
– Contract Bills of Quantities Unit Rates, Schedule of Rates
used for varied work similar in nature and executed
under similar circumstances
– Adjustment based on new rates or price derived from
relevant prices with reasonable adjustments or from
reasonable cost of work including reasonable profit
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Clause 20.1 Notice for Variation Claims
• Henry Boot Constr v GEC Alstom Combined Cycles
– Humphrey Lloyd QC ruled that variations do not have to
be valued fairly but in accordance with contract terms
and rates agreed even if it meant that bill rates were
unduly favourable to the parties
– no express provisions requiring Contractor to notify
Engineer in order to get compensation for works
executed under an instruction constituting as a Variation
– When Engineer requires the Works to be measured,
reasonable notice given to Contractor if attendance or
assistance or additional particulars are required
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Clause 20.1 Notice for Variation Claims
• Henry Boot Constr v GEC Alstom Combined Cycles
– Such measurement and evaluation do not provide for any
other compensation such as abortive works, re-
engineering works, costs related to disruption,
prolongation, suspension, idling costs and such like,
arising from the Variations
– Under Clause 20, Contractor is contractually obliged to
notify Engineer for such claims arising out of complying
with such Variations
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Clause 20.1 Notice for Variation Claims
• Henry Boot Constr v GEC Alstom Combined Cycles
– Under Clause 20.1, Contractor is contractually obliged to
notify Engineer if the Variation will constitute:
• any time implications arising out of complying with
Variations, any entitlement to an extension of the Time
for Completion, the Contractual Completion Date will be
delayed due to such Valid Variations, such as substantial
change in the quantity of an item of work in the Contract
• abortive works, re-engineering works, costs related to
disruption, prolongation, suspension, idling costs
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Recovering as a Variation or a Claim
– Whether claim for compensation is a Variation or a Claim
– Compensation for Variations for costs related to as-built
works, evaluated and re-measured under contractual
provisions such as Clause 12 [Measurement and
Evaluation]
– Claims arising from Variations and additional costs may
include loss and expense, and time related claims such as
EOT and EOT related costs, all of which are not
encapsulated in Clause 12 but necessarily incurred as a
result of the various factors
– Contractor may engage two approaches in seeking
compensation as a Variation and / or as a Claim
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Valuing Variations
– Variations evaluated using methods of measurement of
net actual as-built quantity of Permanent Works, using BQ
Unit Rates, Schedule of Rates or other applicable rates
– Contractual procedure for evaluation of variations
enshrined in FIDIC Form under [Measurement and
Evaluation] clauses. Onus on Engineer and Cost
Consultants to measure and evaluate the variations
– Contentious issue arises when Engineer imposes Clause
20.1 relating to detailed particulars of a Claim to compel
Contractor to submit such details and supporting
particulars for the Engineer’s review and evaluation before
approving the variation claims
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Valuing Claims
– Genesis of Claims lies in several Contract Condition
Clauses
– Claim for compensation due to variations is for additional
costs like loss and expense, time related claims for EOT
and EOT related costs, disruption, prolongation and
suspension costs, which are not encapsulated in
Evaluation of Variations but necessarily incurred
– Claims evaluated based on actual costs incurred, subject
to detailed supporting particulars of the basis of the
claim and additional payment claimed due under the
relevant provision of the Contract
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Valuing Claims
• Loss and Expense Claims
– Delayed drawings or instructions
– Abortive Works
– Costs due to disruption, prolongation, suspension, idling
time
– Re-engineering and pre-planning works
– Substantial changes in quantities and contract price
above certain percentage requiring adjustment of the
contract unit rates
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Valuing Claims
• Heads of Claims
– Direct Costs, indirect costs – subject to strict proof
– Overheads, financing charges and interests, FG Minter v
Welsh Health Technical Services Organisation
– Profit and Loss of Profit
• Global Claims
– Crosby & Sons Ltd v Portland Urban District Council
– Onus on Contractor to particularise detailed claims, not
just a scientific thesis and academically compelling
argument to substantiate the claims
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variation Without Engineer’s Instruction
– If an Engineer’s Instruction constitutes a Variation, the
Contract provides that the Variation shall be subject to
Evaluation and Adjustment
– Scenario: when Contractor submits a Variation Claim for
Engineer’s Instruction not clearly stipulated as a
Variation, and Engineer disapproves the Variation, but
still compelling the Contractor to comply with the
Instruction
– No contract protocol for Contractor to reserve rights of
claims and to protect his position in relation to such
Engineer’s Instruction which ought to constitute as a
Variation
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variation Without Engineer’s Instruction
– Most FIDIC Forms stipulates that the Contractor shall not
make any alteration and/or modification of the Works,
unless and until the Engineer instructs or approves a
Variation in writing
– Where an instruction constituting as a Variation is not
expressly stated as such, and the Contractor notifies the
Engineer of cost and time implications of the variation,
the Engineer must respond in writing that the same
ought to constitute as a Variation
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variation Without Engineer’s Instruction
– Once a Variation is approved in writing, the Contractor
shall acknowledge receipt, and the Contractor shall
execute and be bound by such an approved Variation
– Each Variation shall then be evaluated in accordance with
the Contract provisions governing Measurement and
Evaluation
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Variations Under FIDIC Forms
Variation Without Engineer’s Instruction
– When the Engineer disapproves or rejects a Variation, the
instruction is deemed as an invalid instruction with no
contractual effect
– Complying with the instruction constituting as a Variation
which the Engineer has disapproved as a Variation would
disentitle the Contractor to any compensation
– Contractually, the Contractor is precluded from any rights
of claims for Variations executed in the absence of an
Engineer’s Instruction
– Compensation under doctrine of quantum meruit claims,
doctrine of unfair enrichment, or under equity
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
FLOW CHART – Engineer’s Instructions Constituting as a Variation, Evaluation and Claims for Additional Payment
Variations Under FIDIC Forms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
 Interactive Voting System – Multiple Choice Questions
 The FIDIC Forms, or the Guidance
Notes, should provide clear and
unambiguous contractual procedures
to distinguish the difference between
Claims for Variations and Additional
Works as opposed to Claims for
Compensation due to Variations and
other contractual basis?
1) AGREE
2) NO, the present provisions are
adequate
Variations Under FIDIC Forms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
 Interactive Voting System – Multiple Choice Questions
 Choose one of the following scenario:
1) The Contractor must submit,
pursuant to Clause 20.1,
compensation claims for evaluation
and remeasurement of Variation
Works executed
2) The Engineer proceeds
straightaway to evaluate the
Variation Works upon completion
pursuant to Clause 12
[Measurement and Evaluation]
Variations Under FIDIC Forms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
 Interactive Voting System – Multiple Choice Questions
 The FIDIC Form can be further
improved by stipulating that the
Engineer, when issuing an instruction
constituting as a Variation, to inform
the Contractor in writing that the
instruction is a Variation.
1) AGREE
2) Not necessary, the present
provisions are adequate
Variations Under FIDIC Forms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
 Interactive Voting System – Multiple Choice Questions
 The Engineer has issued an
instruction, and the Contractor has
notified the Engineer that it
constitutes a Variation, which the
Engineer disapproves. Should the
FIDIC Form include provisions for the
Contractor to proceed with the
instruction pending resolution of this
dispute to protect the Contractor?
1) YES
2) NO, the Contractor must comply
without compensation
MSc | BSc(Hons) | LLB(Hons) | FCIArb | FSIArb
Adrias has more than two decades of practical working experience
in the construction industry, working currently as in-house legal
counsel for an MNC Company. Adrias is professionally trained in
litigation, arbitration, adjudication, mediation and dispute
resolution, and is an accredited arbitrator. He has handled several
institutional and ad-hoc arbitral proceedings, as well as having
tutored in SIArb, and conducted numerous workshops and
seminars on diverse construction, contractual and legal issues
including various Standard Forms of Contracts. He also lectures at
the Royal Melbourne Institute of Technology, at the Singapore
Institute of Management Campus teaching law subjects.
email: adriastan@yahoo.com
sg.linkedin.com/in/adrias-tan-5ab34035
Variations Under FIDIC Forms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Adrias Tan

More Related Content

What's hot

FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMauro Jasse
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMP®, CCP®
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN PanigrahiSN Panigrahi, PMP
 
Contractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction ContractsContractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction ContractsGary L. Henry
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planningjosephb987
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 

What's hot (20)

Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Risk management in a construction projects between knowledge and application ...
Risk management in a construction projects between knowledge and application ...Risk management in a construction projects between knowledge and application ...
Risk management in a construction projects between knowledge and application ...
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Contractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction ContractsContractual Risk Transfer in Construction Contracts
Contractual Risk Transfer in Construction Contracts
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planning
 
Pmp Final Review - M Maged
Pmp Final Review - M MagedPmp Final Review - M Maged
Pmp Final Review - M Maged
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 

Similar to FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan

Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreementChirag Jain
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxRules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxTTconstructionspvtlt
 
Item # 13 - Plan Review Process Revisions
Item # 13 - Plan Review Process RevisionsItem # 13 - Plan Review Process Revisions
Item # 13 - Plan Review Process Revisionsahcitycouncil
 
Contracts for difference
Contracts for differenceContracts for difference
Contracts for differenceGeoff White
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...César del Riego y Fuentes
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law39 Essex Chambers
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen AntovAssen Antov
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsAC&C Consulting Co., Ltd.
 

Similar to FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan (20)

Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxRules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
 
Contract closing ppt
Contract closing pptContract closing ppt
Contract closing ppt
 
Item # 13 - Plan Review Process Revisions
Item # 13 - Plan Review Process RevisionsItem # 13 - Plan Review Process Revisions
Item # 13 - Plan Review Process Revisions
 
Contracts for difference
Contracts for differenceContracts for difference
Contracts for difference
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 

FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan

  • 1. Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Senior Legal Counsel, Hyundai Engg & Construction Co Ltd
  • 2. Variations Under FIDIC Forms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Senior Legal Counsel, Hyundai Engineering & Construction Co Ltd Fellow, Chartered Institute of Arbitrators Fellow, Singapore Institute of Arbitrators Fellow, Singapore Institute of Builders Member, Society of Construction Law, UK Member, Society of Construction Law, Singapore Associate Member, Singapore Academy of Law Associate Lecturer, Royal Melbourne Institute of Technology (SIM Singapore) Panel of Arbitrators, SIArb
  • 3. Variations give Contractor a right to additional money. How does entitlement to compensation interrelate with other FIDIC clauses? Can Contractor avoid the problems associated with Clause 20.1 notice by claiming as a Variation instead? • Variations compared to “Claims” under FIDIC. • Does Contractor have to give notice under clause 20 in order to get money or time for a Variation? • Does Contractor have a choice as to whether it recovers as a Variation or a “Claim”? • Different approaches to valuing variations and “Claims” • Claiming for Variation in absence of an Engineer’s instruction © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Variations Under FIDIC Forms ADRIAS TAN
  • 4. Variations Under FIDIC Forms Variations Compared to Claims • Definition of Variation ― Defined as any change in form, character, kind, quality, quantity, line, level, position, alignment, or dimension of existing work or any additional work which vary the Original Scope and Extent of Works that the Engineer finds necessary, appropriate or desirable to complete the works ― May be initiated by Employer’s Representative at any time during the Contract Period, either by instruction or by a request for the Contractor to submit a proposal © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 5. Variations Under FIDIC Forms Variations Compared to Claims • Contractual Basis for Variations – Changes in quantities of any item of work included in the Contract – Changes to quality and other characteristics of any item of work – Changes to levels, positions and/or dimensions of any part of work – Omission of any work unless it is to be carried out by others – Any additional work, Plant, Materials or services necessary for Permanent Works, including any associated Tests on Completion, boreholes and other testing and exploratory work – Changes to sequence or timing of execution of works © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 6. Variations Under FIDIC Forms Variations Compared to Claims • Engineer’s Instruction – If Engineer’s Instruction constitutes as Variation, then contract provisions on Variations and Adjustments shall apply – Contractor may be requested to submit a proposal constituting as a Variation – Engineer’s Instruction constituting as a Variation issued for an approved Contractor’s Value Engineering Proposal – Variations evaluated in accordance with the Contract provisions governing Measurement and Evaluation, for re-measurement of the as-built Works executed © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 7. Variations Under FIDIC Forms Variations Compared to Claims • Definition of Claims – Claims arise when Contractor considers himself to be entitled to time, cost and compensation for reasonable profit, under any FIDIC Clauses or otherwise in connection with the Contract – Claims can also incur cost or time implications arising from Variations, such as abortive works, disruption, prolongation, suspension, re-engineering works © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 8. Variations Under FIDIC Forms Variations Compared to Claims © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb • Contractual Basis for Claims – Delayed drawings or instructions – Right of access – Setting out – Unforeseen physical conditions – Fossils – Testing – Extension of Time for Completion – Loss and Expense due to Variations – Delay caused by Authorities – Suspension of works – Evaluation and Measurement – Omissions – Value Engineering – Interference with tests on completion – Changes in legislation – Employer’s Risks
  • 9. Variations Under FIDIC Forms Variations Compared to Claims • Scope of Claims – loss and expense claims, breaches under general law, or under the prevailing Conditions of Contract – Time related claims, extension of the Time for Completion – Time related costs, loss and expense – Contractor notifies Engineer where work has been delayed by reasons beyond his control – Failure to do so would render Contractor liable for liquidated damages for delay © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 10. Variations Under FIDIC Forms Variations Compared to Claims • Variations and Claims Conflated – Distinction between evaluation of Variation Claims under Clause 12 [Measurement and Evaluation] and Claims for Additional Compensation arising from Variations such as abortive works, prolongation, suspension, disruption, delay under Clause 20.1 – Claims for Variations not administered under Clause 20.1, a commonly misunderstood procedure – Claims for Compensation due to Additional Costs arising from Variations administered under Clause 20.1 © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 11. Variations Under FIDIC Forms Clause 20.1 Notice for Variation Claims • Prevailing Express Contract Provisions – Cost compensation for Variations evaluated pursuant with contract provisions on Measurement and Evaluation, for re-measurement of as-built Works executed, including omission – Contract Bills of Quantities Unit Rates, Schedule of Rates used for varied work similar in nature and executed under similar circumstances – Adjustment based on new rates or price derived from relevant prices with reasonable adjustments or from reasonable cost of work including reasonable profit © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 12. Variations Under FIDIC Forms Clause 20.1 Notice for Variation Claims • Henry Boot Constr v GEC Alstom Combined Cycles – Humphrey Lloyd QC ruled that variations do not have to be valued fairly but in accordance with contract terms and rates agreed even if it meant that bill rates were unduly favourable to the parties – no express provisions requiring Contractor to notify Engineer in order to get compensation for works executed under an instruction constituting as a Variation – When Engineer requires the Works to be measured, reasonable notice given to Contractor if attendance or assistance or additional particulars are required © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 13. Variations Under FIDIC Forms Clause 20.1 Notice for Variation Claims • Henry Boot Constr v GEC Alstom Combined Cycles – Such measurement and evaluation do not provide for any other compensation such as abortive works, re- engineering works, costs related to disruption, prolongation, suspension, idling costs and such like, arising from the Variations – Under Clause 20, Contractor is contractually obliged to notify Engineer for such claims arising out of complying with such Variations © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 14. Variations Under FIDIC Forms Clause 20.1 Notice for Variation Claims • Henry Boot Constr v GEC Alstom Combined Cycles – Under Clause 20.1, Contractor is contractually obliged to notify Engineer if the Variation will constitute: • any time implications arising out of complying with Variations, any entitlement to an extension of the Time for Completion, the Contractual Completion Date will be delayed due to such Valid Variations, such as substantial change in the quantity of an item of work in the Contract • abortive works, re-engineering works, costs related to disruption, prolongation, suspension, idling costs © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 15. Variations Under FIDIC Forms Recovering as a Variation or a Claim – Whether claim for compensation is a Variation or a Claim – Compensation for Variations for costs related to as-built works, evaluated and re-measured under contractual provisions such as Clause 12 [Measurement and Evaluation] – Claims arising from Variations and additional costs may include loss and expense, and time related claims such as EOT and EOT related costs, all of which are not encapsulated in Clause 12 but necessarily incurred as a result of the various factors – Contractor may engage two approaches in seeking compensation as a Variation and / or as a Claim © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 16. Variations Under FIDIC Forms Valuing Variations – Variations evaluated using methods of measurement of net actual as-built quantity of Permanent Works, using BQ Unit Rates, Schedule of Rates or other applicable rates – Contractual procedure for evaluation of variations enshrined in FIDIC Form under [Measurement and Evaluation] clauses. Onus on Engineer and Cost Consultants to measure and evaluate the variations – Contentious issue arises when Engineer imposes Clause 20.1 relating to detailed particulars of a Claim to compel Contractor to submit such details and supporting particulars for the Engineer’s review and evaluation before approving the variation claims © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 17. Variations Under FIDIC Forms Valuing Claims – Genesis of Claims lies in several Contract Condition Clauses – Claim for compensation due to variations is for additional costs like loss and expense, time related claims for EOT and EOT related costs, disruption, prolongation and suspension costs, which are not encapsulated in Evaluation of Variations but necessarily incurred – Claims evaluated based on actual costs incurred, subject to detailed supporting particulars of the basis of the claim and additional payment claimed due under the relevant provision of the Contract © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 18. Variations Under FIDIC Forms Valuing Claims • Loss and Expense Claims – Delayed drawings or instructions – Abortive Works – Costs due to disruption, prolongation, suspension, idling time – Re-engineering and pre-planning works – Substantial changes in quantities and contract price above certain percentage requiring adjustment of the contract unit rates © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 19. Variations Under FIDIC Forms Valuing Claims • Heads of Claims – Direct Costs, indirect costs – subject to strict proof – Overheads, financing charges and interests, FG Minter v Welsh Health Technical Services Organisation – Profit and Loss of Profit • Global Claims – Crosby & Sons Ltd v Portland Urban District Council – Onus on Contractor to particularise detailed claims, not just a scientific thesis and academically compelling argument to substantiate the claims © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 20. Variations Under FIDIC Forms Variation Without Engineer’s Instruction – If an Engineer’s Instruction constitutes a Variation, the Contract provides that the Variation shall be subject to Evaluation and Adjustment – Scenario: when Contractor submits a Variation Claim for Engineer’s Instruction not clearly stipulated as a Variation, and Engineer disapproves the Variation, but still compelling the Contractor to comply with the Instruction – No contract protocol for Contractor to reserve rights of claims and to protect his position in relation to such Engineer’s Instruction which ought to constitute as a Variation © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 21. Variations Under FIDIC Forms Variation Without Engineer’s Instruction – Most FIDIC Forms stipulates that the Contractor shall not make any alteration and/or modification of the Works, unless and until the Engineer instructs or approves a Variation in writing – Where an instruction constituting as a Variation is not expressly stated as such, and the Contractor notifies the Engineer of cost and time implications of the variation, the Engineer must respond in writing that the same ought to constitute as a Variation © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 22. Variations Under FIDIC Forms Variation Without Engineer’s Instruction – Once a Variation is approved in writing, the Contractor shall acknowledge receipt, and the Contractor shall execute and be bound by such an approved Variation – Each Variation shall then be evaluated in accordance with the Contract provisions governing Measurement and Evaluation © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 23. Variations Under FIDIC Forms Variation Without Engineer’s Instruction – When the Engineer disapproves or rejects a Variation, the instruction is deemed as an invalid instruction with no contractual effect – Complying with the instruction constituting as a Variation which the Engineer has disapproved as a Variation would disentitle the Contractor to any compensation – Contractually, the Contractor is precluded from any rights of claims for Variations executed in the absence of an Engineer’s Instruction – Compensation under doctrine of quantum meruit claims, doctrine of unfair enrichment, or under equity © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 24. FLOW CHART – Engineer’s Instructions Constituting as a Variation, Evaluation and Claims for Additional Payment
  • 25. Variations Under FIDIC Forms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb  Interactive Voting System – Multiple Choice Questions  The FIDIC Forms, or the Guidance Notes, should provide clear and unambiguous contractual procedures to distinguish the difference between Claims for Variations and Additional Works as opposed to Claims for Compensation due to Variations and other contractual basis? 1) AGREE 2) NO, the present provisions are adequate
  • 26. Variations Under FIDIC Forms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb  Interactive Voting System – Multiple Choice Questions  Choose one of the following scenario: 1) The Contractor must submit, pursuant to Clause 20.1, compensation claims for evaluation and remeasurement of Variation Works executed 2) The Engineer proceeds straightaway to evaluate the Variation Works upon completion pursuant to Clause 12 [Measurement and Evaluation]
  • 27. Variations Under FIDIC Forms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb  Interactive Voting System – Multiple Choice Questions  The FIDIC Form can be further improved by stipulating that the Engineer, when issuing an instruction constituting as a Variation, to inform the Contractor in writing that the instruction is a Variation. 1) AGREE 2) Not necessary, the present provisions are adequate
  • 28. Variations Under FIDIC Forms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb  Interactive Voting System – Multiple Choice Questions  The Engineer has issued an instruction, and the Contractor has notified the Engineer that it constitutes a Variation, which the Engineer disapproves. Should the FIDIC Form include provisions for the Contractor to proceed with the instruction pending resolution of this dispute to protect the Contractor? 1) YES 2) NO, the Contractor must comply without compensation
  • 29. MSc | BSc(Hons) | LLB(Hons) | FCIArb | FSIArb Adrias has more than two decades of practical working experience in the construction industry, working currently as in-house legal counsel for an MNC Company. Adrias is professionally trained in litigation, arbitration, adjudication, mediation and dispute resolution, and is an accredited arbitrator. He has handled several institutional and ad-hoc arbitral proceedings, as well as having tutored in SIArb, and conducted numerous workshops and seminars on diverse construction, contractual and legal issues including various Standard Forms of Contracts. He also lectures at the Royal Melbourne Institute of Technology, at the Singapore Institute of Management Campus teaching law subjects. email: adriastan@yahoo.com sg.linkedin.com/in/adrias-tan-5ab34035 Variations Under FIDIC Forms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Adrias Tan